Case Study Buildings

download Case Study Buildings

of 14

Transcript of Case Study Buildings

  • 7/23/2019 Case Study Buildings

    1/14

    E

    nergyEfficiency

    Case Studies

    Roeland De MeulenaereLaborelec

    January 2008

    Case study: Buildings

  • 7/23/2019 Case Study Buildings

    2/14

    2

    Energy Efficiencywww.leonardo-energy.org

    Energy Efficiency

    IntroductionWith all the environmental problems caused by CO2emissions, energy saving

    is a hot topic at the moment. But how much do energy savings cost? How long

    does it take until you recover your investment? Where can you save energy?

    And how much CO2emissions are actually avoided?

    This document provides answers to questions such as these, based on

    commonly used methods of saving energy. Various possibilities for saving

    energy are discussed in detail.

    The five case studies presented in this document are:

    1. Frequency regulator and oxygen sensor for superheated boilers

    2. Energy management system

    3. Thermal bridges

    4. Ventilation

    5. Lighting

    The following energy prices are used in the case studies:

    Electricity: 75/MWhGas: 25 /MWh

    Fuel oil: 0.60 /l

  • 7/23/2019 Case Study Buildings

    3/14

    3

    Case Study: Buildingswww.leonardo-energy.org

    Case Study: Buildings

    Frequency regulator and oxygen sensor for

    superheated boilers

    Introduction

    Many buildings are heated with natural gas. In many cases the boilers in which

    the gas is converted into heat do not operate efficiently, due to faulty regulation

    or poor adjustment. In this case we look at the real-life example of a hospital.

    Present situation

    The boilers in the hospital work with simple on/off regulation and an excess

    supply of air in order to guarantee full combustion of the natural gas. The air is

    brought to the gas by means of a fan.

    In such a system the excess air which does not actually contribute towards the

    combustion also has to be heated up by the flame. The hot air disappears up

    the flue along with the combustion gases. This can be avoided by controlling

    the supply of air more accurately, resulting in lower gas consumption because

    less air has to be heated up.

    In this case four superheated boilers are used, one of 8 MW and three of 11.7

    MW.

    Proposal

    We examined whether one of the 11.7 MW boilers could be fitted with a

    frequency regulator on the air supply fan, and/or an oxygen sensor in the flue

    pipe with feedback to the regulator.

    A frequency regulator yields electricity savings compared to the present

    regulation with a damper valve (depending on the load on the boiler), while an

    oxygen sensor yields fuel savings (depending on the burner setting).

    Savings and investment

    The air supply fan was fitted with a frequency regulator. The power

    consumption is proportional to the cube of the speed (rpm). In other words, a

    small reduction in speed yields a large saving in power.

    The oxygen sensor makes it possible to raise the efficiency of the boiler by

    reducing the amount of excess oxygen, so that less fuel is used to generate the

  • 7/23/2019 Case Study Buildings

    4/14

    4

    Energy Efficiencywww.leonardo-energy.org

    same amount of heat.

    Theoretical calculations were carried out using simulation software with the

    frequency curve based on a standard normal distribution of the fan power. The

    savings yielded by the O2 sensor were calculated on the basis of the

    combustion coefficient at different O2levels and the thermal consumption of the

    system.

    These calculations yielded the following savings, assuming 6000 hours of

    operation per year and a flue temperature of 190C:

    Table 1: Calculated values and the savings achieved using an oxygen sensorand a frequency regulator

    Various installers were invited to submit offers. One of these offers (in Belgium)

    represented a capital cost of 39.883 (incl. VAT), which in turn represented a

    payback period of 1.6 years.

    Energy management system

    Introduction

    An energy management system (EMS) is a central controller for utilities, with a

    single computer controlling everything throughout the building: temperatures,

    lighting, time switches etc. The computer also logs all the data. Such a system

    can yield considerable energy savings if properly used. For example,

    ventilation/airco/heating can be switched off at night or during weekends. Note

    that an EMS by itself does not yield any energy savings: what counts is making

    the right use of it!

    Present situation New situation Saving

    Electrical power of fan 22 kW 22 kW

    Electricity consumption 132 MWh/year 64 MWh/year 68 MWh/year

    Excess oxygen 5% 2%

    Combustion efficiency 90.1% 91.4%

    Thermal consumption 54756 MWh/year 53977 MWh/year 779 MWh/year

    24575 /year

  • 7/23/2019 Case Study Buildings

    5/14

    5

    Case Study: Buildingswww.leonardo-energy.org

    Present situation

    In a hotel the rooms are kept at a temperature of at least 20C. If there are

    guests in the room they can adjust the temperature as they wish. The

    ventilation system is already fitted with a heat recovery system.

    Proposal

    By using an energy management system the temperature in the rooms can be

    controlled separately.

    If a room is unoccupied the temperature can be set lower than the present 20

    C. In the winter a minimum of 16C is enough, and by having a minimum of 18

    C in summer no cooling is necessary, only heating. There is a difference in

    temperature between winter and summer because the comfort temperature is

    different.

    Note that the temperatures chosen depend on the thermal inertia of the

    building. If the building has high inertia it is better to set the temperature higher,

    because people will set the heating very high when they come in and not turn it

    down again, as the walls take a long time to warm up. Conversely, if the inertia

    is low then the temperature can also be set lower.

    Savings and investment

    The simulation software used for this calculation determines the amount of heat

    required in terms of degree-hours. A degree-hour represents the difference

    between the actual temperature and the reference temperature, summed per

    hour over a certain period. For instance, if the reference temperature is 15C,

    the software calculates how many hours the average outside temperature was

    less than 15C during the time intervals concerned. If the average outside

    temperature is 13C for one hour and 14C for another hour, then there are 3

    degree-hours during this two-hour period. This information can be used to

    calculate the amount of heating required.

    By comparing the old and new situations and comparing them with one

    another, it is possible to see how much heat was being wasted in the old

    situation.

    If these data are multiplied by the boiler efficiency and the efficiency of the heat

    recovery system, we obtain the ultimate saving. The price of the energy

    management system is not taken into account in the calculation, since prices

    vary greatly according to the number of measuring points, the regulation

    functions, read-outs etc.

  • 7/23/2019 Case Study Buildings

    6/14

    6

    Energy Efficiencywww.leonardo-energy.org

    Table 2: Calculated values and the savings achieved using an energy

    management system

    Other utilities connected to the energy management system:

    outside lighting

    corridor lighting (set to 50% at night)

    ventilation system in conference rooms and restaurant

    lobby lighting

    etc.

    N of rooms 146

    Occupancy 61%

    Efficiency of heat recovery system 50%

    Present situation:

    Zero occupancy 20CConsumption 1714 kWh

    Proposal:

    Zero occupancy

    Winter (November to March) 16 C

    Summer (April to October) 18 C

    Consumption

    Winter 763 kWh

    Summer 451 kWh

    Total consumption 1213 kWh

    Saving:

    1 room empty all year round 501 kWh

    All rooms, actual occupancy 29091 kWh

    727 /yearr

  • 7/23/2019 Case Study Buildings

    7/14

    7

    Case Study: Buildingswww.leonardo-energy.org

    Thermal bridges

    Introduction

    A cold bridge is formed where a material used in part of an outside wall has better heat conduction than

    the wall itself, if there is no additional insulation around it.

    Thermal bridges are a frequent problem in buildings, allowing heat to escape in winter and to enter in

    summer, so that more energy has to be used for heating and cooling respectively.

    The best way to deal with thermal bridges is avoid them during construction of the building in the first place.

    In existing buildings they can be eliminated by fitting additional insulation. However, the insulation must be

    properly fitted and must include vapour-proof flashing.

    Thermal bridges can be detected using thermal imaging.

    In the case study considered here, the thermal bridges are load-bearing beams that are not insulated.

    Present situation

    In the walls of the building there are 35 metal beams that are not insulated, forming thermal bridges with all

    the attendant energy losses. They were detected using thermal imaging.

    Fig. 1: A cold bridge

  • 7/23/2019 Case Study Buildings

    8/14

    8

    Energy Efficiencywww.leonardo-energy.org

    Fig. 2: A cold bridge made visible by IR thermal imaging

    Proposal

    Thermal bridges can best be eliminated at the design stage of the building, as

    prevention is better than cure.

    However, if they are detected at a later stage then they should be insulated as

    best possible.

    In order to fulfil the requirements of vapour proof flashing, the metal beams

    were insulated with rolls of polyurethane (PU) covered with a thin layer of

    aluminium on the outside.

    Savings and investment

    By definition, a cold bridge has a very high U value (heat transfer coefficient):

    the higher the U value, the greater the heat losses. The U value depends on

    the thickness of the part and the material of which is made. The aim of fitting

    extra insulation is to make the U value as low as possible. In this case the U

    value of the beams was reduced from 5.87 to 0.6 W/m.K.

    The difference in the U value is multiplied by the difference between the

    average inside and outside temperature and the operating hours of the heating

    system. By taking into account the efficiency of the heating system and the

    cross-sectional area of the beam, the annual saving can be calculated.

  • 7/23/2019 Case Study Buildings

    9/14

    9

    Case Study: Buildingswww.leonardo-energy.org

    Table 3: Calculation of the savings achieved by eliminating thermal bridges

    Heat transfer coefficient (U) of the beam with-out insulation 5.87 [W/(mxK)]

    Heat transfer coefficient (U) of the beam withinsulation 0.6 [W/(mxK)]

    Inside temperature during the day 18C

    Efficiency of the heating system 58%

    Operating hours 5800hours

    Annual energy saving (per m of insulatedbeam) 316kWh/year

    Area to be insulated 43.89m(0.33m x 3.8m x35 pieces)

    Annual energy saving 13.9MWh/year

    Fuel: fuel oil

    Energy price: 0.6/litre

    Annual saving in energy costs (per m ofinsulated beam) 18.96

    Annual financial saving 832.15

    Cost of the insulation work 5.08/m(36.58/(12m*0.6m))

    Payback period 0.3years

  • 7/23/2019 Case Study Buildings

    10/14

    10

    Energy Efficiencywww.leonardo-energy.org

    Ventilation

    Introduction

    New buildings nowadays are designed to be as airtight and well-insulated as

    possible, but it is still important for the building to be properly ventilated. The

    ventilation can be controlled by making the building airtight and installing a

    good ventilation system. This makes it possible to ensure not too much or too

    little ventilation, and avoids wasting energy by having to cool the air too much.

    Older ventilation systems are frequently overdimensioned, and so it can help to

    retrofit them with a frequency regulator combined with CO2 sensors. The

    sensors make it possible to maintain good air quality without supplying too

    much fresh air. However, such retrofitting is not always possible and in some

    cases can also be very expensive. One alternative is to recirculate the excess

    amount of air extracted, as the extraction air does not have to be heated up so

    much with respect to the fresh outside air drawn in, or even does not have to be

    heated at all. The aim in this case is to recirculate as much air as possible.

    Present situation

    The ventilation system in this case is a ventilation group with a mixer section,

    set to a fixed minimum amount of fresh air (20%). This applies to all operating

    times, despite being set to the minimum.

    Fig. 3: The ventilation group

    Proposal

    The aim was to limit consumption outside office hours. This was achieved by

    reducing the amount of fresh air drawn in (so that less cold air has to be

  • 7/23/2019 Case Study Buildings

    11/14

    11

    Case Study: Buildingswww.leonardo-energy.org

    warmed up), and by lowering the temperature at which air is blown in.

    It was not technically feasible to fit frequency regulation without replacing a

    large part of the ventilation group. It was therefore decided to adjust the mixing

    register more accurately, so that more air was recirculated and thus less air had

    to be heated up.

    The proportion of fresh air was reduced to 10% during the hours when there is

    nobody in the offices, and the temperature was lowered to 18C.

    Savings and investment

    Table 4: Calculation of the savings achieved by readjusting the ventilation

    system

    In this case also the calculation is based on the degree-hour method.

    For a ventilation group with a flow rate of 10,000 m/h this can yield a gas

    saving of 24.6 MWh if the minimum air settings are reduced to 10% and 18C

    during office hours. This represents an annual saving of 615. The onlyinvestment is the labour cost necessary to adjust the settings.

    Heating

    Energy consumption ofair processing Former situation New situation

    Operating times 0000-2400 0600-1900 1900-0600

    Air flow rate 10000 m/h 10000 m/h 10000 m/h

    Proportion of fresh air 20% 20% 10%

    Fresh air flow rate 2000 m/h 2000 m/h 1000 m/h

    Room injection tempera-ture 21 C 21 C 18 C

    Degree-hours at desiredinjection temperature 90504 C*h 46921 C*h 32248 C*h

    N of operating hours ofventilation system 8331 h 4439 h 3629 h

    Amount of energy required 81.08 MWh/year 42.03MWh/year 14.44 MWh/year

    Saving 24.60 MWh/year

  • 7/23/2019 Case Study Buildings

    12/14

    12

    Energy Efficiencywww.leonardo-energy.org

    Lighting

    Introduction

    Lighting is an item that normally has little attention paid to it, as relighting is

    seldom economically feasible (due to a large number of separate users, low

    consumption per user and low number of operating hours). Relighting is usually

    done as part of a larger project, when it is necessary to draw up a complete

    lighting plan.

    Present situation

    The office rooms (10 x 30 m on five floors) in this case study have 150 lighting

    units (30 per floor), each with two fluorescent tubes of 36 W. The units are fitted

    with an electromagnetic ballast and have white reflectors, which however have

    become dulled over the course of the years. The units are attached to the

    system ceiling in three rows.

    Fig. 4: Schematic representation of one floor

    30m

    10m

    One floor

    WINDO

    WOS

    Lighting units

  • 7/23/2019 Case Study Buildings

    13/14

    13

    Case Study: Buildingswww.leonardo-energy.org

    Proposal

    Initial energy savings were obtained by fitting new lighting units (at the same

    points) with an electronic ballast instead of an electromagnetic one. Further

    savings were achieved by the new units having more efficient mirror optics, so

    reflecting the light better. This enabled a lower lighting power to be used.

    Yet more energy savings were obtained by regulating the lighting level

    according to the amount of natural light. At times when there is a lot of daylight

    the lights nearest to the window are switched off entirely, while the ones in the

    middle operate at a lower level.

    Savings and investment

    Data:

    The lights burn from Monday to Friday, 0600 to 1900, 52 weeks per year. The

    number of operating hours is therefore 3380 hours per year.

    There are 150 lighting units, each with two fluorescent tubes.

    Savings possibility 1:

    In the current situation the energy consumption per lighting unit is 86.4 W (sum

    of the two tubes plus the starter losses), giving a consumption of 43.8 MWh per

    year.

    The energy saving in the new situation is obtained by using electronic ballasts

    whose energy loss is practically nil (1 or 2% of the total consumption). In

    addition, more efficient mirror optics enable the consumption to be lowered to

    32.3 MWh per year.

    Savings possibility 2:

    The electronic ballasts afford the possibility of dimming the lights, and with a

    simple extension they can be regulated according to the amount of natural light,

    so that the lighting units do not have to operate constantly at full power.

    It is assumed that the lights nearest the windows will operate at 100% for 3

    hours per day. The ones in the middle row will operate at 50% for 10 hours per

    day and at 100% for 3 hours, while the ones farthest from the window will

    operate constantly at 100%.

    The installed capacity of the new lighting units (and ballasts) is 9577 W.

    1/3 operating constantly: 10.8 MWh

    1/3 operating for 10 hours at 50% and 3 hours at 100%: 6.6 MWh

    1/3 operating only 3 hours per day: 2.5 MWh

  • 7/23/2019 Case Study Buildings

    14/14

    14

    Energy Efficiencywww.leonardo-energy.org

    Total consumption: 19.9 MWh

    The additional saving is 12.5 MWh.

    Investments:

    Savings possibility 1 costs 75 per lighting unit (total: 11,250), while

    possibility 2 costs 20 per unit ( 3,000).

    Summary:

    Table 5: Calculation of the savings achieved by lighting modifications

    Here it should be noted that possibility 2 is not independent of possibility 1,

    since only electronic ballasts can be dimmed.

    Consump-tion Saving

    Cumulativesaving

    Invest-ment

    Cumulativeinvestment

    Paybacktime

    Cumulativepayback

    Present 44 MWh

    Saving 1 32 MWh 26% 26% 11250 11250 13.2 13.2 years

    Saving 2 20 MWh 39% 55% 3000 14250 3.2 7.9 years