Case for Solar Rooftop in Indonesia V. 12 Jan...
-
Upload
phamkhuong -
Category
Documents
-
view
214 -
download
0
Transcript of Case for Solar Rooftop in Indonesia V. 12 Jan...
SOLAR ROOFTOPSOLAR ROOFTOP
CASE FOR INDONESIA
Centre for Science and Environment
New Delhi, India
Table of Contents
• Solar Rooftop/Decentralised Systems for Indonesia
• Indian Solar Sector
• Falling Prices of Solar Energy• Falling Prices of Solar Energy
• Increasing Electricity Tariffs
• Dependency on DG Sets
• Reduce Burden on the Grid
• Other Renewable Energy Options
• Conclusion
SOLAR ROOFTOP/DECENTRALISED
SYSTEMS FOR INDONESIA
Solar systems or decentralized solar systems makes
sense for Indonesia for a variety of reason
▫ Solar is becoming one of the cheapest source of power
▫ Respite for customers from increasing electricity tariffs▫ Respite for customers from increasing electricity tariffs
▫ Reduce dependency on diesel at times of power cuts
and for remote villages
▫ Increase access in remote villages
▫ Reduce burden on the grid
▫ Climate change reasons
PRESENT POWER SCENARIO
Renewable Energy, 18.18%
Gas, 8.19%
Diesel, 0.30%
Nuclear, 2.05%
Hydro, 13.59%
Solar –25.54%
Small Hydro Power - 7.21%
BioPower -13.42%
Waste to Power - 0.19%
Coal, 58.32%
India has an installed capacity of 330,860 MW of power
generation, out of which 60,157 MW is of renewable energy.
Per capita consumption of India 1,075 kWh in 2015-16
Renewable Energy
Wind –53.64%
• Launched in 2010
• Set the target of installing 20,000 MW of grid
connected and 2,000 MW of off-grid solar power by
NATIONAL SOLAR MISSION
connected and 2,000 MW of off-grid solar power by
2022
• Now the target has been increased to 100,000 MW
of solar power by 2022
SOLAR POWER IN INDIA
2 2 9 32 481 1,686 2,647
3,744
6,763
12,289 14,751
-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000
• Initial Stage: Feed-in Tariffs were provided since the cost of solar was high, developers needed financial support
• Reverse bidding has resulted in reducing cost of solar so much that now benchmark tariffs are not needed. There is no financial support – not even available subsidies – viability gap funding are being used.
-
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18 (October
2017)
JNNSM Phase I (2010)
CERC Benchmark Tariff
Lowest Tariff Quoted
Average Tariff Quoted
INR/kWh INR/kWh INR/kWh
CSP 15.31 10.49 11.48
SOLAR: REDUCTION IN TARIFF
Batch ICSP 15.31 10.49 11.48
SPV 17.81 10.85 12.16
Batch II SPV 15.39 7.49 8.77
From Rs 10.49 being quoted in 2010, the lowest bid was of Rs 2.44 per unit was quoted in auctions for Bhadla Solar Park won by ACME Solar in May 2017.
SOLAR: REDUCTION IN TARIFF
5.08 4.94 4.82 4.78 4.69 4.41 4.34
3.25
2.62 2.44
3.47
200
400
600
800
1000
1200
1400
1600
1.00
2.00
3.00
4.00
5.00
6.00 Capacity Lowest Bid
• In the last two years, the price of solar has halved and now has achieved grid parity in Indian market. This is because of the 1. Reducing costs due to sharp fall in Chinese module prices2. Massive economies of scale brought in by 10 GW of auctions3. Risk mitigation by protecting developers from discoms’ failure to pay
0
200
-
Jharkhand, 2016
UP -SECI, 2016
Gujarat -SECI, 2016
Karnataka -SECI, 2016
Chhattisgarh -SECI, 2016
UP -NTPC, 2016
Karnataka -NSM, 2016
AP -SECI, 2016
Karnataka, 2016
Telangana -NSM, 2016
Maharashtra -SECI, 2016
Rajasthan -NTPC, 2016
Rajasthan -NTPC, 2016
Madhya Pradesh -
SECI, 2017
AP -SECI, 2017
Rajasthan -Bhadla
IV, NSM, 2017
Rajasthan -Bhadla
III, NSM, 2017
Tamil Nadu, 2017
1,690
1,442
1,000 1,000
1,200
1,400
1,600
1,800
Capital Costs (In lakhs per MW)
SOLAR: REDUCTION IN COSTS
800 691
587 531
-
200
400
600
800
1,000
2010-11 2011-12 2012 -13 2013-14 2014-15 2015-16 2016-17
The capital costs have fallen by over 70% in the last 7 years and the oversupply in the global markets on account of Chinese manufacturers are the major reason for it.
Solar Park to bring in
economies of scale
Manufacturing Support
Transmission support
• Rs 970 crores as capital subsidy
• SECI enhancing the local
• Solar parks were developed with government support to helps in land acquisition for the developers.
• “Must Run” status for solar plants
• Net metering policy for grid connected solar rooftop plants
• Green corridors reduces
SUPPORT MECHANISM FOR SOLAR
Support for Solar
Solar Purchase Obligation
Reducing investment in
coal
Exemptions & Other Incentives
the local manufacturing industry by creating demand for them
reducesevacuations
• No charges on open access
CEA has said that there is no need for enhancing coal capacity in the near future apart from the ones in pipeline.
• Excise & Custom duty exemptions for most of the Equipment, Machinery etc
• 10 year tax holiday
• Favourable global costs trends helped all countries including India
• Government ambitions has resulted in flood of investment, further reducing the costs because of economies of scale
• Policies that have been critical for the development of RE sector
• Grid integration is not a challenge up to a significant share of
LEARNINGS FROM INDIA
• Grid integration is not a challenge up to a significant share of renewable energy
• Distributed generation could be a valuable tool to address energy access and deal with cuts in urban areas
• Other benefits:
▫ Reduced need for polluting coal power plants for which finances are harder to acquire
▫ Distributed generation may help in reforming discoms which supply subsidized electricity
SOLAR’S TIME IN THE SUN
Costs in India and China are at USD 0.65 per Watt-peak and USD 0.80 per
Watt-peak, lowest as it has ever been. It is expected to stabilize below USD
0.50 per Watt-peak.
FALLING PRICES ACROSS THE GLOBE
0.050
0.020
0.070
0.050
0.080
0.080
0.110
0.090
0.110
0.120
India
Mexico2014 2015 2016 2017
0.400
0.070
0.060
0.049
0.080
0.140
0.220
0.069
0.085
0.178
0.250
0.080
0.096
0.180
0.300
0.090
- 0.050 0.100 0.150 0.200 0.250 0.300 0.350
China
USA
Japan
Germany
USD/KWh
SOLAR ROOFTOP COSTS IN INDONESIA
(as estimated in 2014)
4,000
5,000
6,000
USD/KW
-
1,000
2,000
3,000
4,000
2015 2020 2030 2040 2050
Source: IEA, 2014
USD/KW
1300
1500
1700
1900
USD/KW
CAPITAL COSTS IN INDONESIA
(as estimated in 2017)
Source: Mott McDonald, 2017
500
700
900
1100
1300
Indonesia Thailand Phillipines Malaysia Myanmar India
USD/KW
In 3 years, the estimates have fallen from USD 1800-4800 per watt-peak have fallen to USD 1100-1700 per watt-peak.
0.10
0.12
0.14
USD/KW
LCOE IN INDONESIA
(as estimated in 2017)
Source: Mott McDonald, 2017
-
0.02
0.04
0.06
0.08
Indonesia Thailand Phillipines Malaysia Myanmar India
USD/KW
ELECTRICITY PRICES IN INDONESIA
Categories of Customers Electricity Tariffs Range (USD/kWh)
Special Category – Subsidized 0.01 – 0.08
Residential 0.01 – 0.10
Business 0.02 – 0.10
Industrial 0.01 – 0.09
Government 0.04 – 0.10
Consumers paying higher tariffs than the generation cost of electricity of rooftop systems more than 0.06 per unit
• Although subsidised, S-2 and S-3 category consumers• Customers with a connection of more than 900 V-RTM under R-1, R2 and R3
• B-1 with capacity of 1300 VA and higher, B-2, B-3 category of consumers • Categories higher than I-1 1300 VA capacity • P-1 with capacity of 1300 VA and higher, P-2, P-3 category of consumers
INCREASING TARIFFS
• Stages of subsidy withdrawal under President Joko Widodo
▫ Stage I – 2014
� Cut 280 trillion rupiah (USD 24 billion) subsidy bill by increasing tariffs for its top electricity consumers by 10-11% for all consumers and 5.5% for government and households
▫ Stage II – 2016▫ Stage II – 2016
� Fall of subsidies to IDR 59.23 trillion in 2016
▫ Stage III – 2017
� Subsidy for 900-VA customers would be gradually revoked starting from January to May 2017
• Only 4.3 million 900-VA and 450-VA customers would be eligible for cheap electricity and receive government subsidies
POWER QUALITY & OUTAGES IN CITIES
• According to news reports, major cities in Indonesia like
Bandung, Surabaya, Medan, Semarang etc. are facing
problems with both quality power and outages
• Asian Development Bank (ADB) report quotes power
outages as one of the most important factors inoutages as one of the most important factors in
hindering business operations in Indonesia
• Among foreign investors, the Japanese companies
complained about power shortages.
• Power voltage levels were fairly low throughout the 25
locations monitored through the WRI-Prayas initiative
SOLAR FOR THE ACCESS IN REMOTE ISLANDS
• Based on this analysis, changes in population density account for only 18%
of the differences in electrification ratios.
• Electrification is a factor of the costs and difficulty of connecting rural areas
instead of population density
• Solar can provide electricity to remote islands
• Electrification in the
▫ Western part of the country as high as 99.98% (DKI Jakarta)
▫ Eastern part of the country as low as 47.8% (Papua)
• More than nine hundred permanently inhabited
ACCESS IN REMOTE ISLANDS-I
• More than nine hundred permanently inhabited Islands
▫ The non-availability of quality power can have severe spillover effects.
▫ Facing problems in business investment
▫ Logistical challenge for maintaining a reliable electricity grid supply
ACCESS IN REMOTE ISLANDS-II
• Electricity access is a matter of both policy and settlement patterns.
• In Indonesia, around 20% variation in electrification ratios is seen among the provinces. seen among the provinces.
• Both Funding from various schemes and geographical/settlement patterns determine the level of electrification and quality of power supplied.
• Still around 12-14 % of population has limited or no access to grid based electricity.
• Research shows that the last 10% of electrification is very costly.
• In this context solar power and other renewables can play an important role.
DEPENDENCY ON DG-SETS
• Power interruptions prompted to rely on private
generators
• Seeking services of a ‘Floating Power Plant (based on
diesel)’ from Turkeydiesel)’ from Turkey
• As per the CSE analysis, a diesel gen-set with efficiency in
the range of 0.3-0.6 liters/kWh and with average diesel
price of USD 0.68 per liter (current price in
Indonesia), would generate electricity at the cost of USD
0.2 to USD 0.4 per kWh.
• Electricity procurement prices in remote villages is as
high as USD 0.18 per kWh.
REGIONAL POWER GENERATION COSTSElectricity generation costs in Indonesia varies from USD 0.065 to USD 0.175 per
unit. The prices are higher in remote villages.
9.2810.14 10.210.398
12.1712.4312.7513.5413.6613.68
17.3217.52
12
14
16
18
20
6.51 6.51 6.51 6.52 6.54 6.627.77 7.86 8.07 8.1
9.01 9.2810.14 10.210.398
0
2
4
6
8
10
An ADB study with geospatial electrification planning for the island of Sumba in Nusa Tenggara Timur found that it would be less costly to use renewable off-grid technologies rather than grid extension to serve some 30% of the households remaining to be electrified.
INCREASE IN ELECTRICITY REQUIREMENT
5256
51
62
7583
300
350
400
450
500Sumatra Eastern Indonesia Java-Bali 457
Electricity demand is projected to increase two and half times in the next 10 years
151 162197
228261
298 31821 23
6036
44
52
2932
41 51
0
50
100
150
200
250
300
2015 2016 2018 2020 2022 2024 2025
200
• National average cost of generation in Indonesia is as
high as USD 0.18 per kWh in East Nusa Tenggara (NTT)
and Maluku.
• Cost of solar power procurement should encourage PLN
SOLAR SYSTEMS CAN HELP PLN
• Cost of solar power procurement should encourage PLN
to promote solar especially in remote islands and their
villages
• Help manage demand and reduce dependency on grid
• Beneficial for consumers who are paying tariffs more
than USD 0.06 per unit
• Help source the increasing demand through solar instead
of depending on fossil fuels
WHERE ALL OTHER RENEWABLE OPTIONS
CAN BE ADOPTED IN INDONESIA?
Type of Energy Option Potential Area of Application
Wind Areas with high wind intensity
Biomass Rural and agriculture
Tidal 54,720 Kms of coastlineTidal 54,720 Kms of coastline
Hybrid systems (like solar-wind, tidal-wind, floating solar etc.)
For Floating Solar PlantsIndonesia has around 93,000 square kilometers of inland seas (straits, bays, and other bodies of water). When 1 sqkms can have 100 MW, then even 0.1 % of this 93,000 sqkms can give around 9.3 GW
CHALLENGES WITH THESE OPTIONS
• Testing of solar and other renewable options as a viable business models on pilot project basis
• Development of regulatory models for governance of • Development of regulatory models for governance of these renewable energy options.
• Forecasting and grid integration of intermittent renewable power although not a challenge for 25 per cent RE share
• Addressing issues like tariff, subsidy, grid integration etc. to sustain a conducive ecosystem for these technologies.
POLICY GAPS
• Indonesia, today lacks ambition for renewable energy especially solar
that can pool demand and attract investment.
• Focus still lies in fossil fuels – when the country can take advantage of
lowered costs of solar for both access and power cuts
• Another important aspect for enhancing investment in the sector is the • Another important aspect for enhancing investment in the sector is the
supporting mechanism
▫ The regulatory framework including FiT should be supporting the development
of RE instead of acting as disincentive which it currently is.
▫ High taxes on auxiliary equipment - (aluminum frame, ethylene vinyl acetate
film, back sheet, junction box, silver solder ribbon and sealant etc) are taxed in
range of 13 to 20 per cent.
▫ Mandatory high domestic content requirement (25.63 per cent on goods
sourced, 100 per cent on services and 43.85 per cent on both combined)