CAPER Battery Energy Bhargav Patel Kongmeeng Her Storage ...
Transcript of CAPER Battery Energy Bhargav Patel Kongmeeng Her Storage ...
1
CAPER Battery Energy Storage System (BESS)
• At Distribution Level • Our Design Approach •
TEAM MEMBERS : Johnson Ngocorai Alaa Aldalooj Bhargav Patel Kongmeeng Her Lawrence Cole (Project Lead)
Project Mentors : Nabila BouSaba (Advisor) Dr. Sukumar Kamalasadan (Faculty Mentor) Lee Easter (Technical Advisor) Project Sponsor : Sherif Abdelrazek, Ph.D.
2
Table of Contents
01 Objective and Scope
03 Optimal Placement of DER 02 Long Term Dynamics
04 Analysis
05 Future Plan
06 Conclusion
3
Objective and Scope
SCOPE :
❖ Complete review of available distribution BESS chemistries and technologies for optimal technology selection
❖ Model BESS and PV system in CYME ❖ Evaluate performance of selected BESS ❖ Analyze the circuit efficiency with and without the BESS and PV system ❖ Find optimal location of BESS and PV system on the feeder
OBJECTIVE :
Design and find the optimum location for a 1 MW (2 MWh) BESS with 2 MW Solar facility within the feeder such that the value from the new Distributed Energy Resources is maximized.
4
Battery Chemistries
5
Battery Chemistries
6
01 Objective and Scope
03 Optimal Placement of DER 02 Long Term Dynamics
04 Analysis
05 Future Plan
06 Conclusion
Table of Contents
7
Model Structure and Devices Locations
8
LTD Simulations for Various Combinations of Feeder Load and PV Active Power Profiles
● Heavy and light load profiles
● Clear and intermittent PV power profiles
● Find the most vulnerable locations as it pertains to over/under voltage
● Study aims to use outcomes as guidance in DER and BESS placement criterion
PV_ClearDay_1Day
PV_IntermittentDay_1
Day
PV_Real_Measurements_FullYear
Light_Load_1Day
Heavy_Load_1Day
Real_Measurements_Load_Full
Year
9
LTD Results - Four Combinations - One Day Data Type
PV Load
C1 Clear-1Day Heavy-1Day
C2 Clear-1Day Light-1Day
C3 Intermittent-1Day Heavy-1Day
C4 Intermittent-1Day Light-1Day
10
Long Term Dynamics Results (Feeder Voltage Profiles)
● No voltage violation throughout C1 through C4.
● Voltage drops more in case-1 and case-3 as Heavy Loads were used in both cases.
11
Long Term Dynamics Results (Regulators Taps Operations)
12
Long Term Dynamics Results C5 to C9 (Feeder Voltage Profile)
● Voltage profiles are within allowable limits.
● Voltage regulators are tapping accordingly for all loads types provided.
PV Load
C5 Clear-Full Year Real-Full Year
C6 Intermittent-Full Year Real-Full Year
C7 Real-Full Year Real-Full Year
C8 Real-Full Year Light-Full Year
C9 Real-Full Year Heavy-Full Year
13
Long Term Dynamics Results C5 to C9 (Feeder Voltage Profile)
OLTC LReg1 LReg2 Total number of Taps
Case Taps-A Taps-B Taps-C Taps-A Taps-B Taps-C Taps-A Taps-B Taps-C
Case-5 1065 858 960 2260 1192 2025 2297 1260 1994 13911
Case-6 698 424 513 2091 705 1808 1894 681 1581 10395
Case-7 681 462 578 2021 687 1703 1836 653 1609 10230
Case-8 431 327 223 469 282 133 448 255 760 3328
Case-9 146 153 89 3070 489 2491 2613 679 1879 11609
14
01
03 Optimal Placement of DER 02 Long Term Dynamics
04 Analysis
05 Future Plan
06 Conclusion
Table of Contents
Objective and Scope
15
DER Optimal Placement Criterion
Key Factors ●Feeder’s furthest locations have voltage vulnerability ●Taps operations minimization ●Line losses reduction ●PCC over voltage due to reverse power flow ●Facility placed at the n number of tentative locations. ●Voltage Deviation Index (VDI) is calculated as follows:
16
Tentative Locations for New DER Placement Criterion
System OLTC and line regulators
Shunt Capacitor
17
01
03 Optimal Placement of DER 02 Long Term Dynamics
04 Analysis
05 Future Plan
06 Conclusion
Table of Contents
Objective and Scope
18
Long Term Dynamics for 7 locations - C1 -Voltage Profiles
Voltage Deviation Index (VDI)
PCC2-Index PCC1 PCC2 Location-2
PCC2-1 0.0328 0.0423 0.0281
PCC2-2 0.0333 0.035 0.0426 PCC2-3 0.0327 0.042 0.0281
PCC2-4 0.0297 0.0358 0.0287 PCC2-5 0.0333 0.0344 0.037
PCC2-6 0.0333 0.0327 0.0403 PCC2-7 0.0333 0.049 0.0491
19
Long Term Dynamics for 7 locations - C1 -Voltage Profiles
OLTC LReg1 LReg2 Total Taps operations
Losses (kWh) PCC2-
Index Taps-A Taps-B Taps-C Taps-A Taps-B Taps-C Taps-A Taps-B Taps-C
PCC2-1 4 3 4 20 12 18 16 6 11 94 209
PCC2-2 4 3 4 20 6 16 14 8 11 86 204
PCC2-3 4 3 4 20 12 18 16 6 11 94 206
PCC2-4 4 3 4 20 12 18 16 6 11 94 209
PCC2-5 4 3 4 20 6 11 14 8 11 81 204
PCC2-6 4 3 4 20 6 16 14 8 11 86 204
PCC2-7 4 3 4 20 6 16 14 8 11 86 212
20
Long Term Dynamics for 7 locations - C5 -Voltage Profiles
● Minimal VDI was achieved by placing DER in PCC2-2, PCC2-5, and PCC2-6
21
Long Term Dynamics for 7 locations - C5 - Taps Operations & Power Losses
OLTC LReg1 LReg2 Total Taps operations
Losses (MWh)
PCC2-Index
Taps-A
Taps-B
Taps-C
Taps-A
Taps-B
Taps-C
Taps-A
Taps-B
Taps-C
PCC2-1 1862 1569 1637 3507 2685 3420 2821 2086 2525 22112 587
PCC2-2 1864 1575 1639 2605 1680 2364 3187 2436 2994 20344 558
PCC2-3 1862 1569 1637 3499 2679 3416 2819 2086 2527 22094 587
PCC2-4 1858 1563 1629 3485 2663 3416 2815 2078 2525 22032 616
PCC2-5 1860 1569 1631 2601 1680 2364 3195 2416 2988 20304 593
PCC2-6 1860 1569 1633 2601 1680 2362 3193 2412 2988 20298 588
PCC2-7 1842 1559 1627 2589 1668 2360 3179 2398 2978 20200 643
● There is a trade-off between optimal location as far as different evaluation indexes are concerned.
● Throughout the whole year, minimal losses are achieved when DER is placed at PCC2-2, PCC2-5 and PCC2-6.
22
Probable Value Streams
Line Loss Reduction
Regulator Tap Operations Reduction
Voltage Profile Improvement
Energy Time Shift
Solar Hosting Capacity Increase
Probable Value
Streams
23
Long Term Dynamics for 7 locations - C7 - Taps Operations & Power Losses
● Minimum line losses occur when the PV facility is placed at PCC2-2 ● PCC2-5 and PCC2-6 are next best locations to place DER
24
Taps Operations and Power Losses Cost Savings
Taps
($0.07/tap) Line Losses
($0.10/kWh) Total Cost
PCC2-1 $1223 $48,541 $49,764
PCC2-2 $1160 $46,682 $47,841
PCC2-3 $1223 $48,410 $49,633
PCC2-4 $1220 $50,162 $51,381
PCC2-5 $1158 $48,681 $49,839
PCC2-6 $1159 $48,373 $49,532
PCC2-7 $1469 $59,297 $60,766
● The taps cost are calculated from the total taps in one year multiplied by the cost per tap
● Calculation results for the line loss cost is from the total line losses in one year multiplied by the cost per kWh
● As seen PCC2-2 would cost the least as it saves the most on line losses
25
01 Objective and Scope
03 Optimal Placement of DER 02 Long Term Dynamics
04 Analysis
05 Future Plan
06 Conclusion
Table of Contents
26
Future Plan
11-09-2017 CAPER
Conference
11-11-2017 Add BESS and
evaluate its performance at
the selected location
11-13-2017 Work on the Python script to ensure BESS performs
as desired
11-17-2017 Test the BESS and PV system
at all 7 locations to confirm the
optimal location
11-23-2017 Gather all
results and analyze and fix
any other issues
11-30-2017 Work on the
documentation and initial
report
12-3-2017 Create a Final
report with changes from the initial one
12/8/2017 Poster
Presentation and Prototype Demonstration
(EXPO) Preparation
12/9/2017 Final Report
and Comprehensive
Document Submission
27
Conclusion
● An iterative criterion is implemented to select optimal place for an additional 2 MW PV facility (DER-2).
● It is more valuable to add DER at the downstream part of line regulator-2 as far as all evaluation indexes are concerned.
● Base on the monetary values, line loss reduction is the most valuable index, PCC2-2 should be considered as an optimal location for DER.
28
Acknowledgements
This work is supported by CAPER and DUKE ENERGY
● UNCC CAPER 1 senior design team would like to acknowledge our sponsor, Duke Energy, and CAPER along with EPIC for their guidance throughout this project.
● A special thanks and acknowledgment to Muhammad Ahmed (Graduate Research Assistant) for his help with the CYME simulation software and giving constructive feedback.
29
Thank You! Any Questions?