Blue Grass Chemical Agent-Destruction Pilot Plant Systems Contractor Update June 13, 2012
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, 2013 Version2
-
Upload
program-executive-office-assembled-chemical-weapons-alternatives-peo-acwa -
Category
Documents
-
view
15 -
download
0
description
Transcript of Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, 2013 Version2
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update
June 4, 2013
Presented to:
Kentucky Chemical Demilitarization Citizens’ Advisory Commission and
Chemical Destruction Community Advisory Board
Presented by:
Jeff BrubakerSite Project Manager
A Partnership for Safe Chemical Weapons Destruction
Organisation for the Prohibition of Chemical Weapons Treaty Council Visit
Blue Grass Chemical Agent-Destruction Pilot Plant Update
2
The Organisation for the Prohibition of Chemical Weapons Executive Council Chair and Director General as well as contingent ambassadors from around the world visited the BGCAPP project and met with the Kentucky Chemical Demilitarization Citizens’ Advisory Commission and Chemical Destruction Community Advisory Board as part of their visit.
A Partnership for Safe Chemical Weapons Destruction
3
Northwestern Corner - Observation Point
1 2
1
3
5
2
6
Hydrolysate Storage Area
Control and Support Building
Munitions Demilitarization Building (MDB) Filter Banks
MDB
Utility Building
Supercritical Water Oxidation Building (not visible in photo)
Laboratory Building (not visible in photo)
7 65
4
3
7
4
Blue Grass Chemical Agent-Destruction Pilot Plant Construction Site (May 2013)
A Partnership for Safe Chemical Weapons Destruction
4
Blue Grass Updates
Construction now more than 68 percent complete
Systemization activities now more than 8 percent complete
Workers are installing the Munitions Washout System and rocket demilitarization equipment
Reverse Osmosis equipment has been received and is awaiting placement
Supercritical Water Oxidation equipment is slated for delivery late summer
Enclosure of the Munitions Demilitarization Building is almost complete
Construction of Hydrolysate Storage Area tanks is progressing
Project workers install the roof on the second of what will be five tanks in the Hydrolysate Storage Area. These tanks will hold the wastewater from processing, hydrolysate, before it is treated in the supercritical water oxidation process.
A Partnership for Safe Chemical Weapons Destruction
Explosive Destruction Technologies Environmental Assessment (EA)
5
Release of the EA and a draft Finding of No Significant Impact is expected toward the end of June
The release will be widely advertised and the document will be on-line, in our information repositories and at the Blue Grass Chemical Stockpile Outreach Office
Release of the EA will open a 30-day public comment period. Complete instructions on how and where to comment will be provided
During the public comment period, a public meeting will be held to further explain the EA and to respond to stakeholder questions on the document
A Partnership for Safe Chemical Weapons Destruction
6
Safety Performance
12-month rolling rate
Accidents per 200,000 job hours
Occupational Safety and Health Administration Voluntary Protection Program Star Status site
Lost-time injury rate is 88 percent lower and recordable injury rate is 31 percent lower than industry average
As of April 30, 2013 the project has worked 864,835 hours and 171 days without a lost time accident.
Occupational Safety and Health Administration Voluntary Protection Program Star Status site
Lost-time injury rate is 88 percent lower and recordable injury rate is 31 percent lower than industry average
As of April 30, 2013 the project has worked 864,835 hours and 171 days without a lost time accident.
3.9
1.5
2.68
0.18
Recordable Injuries Lost-Time Injuries
Construction IndustryBechtel Parsons
A Partnership for Safe Chemical Weapons Destruction
7
Current Staffing
Sheet-metal workers insulate ducting on top of the Munitions Demilitarization Building (top left), while electricians install lighting in the Control and Support Building.
Total project employment―1,077
Richmond, Ky.―1,063― Nonmanual―553― Craft―510― Local hires―58 percent
Other locations―14― San Diego, Calif.― Columbus, Ohio― Frederick, Md.
A Partnership for Safe Chemical Weapons Destruction
Blue Grass-Specific Equipment Update
8
Des
ign
Fabri
cation
On S
ite
Inst
alla
tion
Test
ing
Equipment Purpose
Status
- update since last meeting
A Partnership for Safe Chemical Weapons Destruction
9
Control and Support Building
Electricians stage large cable spools outside the Control and Support Building (CSB) (above) for future cable pulling activities. Inside the CSB, electricians install intricate wiring within facility control system cabinets (at right).
A Partnership for Safe Chemical Weapons Destruction
10
Munitions Demilitarization Building
Construction crews work to set the Rocket Cutting Machine and associated conveyors (above) inside the Munitions Demilitarization Building. Elsewhere inside the building, the Rocket Shear Machine (at right) has been set.
A Partnership for Safe Chemical Weapons Destruction
Munitions Demilitarization Building(continued)
11
An electrician installs components at one of two large Munitions Demilitarization Building (MDB) filter areas (above). An electrician installs cable tray and conduit inside the MDB (at right).
A Partnership for Safe Chemical Weapons Destruction
Hydrolysate Storage Area and Supercritical Water Oxidation Process Building
12
Boilermakers have erected three of five Hydrolysate Storage Area tanks (above). Construction crews install reinforcing steel for a future effluent process tank area foundation (at right) adjacent to the SCWO Building.
A Partnership for Safe Chemical Weapons Destruction
Utility Building
13
A pipefitter aligns piping inside the Utility Building boiler room (above) and elsewhere in the building air handling unit dryers (at right) have been installed.
A Partnership for Safe Chemical Weapons Destruction
Questions/Discussion
11
For more information about the Blue Grass Chemical Agent-Destruction Pilot Plant project, please contact the Blue Grass Chemical Stockpile Outreach Office at (859) 626-8944.
ECONOMIC DEVELOPMENT WORKING GROUP UPDATE
Presented by
Craig Williams, EDWG co-chair
4 June 2013
Excerpts from Phase I - Draft Job Loss Aversion
• Any attempt to plan for mitigating the effects of an anticipated economic event begins with an accurate and realistic understanding of the area’s existing workforce and economic environment.
•
• STUDY AREA DEFINITION
•
• The area specified for this study consists of the Kentucky counties of Madison and Rockcastle, known as the Richmond-Berea, KY micropolitan statistical area. Madison County is the home of the principal cities of the micro area, Richmond and Berea, as well as Boonesboro, Kirksville and Waco. In addition to its county seat of Mount Vernon, Rockcastle County includes the cities of Brodhead and Livingston.
Data Will Include
19