BIDS AND AWARDS COMMITTEE FOR THE...
Transcript of BIDS AND AWARDS COMMITTEE FOR THE...
![Page 1: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/1.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e1
BIDS AND AWARDS COMMITTEE FOR THE INTEGRATED GOVERNMENT PHILIPPINES PROJECT (BAC4IGOV)
Supplemental Bid Bulletin No. 3
Design, Supply, Delivery, Installation, Splicing, Testing Commissioning,
Operation and Maintenance of Brand New Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo)
Bid Reference No. BAC4IGOV-2015-10-050
Please be advised of the changes in the schedule of the Bid Submission and Bid Opening for this project:
ACTIVITY PREVIOUS SCHEDULE REVISED SCHEDULE
Bid Submission 06 November 2015
12 Noon 11 November 2015
12 Noon
Bid Opening 06 November 2015
3 PM 11 November 2015
1 PM
After considering the queries, clarifications, recommendations and suggestions, the BAC4IGOV hereby decides to include, revise, amend, delete and/or adapt the following provisions
Original Provision Amended Provision
Technical Specifications
Lot 1: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning,
Operation and Maintenance of Brand New Fiber Optic cable in Baguio City
E. CONTRACTORS MUST SUBMIT THE FOLLOWING DURING POST QUALIFICATION:
E. CONTRACTORS MUST PRESENT THE FOLLOWING NOT MORE THAN THREE (3) CALENDAR DAYS AFTER RECEIPT OF NOTICE FROM THE BAC4IGOV THAT THE BIDDER HAS BEEN DECLARED L/SCB.
Lot 2: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning,
Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi City
II. SCOPE OF WORK
1. Laying of FOC cables (96 and 48 cores) at Baguio approximately twenty (20) kms with Thirty Four (34) agencies to be connected.
1. Laying of FOC cables (96 and 48 cores) at LEGAZPI approximately twenty (20) kms with Thirty Four (34) agencies to be connected.
F. CONTRACTORS MUST SUBMIT THE FOLLOWING DURING POST QUALIFICATION:
F. CONTRACTORS MUST PRESENT THE FOLLOWING NOT MORE THAN THREE (3) CALENDAR DAYS AFTER RECEIPT OF NOTICE FROM
![Page 2: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/2.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e2
THE BAC4IGOV THAT THE BIDDER HAS BEEN DECLARED L/SCB.
Lot 3: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning,
Operation and Maintenance of Brand New Fiber Optic Cable in Palo Leyte
K. MAINTENANCE OF FOC NETWORK IN REGIONAL GOVERNMENT CENTER IN LEGAZPI CITY FOR TWO (2) YEARS
B. MAINTENANCE OF FOC NETWORK IN REGIONAL GOVERNMENT CENTER IN LEGAZPI CITY FOR TWO (2) YEARS
L. FIBER OPTIC CABLE SPECIFICATIONS
C. FIBER OPTIC CABLE SPECIFICATIONS
M. HANDLING AND STORAGE OF FIBER OPTIC CABLES, EQUIPMENT, FACILITIES AND MATERIALS
D. HANDLING AND STORAGE OF FIBER OPTIC CABLES, EQUIPMENT, FACILITIES AND MATERIALS
N. CONTRACTORS MUST SUBMIT THE FOLLOWING NOT MORE THAN THREE (3) DAYS AFTER THE DECLARATION OF LCB OR SCB:
E. CONTRACTORS MUST PRESENT THE FOLLOWING NOT MORE THAN THREE (3) CALENDAR DAYS AFTER RECEIPT OF NOTICE FROM THE BAC4IGOV THAT THE BIDDER HAS BEEN DECLARED L/SCB
Annex V-A Technical Bid Form page 3 of 5
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred twenty (120) calendar days from date of receipt of Notice to Proceed (NTP).
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty (180) calendar days from date of receipt of Notice to Proceed (NTP).
Annex V-B Technical Bid Form page 3 of 5
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred twenty (120) calendar days from date of receipt of Notice to Proceed (NTP).
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty (180) calendar days from date of receipt of Notice to Proceed (NTP).
Annex V-C Technical Bid Form page 3 of 5
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred twenty (120) calendar days from date of receipt of Notice to Proceed (NTP).
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty (180) calendar days from date of receipt of Notice to Proceed (NTP).
![Page 3: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/3.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e3
Lot 2:
Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi City
Revised Annex VIII-B1 Revised Detailed Financial Breakdown
Page 1 of 4
No Stipulation
ITEM Qty Utilization
Cost Total
Utilization Cost
Optical Loss Test Set (Power Meter & Light Source)
1 set
Revised Annex VIII-B1 Revised Detailed Financial Breakdown
Page 2 of 4
No Stipulation Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning of Brand New Fiber Optic Cable Network in Legazpi
ITEM Qty Unit Cost
Total Cost per
Item
Please use the following forms attached in this Supplemental Bid Bulletin:
Revised Technical Specifications as of 03 November 2015 Revised Annex V-A as of 03 November 2015 Revised Annex V-B as of 03 November 2015 Revised Annex V-C as of 03 November 2015 Revised Annex VIII-B1 as of 03 November 2015 Revised Checklist for Bidders as of 03 November 2015
For information and guidance of all concerned.
Issued this 3rd day of November 2015.
(SGD.) DENIS F. VILLORENTE Chairman, BAC4IGOV
![Page 4: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/4.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e4
Revised Technical Specifications as of 03 November 2015
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” per line number under Bidder’s Statement of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”.
LOT 1: DESIGN, SUPPLY, DELIVERY, INSTALLATION, SPLICING, TESTING
COMMISSIONING, OPERATION AND MAINTENANCE OF BRAND NEW FIBER OPTIC CABLE IN BAGUIO CITY
ITEM SPECIFICATION STATEMENT OF COMPLIANCE
A. DESIGN, SUPPLY, DELIVERY, INSTALLATION, SPLICING, TESTING, AND COMMISSIONING OF BRAND NEW FIBER OPTIC CABLE NETWORK IN REGIONAL GOVERNMENT CENTERS IN BAGUIO CITY
I. Overview
The project consists of aerial and underground installation (micro-trenching method and/or buried/conduit/directional boring), configuration, testing, and commissioning of approximately twenty eight kilometers (28 km) of fiber optic cables in Baguio City
II. Scope of Work
The Work includes the supply of engineering services, furnishing of materials, labor, supervision, tools, supplies, and performance of all operations necessary to complete the project, all in accordance with the contract documents and subject to the terms and conditions of the Contract.
The Work covers the design-and-build of the above-mentioned project particularly the following components:
a. As-build plans of all plans and drawings (network, route, termination, splicing, etc.) required by the project;
b. Aerial and underground installation (micro-trenching method and/or buried/conduit/directional boring) and appurtenances for the proposed project;
![Page 5: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/5.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e5
c. Optical Distribution Frame (ODF)/Cabinet including patch cord/pig tails, optical fiber trays, db loss/amplification and other equipment and accessories, if necessary;
d. Pole line hardware;
e. Installation of underground (micro-trenching method and/or buried/conduit/directional boring) for the backbone and aerial or underground fiber optic cable (for the distribution)
f. Splicing and termination of fiber optic cable;
g. Testing and commissioning (provisional and final
acceptance) of newly installed FOC; and
h. Restoration of all affected facilities.
Note: Scope of work for the Fiber Network will be up to the Optical Distribution Frame (ODF) only.
All connections are to be directly terminated to the user nodes using ODFs/Patch Panels.
1. Laying of FOC cables (96 and 48 cores) at Baguio approximately twenty-eight (28) kms with Forty three (43) agencies to be connected(refer to the attached Baguio FOC Network Line Diagram)
1. ICTO 2. LTFRB 3. LTO 4. NTC 5. DENR 6. NEDA 7. HLURB 8. DOLE 9. NPC 10. DEPED 11. PHILHEALTH 12. DOH 13. NFA 14. BNH BCNHS
(Correction for SBB)
15. DPWH 16. DILG 17. PAGASA 18. SUPREME
COURT 19. OCD 20. DOST 21. BES 22. CSC 23. BI 24. BIR 25. PAGIBIG 26. BWD 27. NBI 28. DOTC
29. DOT 30. UP 31. GSIS 32. DA 33. BGH 34. COMELEC 35. CHR 36. DENR CAR 37. DENR MGB 38. SSS 39. PIA 40. MES 41. RES 42. SPED 43. BCSAT
1.1. Installation of 4-ways HDPE underground micro-trenching method and/or buried/conduit/directional boring for the fiber optic cable backbone approximately ten(10) kms.
2. Termination of 96 cores FOC on PoP(Point of Presence) and 48 cores FOC on the client agencies/stations
![Page 6: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/6.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e6
3. Provide and install Optical Distribution Frame (ODF)/Cabinet including patch cord/pig tails, optical fiber trays, and accessories at all designated/target Agencies
4. Testing of new FOC
5. Commissioning
6. Restoration of all affected facilities /infrastructure
and demobilization
7. facilities /infrastructure and demobilization
III. SURVEY, ENGINEERING AND CONSTRUCTION/DESIGN
(after contract awarding before installation)
1. The Contractor is required to carry out the detailed site survey and engineering for the Optical Fiber Cable Routes to justify the installation and construction designs together with the bill of quantities (BOQ). Included in the Contractor’s BOQ is all local materials and labor. (Initial Cable Route Plan will be provided by DOST/ICT Office for reference)
2. The Contractor shall submit a detailed work plan and installation/construction design drawings to DOST/ICT Office for approval within ten (10) calendar days after receipt of Contract and prior to installation. DOST/ICT Office will check and review the design drawings accompanied by justification/verification reports, and will give their decision whether the design drawings are acceptable or not, within one (1) week time from the date of DOST/ICT Office receipt of design drawings.
3. As part of each telecommunications work order/project, detail schematic drawings shall be prepared for each fiber optic span/cable route, showing the following information:
Fiber cable data:
1. Cable manufacturer;
2. Cable size (number of fibers);
3. Cable type;
4. Cable make-up;
5. Type of fiber;
6. Transmission characteristics (dB loss/km at
given wavelength); and
7. Dispersion specification in ps/ (nm. km).
![Page 7: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/7.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e7
Other information:
1. Trunk number/cable number;
2. Span length;
3. Manhole/handhole number and duct number;
4. Major intersections and key streets;
5. Fiber cable splice points with station location;
6. Splice-to-splice cable lengths;
7. Change in cable route; and
8. budget loss link calculation.
4. Preparation of Designs Drawings
4.1. Kinds of installation Drawings
4.1.1. The Contractor shall, at his own expense, produce installation/construction designs/drawings in conformity with design principles, and are to be approved by DOST/ICT Office.
4.1.2. Preparation and Standard Size of installation/construction Designs/Drawings: The Contractor shall produce the installation/construction designs/drawing on standard size paper.
4.1.3. As noted in other sections of this TOR, The Contractor shall supply drawings in a Computer-aided design (CAD) format.
4.1.4. Geospatial data indicating the route plan including the splicing point, termination point, and ODF.
5. Reports, Specifications, Practices and Procedures
5.1. Preparation of Technical Documents
The following reports, Specifications, Practices and Procedures shall be prepared by the Contractor, called as the “Technical Documents” in this paragraph, to be approved by DOST-ICT Office. The Contractor must submit a progress report every Monday.
5.1.1. Survey report
5.1.2. Design reports.
5.1.3. Material Specifications for Optical Fiber
Cable and Duct/Trench Systems.
![Page 8: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/8.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e8
5.1.4. Installation/Construction Practices, for Optical Fiber Cable, Duct and Direct buried Systems.
5.1.5. Factory Inspection/Test Procedures.
5.1.6. Inspection and Acceptance Test Procedures, for Duct System and Optical Fiber Cable Systems.
5.1.7. Others
5.2. Number of Copies of Installation/Construction. Designs/Drawings, Reports, Specifications, Practices and Procedures (as part of requirement for payments)
The Contractor shall submit to DOST/ICT Office the specified numbers of original and of copies of the installation/construction designs/drawings and technical documents such as:
5.2.1. Softcopy, in original editable format, of all as-built plans and drawings involved in the project;
5.2.2. Design standard and application
details;
5.2.3. Survey and design reports;
5.2.4. Material Specifications
5.2.5. Installation / Construction Practices in
accordance with ITU-T Standard.
5.2.6. Factory Inspection / Test Procedures;
and
5.2.7. Inspection and Acceptance Test
Procedures
6. Construction Plan/Design
All Construction Plans/Designs shall be in accordance with DOST/ICT Office Specifications. Construction Plans/Designs are composed of:
6.1. Optical Fiber Cable Plan
6.1.1. Key Map for Optical Fiber Cable route
6.1.2. Optical Fiber Cable plan
6.1.3. Optical fiber cable arrangement and
termination on ODF frames.
6.1.4. Optical fiber cable arrangement on
Splice Closure.
6.1.5. Schematic diagram for fiber optics
![Page 9: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/9.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e9
cores assignment
6.1.6. Cable Entrance Facilities/Structural
Cabling inside the agencies
6.2. Contents of Installation/Construction drawings
for Optical Fiber Cable System.
6.2.1. Key Map for Optical Fiber Cable route.
Key map is to indicate the proposed optical fiber cable route between two nodes with latest route conditions as well as future plan along the route. Following items shall be considered:
6.2.1.1. The proposed optical fiber cable route shall be covered from end to the other end;
6.2.1.2. The road, river, railway, remarkable buildings and typical public facilities including the planned ones with each name along the junction/trunk route;
6.2.1.3. Proposed or existing location of
the nodes;
6.2.1.4. Size, type and capacity of the
proposed optical fiber cable;
6.2.1.5. Location of repeater, if
applied; and
6.2.1.6. Road side of proposed optical fiber cable route indicated by writing the road name.
7. Optical Fiber Cable Plan must include the following
specifics :
7.1. All proposed manhole/handhole and duct runs
with type, name, capacity and distances;
7.2. Assignment of duct for proposed optical fiber
cable;
7.3. Typical drawing(s) for cable arrangement in
manhole/handhole;
7.4. Splice points of optical fiber cable W/ 3 POINT
reference and GPS coordinates;
7.5. Distance between existing facilities (such as center/ edge of the Road & canal) and DOST/ICT Office proposed facilities should be reflected on engineering and as built plan.
7.6. Number and distance of micro-ducts;
![Page 10: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/10.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e10
7.7. Road side of proposed optical fiber cable
route indicated by writing the road name;
7.8. Location of cable within railroad right-of-way;
7.9. North Point; and
7.10. Should reflect the Town/Barangay
Boundaries.
8. Optical Fiber Cable arrangement and termination
This drawing shall cover terminations in the ICT room; cable runs from entrance in building and to the cable entrance point from duct/pole route.
8.1. Location and dimensions of fiber distribution
frame with 3 dimensions.
8.2. Location of termination of joint, assignment and arrangement of termination O/F cords and detailed cable runs.
8.3. Details of cable racking structure and racking
method.
8.4. Contents of Optical Fiber Cable System such as junction section, capacity of line system, attenuation loss, name of optical mode and so on.
9. Schematic diagrams for optical fiber cable core
and fiber optics covers.
This drawing shall cover all necessary factors for interfacing with transmission systems as the line system design.
10. Contents of Installation/Construction Drawings for
the Micro-Duct System
10.1. The duct systems drawings are composed of 2 kinds of drawings, and are to be combined and drawn on A-1 size paper. One is the geographic plan for roads along routes of duct system drawn to a scale of 1/1000.
10.2. The other is the longitudinal profile of vertical section along the center line of duct system routes, and is to be on a scale of 1/1000 for horizontal length and 1/100 for vertical level.
The plan drawin g shall contain:
10.2.1. Location of manhole with their names and types supported by cross-section drawings of roads for such location at a scale of 1/100;
10.2.2. Location of ducts runs with the duct
![Page 11: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/11.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e11
composition and each duct span length between adjacent 2 centers of manhole, Riser ducts or the internal wall of a cable vault;
10.2.3. Location of length of sections showing details of protective measures;
10.2.4. Location and length of duct bridges, duct attachments to bridges and boring sections supported by detailed drawings of structure; and
10.2.5. Direction of north to be indicated.
10.3. Longitudinal profile drawings shall contain:
10.3.1. Level of ground, top and bottom of duct run at each 30,’s horizontal distance, and levels of bottom and shoulder (outer side) of manhole;
10.3.2. Top and bottom levels of other underground facilities (power cable, water/sewage pipe etc.) and levels of natural or artificial features along the duct routes (river, culvert, railways, etc.); and
10.3.3. Longitudinal profile drawings shall be so arranged to have the manhole on the plan drawing.
11. The contractor is required to designate a qualified on-site engineer for proper supervision and coordination of the project. He must undergo interview with DOST/ICT Office FOC Team for verification.
12. The Contractor shall, in order to keep the design accurate and practical and at his own expense, perform the following:
12.1. When necessary, make test holes at key point of the route to avoid interference with underground facilities and/or hard – rocks as much as practically possible;
12.2. Obtain prior approval from municipalities and/or other relevant authorities/agencies, and third parties for the execution of the work.
12.3. The Contractor shall abide and comply with the terms and conditions specified in the permits obtained from said municipalities
![Page 12: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/12.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e12
and/or other relevant authorities/agencies.
ALL necessary Right of Way and Joint Pole Agreement (JPA) permits shall be secured by the Contractor in favor of the DOST – ICT Office.
All permits and fees/charges for the JPA lease, road/underground trench/duct monthly lease will be eventually shouldered by the Project once the Final Acceptance Certificate is issued by DOST/ICT Office.
All charges pertaining to permits and other fees for JPA lease and Right of Way for the duration of the contract shall be at the expense of the Contractor.
13. The Contractor must conduct due diligence and shall restudy and amend/modify the design drawings not only dependent upon the comments of DOST/ICT Office but also taking into consideration the design concept, and shall resubmit the modified design drawings to DOST/ICT Office within one (1) week after receipt of DOST/ICT Office comments for their approval.
14. In case the Contractor’s re-study of the design is incomplete, and DOST/ICT Office disapproval is repeated, then the Contractor shall be fully responsible for any delay in progress, cost of re-design etc. and DOST/ICT Office will keep the right to order the replacement of the Contractor’s engineer/management in charge of installation/construction design at the Contractor’s own expense.
15. The Contractor shall submit the combined bill of quantities for Duct System and Optical Fiber Cable System as a part of installation/construction design, and shall get approval from DOST/ICT Office and/or Consultant following the same procedures as applied to get approval for installation/construction drawings.
In case the bill of quantities for the Optical Fiber Cable System associated with the related installation/constructions drawings are within the originally contracted amount and are approved by DOST/ICT Office, then, such DOST/ICT Office approval shall be considered as commencement order for site implementation of the approved Bill
![Page 13: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/13.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e13
of Quantities.
16. The Contractor shall be responsible for his installation/construction drawings and Bill of Quantities, as a consequential obligation under the Contract to DOST/ICT Office, NGAs and LGUs, other organization/authorities concerned and also to third parties/personnel until the completion of the project.
17. The Contractor shall regard the implementation schedule as the priority requirement. In case the priority order for any section is required by DOST/ICT Office, then, the Contractor shall adjust the schedule accordingly.
17.1. The Contractor shall submit the survey schedule, in great detail for existing facilities, at least ten (10) days prior to the commencement of the survey for each section.
18. In case an agency was found to be in a different location/site than the one specified in the TOR in the detailed site survey/engineering to be done by the winning Contractor, Contractor is required to connect said agency to the Fiber Infra Network.
IV. PROJECT MILESTONES
1. Implementation Schedule
1.1. The Contractor shall submit an integrated project implementation plan for Baguio City showing the following:
1.2. Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty (180) calendar days from date of receipt of Notice to Proceed (NTP);
1.2.1. Number of work teams at any given
time;
1.2.2. Specific dates for work and quality inspection by the DOST/ICT Office team in the FOO clusters;
1.3. The Contractor shall submit integrated implementation updates every 1st day of the week (Monday) to DOST/ICT Office throughout the contractual installation/construction period from the effective date of the Contract until the completion of the Project showing the
![Page 14: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/14.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e14
following detailed milestone, and in accordance with the established schedule and priorities.
1.4. The implementation shall be accurate and
include the following considerations:
1.4.1. To ensure that the work-force is well-distributed through the contractual period taking quality control and timely progress into consideration;
1.4.2. To allow sufficient time and manpower for self-inspections/tests prior to being witnessed by DOST/ICT Office for interim inspections/tests and provisional acceptance tests;
1.4.3. To allow reasonable time for witnessing by DOST/ICT Office of interim inspections/tests considering the work sequence such as cable laying work after DOST/ICT Office has accepted completed systems;
1.4.4. To ensure the sites are properly
managed so as to ensure:
a. Coordination with NGAs, LGUs and other authorities/agencies concerned;
b. Obtaining site implementation
permits and site-entry permits;
c. Adequacy of site security
arrangements.
1.4.5. To keep sufficient time and manpower from transferring site know-how quality control, tools/formats, standard safety arrangement, first aid, etc., to the local staff and local foreman.
1.4.6. To make sure the quality/functions of domestic products fully conform to the specifications any time necessary to upgrade the same.
1.5. The Contractor shall be responsible for conforming to the integrated implementation schedules as strictly as possible after examination and approval by DOST/ICT OFFICE.
1.6. If discrepancies/ambiguities are found or
some deviation is necessary in the actual
![Page 15: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/15.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e15
implementation progress, the Contractor shall report the same to DOST/ICT Office and shall take all corrective actions/measures at Contractor’s own expense in accordance with the instructions given by DOST/ICT Office.
1.7. The initial synchronized and integrated implementation schedule specified for the project shall be submitted for DOST/ICT Office’s approval within five (5) days after the effective date of the Contract.
V. AS-BUILT DRAWINGS
1. Technical documents including the As-Built
Drawings shall be required by DOST/ICT Office.
1.1. Documents for Execution of Provisional
Acceptance Test:
1.2. For the main purpose of executing the Provisional Acceptance Test, the Vendor shall prepare the As-Built Drawings. The As-Built Drawing shall be made in a CAD format.
1.3. As-Built Drawings for Cable Networks
The following as-built drawing having the same sizes as the designs/drawings:
1.3.1. General Map to cover all of the
serving area;
1.3.2. Junction Cable Diagram for the
Network;
1.3.3. Key Map for Cable Route (each
cable section);
1.3.4. Junction Cable Duct assignment
Diagram (each cable section);
1.3.5. Detailed fiber core assignments(each cable section/splicing point);
1.3.6. Junction Cable Location Map (each
cable section);
1.3.7. Optical Fiber Cable Arrangement and Termination on the fiber distribution frame;
1.3.8. Schematic diagram for Fiber Optics
Cores Assignment; and
1.3.9. Special Design Drawing, if any.
![Page 16: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/16.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e16
VI. BILL OF QUANTITIES
1. The contractor must attach a detailed Bill of Quantities (BOQ) showing all the components required to complete the project. This may include, but not limited to:
1.1. Fiber Optic Cable (SMF., ITU –T Recommendation G.652d, NECA/FOA 301 Compliant), Closure, and Cabinet
1.2. Pole Line hardware and accessories
1.3. Poles
1.4. Underground micro-trenching method and/or buried/conduit/directional boring) for the backbone and aerial or underground fiber optic cable (for the distribution
1.5. Optical Distribution Frame (ODF)/Cabinet including patch cord/pig tails, optical fiber trays, db loss/amplification and other equipment, if necessary and accessories
1.6. Engineering, Right of Way, Permits
1.7. List of Equipment
1.8. Contingency
VII. TESTING, COMMISSIONING AND ACCEPTANCE
1. The contractor is responsible in the performance of all civil and cable network pre-test requirement but not limited to:
1.1. Fiber Optic Cable (FOC) – attenuation and all its related testing, power meter test, and grounding test and all other test that may need to perform to complete the FOC test requirements.
1.1.1. On-reel acceptance tests shall be performed on the cable to confirm the manufacturer’s tests before the installation operation begins. This will also be used to validate the fiber loss/km; at wavelength 1310nm loss shall be 0.4 db/km or less; at 1550nm shall be 0.3dB/km or less.
1.1.2. End-to-end acceptance tests (typically conducted after completion of installation and splicing and before installing terminal
![Page 17: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/17.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e17
equipment).
1.1.3. End-to-end attenuation is the amount of optical power loss between cable system connector tips. This will include the fiber and splice /connector loss in the cable system after it has been installed.
1.1.4. Splice acceptance tests (individual
splice insertion losses)
splice loss shall not be above 0.1
dB for fusion and 0.2 dB for mechanical splices; and
connectors shall have insertion
losses of 0.5 dB or less.
1.1.5. All test equipment that will be utilized for this project shall have updated calibration certificates to ensure accuracy of results. Contractor is required to submit Calibration Certificates prior to testing.
2. Link Loss Requirements
During the design stage a link loss calculation shall be prepared and included with the project proposal and design packages. The link loss budget shall include:
2.1. Total fiber attenuation (loss), not more
than 6db.
2.2. Splice loss (including pigtail splices, if
pigtails are used).
2.3. Connector loss.
2.4. The calculated dB loss cannot exceed the operating range of the terminal equipment that will be installed. Measured end-to-end loss should measure less than the calculated loss. Fibers that measure a higher loss than the link loss budget will not be accepted.
3. Contractor Performance and Workmanship
3.1. DOST/ICT Office will issue provisional and final acceptance certificate to the Contractor certifying that the scope of work has been performed and accomplished in accordance with the approved plans and specification schedules, variation orders if any, and other related contract document.
![Page 18: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/18.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e18
3.2. The contractor likewise agrees to correct any defect accruing after the final acceptance of the site facility under the project within the guarantee period. Effective duration of which shall be one (1) year commencing from the date of final acceptance by DOST/ICT Office.
B. MAINTENANCE OF FOC NETWORK IN REGIONAL
GOVERNMENT CENTER IN BAGUIO CITY FOR TWO (2) YEARS
Note: The maintenance of FOC Network will start once the project is 100% accepted.
I. SCOPE OF WORK
The work includes the following services to be rendered by the Contractor to ensure the continuous operation of the FOC Network
- Conduct daily physical inspections for the coverage
Area.
- All route covering all Agencies connected must be
inspected at least every quarter per year
- 24/7 maintenance team
- Monthly maintenance report. In case of problems encountered and restorations are being done, a separate incident report shall be accomplished.
- Restoration and replacement of damaged FOC
- Repair / restoration of ODF
- Pole replacement / relocation / straightening /
erection
- Repair of damaged duct system
- Re-tensioning and separation of FOC to powerline
- Replacement of FOC pigtail and/or patchcord at
the ODF
- Replacement of Network Equipment (Active
Equipment) and ODF
- Conduct re-tensioning of FOC
- Straightening of leaning concrete pole
- Replacement, relocation & erection of concrete
pole
- Replacement of stolen & burned FOC
- Re-labeling of pole tag
- Re-grounding
- Tree/branch-trimming, if necessary
![Page 19: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/19.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e19
- Restoration and replacement of damaged micro-
ducts
- Maintenance of a warehouse for safe keeping of
spare materials needed
- Contractor is required to secure a 24/7 on-call/standby service crew for immediate response in case of network failure.
II. RESPONSE AND REPORT TIME TARGET
Contractor considers all interruptions in service as urgent priority. Expected response and repair time are given in the table below:
Hours/Days of Coverage
Response Time
Restoration
Maximum Time to Respond
Maximum Time to UP the Network
24 x 7 x 365 Days
Monday to
Sunday 1 Hour
6 Hours from the issuance of trouble ticket
III. MANPOWER REQUIREMENTS
Personnel must be properly trained to use such equipment and do the troubleshooting and restoration and must be available on a moment’s notice.
In order to effectively maintain the FOC Network, maintenance personnel, at the minimum, must include the following:
a) One (1) Project Engineer/Coordinator
b) One(1) FOC team that consists of seven (7)
personnel
- One (1) OSP Supervisor
- Two (2) Lineman
- Two (2) Splicers/Commissioning personnel
- Two (2) Support personnel
IV. TOOLS, EQUIPMENT AND MATERIAL REQUIREMENTS
As part of the activity, the following equipment, facilities, tools and materials must be available at all times.
1. List of Tools and Equipment
Contractor must have the following tools and equipment to do the preventive maintenance and restoration activities in the duration of the contract but not to be delivered to ICTO.
![Page 20: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/20.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e20
# Quantity Unit
Description
1 1 set Arc Fusion Machine
2 1 set Optical Loss Test Set (Power Meter & Light Source)
3 1 set Optical Time Domain Reflectometer (OTDR)
4 2 sets Fiber Extension Ladder 24 feet length
5 2 sets Lineman safety belts
6 2 sets Lineman Tool Kit
7 1 set Cable jack/trailer
8 2 sets Digging bar, shovel, clamshell digger,
9 2 sets Carpentry Tools
10 2 pcs. Wheel meter
11 2 pcs. Cable Cutter
12 2 pcs. Messenger wire cutter
And other necessary tools and equipment needed for maintenance of FOC
2. FOC Network Maintenance Supplies for Baguio City
Listed in the table are the common materials necessary for the maintenance of the network. (To be delivered by the winning bidder to Baguio ICTO)
# Quantity Unit Description
1 3 drums
96 core, FOC, SM, 1310, Air blown fiber or underground or buried, depends on the FOC supplied during installation 4km/drum
2 3 drums
48 core, FOC, SM, 1310. Self-support, depends on the FOC supplied during installation 4km/drum
2 30 sets FOC Splice Closure-48 core
3 100 pcs. Patch Cord, LC/LC
4 3000 mtrs. 4-way micro-duct or underground HDPE, depends on the FOC supplied during installation
5 1 lot Different size of pole clamps (10 each)
![Page 21: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/21.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e21
6 1 lot Different types of suspension clamps (10 each)
7 100 pcs. Messenger/Guy grip
Other necessary materials for cable attachments on aerial/underground
Note: All the above mentioned materials shall be made available at the time of the Final Acceptance.
3. Others
3.1. Vehicles
Contractor must have the following vehicles to mobilize necessary tools and materials that will be used in the maintenance of the network in the duration of the contract but not to be delivered to ICTO
3.1.1. One (1) Splicing Van with Ladder
rack/holder
3.1.2. One (1) Bucket/Boom Truck
3.1.3. One (1) Service Vehicle with Ladder
rack/holder
3.2. Warehouse (ICTO will provide a 300 square
meter open space)
Contractor is required to maintain the quantity of materials in their storage warehouse. Warehouseman must always update and maintain record of the list of components and materials, and prepare reports when stocks are being used. In case of any theft, loss or damages on the materials provided by ICTO, the Contractor or the winning Maintenance Provider will be accountable and must immediately replace the said materials.
3.3. Personnel Protective Equipment (PPE) and
Safety Devices
Contractor must also provide and ensure that all personnel are wearing proper PPE at all times and use safety device in their working area to avoid any accident.
C. FIBER OPTIC CABLE SPECIFICATIONS
I. General Scope:
This covers the minimum requirement of single mode optical fiber cables for the iGovPhil Regional
![Page 22: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/22.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e22
FOC Network as per ITU-T Recommendation G.652d standard.
All the terms used in this specification of single-mode optical fiber cable shall be as defined in the latest ITU-T Recommendation G.652d.
Characteristics not clearly defined in these specifications shall comply with the latest ITU-T G.652d recommendation.
II. Cable Construction: General considerations
The basic purpose is to keep transmission and mechanical strength properties stable in the course of the cable manufacturing process, cable installation work and operation.
Optical fiber cables offered must be able to withstand all possible weather conditions in the Philippines when used in outside plant and installed aerial or underground. The optical fiber cables and accessories offered must be mechanically strong and chemically resistant to be suitable for use under extreme external conditions.
1. Design Consideration
The maximum number of optical fibers in a loose tube shall be 12 fibers for cables 48-fiber and above. This requirement must be strictly complied.
The loose tubes and interstices of cable core shall be filled with a suitable compound that could prevent long term penetration of water. Information on the material used for the filling compound shall be stated by the manufacturer.
1.1 Figure-8/Self-support Fiber optic cable
1.1.1 Cable Sheath
1.1.1.1 Black HDPE, a compound of PE and carbon black shall be used for the cable sheath.
1.1.1.2 The moisture barrier shall consist of a longitudinally applied laminate of polymer coated aluminum foil.
1.1.1.3 A rip cord having a
minimum breaking load of
![Page 23: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/23.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e23
150N shall be laid beneath the outer sheath to facilitate access to the fiber.
1.1.1.4 Cable sheath marking
shall be as follows;
1. Property of DOST
Philippines;
2. Manufacturer’s Name
and Fiber Count;
3. Date of Manufacture;
4. Length Marker; and
5. Fiber type: SM
1.1.1.5 The completed cable shall have sequentially numbered length markers at regular intervals of one meter (1.0m).
1.1.1.6 The figure-8/self-support optical fiber cable shall have 3.2mm thick yellow stripe marked continuously on the sheath.
1.1.2 Strength Member
1.1.2.1 One or more strength members shall be incorporated into a cable structure designed to carry the tensile load associated with installation.
1.1.2.2 The fiber reinforced plastic (FRP), serving mainly as the central strength member must be laminated with an MDPE-Jacket to prevent disintegration/breakage of plastic materials used.
1.2 Air-blown Micro-fiber optic cable
1.2.1 Cable Sheath
1.2.1.1 Black HDPE, a compound
of PE and carbon black
![Page 24: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/24.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e24
shall be used for the cable sheath.
1.2.1.2 The moisture barrier shall consist of a longitudinally applied laminate of polymer coated aluminum foil.
1.2.1.3 A rip cord having a minimum breaking load of 150N shall be laid beneath the outer sheath of facilitate access to the fiber.
1.2.1.4 Cable sheath marking
shall be as follows;
- Property of DOST
Philippines;
- Manufacturer's Name
and Fiber Count;
- Date of Manufacture;
- Length Marker; and\
- Fiber type: SM
1.2.1.5 The completed cable shall have sequentially numbered length markers at regular intervals of one meter (1.0 m).
1.2.2 Strength Member
1.2.2.1 One or more strength members shall be incorporated into a cable structure designed to carry the tensile load associated with installation.
1.2.2.2 The fiber reinforced plastic (FRP), serving mainly as the central strength member must be laminated with an MDPE-Jacket to prevent disintegration/breakage of plastic materials used.
1.3 Identification
![Page 25: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/25.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e25
1.3.1 The color coding of the loose tubes and the individual fibers within each loose tube shall be as follows:
Tube No./ Fiber No.
Fiber Color
Tube Color
1 Blue Blue
2 Orange Orange
3 Green Green
4 Brown Brown
5 Slate Slate
6 White White
7 Red Red
8 Black Black
9 Yellow Yellow
10 Violet Violet
11 Rose Rose
12 Aqua blue
Aqua Blue
2. Packing of Cables
2.1 Cable protection shall include, as a minimum, a covering placed between the cable reel flanges and over the exposed layer of the cable. The covering shall be weather resistant and shall limit solar heating of the cable such that the cable surface temperature does not exceed 10ºC above ambient temperatures under maximum solar radiation.
2.2 The cable ends shall be accessible for testing, and securely fastened to the reel to prevent the cable from becoming loose in transit or during cable installation.
2.3 End caps shall be securely installed to both cable ends to prevent escape of filling compound and entry of moisture during shipping, handling, and storage.
2.4 The manufacturer shall state the sizes of cable drums used for the purpose of packing the offered single mode optical fiber cables. The minimum diameter of spool of the cable drums shall be at least
![Page 26: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/26.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e26
20 times the cable diameter.
2.5 The spindle hole of each cable drum shall
be greater than 100mm.
2.6 Cable length per reel/drum must be
continuous.
3. Cable Sizes
The manufacturer shall state the outer diameter of the various sizes of the single mode fiber optic cables offered, subject to DOST/ICT Office's approval.
D. HANDLING AND STORAGE OF FIBER OPTIC CABLES, EQUIPMENT, FACILITIES AND MATERIALS
Contractor shall ensure that all FOC, equipment and materials necessary for the project are properly handled and secured.
1. As part of the Contract, Contractor must acquire storage house (warehouse) to keep and secure all necessary materials and facilities prior to installations.
2. Contractor must submit Handling and Storage Procedures particularly of the Fiber Optic Cable. This also includes the shipment or transfer of FOC when necessary.
E. CONTRACTORS MUST PRESENT THE FOLLOWING NOT MORE THAN THREE (3) CALENDAR DAYS AFTER
RECEIPT OF NOTICE FROM THE BAC4IGOV THAT THE
BIDDER HAS BEEN DECLARED L/SCB.
1. Contractor’s Qualifications:
1.1 Written Statement of the contractor signed by their authorized representative that they have at least 10 years of direct experience on planning, engineering, supply and delivery, installation, testing and commissioning and experience in operations and maintenance of optical fiber transmission backbone projects/systems with major telecommunications carriers in the Philippines.
1.2 Contractor shall submit resume of key
personnel to be assigned to the project
1.3 Must hold a PCAB License on Communications Facilities for a minimum of 5 consecutive years from the date of Bid Opening. ( In case of renewal, the bidder must submit PCAB
![Page 27: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/27.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e27
application and Official Receipt)
2. Specification of offered FOC
2.1 Contractor must provide to DOST/ICT Office the brochure or detailed specifications of their offered fiber optic cable (FOC) vis-à-vis to comply with ITU-T Recommendation G.652d.
2.2 Contractor must submit a manufacturer’s ISO certification or other internationally accepted third party certifying authority of their offered FOC.
2.3 The optical fiber cables shall have an expected shelf life span of more than forty (40) years. Contractor must submit a manufacturer’s certification stating the life span of the offered single-mode fiber cables and provide information on how the life span of the offered optical fiber cables was determined.
F. DESIGN CONCEPT
For the design concept in hard copy, the following must be included:
a. The proposed Contractor’s Fiber Network Infra Map/Diagram as basis for implementation, duly signed by a licensed Professional Electronics and Communication Engineer (PECE).
b. Link Loss Budget Calculation from nodes to nodes: (Note: Link loss budget calculation from nodes to nodes should not be more than 6db at 1310nm)
Formula in computing the budget loss calculation:
cable loss + splice losses + connector losses = Budget loss calculation
Wherein:
cable loss = db/km x km
splice loss = db/splice x number of splice
G. INTEGRATED PROJECT PLAN SHOWING THE
FOLLOWING: (LETTERS A-D SHOULD BE IN GANTT CHART FORMAT)
a. Critical Tasks;
b. Milestones;
c. Dependencies;
d. Logs/Slippages (%);
![Page 28: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/28.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e28
e. Manpower Schedule;
f. Equipment Utilization; and
g. Organizational Chart
The schedule of activities must be within the one hundred eighty (180) calendar day-completion period of the project.
H. CONTRACT FOR THE FOC NETWORK MAINTENANCE IS TWO (2) YEARS.
I. Payment Terms and Condition
a. For FOC Network Maintenance Supplies and Materials to be delivered by the winning bidder, full payment will be made upon the acceptance of the delivery.
b. For the Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning of Brand New Fiber Optic Cable Network, payment will be made in Partial Payment as folows;
1. 20% payment – After the contructor installed
20% of the Total FOC km.
2. 40% payment- Afer the contructor installed
another 40% of the Total FOC km.
3. 40% payment- After the acceptance
c. For Maintenance of ICTO-DOST Fiber Optic Cable (FOC) Networks in Baguio City, payment will be made every three (3) months.
J. Duration: 180 calendar days
Name of Company
Signature Over Printed Name Of Authorized Representative
Date
![Page 29: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/29.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e29
Revised Technical Specifications as of 03 November 2015
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” per line number under Bidder’s Statement of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”.
LOT 2: DESIGN, SUPPLY, DELIVERY, INSTALLATION, SPLICING, TESTING
COMMISSIONING, OPERATION AND MAINTENANCE OF BRAND NEW FIBER OPTIC CABLE IN LEGAZPI CITY
ITEM SPECIFICATION STATEMENT OF COMPLIANCE
A. DESIGN, SUPPLY, DELIVERY, INSTALLATION, SPLICING, TESTING, AND COMMISSIONING OF BRAND NEW FIBER OPTIC CABLE NETWORK IN REGIONAL GOVERNMENT CENTERS IN LEGAZPI CITY
I. Overview
The project consists of aerial and underground installation (micro-trenching method and/or buried/conduit/directional boring), configuration, testing, and commissioning of approximately twenty kilometers (20 km) of fiber optic cables in Legazpi City
II. Scope of Work
The Work includes the supply of engineering services, furnishing of materials, labor, supervision, tools, supplies, and performance of all operations necessary to complete the project, all in accordance with the contract documents and subject to the terms and conditions of the Contract.
The Work covers the design-and-build of the above-mentioned project particularly the following components:
a. As-build plans of all plans and drawings (network, route, termination, splicing, etc.) required by the project;
b. Aerial and underground installation (micro-trenching method and/or buried/conduit/directional boring) and appurtenances for the proposed project;
c. Optical Distribution Frame (ODF)/Cabinet including
![Page 30: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/30.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e30
patch cord/pig tails, optical fiber trays, db loss/amplification and other equipment and accessories, if necessary;
d. Pole line hardware;
e. Installation of underground (micro-trenching method and/or buried/conduit/directional boring) for the backbone and aerial or underground fiber optic cable (for the distribution)
f. Splicing and termination of fiber optic cable;
g. Testing and commissioning (provisional and final
acceptance) of newly installed FOC; and
h. Restoration of all affected facilities.
Note: Scope of work for the Fiber Network will be up to the Optical Distribution Frame (ODF) only. All connections are to be directly terminated to the user nodes using ODFs/Patch Panels.
1. Laying of FOC cables (96 and 48 cores) at LEGAZPI approximately twenty (20) kms with Thirty Four (34) agencies to be connected
1. DOST 2. LTFRB 3. LTO 4. CSC 5. NEDA 6. BUREAU OF TREASURY 7. COAST GUARD 8. COA 9. DAR – ADJUDICATION BOARD 10. DENR-EMB 11. PRC 12. DENR 13. NTC
14. NAPOLCOM 15. BUREAU OF PROTECTION 16. MARITIME 17. ICTO 18. DENR CENRO 19. DENR PENRO 20. DTI ALBAY PROVINCIAL OFFICE 21. CUSTOMS 22. NBI 23. NFA
24. DEPED 25. DPWH 26. TESDA 27. BOT 28. DOJ 29. DBM 30. NAVAL 31. DA BUREAU OF PLANT INDUSTRY 32. HUMAN RIGHTS COMMISSION 33. COMELEC 34. PPA
1.1. Installation of 4-ways HDPE underground micro-trenching method and / or buried / conduit / directional boring for the fiber optic cable backbone approximately fifteen (15) kms.
2. Termination of 96 cores FOC on PoP(Point of Presence) and 48 cores FOC on the client agencies/stations
![Page 31: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/31.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e31
3. Provide and install Optical Distribution Frame (ODF)/Cabinet including patch cord/pig tails, optical fiber trays, and accessories at all designated/target Agencies
4. Testing of new FOC
5. Commissioning
6. Restoration of all affected facilities /infrastructure
and demobilization
III. Survey, ENGINEERING AND CONSTRUCTION/DESIGN
(after contract awarding before installation)
1. The Contractor is required to carry out the detailed site survey and engineering for the Optical Fiber Cable Routes to justify the installation and construction designs together with the bill of quantities (BOQ). Included in the Contractor’s BOQ is all local materials and labor. (Initial Cable Route Plan will be provided by DOST/ICT Office for reference)
2. The Contractor shall submit a detailed work plan and installation/construction design drawings to DOST/ICT Office for approval within ten (10) calendar days after receipt of Contract and prior to installation. DOST/ICT Office will check and review the design drawings accompanied by justification/verification reports, and will give their decision whether the design drawings are acceptable or not, within one (1) week time from the date of DOST/ICT Office receipt of design drawings.
3. As part of each telecommunications work order/project, detail schematic drawings shall be prepared for each fiber optic span/cable route, showing the following information:
Fiber cable data:
1. Cable manufacturer;
2. Cable size (number of fibers)
3. Cable type;
4. Cable make-up;
5. Type of fiber;
6. Transmission characteristics (dB loss/km at
given wavelength); and
7. Dispersion specification in ps/(nm . km).
![Page 32: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/32.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e32
Other information:
1. Trunk number/cable number;
2. Span length;
3. Manhole/handhole number and duct number;
4. Major intersections and key streets;
5. Fiber cable splice points with station location;
6. Splice-to-splice cable lengths;
7. Change in cable route; and
8. Budget loss link calculation.
4. Preparation of Designs Drawings
4.1. Kinds of installation Drawings
4.1.1. The Contractor shall, at his own expense, produce installation/construction designs/drawings in conformity with design principles, and are to be approved by DOST/ICT Office.
4.1.2. Preparation and Standard Size of installation/construction Designs/Drawings: The Contractor shall produce the installation/construction designs/drawing on standard size paper.
4.1.3. As noted in other sections of this TOR, The Contractor shall supply drawings in a Computer-aided design (CAD) format.
4.1.4. Geospatial data indicating the route plan including the splicing point, termination point, and ODF.
5. Reports, Specifications, Practices and Procedures
5.1. Preparation of Technical Documents
The following reports, Specifications, Practices and Procedures shall be prepared by the Contractor, called as the “Technical Documents” in this paragraph, to be approved by DOST-ICT Office. The Contractor must submit a progress report every Monday.
5.1.1. Survey report
5.1.2. Design reports.
5.1.3. Material Specifications for Optical Fiber
![Page 33: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/33.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e33
Cable and Duct/Trench Systems.
5.1.4. Installation/Construction Practices, for Optical Fiber Cable, Duct and Direct buried Systems.
5.1.5. Factory Inspection/Test Procedures.
5.1.6. Inspection and Acceptance Test Procedures, for Duct System and Optical Fiber Cable Systems.
5.1.7. Others
5.2. Number of Copies of Installation/Construction. Designs/Drawings, Reports, Specifications, Practices and Procedures (as part of requirement for payments)
The Contractor shall submit to DOST/ICT Office the specified numbers of original and of copies of the installation/construction designs/drawings and technical documents such as:
5.2.1. Softcopy, in original editable format, of all as-built plans and drawings involved in the project;
5.2.2. Design standard and application
details;
5.2.3. Survey and design reports;
5.2.4. Material Specifications
5.2.5. Installation / Construction Practices in
accordance with ITU-T Standard.
5.2.6. Factory Inspection / Test Procedures;
and
5.2.7. Inspection and Acceptance Test
Procedures
6. Construction Plan/Design
All Construction Plans/Designs shall be in accordance with DOST/ICT Office Specifications. Construction Plans/Designs are composed of:
6.1. Optical Fiber Cable Plan
6.1.1. Key Map for Optical Fiber Cable route
6.1.2. Optical Fiber Cable plan
6.1.3. Optical fiber cable arrangement and
termination on ODF frames.
6.1.4. Optical fiber cable arrangement on
Splice Closure.
![Page 34: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/34.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e34
6.1.5. Schematic diagram for fiber optics
cores assignment
6.1.6. Cable Entrance Facilities/Structural
Cabling inside the agencies
6.2. Contents of Installation/Construction drawings
for Optical Fiber Cable System.
6.2.1. Key Map for Optical Fiber Cable route.
Key map is to indicate the proposed optical fiber cable route between two nodes with latest route conditions as well as future plan along the route. Following items shall be considered:
6.2.1.1. The proposed optical fiber cable route shall be covered from end to the other end;
6.2.1.2. The road, river, railway, remarkable buildings and typical public facilities including the planned ones with each name along the junction/trunk route;
6.2.1.3. Proposed or existing location of
the nodes;
6.2.1.4. Size, type and capacity of the
proposed optical fiber cable;
6.2.1.5. Location of repeater, if
applied; and
6.2.1.6. Road side of proposed optical fiber cable route indicated by writing the road name.
7. Optical Fiber Cable Plan must include the following
specifics :
7.1. All proposed manhole/handhole and duct runs
with type, name, capacity and distances;
7.2. Assignment of duct for proposed optical fiber
cable;
7.3. Typical drawing(s) for cable arrangement in
manhole/handhole;
7.4. Splice points of optical fiber cable W/ 3 POINT
reference and GPS coordinates;
7.5. Distance between existing facilities (such as center/ edge of the Road & canal) and DOST/ICT Office proposed facilities should be reflected on engineering and as built plan.
7.6. Number and distance of micro-ducts;
![Page 35: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/35.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e35
7.7. Road side of proposed optical fiber cable
route indicated by writing the road name;
7.8. Location of cable within railroad right-of-way;
7.9. North Point; and
7.10. Should reflect the Town/Barangay
Boundaries.
8. Optical Fiber Cable arrangement and termination
This drawing shall cover terminations in the ICT room; cable runs from entrance in building and to the cable entrance point from duct/pole route.
8.1. Location and dimensions of fiber distribution
frame with 3 dimensions.
8.2. Location of termination of joint, assignment and arrangement of termination O/F cords and detailed cable runs.
8.3. Details of cable racking structure and racking
method.
8.4. Contents of Optical Fiber Cable System such as junction section, capacity of line system, attenuation loss, name of optical mode and so on.
9. Schematic diagrams for optical fiber cable core
and fiber optics covers.
This drawing shall cover all necessary factors for interfacing with transmission systems as the line system design.
10. Contents of Installation/Construction Drawings for
the Micro-Duct System
10.1. The duct systems drawings are composed of 2 kinds of drawings, and are to be combined and drawn on A-1 size paper. One is the geographic plan for roads along routes of duct system drawn to a scale of 1/1000.
10.2. The other is the longitudinal profile of vertical section along the center line of duct system routes, and is to be on a scale of 1/1000 for horizontal length and 1/100 for vertical level.
The plan drawing shall contain:
10.2.1. Location of manhole with their names and types supported by cross-section drawings of roads for such location at a scale of 1/100;
10.2.2. Location of ducts runs with the duct
![Page 36: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/36.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e36
composition and each duct span length between adjacent 2 centers of manhole, Riser ducts or the internal wall of a cable vault;
10.2.3. Location of length of sections showing details of protective measures;
10.2.4. Location and length of duct bridges, duct attachments to bridges and boring sections supported by detailed drawings of structure; and
10.2.5. Direction of north to be indicated.
10.3. Longitudinal profile drawings shall contain:
10.3.1. Level of ground, top and bottom of duct run at each 30,’s horizontal distance, and levels of bottom and shoulder (outer side) of manhole;
10.3.2. Top and bottom levels of other underground facilities (power cable, water/sewage pipe etc.) and levels of natural or artificial features along the duct routes (river, culvert, railways, etc.); and
10.3.3. Longitudinal profile drawings shall be so arranged to have the manhole on the plan drawing.
11. The contractor is required to designate a qualified on-site engineer for proper supervision and coordination of the project. He must undergo interview with DOST/ICT Office FOC Team for verification.
12. The Contractor shall, in order to keep the design accurate and practical and at his own expense, perform the following:
12.1. When necessary, make test holes at key point of the route to avoid interference with underground facilities and/or hard – rocks as much as practically possible;
12.2. Obtain prior approval from municipalities and/or other relevant authorities/agencies, and third parties for the execution of the work.
12.3. The Contractor shall abide and comply with the terms and conditions specified in the permits obtained from said municipalities
![Page 37: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/37.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e37
and/or other relevant authorities/agencies.
ALL necessary Right of Way and Joint Pole Agreement (JPA) permits shall be secured by the Contractor in favor of the DOST – ICT Office.
All permits and fees/charges for the JPA lease, road/underground trench/duct monthly lease will be eventually shouldered by the Project once the Final Acceptance Certificate is issued by DOST/ICT Office.
All charges pertaining to permits and other fees for JPA lease and Right of Way for the duration of the contract, shall be at the expense of the Contractor.
13. The Contractor must conduct due diligence and shall restudy and amend/modify the design drawings not only dependent upon the comments of DOST/ICT Office but also taking into consideration the design concept, and shall resubmit the modified design drawings to DOST/ICT Office within one (1) week after receipt of DOST/ICT Office comments for their approval.
14. In case the Contractor’s re-study of the design is incomplete, and DOST/ICT Office disapproval is repeated, then the Contractor shall be fully responsible for any delay in progress, cost of re-design etc. and DOST/ICT Office will keep the right to order the replacement of the Contractor’s engineer/management in charge of installation/construction design at the Contractor’s own expense.
15. The Contractor shall submit the combined bill of quantities for Duct System and Optical Fiber Cable System as a part of installation/construction design, and shall get approval from DOST/ICT Office and/or Consultant following the same procedures as applied to get approval for installation/construction drawings.
In case the bill of quantities for the Optical Fiber Cable System associated with the related installation/constructions drawings are within the originally contracted amount and are approved by DOST/ICT Office, then, such DOST/ICT Office approval shall be considered as commencement order for site implementation of the approved Bill
![Page 38: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/38.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e38
of Quantities.
16. The Contractor shall be responsible for his installation/construction drawings and Bill of Quantities, as a consequential obligation under the Contract to DOST/ICT Office, NGAs and LGUs, other organization/authorities concerned and also to third parties/personnel until the completion of the project.
17. The Contractor shall regard the implementation schedule as the priority requirement. In case the priority order for any section is required by DOST/ICT Office, then, the Contractor shall adjust the schedule accordingly.
17.1. The Contractor shall submit the survey schedule, in great detail for existing facilities, at least ten (10) days prior to the commencement of the survey for each section.
18. In case an agency was found to be in a different location/site than the one specified in the TOR in the detailed site survey/engineering to be done by the winning Contractor, Contractor is required to connect said agency to the Fiber Infra Network.
IV. PROJECT MILESTONES
1. Implementation Schedule
1.1. The Contractor shall submit an integrated project implementation plan showing the following:
1.2. Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty (180) calendar days from date of receipt of Notice to Proceed (NTP);
1.2.1. Number of work teams at any given
time;
1.2.2. Specific dates for work and quality inspection by the DOST/ICT Office team in the FOO clusters;
1.3. The Contractor shall submit integrated implementation updates every 1st day of the week (Monday) to DOST/ICT Office throughout the contractual installation/construction period from the effective date of the Contract until the completion of the Project showing the following detailed milestone, and in
![Page 39: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/39.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e39
accordance with the established schedule and priorities.
1.4. The implementation shall be accurate and
include the following considerations:
1.4.1. To ensure that the work-force is well-distributed through the contractual period taking quality control and timely progress into consideration;
1.4.2. To allow sufficient time and manpower for self-inspections/tests prior to being witnessed by DOST/ICT Office for interim inspections/tests and provisional acceptance tests;
1.4.3. To allow reasonable time for witnessing by DOST/ICT Office of interim inspections/tests considering the work sequence such as cable laying work after DOST/ICT Office has accepted completed systems;
1.4.4. To ensure the sites are properly
managed so as to ensure:
a. Coordination with NGAs, LGUs and other authorities/agencies concerned;
b. Obtaining site implementation
permits and site-entry permits;
c. Adequacy of site security
arrangements.
1.4.5. To keep sufficient time and manpower from transferring site know-how quality control, tools/formats, standard safety arrangement, first aid, etc., to the local staff and local foreman.
1.4.6. To make sure the quality/functions of domestic products fully conform to the specifications any time necessary to upgrade the same.
1.5. The Contractor shall be responsible for conforming to the integrated implementation schedules as strictly as possible after examination and approval by DOST/ICT OFFICE.
1.6. If discrepancies/ambiguities are found or some deviation is necessary in the actual implementation progress, the Contractor shall report the same to DOST/ICT Office and shall
![Page 40: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/40.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e40
take all corrective actions/measures at Contractor’s own expense in accordance with the instructions given by DOST/ICT Office.
1.7. The initial synchronized and integrated implementation schedule specified for the project shall be submitted for DOST/ICT Office’s approval within five (5) days after the effective date of the Contract.
V. AS-BUILT DRAWINGS
1. Technical documents including the As-Built
Drawings shall be required by DOST/ICT Office.
1.1. Documents for Execution of Provisional
Acceptance Test:
1.2. For the main purpose of executing the Provisional Acceptance Test, the Vendor shall prepare the As-Built Drawings. The As-Built Drawing shall be made in a CAD format.
1.3. As-Built Drawings for Cable Networks
The following as-built drawing having the same sizes as the designs/drawings:
1.3.1. General Map to cover all of the serving
area;
1.3.2. Junction Cable Diagram for the
Network;
1.3.3. Key Map for Cable Route (each cable
section);
1.3.4. Junction Cable Duct assignment
Diagram (each cable section);
1.3.5. Detailed fiber core assignments(each
cable section/splicing point);
1.3.6. Junction Cable Location Map (each
cable section);
1.3.7. Optical Fiber Cable Arrangement and Termination on the fiber distribution frame;
1.3.8. Schematic diagram for Fiber Optics
Cores Assignment; and
1.3.9. Special Design Drawing, if any.
![Page 41: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/41.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e41
VI. BILL OF QUANTITIES
1. The contractor must attach a detailed Bill of Quantities (BOQ) showing all the components required to complete the project. This may include, but not limited to:
1.1. Fiber Optic Cable (SMF., ITU –T Recommendation G.652d, NECA/FOA 301 Compliant), Closure, and Cabinet
1.2. Pole Line hardware and accessories
1.3. Poles
1.4. Underground micro-trenching method and/or buried/conduit/directional boring) for the backbone and aerial or underground fiber optic cable (for the distribution
1.5. Optical Distribution Frame (ODF)/Cabinet including patch cord/pig tails, optical fiber trays, db loss/amplification and other equipment, if necessary and accessories
1.6. Engineering, Right of Way, Permits
1.7. List of Equipment
1.8. Contingency
VII. TESTING, COMMISSIONING AND ACCEPTANCE
1. The contractor is responsible in the performance of all civil and cable network pre-test requirement but not limited to:
1.1. Fiber Optic Cable (FOC) – attenuation and all its related testing, power meter test, and grounding test and all other test that may need to perform to complete the FOC test requirements.
Contractor is also required to submit their FOC testing procedures/protocols.
1.1.1. On-reel acceptance tests shall be performed on the cable to confirm the manufacturer’s tests before the installation operation begins. This will also be used to validate the fiber loss/km; at wavelength 1310nm loss shall be 0.4 db/km or less; at 1550nm shall be 0.3dB/km or less.
1.1.2. End-to-end acceptance tests (typically conducted after completion of installation and splicing and
![Page 42: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/42.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e42
before installing terminal equipment).
1.1.3. End-to-end attenuation is the amount of optical power loss between cable system connector tips. This will include the fiber and splice /connector loss in the cable system after it has been installed.
1.1.4. Splice acceptance tests (individual
splice insertion losses)
- splice loss shall not be above 0.1 dB for fusion and 0.2 dB for mechanical splices; and
- connectors shall have insertion
losses of 0.5 dB or less.
1.1.5. All test equipment that will be utilized for this project shall have updated calibration certificates to ensure accuracy of results. Contractor is required to submit Calibration Certificates prior to testing.
2. Link Loss Requirements
During the design stage a link loss calculation shall be prepared and included with the project proposal and design packages. The link loss budget shall include:
2.1. Total fiber attenuation (loss), not more that
6db.
2.2. Splice loss (including pigtail splices, if
pigtails are used).
2.3. Connector loss.
2.4. The calculated dB loss cannot exceed the operating range of the terminal equipment that will be installed. Measured end-to-end loss should measure less than the calculated loss. Fibers that measure a higher loss than the link loss budget will not be accepted.
3. Contractor Performance and Workmanship
3.1. DOST/ICT Office will issue provisional and final acceptance certificate to the Contractor certifying that the scope of work has been performed and accomplished in accordance with the approved plans and specification schedules, variation orders if any, and other related contract document.
![Page 43: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/43.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e43
3.2. The contractor likewise agrees to correct any defect accruing after the final acceptance of the site facility under the project within the guarantee period. Effective duration of which shall be one (1) year commencing from the date of final acceptance by DOST/ICT Office.
B. MAINTENANCE OF FOC NETWORK IN REGIONAL
GOVERNMENT CENTER IN BAGUIO CITY FOR TWO (2) YEARS
Note: The maintenance of FOC Network will start once the project is 100% accepted.
I. SCOPE OF WORK
The work includes the following services to be rendered by the Contractor to ensure the continuous operation of the FOC Network
- Conduct daily physical inspections for the
coverage Area.
- All route covering all Agencies connected must be inspected at least every quarter per year
- 24/7 maintenance team
- Monthly maintenance report. In case of problems encountered and restorations are being done, a separate incident report shall be accomplished.
- Restoration and replacement of damaged FOC
- Repair / restoration of ODF
- Pole replacement / relocation / straightening
/ erection
- Repair of damaged duct system
- Re-tensioning and separation of FOC to
powerline
- Replacement of FOC pigtail and/or patchcord
at the ODF
- Replacement of Network Equipment (Active
Equipment) and ODF
- Conduct re-tensioning of FOC
- Straightening of leaning concrete pole
- Replacement, relocation & erection of
concrete pole
- Replacement of stolen & burned FOC
- Re-labeling of pole tag
![Page 44: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/44.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e44
- Re-grounding
- Tree/branch-trimming, if necessary
- Restoration and replacement of damaged
micro-ducts
- Maintenance of a warehouse for safe keeping
of spare materials needed
- Contractor is required to secure a 24/7 on-call/standby service crew for immediate response in case of network failure.
II. RESPONSE AND REPORT TIME TARGET
Contractor considers all interruptions in service as urgent priority. Expected response and repair time are given in the table below:
Hours/Days of Coverage
Response Time Restoration
Maximum Time to Respond
Maximum Time to UP the Network
24 x 7 x 365 Days
Monday to
Sunday 1 Hour
6 Hours from the issuance of trouble
ticket
III. MANPOWER REQUIREMENTS
Personnel must be properly trained to use such equipment and do the troubleshooting and restoration and must be available on a moment’s notice.
In order to effectively maintain the FOC Network, maintenance personnel, at the minimum, must include the following:
a. One (1) Project Engineer/Coordinator
b. One(1) FOC team that consists of seven (7)
personnel
- One (1) OSP Supervisor
- Two (2) Lineman
- Two (2) Splicers/Commissioning personnel
- Two (2) Support personnel
![Page 45: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/45.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e45
IV. TOOLS, EQUIPMENT AND MATERIAL
REQUIREMENTS
As part of the activity, the following equipment, facilities, tools and materials must be available at all times.
1. List of Tools and Equipment
Contractor must have the following tools and equipment to do the preventive maintenance and restoration activities in the duration of the contract but not to be delivered to ICT OFFICE.
# Quantity Unit Description
1 1 set Arc Fusion Machine
2 1 set Optical Loss Test Set (Power Meter & Light Source)
3 1 set Optical Time Domain Reflectometer (OTDR)
4 2 sets Fiber Extension Ladder 24 feet length
5 2 sets Lineman safety belts
6 2 sets Lineman Tool Kit
7 1 set Cable jack/trailer
8 2 sets Digging bar, shovel, clamshell digger,
9 2 sets Carpentry Tools
10 2 pcs. Wheel meter
11 2 pcs. Cable Cutter
12 2 pcs. Messenger wire cutter
And other necessary tools and equipment needed for maintenance of FOC
2. FOC Network Maintenance Supplies for
Legazpi City
Listed in the table are the common materials necessary for the maintenance of the network. (To be delivered by the winning bidder to Legazpi ICT Office)
![Page 46: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/46.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e46
# Quantity Unit Description
1 3 drums
96 core, FOC, SM, 1310, Air blown fiber or underground or buried, depends on the FOC supplied during installation 4km/drum
2 3 drums
48 core, FOC, SM, 1310. Self-support, depends on the FOC supplied during installation 4km/drum
2 30 sets FOC Splice Closure-48 core
3 100 pcs. Patch Cord, LC/LC
4 3000 mtrs.
4-way micro-duct or underground HDPE, depends on the FOC supplied during installation
5 1 lot Different size of pole clamps (10 each)
6 1 lot Different types of suspension clamps (10 each)
7 100 pcs. Messenger/Guy grip
Other necessary materials for cable attachments on aerial/underground
Note: All the above mentioned materials shall be made available at the time of the Final Acceptance.
3. Others
3.1 Vehicles
Contractor must have the following vehicles to mobilize necessary tools and materials that will be used in the maintenance of the network in the duration of the contract but not to be delivered to ICT OFFICE
3.1.1 One (1) Splicing Van with Ladder
rack/holder
3.1.2. One (1) Bucket/Boom Truck
3.1.3. One (1) Service Vehicle with
Ladder rack/holder
3.2 Warehouse (ICT OFFICE will provide a
300 square meter open space )
Contractor is required to maintain the quantity of materials in their storage
![Page 47: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/47.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e47
warehouse. Warehouseman must always update and maintain record of the list of components and materials, and prepare reports when stocks are being used. In case of any theft, loss or damages on the materials provided by ICTO, the Contractor or the winning Maintenance Provider will be accountable and must immediately replace the said materials.
3.3 Personnel Protective Equipment (PPE)
and Safety Devices
Contractor must also provide and ensure that all personnel are wearing proper PPE at all times and use safety device in their working area to avoid any accident.
C. FIBER OPTIC CABLE SPECIFICATIONS
I. General Scope:
This covers the minimum requirement of single mode optical fiber cables for the iGovPhil Regional FOC Network as per ITU-T Recommendation G.652d standard.
All the terms used in this specification of single-mode optical fiber cable shall be as defined in the latest ITU-T Recommendation G.652d.
Characteristics not clearly defined in these specifications shall comply with the latest ITU-T G.652d recommendation.
II. Cable Construction: General considerations
The basic purpose is to keep transmission and mechanical strength properties stable in the course of the cable manufacturing process, cable installation work and operation.
Optical fiber cables offered must be able to withstand all possible weather conditions in the Philippines when used in outside plant and installed aerial or underground. The optical fiber cables and accessories offered must be mechanically strong and chemically resistant to be suitable for use under extreme external conditions.
1. Design Consideration
The maximum number of optical fibers in a loose tube shall be 12 fibers for cables 48-
![Page 48: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/48.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e48
fiber and above. This requirement must be strictly complied.
The loose tubes and interstices of cable core shall be filled with a suitable compound that could prevent long term penetration of water. Information on the material used for the filling compound shall be stated by the manufacturer.
1.1. Figure-8/Self-support Fiber optic cable
1.1.1. Cable Sheath
1.1.1.1. Black HDPE, a compound of PE and carbon black shall be used for the cable sheath.
1.1.1.2. The moisture barrier shall consist of a longitudinally applied laminate of polymer coated aluminum foil.
1.1.1.3. A rip cord having a minimum breaking load of 150N shall be laid beneath the outer sheath to facilitate access to the fiber.
1.1.1.4. Cable sheath marking
shall be as follows;
1. Property of DOST
Philippines;
2. Manufacturer’s Name
and Fiber Count;
3. Date of Manufacture;
4. Length Marker; and
5. Fiber type: SM
1.1.1.5. The completed cable shall have sequentially numbered length markers at regular intervals of one meter (1.0m).
1.1.1.6. The figure-8/self-support optical fiber cable shall have 3.2mm thick yellow
![Page 49: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/49.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e49
stripe marked continuously on the sheath.
1.1.2. Strength Member
1.1.2.1. One or more strength members shall be incorporated into a cable structure designed to carry the tensile load associated with installation.
1.1.2.2. The fiber reinforced plastic (FRP), serving mainly as the central strength member must be laminated with an MDPE-Jacket to prevent disintegration/breakage of plastic materials used.
1.2. Air-blown Micro-fiber optic cable
1.2.1. Cable Sheath
1.2.1.1. Black HDPE, a compound of PE and carbon black shall be used for the cable sheath.
1.2.1.2. The moisture barrier shall consist of a longitudinally applied laminate of polymer coated aluminum foil.
1.2.1.3. A rip cord having a minimum breaking load of 150N shall be laid beneath the outer sheath to facilitate access to the fiber.
1.2.1.4. Cable sheath marking
shall be as follows;
1. Property of DOST
Philippines;
2. Manufacturer’s
Name and Fiber
![Page 50: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/50.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e50
Count;
3. Date of
Manufacture;
4. Length Marker; and
5. Fiber type: SM
1.2.1.5. The completed cable shall have sequentially numbered length markers at regular intervals of one meter (1.0m).
1.2.2. Strength Member
1.2.2.1. One or more strength members shall be incorporated into a cable structure designed to carry the tensile load associated with installation.
1.2.2.2. The fiber reinforced plastic (FRP), serving mainly as the central strength member must be laminated with an MDPE-Jacket to prevent disintegration/breakage of plastic materials used.
1.3. Identification
1.3.1 The color coding of the loose tubes and the individual fibers within each loose tube shall be as follows:
Tube No./
Fiber No.
Fiber Color
Tube Color
1 Blue Blue
2 Orange Orange
3 Green Green
4 Brown Brown
5 Slate Slate
6 White White
7 Red Red
![Page 51: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/51.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e51
8 Black Black
9 Yellow Yellow
10 Violet Violet
11 Rose Rose
12 Aqua blue
Aqua Blue
2. Packing of Cables
2.1. Cable protection shall include, as a minimum, a covering placed between the cable reel flanges and over the exposed layer of the cable. The covering shall be weather resistant and shall limit solar heating of the cable such that the cable surface temperature does not exceed 10°C above ambient temperatures under maximum solar radiation.
2.2. The cable ends shall be accessible for testing, and securely fastened to the reel to prevent the cable from becoming loose in transit or during cable installation.
2.3. End caps shall be securely installed to both cable ends to prevent escape of filling compound and entry of moisture during shipping, handling, and storage.
2.4. The manufacturer shall state the sizes of cable drums used for the purpose of packing the offered single mode optical fiber cables. The minimum diameter of spool of the cable drums shall be at least 20 times the cable diameter.
2.5. The spindle hole of each cable drum
shall be greater than 100mm.
2.6. Cable length per reel /drum must be
continuous.
3. Cable Sizes
The manufacturer shall state the outer diameter of the various sizes of the single mode fiber optic cables offered, subject to DOST/ICT Office's approval.
D. HANDLING AND STORAGE OF FIBER OPTIC CABLES, EQUIPMENT, FACILITIES AND MATERIALS
Contractor shall ensure that all FOC, equipment and
![Page 52: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/52.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e52
materials necessary for the project are properly handled and secured.
1. As part of the Contract, Contractor must acquire storage house (warehouse) to keep and secure all necessary materials and facilities prior to installations.
2. Contractor must submit Handling and Storage Procedures particularly of the Fiber Optic Cable. This also includes the shipment or transfer of FOC when necessary.
E. CONTRACTORS MUST PRESENT THE FOLLOWING NOT MORE THAN THREE (3) CALENDAR DAYS AFTER RECEIPT OF NOTICE FROM THE BAC4IGOV THAT THE BIDDER HAS BEEN DECLARED L/SCB.
1. Contractor’s Qualifications:
1.1. Written Statement of the contractor signed by their authorized representative that they have at least 10 years of direct experience on planning, engineering, supply and delivery, installation, testing and commissioning and experience in operations and maintenance of optical fiber transmission backbone projects/systems with major telecommunications carriers in the Philippines.
1.2. Contractor shall submit resume of key
personnel to be assigned to the project
1.3. Must hold a PCAB License on Communications Facilities for a minimum of 5 consecutive years from the date of Bid Opening. ( In case of renewal, the bidder must submit PCAB application and Official Receipt)
2. Specification of offered FOC
2.1 Contractor must provide to DOST/ICT Office the brochure or detailed specifications of their offered fiber optic cable (FOC) vis-à-vis to comply with ITU-T Recommendation G.652d.
2.2 Contractor must submit a manufacturer’s ISO certification or other internationally accepted third party certifying authority of their offered FOC.
![Page 53: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/53.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e53
2.3 The optical fiber cables shall have an expected shelf life span of more than forty (40) years. Contractor must submit a manufacturer’s certification stating the life span of the offered single-mode fiber cables and provide information on how the life span of the offered optical fiber cables was determined.
F. DESIGN CONCEPT
For the design concept in hard copy, the following must be included:
a. The proposed Contractor’s Fiber Network Infra Map/Diagram as basis for implementation, duly signed by a licensed Professional Electronics and Communication Engineer (PECE).
b. Link Loss Budget Calculation from nodes to nodes: (Note: Link loss budget calculation from nodes to nodes should not be more than 6db at 1310nm)
Formula in computing the budget loss calculation:
cable loss + splice losses + connector losses = Budget loss calculation
Wherein:
cable loss = db/km x km
splice loss = db/splice x number of splice
G. INTEGRATED PROJECT PLAN SHOWING THE
FOLLOWING: (LETTERS A-D SHOULD BE IN GANTT CHART FORMAT)
a. Critical Tasks;
b. Milestones;
c. Dependencies;
d. Logs/Slippages (%);
e. Manpower Schedule;
f. Equipment Utilization; and
g. Organizational Chart
The schedule of activities must be within the one hundred eighty (180) calendar day-completion period of the project.
H. CONTRACT FOR THE FOC NETWORK MAINTENANCE IS TWO(2) YEARS.
I. Payment Terms and Condition
![Page 54: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/54.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e54
a. For FOC Network Maintenance Supplies and Materials to be delivered by the winning bidder, full payment will be made upon the acceptance of the delivery.
b. For the Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning of Brand New Fiber Optic Cable Network, payment will be made in Partial Payment as folows;
1. 20% payment – After the contructor installed
20% of the Total FOC km.
2. 40% payment- Afer the contructor installed
another 40% of the Total FOC km.
3. 40% payment- After the acceptance
c. For Maintenance of ICT OFFICE-DOST Fiber Optic Cable (FOC) Networks in LEGAZPI CITY, payment will be made every three (3) months.
C. Duration : 180 calendar days
Name of Company
Signature Over Printed Name Of Authorized Representative
Date
![Page 55: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/55.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e55
Revised Technical Specifications as of 03 November 2015
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” per line number under Bidder’s Statement of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”.
LOT 3: DESIGN, SUPPLY, DELIVERY, INSTALLATION, SPLICING, TESTING
COMMISSIONING, OPERATION AND MAINTENANCE OF BRAND NEW FIBER OPTIC CABLE IN PALO, LEYTE
ITEM SPECIFICATION STATEMENT OF COMPLIANCE
A. DESIGN, SUPPLY, DELIVERY, INSTALLATION, SPLICING, TESTING, AND COMMISSIONING OF BRAND NEW FIBER OPTIC CABLE NETWORK IN REGIONAL GOVERNMENT CENTERS IN PALO, LEYTE
I. Overview
The project consists of aerial and underground installation (micro-trenching method and/or buried/conduit/directional boring), configuration, testing, and commissioning of approximately twenty kilometers (20 km) of fiber optic cables in Palo, Leyte
II. Scope of Work
The Work includes the supply of engineering services, furnishing of materials, labor, supervision, tools, supplies, and performance of all operations necessary to complete the project, all in accordance with the contract documents and subject to the terms and conditions of the Contract.
The Work covers the design-and-build of the above-mentioned project particularly the following components:
a. As-build plans of all plans and drawings (network, route, termination, splicing, etc.) required by the project;
b. Aerial and underground installation (micro-trenching method and/or buried/conduit/directional boring) and appurtenances for the proposed project;
![Page 56: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/56.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e56
c. Optical Distribution Frame (ODF)/Cabinet including patch cord/pig tails, optical fiber trays, db loss/amplification and other equipment and accessories, if necessary;
d. Pole line hardware;
e. Installation of underground (micro-trenching method and/or buried/conduit/directional boring) for the backbone and aerial or underground fiber optic cable (for the distribution)
f. Splicing and termination of fiber optic cable;
g. Testing and commissioning (provisional and final
acceptance) of newly installed FOC; and
h. Restoration of all affected facilities.
Note: Scope of work for the Fiber Network will be up to the Optical Distribution Frame (ODF) only. All connections are to be directly terminated to the user nodes using ODFs/Patch Panels.
1. Laying of FOC cables (96 and 48 cores) at Palo, Leyte approximately twenty (20) kms with Twenty (20) agencies to be connected
1. DOST 2. CSC 3. COA 4. DOH 5. POPCOM 6. DEPED RO 7. DEPED DO 8. PCA 9. NEDA 10. DPWH
11. DENR CENRO 12. DENR PENRO 13. DENR EMB 14. LHO 15. LPH 16. PHS 17. BIR 18. LAC 19. NFA 20. DTI
1.1 Installation of 4-ways HDPE underground micro-trenching method and / or buried / conduit / directional boring for the fiber optic cable backbone approximately eight (8) kms.
2. Termination of 96 cores FOC on PoP(Point of Presence) and 48 cores FOC on the client agencies/stations
3. Provide and install Optical Distribution Frame (ODF)/Cabinet including patch cord/pig tails, optical fiber trays, and accessories at all designated/target Agencies
4. Testing of new FOC
![Page 57: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/57.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e57
5. Commissioning
6. Restoration of all affected facilities /infrastructure
and demobilization
III. SURVEY, ENGINEERING AND CONSTRUCTION/DESIGN
(after contract awarding before installation)
1. The Contractor is required to carry out the detailed site survey and engineering for the Optical Fiber Cable Routes to justify the installation and construction designs together with the bill of quantities (BOQ). Included in the Contractor’s BOQ is all local materials and labor. (Initial Cable Route Plan will be provided by DOST/ICT Office for reference)
2. The Contractor shall submit a detailed work plan and installation/construction design drawings to DOST/ICT Office for approval within ten (10) calendar days after receipt of Contract and prior to installation. DOST/ICT Office will check and review the design drawings accompanied by justification/verification reports, and will give their decision whether the design drawings are acceptable or not, within one (1) week time from the date of DOST/ICT Office receipt of design drawings.
3. As part of each telecommunications work order/project, detail schematic drawings shall be prepared for each fiber optic span/cable route, showing the following information:
Fiber cable data:
1. Cable manufacturer;
2. Cable size (number of fibers)
3. Cable type;
4. Cable make-up;
5. Type of fiber;
6. Transmission characteristics (dB loss/km at
given wavelength); and
7. Dispersion specification in ps/(nm . km).
![Page 58: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/58.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e58
Other information:
1. Trunk number/cable number;
2. Span length;
3. Manhole/handhole number and duct number;
4. Major intersections and key streets;
5. Fiber cable splice points with station location;
6. Splice-to-splice cable lengths;
7. Change in cable route; and
8. budget loss link calculation.
4. Preparation of Designs Drawings
4.1 Kinds of installation Drawings
4.1.1 The Contractor shall, at his own expense, produce installation / construction designs/drawings in conformity with design principles, and are to be approved by DOST/ICT Office.
4.1.2 Preparation and Standard Size of installation/construction Designs/Drawings: The Contractor shall produce the installation/construction designs/drawing on standard size paper.
4.1.3 As noted in other sections of this TOR, The Contractor shall supply drawings in a Computer-aided design (CAD) format.
4.1.4 Geospatial data indicating the route plan including the splicing point, termination point, and ODF.
5. Reports, Specifications, Practices and Procedures
5.1 Preparation of Technical Documents
The following reports, Specifications, Practices and Procedures shall be prepared by the Contractor, called as the “Technical Documents” in this paragraph, to be approved by DOST-ICT Office. The Contractor must submit a progress report every Monday.
5.1.1 Survey report
5.1.2 Design reports.
5.1.3 Material Specifications for Optical Fiber
Cable and Duct/Trench Systems.
![Page 59: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/59.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e59
5.1.4 Installation/Construction Practices, for Optical Fiber Cable, Duct and Direct buried Systems.
5.1.5 Factory Inspection/Test Procedures.
5.1.6 Inspection and Acceptance Test Procedures, for Duct System and Optical Fiber Cable Systems.
5.1.7 Others
5.2 Number of Copies of Installation/Construction. Designs/Drawings, Reports, Specifications, Practices and Procedures (as part of requirement for payments)
The Contractor shall submit to DOST/ICT Office the specified numbers of original and of copies of the installation/construction designs/drawings and technical documents such as:
5.2.1 Softcopy, in original editable format, of all as-built plans and drawings involved in the project;
5.2.2 Design standard and application
details;
5.2.3 Survey and design reports;
5.2.4 Material Specifications
5.2.5 Installation / Construction Practices in
accordance with ITU-T Standard.
5.2.6 Factory Inspection / Test Procedures;
and
5.2.7 Inspection and Acceptance Test
Procedures
6. Construction Plan/Design
All Construction Plans/Designs shall be in accordance with DOST/ICT Office Specifications. Construction Plans/Designs are composed of:
6.1 Optical Fiber Cable Plan
6.1.1 Key Map for Optical Fiber Cable route
6.1.2 Optical Fiber Cable plan
6.1.3 Optical fiber cable arrangement and
termination on ODF frames.
6.1.4 Optical fiber cable arrangement on
Splice Closure.
6.1.5 Schematic diagram for fiber optics
![Page 60: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/60.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e60
cores assignment
6.1.6 Cable Entrance Facilities/Structural
Cabling inside the agencies
6.2 Contents of Installation/Construction drawings
for Optical Fiber Cable System.
6.2.1 Key Map for Optical Fiber Cable route.
Key map is to indicate the proposed optical fiber cable route between two nodes with latest route conditions as well as future plan along the route. Following items shall be considered:
6.2.1.1 The proposed optical fiber cable route shall be covered from end to the other end;
6.2.1.2 The road, river, railway, remarkable buildings and typical public facilities including the planned ones with each name along the junction/trunk route;
6.2.1.3 Proposed or existing location of
the nodes;
6.2.1.4 Size, type and capacity of the
proposed optical fiber cable;
6.2.1.5 Location of repeater, if
applied; and
6.2.1.6 Road side of proposed optical fiber cable route indicated by writing the road name.
7. Optical Fiber Cable Plan must include the following
specifics :
7.1 All proposed manhole/handhole and duct runs
with type, name, capacity and distances;
7.2 Assignment of duct for proposed optical fiber
cable;
7.3 Typical drawing(s) for cable arrangement in
manhole/handhole;
7.4 Splice points of optical fiber cable W/ 3 POINT
reference and GPS coordinates;
7.5 Distance between existing facilities (such as center/ edge of the Road & canal) and DOST/ICT Office proposed facilities should be reflected on engineering and as built plan.
7.6 Number and distance of micro-ducts;
![Page 61: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/61.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e61
7.7 Road side of proposed optical fiber cable
route indicated by writing the road name;
7.8 Location of cable within railroad right-of-way;
7.9 North Point; and
7.10 Should reflect the Town/Barangay Boundaries.
8. Optical Fiber Cable arrangement and termination
This drawing shall cover terminations in the ICT room; cable runs from entrance in building and to the cable entrance point from duct/pole route.
8.1 Location and dimensions of fiber distribution
frame with 3 dimensions.
8.2 Location of termination of joint, assignment and arrangement of termination O/F cords and detailed cable runs.
8.3 Details of cable racking structure and racking
method.
8.4 Contents of Optical Fiber Cable System such as junction section, capacity of line system, attenuation loss, name of optical mode and so on.
9. Schematic diagrams for optical fiber cable core
and fiber optics covers.
This drawing shall cover all necessary factors for interfacing with transmission systems as the line system design.
10. Contents of Installation/Construction Drawings for
the Micro-Duct System
10.1 The duct systems drawings are composed of 2 kinds of drawings, and are to be combined and drawn on A-1 size paper. One is the geographic plan for roads along routes of duct system drawn to a scale of 1/1000.
10.2 The other is the longitudinal profile of vertical section along the center line of duct system routes, and is to be on a scale of 1/1000 for horizontal length and 1/100 for vertical level.
The plan drawing shall contain:
10.2.1 Location of manhole with their names and types supported by cross-section drawings of roads for such location at a scale of 1/100;
10.2.2 Location of ducts runs with the duct
composition and each duct span
![Page 62: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/62.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e62
length between adjacent 2 centers of manhole, Riser ducts or the internal wall of a cable vault;
10.2.3 Location of length of sections showing details of protective measures;
10.2.4 Location and length of duct bridges, duct attachments to bridges and boring sections supported by detailed drawings of structure; and
10.2.5 Direction of north to be indicated.
10.3 Longitudinal profile drawings shall contain:
10.3.1 Level of ground, top and bottom of duct run at each 30,’s horizontal distance, and levels of bottom and shoulder (outer side) of manhole;
10.3.2 Top and bottom levels of other underground facilities (power cable, water/sewage pipe etc.) and levels of natural or artificial features along the duct routes (river, culvert, railways, etc.); and
10.3.3 Longitudinal profile drawings shall be so arranged to have the manhole on the plan drawing.
11. The contractor is required to designate a qualified on-site engineer for proper supervision and coordination of the project. He must undergo interview with DOST/ICT Office FOC Team for verification.
12. The Contractor shall, in order to keep the design accurate and practical and at his own expense, perform the following:
12.1 When necessary, make test holes at key point of the route to avoid interference with underground facilities and/or hard – rocks as much as practically possible;
12.2 Obtain prior approval from municipalities and/or other relevant authorities/agencies, and third parties for the execution of the work.
12.3 The Contractor shall abide and comply with the terms and conditions specified in the permits obtained from said municipalities and/or other relevant authorities/agencies.
![Page 63: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/63.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e63
ALL necessary Right of Way and Joint Pole Agreement (JPA) permits shall be secured by the Contractor in favor of the DOST – ICT Office.
All permits and fees/charges for the JPA lease, road/underground trench/duct monthly lease will be eventually shouldered by the Project once the Final Acceptance Certificate is issued by DOST/ICT Office.
All charges pertaining to permits and other fees for JPA lease and Right of Way for the duration of the contract, shall be at the expense of the Contractor.
13. The Contractor must conduct due diligence and shall restudy and amend/modify the design drawings not only dependent upon the comments of DOST/ICT Office but also taking into consideration the design concept, and shall resubmit the modified design drawings to DOST/ICT Office within one (1) week after receipt of DOST/ICT Office comments for their approval.
14. In case the Contractor’s re-study of the design is incomplete, and DOST/ICT Office disapproval is repeated, then the Contractor shall be fully responsible for any delay in progress, cost of re-design etc. and DOST/ICT Office will keep the right to order the replacement of the Contractor’s engineer/management in charge of installation/construction design at the Contractor’s own expense.
15. The Contractor shall submit the combined bill of quantities for Duct System and Optical Fiber Cable System as a part of installation/construction design, and shall get approval from DOST/ICT Office and/or Consultant following the same procedures as applied to get approval for installation/construction drawings.
In case the bill of quantities for the Optical Fiber Cable System associated with the related installation/constructions drawings are within the originally contracted amount and are approved by DOST/ICT Office, then, such DOST/ICT Office approval shall be considered as commencement order for site implementation of the approved Bill of Quantities.
![Page 64: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/64.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e64
16. The Contractor shall be responsible for his installation/construction drawings and Bill of Quantities, as a consequential obligation under the Contract to DOST/ICT Office, NGAs and LGUs, other organization/authorities concerned and also to third parties/personnel until the completion of the project.
17. The Contractor shall regard the implementation schedule as the priority requirement. In case the priority order for any section is required by DOST/ICT Office, then, the Contractor shall adjust the schedule accordingly.
17.1 The Contractor shall submit the survey schedule, in great detail for existing facilities, at least ten (10) days prior to the commencement of the survey for each section.
18. In case an agency was found to be in a different location/site than the one specified in the TOR in the detailed site survey/engineering to be done by the winning Contractor, Contractor is required to connect said agency to the Fiber Infra Network.
IV. PROJECT MILESTONES
1. Implementation Schedule
1.1 The Contractor shall submit an integrated project implementation plan showing the following:
1.2 Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty (180) calendar days from date of receipt of Notice to Proceed (NTP);
1.2.1 Number of work teams at any given
time;
1.2.2 Specific dates for work and quality inspection by the DOST/ICT Office team in the FOO clusters;
1.3 The Contractor shall submit integrated implementation updates every 1st day of the week (Monday) to DOST/ICT Office throughout the contractual installation/construction period from the effective date of the Contract until the completion of the Project showing the following detailed milestone, and in
![Page 65: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/65.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e65
accordance with the established schedule and priorities.
1.4 The implementation shall be accurate and
include the following considerations:
1.4.1 To ensure that the work-force is well-distributed through the contractual period taking quality control and timely progress into consideration;
1.4.2 To allow sufficient time and manpower for self-inspections/tests prior to being witnessed by DOST/ICT Office for interim inspections/tests and provisional acceptance tests;
1.4.3 To allow reasonable time for witnessing by DOST/ICT Office of interim inspections/tests considering the work sequence such as cable laying work after DOST/ICT Office has accepted completed systems;
1.4.4 To ensure the sites are properly
managed so as to ensure:
a. Coordination with NGAs, LGUs and other authorities/agencies concerned;
b. Obtaining site implementation
permits and site-entry permits;
c. Adequacy of site security
arrangements.
1.4.5 To keep sufficient time and manpower from transferring site know-how quality control, tools/formats, standard safety arrangement, first aid, etc., to the local staff and local foreman.
1.4.6 To make sure the quality/functions of domestic products fully conform to the specifications any time necessary to upgrade the same.
1.5 The Contractor shall be responsible for conforming to the integrated implementation schedules as strictly as possible after examination and approval by DOST/ICT OFFICE.
1.6 If discrepancies/ambiguities are found or some deviation is necessary in the actual implementation progress, the Contractor shall report the same to DOST/ICT Office and shall
![Page 66: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/66.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e66
take all corrective actions/measures at Contractor’s own expense in accordance with the instructions given by DOST/ICT Office.
1.7 The initial synchronized and integrated implementation schedule specified for the project shall be submitted for DOST/ICT Office’s approval within five (5) days after the effective date of the Contract.
V. AS-BUILT DRAWINGS
1. Technical documents including the As-Built
Drawings shall be required by DOST/ICT Office.
1.1. Documents for Execution of Provisional
Acceptance Test:
1.2. For the main purpose of executing the Provisional Acceptance Test, the Vendor shall prepare the As-Built Drawings. The As-Built Drawing shall be made in a CAD format.
1.3. As-Built Drawings for Cable Networks
The following as-built drawing having the same sizes as the designs/drawings:
1.3.1. General Map to cover all of the serving
area;
1.3.2. Junction Cable Diagram for the
Network;
1.3.3. Key Map for Cable Route (each cable
section);
1.3.4. Junction Cable Duct assignment
Diagram (each cable section);
1.3.5. Detailed fiber core assignments(each
cable section/splicing point);
1.3.6. Junction Cable Location Map (each
cable section);
1.3.7. Optical Fiber Cable Arrangement and Termination on the fiber distribution frame;
1.3.8. Schematic diagram for Fiber Optics
Cores Assignment; and
1.3.9. Special Design Drawing, if any.
![Page 67: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/67.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e67
VI. BILL OF QUANTITIES
1. The contractor must attach a detailed Bill of Quantities (BOQ) showing all the components required to complete the project. This may include, but not limited to:
1.1. Fiber Optic Cable (SMF., ITU –T Recommendation G.652d, NECA/FOA 301 Compliant), Closure, and Cabinet
1.2. Pole Line hardware and accessories
1.3. Poles
1.4. Underground micro-trenching method and/or buried/conduit/directional boring) for the backbone and aerial or underground fiber optic cable (for the distribution
1.5. Optical Distribution Frame (ODF)/Cabinet including patch cord/pig tails, optical fiber trays, db loss/amplification and other equipment, if necessary and accessories
1.6. Engineering, Right of Way, Permits
1.7. List of Equipment
1.8. Contingency
VII. TESTING, COMMISSIONING AND ACCEPTANCE
1. The contractor is responsible in the performance of all civil and cable network pre-test requirement but not limited to:
1.1. Fiber Optic Cable (FOC) – attenuation and all its related testing, power meter test, and grounding test and all other test that may need to perform to complete the FOC test requirements.
Contractor is also required to submit their FOC testing procedures/protocols.
1.1.1. On-reel acceptance tests shall be performed on the cable to confirm the manufacturer’s tests before the installation operation begins. This will also be used to validate the fiber loss/km; at wavelength 1310nm loss shall be 0.4 db/km or less; at 1550nm shall be 0.3dB/km or less.
1.1.2. End-to-end acceptance tests (typically conducted after completion of installation and splicing and before installing terminal equipment).
![Page 68: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/68.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e68
1.1.3. End-to-end attenuation is the amount of optical power loss between cable system connector tips. This will include the fiber and splice /connector loss in the cable system after it has been installed.
1.1.4. Splice acceptance tests (individual
splice insertion losses)
- splice loss shall not be above 0.1 dB for fusion and 0.2 dB for mechanical splices; and
- connectors shall have insertion
losses of 0.5 dB or less.
1.1.5. All test equipment that will be utilized for this project shall have updated calibration certificates to ensure accuracy of results. Contractor is required to submit Calibration Certificates prior to testing.
2. Link Loss Requirements
During the design stage a link loss calculation shall be prepared and included with the project proposal and design packages. The link loss budget shall include:
2.1. Total fiber attenuation (loss), not more that
6db.
2.2. Splice loss (including pigtail splices, if pigtails
are used).
2.3. Connector loss.
2.4. The calculated dB loss cannot exceed the operating range of the terminal equipment that will be installed. Measured end-to-end loss should measure less than the calculated loss. Fibers that measure a higher loss than the link loss budget will not be accepted.
3. Contractor Performance and Workmanship
3.1. DOST/ICT Office will issue provisional and final acceptance certificate to the Contractor certifying that the scope of work has been performed and accomplished in accordance with the approved plans and specification schedules, variation orders if any, and other related contract document.
3.2. The contractor likewise agrees to correct any
defect accruing after the final acceptance of
![Page 69: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/69.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e69
the site facility under the project within the guarantee period. Effective duration of which shall be one (1) year commencing from the date of final acceptance by DOST/ICT Office.
B. MAINTENANCE OF FOC NETWORK IN REGIONAL
GOVERNMENT CENTER IN LEGAZPI CITY FOR TWO (2) YEARS
Note: The maintenance of FOC Network will start once the project is 100% accepted.
I. SCOPE OF WORK
The work includes the following services to be rendered by the Contractor to ensure the continuous operation of the FOC Network
- Conduct daily physical inspections for the
coverage Area.
- All route covering all Agencies connected must be
inspected at least every quarter per year
- 24/7 maintenance team
- Monthly maintenance report. In case of problems encountered and restorations are being done, a separate incident report shall be accomplished.
- Restoration and replacement of damaged FOC
- Repair / restoration of ODF
- Pole replacement / relocation / straightening /
erection
- Repair of damaged duct system
- Re-tensioning and separation of FOC to powerline
- Replacement of FOC pigtail and/or patchcord at
the ODF
- Replacement of Network Equipment (Active
Equipment) and ODF
- Conduct re-tensioning of FOC
- Straightening of leaning concrete pole
- Replacement, relocation & erection of concrete
pole
- Replacement of stolen & burned FOC
- Re-labeling of pole tag
- Re-grounding
- Tree/branch-trimming, if necessary
- Restoration and replacement of damaged micro-
ducts
![Page 70: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/70.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e70
- Maintenance of a warehouse for safe keeping of
spare materials needed
- Contractor is required to secure a 24/7 on-call/standby service crew for immediate response in case of network failure.
II. RESPONSE AND REPORT TIME TARGET
Contractor considers all interruptions in service as urgent priority. Expected response and repair time are given in the table below:
Hours/Days of Coverage
Response Time Restoration
Maximum Time to Respond
Maximum Time to UP the Network
24 x 7 x 365 Days
Monday to
Sunday 1 Hour
6 Hours from the issuance of trouble
ticket
III. MANPOWER REQUIREMENTS
Personnel must be properly trained to use such equipment and do the troubleshooting and restoration and must be available on a moment’s notice.
In order to effectively maintain the FOC Network, maintenance personnel, at the minimum, must include the following:
a. One (1) Project Engineer/Coordinator
b. One(1) FOC team that consists of seven (7)
personnel
- One (1) OSP Supervisor
- Two (2) Lineman
- Two (2) Splicers/Commissioning personnel
- Two (2) Support personnel
![Page 71: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/71.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e71
IV. TOOLS, EQUIPMENT AND MATERIAL REQUIREMENTS
As part of the activity, the following equipment, facilities, tools and materials must be available at all times.
1. List of Tools and Equipment
Contractor must have the following tools and equipment to do the preventive maintenance and restoration activities in the duration of the contract but not to be delivered to ICT OFFICE.
# Quantity Unit Description
1 1 set Arc Fusion Machine
2 1 set Optical Loss Test Set (Power Meter & Light Source)
3 1 set Optical Time Domain Reflectometer (OTDR)
4 2 sets Fiber Extension Ladder 24 feet length
5 2 sets Lineman safety belts
6 2 sets Lineman Tool Kit
7 1 set Cable jack/trailer
8 2 sets Digging bar, shovel, clamshell digger,
9 2 sets Carpentry Tools
10 2 pcs. Wheel meter
11 2 pcs. Cable Cutter
12 2 pcs. Messenger wire cutter
And other necessary tools and equipment needed for maintenance of FOC
![Page 72: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/72.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e72
2. FOC Network Maintenance Supplies for Palo Leyte
Listed in the table are the common materials necessary for the maintenance of the network. (To be delivered by the winning bidder to Palo ICT Office)
# Quantity Unit Description
1 3 drums
96 core, FOC, SM, 1310, Air blown fiber or underground or buried, depends on the FOC supplied during installation 4km/drum
2 3 drums
48 core, FOC, SM, 1310. Self-support, depends on the FOC supplied during installation 4km/drum
2 30 sets FOC Splice Closure-48 core
3 100 pcs. Patch Cord, LC/LC
4 3000 mtrs. 4-way micro-duct or underground HDPE, depends on the FOC supplied during installation
5 1 lot Different size of pole clamps (10 each)
6 1 lot Different types of suspension clamps (10 each)
7 100 pcs. Messenger/Guy grip
Other necessary materials for cable attachments on aerial/underground
Note: All the above mentioned materials shall be made available at the time of the Final Acceptance.
3. Others
3.1. Vehicles
Contractor must have the following vehicles to mobilize necessary tools and materials that will be used in the maintenance of the network in the duration of the contract but not to be delivered to ICT OFFICE
3.1.1 One (1) Splicing Van with Ladder
rack/holder
3.1.2. One (1) Bucket/Boom Truck
3.1.3. One (1) Service Vehicle with Ladder
rack/holder
3.2. Warehouse (ICT OFFICE will provide a 300
square meter open space )
![Page 73: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/73.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e73
Warehouse ( ICTO will provide a 300 square meter open space ) Contractor is required to maintain the quantity of materials in their storage warehouse. Warehouseman must always update and maintain record of the list of components and materials, and prepare reports when stocks are being used. In case of any theft, loss or damages on the materials provided by ICTO, the Contractor or the winning Maintenance Provider will be accountable and must immediately replace the said materials.
3.3. Personnel Protective Equipment (PPE) and
Safety Devices
Contractor must also provide and ensure that all personnel are wearing proper PPE at all times and use safety device in their working area to avoid any accident.
C. FIBER OPTIC CABLE SPECIFICATIONS
I. General Scope:
This covers the minimum requirement of single mode optical fiber cables for the iGovPhil Regional FOC Network as per ITU-T Recommendation G.652d standard.
All the terms used in this specification of single-mode optical fiber cable shall be as defined in the latest ITU-T Recommendation G.652d.
Characteristics not clearly defined in these specifications shall comply with the latest ITU-T G.652d recommendation.
II. Cable Construction: General considerations
The basic purpose is to keep transmission and mechanical strength properties stable in the course of the cable manufacturing process, cable installation work and operation.
Optical fiber cables offered must be able to withstand all possible weather conditions in the Philippines when used in outside plant and installed aerial or underground. The optical fiber cables and accessories offered must be mechanically strong and chemically resistant to be suitable for use under extreme external conditions.
1. Design Consideration
![Page 74: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/74.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e74
The maximum number of optical fibers in a loose tube shall be 12 fibers for cables 48-fiber and above. This requirement must be strictly complied.
The loose tubes and interstices of cable core shall be filled with a suitable compound that could prevent long term penetration of water. Information on the material used for the filling compound shall be stated by the manufacturer.
1.1. Figure-8/Self-support Fiber optic cable
1.1.1. Cable Sheath
1.1.1.1. Black HDPE, a compound of PE and carbon black shall be used for the cable sheath.
1.1.1.2. The moisture barrier shall consist of a longitudinally applied laminate of polymer coated aluminum foil.
1.1.1.3. A rip cord having a minimum breaking load of 150N shall be laid beneath the outer sheath to facilitate access to the fiber.
1.1.1.4. Cable sheath marking
shall be as follows;
1. Property of DOST
Philippines;
2. Manufacturer’s Name
and Fiber Count;
3. Date of Manufacture;
4. Length Marker; and
5. Fiber type: SM
1.1.1.5. The completed cable shall have sequentially numbered length markers at regular intervals of one meter (1.0m).
1.1.1.6. The figure-8/self-support
optical fiber cable shall have 3.2mm thick yellow
![Page 75: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/75.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e75
stripe marked continuously on the sheath.
1.1.2. Strength Member
1.1.2.1. One or more strength members shall be incorporated into a cable structure designed to carry the tensile load associated with installation.
1.1.2.2. The fiber reinforced plastic (FRP), serving mainly as the central strength member must be laminated with an MDPE-Jacket to prevent disintegration/breakage of plastic materials used.
1.2. Air-blown Micro-fiber optic cable
1.2.1. Cable Sheath
1.2.1.1. Black HDPE, a compound of PE and carbon black shall be used for the cable sheath.
1.2.1.2. The moisture barrier shall consist of a longitudinally applied laminate of polymer coated aluminum foil.
1.2.1.3. A rip cord having a minimum breaking load of 150N shall be laid beneath the outer sheath to facilitate access to the fiber.
1.2.1.4. Cable sheath marking shall
be as follows;
6. Property of DOST
Philippines;
7. Manufacturer’s Name and
Fiber Count;
8. Date of Manufacture;
9. Length Marker; and
![Page 76: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/76.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e76
10. Fiber type: SM
1.1.1.5. The completed cable shall have sequentially numbered length markers at regular intervals of one meter (1.0m).
1.2.2. Strength Member
1.2.2.1. One or more strength members shall be incorporated into a cable structure designed to carry the tensile load associated with installation.
1.2.2.2. The fiber reinforced plastic (FRP), serving mainly as the central strength member must be laminated with an MDPE-Jacket to prevent disintegration/breakage of plastic materials used.
1.3. Identification
1.3.1 The color coding of the loose tubes
and the individual fibers within each loose tube shall be as follows:
Tube No./
Fiber No.
Fiber Color
Tube Color
1 Blue Blue
2 Orange Orange
3 Green Green
4 Brown Brown
5 Slate Slate
6 White White
7 Red Red
8 Black Black
9 Yellow Yellow
10 Violet Violet
11 Rose Rose
12 Aqua blue
Aqua Blue
2. Packing of Cables
2.1 Cable protection shall include, as a
![Page 77: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/77.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e77
minimum, a covering placed between the cable reel flanges and over the exposed layer of the cable. The covering shall be weather resistant and shall limit solar heating of the cable such that the cable surface temperature does not exceed 10°C above ambient temperatures under maximum solar radiation.
2.2 The cable ends shall be accessible for testing, and securely fastened to the reel to prevent the cable from becoming loose in transit or during cable installation.
2.3 End caps shall be securely installed to both cable ends to prevent escape of filling compound and entry of moisture during shipping, handling, and storage.
2.4 The manufacturer shall state the sizes of cable drums used for the purpose of packing the offered single mode optical fiber cables. The minimum diameter of spool of the cable drums shall be at least 20 times the cable diameter.
2.5 The spindle hole of each cable drum shall
be greater than 100mm.
2.6 Cable length per reel /drum must be
continuous.
3. Cable Sizes
The manufacturer shall state the outer diameter of the various sizes of the single mode fiber optic cables offered, subject to DOST/ICT Office's approval.
![Page 78: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/78.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e78
D. HANDLING AND STORAGE OF FIBER OPTIC CABLES, EQUIPMENT, FACILITIES AND MATERIALS
Contractor shall ensure that all FOC, equipment and materials necessary for the project are properly handled and secured.
1. As part of the Contract, Contractor must acquire storage house (warehouse) to keep and secure all necessary materials and facilities prior to installations.
2. Contractor must submit Handling and Storage Procedures particularly of the Fiber Optic Cable. This also includes the shipment or transfer of FOC when necessary.
E. CONTRACTORS MUST PRESENT THE FOLLOWING NOT MORE THAN THREE (3) CALENDAR DAYS AFTER RECEIPT OF NOTICE FROM THE BAC4IGOV THAT THE BIDDER HAS BEEN DECLARED L/SCB.:
1. Contractor’s Qualifications:
1.1. Written Statement of the contractor signed by their authorized representative that they have at least 10 years of direct experience on planning, engineering, supply and delivery, installation, testing and commissioning and experience in operations and maintenance of optical fiber transmission backbone projects/systems with major telecommunications carriers in the Philippines.
1.2. Contractor shall submit resume of key
personnel to be assigned to the project
1.3. Must hold a PCAB License on Communications Facilities for a minimum of 5 consecutive years from the date of Bid Opening. ( In case of renewal, the bidder must submit PCAB application and Official Receipt)
2. Specification of offered FOC
2.1 Contractor must provide to DOST/ICT Office the brochure or detailed specifications of their offered fiber optic cable (FOC) vis-à-vis to comply with ITU-T Recommendation G.652d.
![Page 79: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/79.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e79
2.2 Contractor must submit a manufacturer’s ISO certification or other internationally accepted third party certifying authority of their offered FOC.
2.3 The optical fiber cables shall have an expected shelf life span of more than forty (40) years. Contractor must submit a manufacturer’s certification stating the life span of the offered single-mode fiber cables and provide information on how the life span of the offered optical fiber cables was determined.
F. DESIGN CONCEPT
For the design concept in hard copy, the following must be included:
b. The proposed Contractor’s Fiber Network Infra Map/Diagram as basis for implementation, duly signed by a licensed Professional Electronics and Communication Engineer (PECE).
c. Link Loss Budget Calculation from nodes to nodes: (Note: Link loss budget calculation from nodes to nodes should not be more than 6db at 1310nm)
Formula in computing the budget loss calculation:
cable loss + splice losses + connector losses = Budget loss calculation
Wherein:
cable loss = db/km x km
splice loss = db/splice x number of splice
G. INTEGRATED PROJECT PLAN SHOWING THE
FOLLOWING: (LETTERS A-D SHOULD BE IN GANTT CHART FORMAT)
d. Critical Tasks;
e. Milestones;
f. Dependencies;
g. Logs/Slippages (%);
h. Manpower Schedule;
i. Equipment Utilization; and
j. Organizational Chart
The schedule of activities must be within the one hundred eighty (180) calendar day-completion period of the project.
![Page 80: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/80.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e80
H. CONTRACT FOR THE FOC NETWORK MAINTENANCE IS TWO(2) YEARS.
I. PAYMENT Terms and Condition
a. For FOC Network Maintenance Supplies and Materials to be delivered by the winning bidder, full payment will be made upon the acceptance of the delivery.
b. For the Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning of Brand New Fiber Optic Cable Network, payment will be made in Partial Payment as folows;
1. 20% payment – After the contructor
installed 20% of the Total FOC km.
2. 40% payment- Afer the contructor installed
another 40% of the Total FOC km.
3. 40% payment- After the acceptance
c. For Maintenance of ICT OFFICE-DOST Fiber Optic Cable (FOC) Networks in PALO, LEYTE payment will be made every three (3) months.
C. Duration : 180 calendar days
Name of Company
Signature Over Printed Name Of Authorized Representative
Date
![Page 81: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/81.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e81
Revised Annex V-A as of 03 November 2015 (page 1 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 1: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Baguio City
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A
RATING OF “FAILED”. Line
No.: Project Requirements
Bidder’s Statement of
Compliance
1
ICT Office Technical Specifications For the Supply, Delivery, Installation, Splicing, Testing
Commissioning, Operation and Maintenance of Brand
New Fiber Optic Cable in Baguio City
2
Brand and Model No.: ___________________________________________________
________________________________________________________________________________ ________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________ ________________________________________________________________________________
BIDDER’S UNDERTAKING I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as
applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and
conditions contained in the bid documents, including the posting of the required performance security
within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 82: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/82.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e82
Revised Annex V-A as of 03 November 2015 (page 2 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 1: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Baguio City
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement
of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line No.:
Other Requirements Bidder’s Statement of
Compliance
3 Bidder has no overdue deliveries or unperformed services
intended for the ICT Office
4 Bidder did not participate as consultant in the preparation of the design or technical specifications of the GOODS as subject of the
bid
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as
applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and conditions contained in the bid documents, including the posting of the required performance security
within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 83: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/83.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e83
Revised Annex V-A as of 03 November 2015 (page 3 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 1: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Baguio City
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement
of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line
No.:
Project Requirements
If Awarded the Contract
Bidder’s Statement of
Compliance
5 Delivery Place and Installation Distribution:
Baguio City
6
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty
(180) calendar days from date of receipt of Notice to Proceed (NTP).
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and
conditions contained in the bid documents, including the posting of the required performance security
within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 84: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/84.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e84
Revised Annex V-A as of 03 November 2015 (page 4 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 1: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Baguio City
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement
of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A
RATING OF “FAILED”. Line No.:
Project Requirements If Awarded the Contract
Bidder’s Statement of Compliance
7 Operations and Maintenance
Manual
To submit Operation and Maintenance Manual upon completion of the project (in CD and hard
copy).
8 Replacement of
Defective Items
Replacement of defective items delivered within fifteen (15) calendar days from receipt of Notice
of Defects from ICT Office. Service unit must be
provided while awaiting replacement.
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and conditions contained in the bid documents, including the posting of the required performance security
within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 85: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/85.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e85
Revised Annex V-A as of 03 November 2015 (page 5 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 1: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Baguio City
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement
of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line
No.:
Project Requirements
If Awarded the Contract
Bidder’s Statement of
Compliance
9 Warranty Warranty Certificate issued in favor of ICT
Office.
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and conditions contained in the bid documents, including the posting of the required performance security
within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 86: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/86.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e86
Revised Annex V-B as of 03 November 2015 (page 1 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 2: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi City
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A
RATING OF “FAILED”. Line
No.: Project Requirements
Bidder’s Statement of
Compliance
1
ICT Office Technical Specifications For the Supply, Delivery, Installation, Splicing, Testing
Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi City
2
Brand and Model No.: ___________________________________________________
________________________________________________________________________________ ________________________________________________________________________________
________________________________________________________________________________ ________________________________________________________________________________
________________________________________________________________________________
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as
applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and
conditions contained in the bid documents, including the posting of the required performance security within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 87: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/87.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e87
Revised Annex V-B as of 03 November 2015 (page 2 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 2: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi City
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line
No.: Other Requirements
Bidder’s Statement of
Compliance
3 Bidder has no overdue deliveries or unperformed services
intended for the ICT Office
4 Bidder did not participate as consultant in the preparation of the design or technical specifications of the GOODS as subject of the
bid
BIDDER’S UNDERTAKING I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as
applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and
conditions contained in the bid documents, including the posting of the required performance security within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 88: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/88.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e88
Revised Annex V-B as of 03 November 2015 (page 3 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 2: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi City
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line
No.:
Project Requirements
If Awarded the Contract
Bidder’s Statement of
Compliance
5 Delivery Place and Installation Distribution:
Legazpi City
6
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty
(180) calendar days from date of receipt of Notice to Proceed
(NTP).
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and conditions contained in the bid documents, including the posting of the required performance security
within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 89: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/89.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e89
Revised Annex V-B as of 03 November 2015 (page 4 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 2: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi City
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line
No.:
Project Requirements
If Awarded the Contract
Bidder’s Statement
of Compliance
7
Operations and
Maintenance
Manual
To submit Operation and Maintenance Manual
upon completion of the project (in CD and hard
copy).
8 Replacement of
Defective Items
Replacement of defective items delivered within
fifteen (15) calendar days from receipt of Notice
of Defects from ICT Office. Service unit must be provided while awaiting replacement.
BIDDER’S UNDERTAKING I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as
applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and
conditions contained in the bid documents, including the posting of the required performance security within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 90: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/90.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e90
Revised Annex V-B as of 03 November 2015 (page 5 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 2: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi City
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line
No.:
Project Requirements
If Awarded the Contract
Bidder’s Statement of
Compliance
9 Warranty Warranty Certificate issued in favor of ICT
Office.
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as
applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and conditions contained in the bid documents, including the posting of the required performance security
within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 91: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/91.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e91
Revised Annex V-C as of 03 November 2015 (page 1 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 3: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Palo, Leyte
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line
No.: Project Requirements
Bidder’s Statement of
Compliance
1
ICT Office Technical Specifications
For the Supply, Delivery, Installation, Splicing, Testing
Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Palo, Leyte
2
Brand and Model No.: ___________________________________________________
________________________________________________________________________________ ________________________________________________________________________________
________________________________________________________________________________ ________________________________________________________________________________
________________________________________________________________________________
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and
conditions contained in the bid documents, including the posting of the required performance security within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 92: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/92.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e92
Revised Annex V-C as of 03 November 2015 (page 2 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 3: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Palo, Leyte
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement
of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line No.:
Other Requirements Bidder’s Statement of
Compliance
3 Bidder has no overdue deliveries or unperformed services
intended for the ICT Office
4 Bidder did not participate as consultant in the preparation of the design or technical specifications of the GOODS as subject of the
bid
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as
applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and conditions contained in the bid documents, including the posting of the required performance security
within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 93: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/93.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e93
Revised Annex V-C as of 03 November 2015 (page 3 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 3: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Palo, Leyte
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement
of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line
No.:
Project Requirements
If Awarded the Contract
Bidder’s Statement of
Compliance
5 Delivery Place and Installation Distribution:
Palo, Leyte
6
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty
(180) calendar days from date of receipt of Notice to Proceed (NTP).
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and
conditions contained in the bid documents, including the posting of the required performance security
within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 94: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/94.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e94
Revised Annex V-C as of 03 November 2015 (page 4 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 3: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Palo, Leyte
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement
of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line
No.:
Project Requirements
If Awarded the Contract
Bidder’s Statement
of Compliance
7
Operations and
Maintenance Manual
To submit Operation and Maintenance Manual
upon completion of the project (in CD and hard copy).
8 Replacement of Defective Items
Replacement of defective items delivered within
fifteen (15) calendar days from receipt of Notice of Defects from ICT Office. Service unit must be
provided while awaiting replacement.
BIDDER’S UNDERTAKING I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as
applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and
conditions contained in the bid documents, including the posting of the required performance security within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 95: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/95.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e95
Revised Annex V-C as of 03 November 2015 (page 5 of 5)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
Lot 3: Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Palo, Leyte
Bid Ref No. BAC4IGOV-2015-10-050
TECHNICAL BID FORM
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement
of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE
ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”. Line
No.:
Project Requirements
If Awarded the Contract
Bidder’s Statement of
Compliance
9 Warranty Warranty Certificate issued in favor of ICT
Office.
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and conditions contained in the bid documents, including the posting of the required performance security
within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
![Page 96: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/96.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e96
Revised Annex VIII-B1 as of 03 November 2015 (page 1 of 4)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
REVISED DETAILED FINANCIAL BREAKDOWN (QUOTED PRICE MUST BE INCLUSIVE OF VAT)
Lot 2: Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning, Operation and Maintenance of Brand New Fiber Optic Network in Legazpi City
Bid Ref No. BAC4IGOV-2015-10-050
INSTRUCTION:
The Sum of the Detailed Financial Breakdown must be equal to the Financial Bid per Annex VII. Do not leave any blanks. Indicate “0” if the item is being offered for free.
ITEM Qty Unit Cost Total Cost per Item
FOC Network Maintenance Supplies and Materials to be delivered by the winning bidder to ICT Office LEGAZPI 96 core, FOC, SM, 1310, Air blown or underground or buried fiber (depending on what type of fiber to be installed) 4km/drum
3 drums
48 core, FOC, SM, 1310. Self-support (depending on what type of fiber to be installed), 4km/drum
3 drums
FOC Splice Closure-48 core 30 sets Patch Cord, LC/LC 100 pcs 4-way micro-duct, HDPE 3000 mtrs Different size of pole clamps (10 each) 1 lot Different types of suspension clamps (10 each) 1 lot Messenger/Guy grip 100 pcs FOC Maintenance for two (2) years (Contractor must have the following tools, equipment, vehicles and manpower to do the preventive maintenance and restoration activities in the duration of the contract but not to be delivered to ICT Office.)
ITEM Qty Utilization
Cost Total Utilization
Cost Arc Fusion Machine 1 set Optical Loss Test Set (Power Meter & Light Source)
1 set
Optical Time Domain Reflectometer (OTDR) 1 set Fiber Extension Ladder 24 feet length 2 sets Lineman safety belts 2 sets Lineman Tool Kit 2 sets Cable jack/trailer 1 set Digging bar, shovel, clamshell digger 2 sets Carpentry Tools 2 sets Wheel meter 2 pcs Cable Cutter 2 pcs Messenger wire cutter 2 pcs
![Page 97: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/97.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e97
Revised Annex VIII-B1 as of 03 November 2015 (page 2 of 4)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
DETAILED FINANCIAL BREAKDOWN (QUOTED PRICE MUST BE INCLUSIVE OF VAT)
Lot 2: Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning, Operation and Maintenance of Brand New Fiber Optic Network in Legazpi City
Bid Ref No. BAC4IGOV-2015-10-050
INSTRUCTION:
The Sum of the Detailed Financial Breakdown must be equal to the Financial Bid per Annex VII. Do not leave any blanks. Indicate “0” if the item is being offered for free.
ITEM Qty Utilization
Cost Total Utilization
Cost Contractor must have the following vehicles to mobilize necessary tools and materials that will be used in the maintenance of the network in the duration of the contract but not to be delivered to ICT Office Splicing Van with Ladder rack/holder 1
Bucket/Boom Truck 1
Service Vehicle with Ladder rack/holder 1
Minimum FOC Network maintenance personnel for Legazpi Project Engineer/Coordinator 1
One (1) FOC team which is consisting of seven (7) personnel:
a. OSP Supervisor 1
b. Lineman 2
c. Splicers/Commissioning personnel 2
d. Support personnel 2
Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning of Brand New Fiber Optic Cable Network in Legazpi
ITEM Qty Unit Cost Total Cost per Item 96 core Optical Fiber Cable
48 core Optical Fiber Cable
Route Survey
Installation of 4-ways HDPE Installation of underground micro-trenching method and/or buried/conduit/directional boring) for the backbone and aerial or underground fiber optic cable for the distribution approximately 15 kms for the backbone cable routes
Underground installation of 96 core for Backbone Network (micro-trenching method and/or buried/conduit/directional boring) and appurtenances for the proposed project
![Page 98: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/98.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e98
Revised Annex VIII-B1 as of 03 November 2015 (page 3 of 4)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
REVISED DETAILED FINANCIAL BREAKDOWN (QUOTED PRICE MUST BE INCLUSIVE OF VAT)
Lot 2: Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning, Operation and Maintenance of Brand New Fiber Optic Network in Legazpi City
Bid Ref No. BAC4IGOV-2015-10-050
INSTRUCTION:
The Sum of the Detailed Financial Breakdown must be equal to the Financial Bid per Annex VII. Do not leave any blanks. Indicate “0” if the item is being offered for free.
ITEM Qty Unit Cost Total Cost per Item
Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning of Brand New Fiber Optic Cable Network in Legazpi Aerial or Underground installation of 48 core for Distribution Network or Fiber to the Building (micro-trenching method and/or buried/conduit/directional boring) and appurtenances for the proposed project
Installation of Optical Distribution Frame (ODF)/Cabinet including patch cord/pig tails, optical fiber trays
Termination of 96 cores FOC on PoP(Point of Presence) and 48 cores FOC on the client agencies/stations
As-build plans of all plans and drawings (network, route, termination, splicing, etc.) required by the project
Splicing and termination of fiber optic cable;
Testing and commissioning (provisional and final acceptance) of newly installed FOC; and
Restoration of all affected facilities.
Permits
TOTAL
![Page 99: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/99.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e99
Revised Annex VIII-B1 as of 03 November 2015 (page 4 of 4)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
INFORMATION AND COMMUNICATIONS TECHNOLOGY OFFICE
REVISED DETAILED FINANCIAL BREAKDOWN (QUOTED PRICE MUST BE INCLUSIVE OF VAT)
Lot 2: Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning, Operation and Maintenance of Brand New Fiber Optic Network in Legazpi City
Bid Ref No. BAC4IGOV-2015-10-050
INSTRUCTION:
The Sum of the Detailed Financial Breakdown must be equal to the Financial Bid per Annex VII. Do not leave any blanks. Indicate “0” if the item is being offered for free.
TOTAL BID PRICE (Amount in Words):
BIDDER’S UNDERTAKING I/We, the undersigned bidder, having examined the bidding documents including Bid Bulletins, as
applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and conditions contained in the bid documents, including the posting of the required performance security within ten
(10) calendar days from receipt of the Notice of Award.
Until a formal contract is prepared and signed, this Bid is binding on us. ___________________________________
Name of Company (in print) ___________________________________
Signature of Company Authorized Representative ___________________________________
Name and Designation (in print) ___________________________________
Date
![Page 100: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/100.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e10
0
ICT OFFICE BAC4IGOV REVISED CHECKLIST OF REQUIREMENTS FOR BIDDERS
AS OF 03 NOVEMBER 2015 Name of Company :_______________________________ Name of Project : Design, Supply, Delivery, Installation, Splicing,
Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo)
Bid Ref No. BAC4IGOV-2015-10-050 APPROVED BUDGET FOR THE CONTRACT : PhP85,380,168.00
Description Qty ABC PhP
(VAT Inclusive)
Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Baguio City
1 lot 31,561,974.00
Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi, Albay
1 lot 32,294,339.00
Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Palo, Leyte
1 lot 21,523,855.00
Ref. No.
Particulars ENVELOPE 1: ELIGIBILITY AND TECHNICAL DOCUMENTS ELIGIBILITY DOCUMENTS
CLASS “A” DOCUMENTS
12.1
(a.1.) ELIGIBILITY DOCUMENTS
i. Registration certificate from the Securities and Exchange Commission (SEC), Department of Trade and Industry (DTI) for sole proprietorship, or Cooperative
Development Authority (CDA) for cooperatives
ii. Business/Mayor's permit for 2015 issued by the city or municipality where the principal place of business of the prospective bidder is located
iii. Valid and Current Tax Clearance per Executive Order 398, Series of 2005, as
finally reviewed and approved by the BIR.
iv. Statement of all its Ongoing (including awarded contract/s not yet started, if any)
within the last three (3) Years, (Annex I) Any of the following documents must be submitted corresponding to listed
contracts per submitted Annex I:
![Page 101: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/101.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e10
1
a) Notice of Award; or b) Notice to Proceed
v. Statement of Completed Single Largest Contract from January 2010 up to the day
before the deadline for the submission bids of similar in nature equivalent to at least fifty percent (50%) of the ABC. Annex I-A
Any of the following documents must be submitted corresponding to listed contracts per submitted Annex I-A:
a) Copy of End User’s Acceptance; or
b) Copy of Official Receipt/sA
vi. Copy of 2014 Annual Income Tax Return submitted through BIR’s
Electronic Filing and Payment System (EFPS) together with the following Audited Financial Statements for 2014 and 2013 (in comparative form or separate
reports):
a) Copy of Independent Auditor’s Report; b) Balance Sheet (Statement of Financial Position);
c) Income Statement (Statement of Comprehensive Income);
Each of the above statements must have stamped “received” by the Bureau of
Internal Revenue (BIR) or its duly accredited and authorized institutions
vii. Duly signed Net Financial Contracting Capacity Computation (NFCC) per Annex
II, in accordance with ITB Clause 5.5 NFCC = [(Current Assets minus Current Liabilities) (K)] minus the value of all
outstanding or uncompleted portions of the projects under ongoing
contracts, including awarded contracts yet to be started coinciding with the contract to be bid.
Where: K: 10 for a contract duration of one year or less, 15 for a contract
duration of more than one year up to two years, and 20 for a contract
duration of more than two years.
Notes: 1. The values of the bidder’s current assets and current liabilities shall be based on
the data submitted to BIR through its Electronic Filing and Payment System. 2. Value of all outstanding or uncompleted contracts refers those listed in Annex-I.
3. The detailed computation using the required formula must be shown as provided above.
CLASS “B” DOCUMENTS (FOR JOINT VENTURE)
i. For Joint Ventures, Bidder to submit either: 1. Copy of the JOINT VENTURE AGREEMENT (JVA) in case the joint
venture is already in existence, or 2. Copy of Protocol / Undertaking of Agreement to Enter into Joint
Venture signed by all the potential join venture partners stating that they will enter into and abide by the provisions of the JVA in the instance that the bid is successful. (Annex III)
The JVA or the Protocol/Undertaking of Agreement to Enter into Joint Venture (Annex III) must include/specify the company/partner and the name of the office designated as authorized representative of the Joint Venture. For Joint Venture, the following documents must likewise be submitted: For Joint Venture Between Two (2) Local Companies, each partner
![Page 102: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/102.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e10
2
should submit: 1. Registration Certificate from the Securities and Exchange Commission
(SEC) for corporations, Department of Trade and Industry (DTI) for sole proprietorship, or Cooperative Development Authority (CDA) for cooperatives;
2. Business/Mayor's permit for 2015 issued by the city or municipality where the principal place of business of the prospective bidder is located;
3. Valid and Current Tax Clearance per Executive Order 398, Series of 2005, as finally reviewed and approved by the BIR.
For item (iv) to (vii) of the required eligibility documents, submission by any of the Joint Venture partner constitutes compliance.
TECHNICAL DOCUMENTS
12.1 (b)(i)
Bid security shall be issued in favor of the INFORMATION AND COMMUNICATIONS
TECHNOLOGY OFFICE (ICT Office) valid at least one hundred twenty (120) days after date of bid opening in any of the following forms:
a) BID SECURING DECLARATION per Annex IV; or
b) Cashier’s / Manager’s Check equivalent to at least 2% of ABC issued by a Local or Universal or Local Commercial Bank.
Description Qty ICT Office ABC
Total Price
Bid Security:
Cash, Cashier’s / Manager’s
Check, (2%) (P)
Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Baguio City
1 lot 31,561,974.00 631,239.48
Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi, Albay
1 lot 32,294,339.00 645,887.98
Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Palo, Leyte
1 lot 21,523,855.00 430,4771.10
12.1
(b)(ii)
Duly signed and completed Technical Bid Form. Bidder must use, accomplish and submit the
Technical Bid Form hereto attached as Annex V-A, B, C as of 11/02
12.1 (b)(ix)
Proof of Authority of the Bidder’s authorized representative/s: a) FOR SOLE PROPRIETORSHIP (IF OWNER OPTS TO APPOINT A
REPRESENTATIVE): Duly notarized Special Power of Attorney
b) FOR CORPORATIONS, COOPERATIVE OR THE MEMBERS OF THE JOINT
VENTURE:
![Page 103: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/103.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e10
3
Duly notarized Secretary’s Certificate evidencing the authority of the designated representative/s.
IN THE CASE OF UNINCORPORATED JOINT VENTURE: Each member shall submit a separate Special Power of Attorney and/or Secretary’s Certificate evidencing the authority of
the designated representative/s.
12.1
(b)(xii)
Omnibus Sworn Statements using the form prescribed. (Annex VI)
a) Authority of the designated representative
b) Non-inclusion of blacklist or under suspension status
c) Authenticity of Submitted Documents
d) Authority to validate Submitted Documents
e) Disclosure of Relations
f) Compliance with existing labor laws and standards
g) Did not pay any form of consideration
Section VI.
Statement of compliance with the Revised Schedule of Requirements
Section
VII. Statement of compliance with the Revised Technical Specifications as of 11/02
ENVELOPE 2: FINANCIAL DOCUMENTS
13.1
(a)
Completed and signed Financial Bid Form. Bidder must use, accomplish and submit
Financial Bid Form hereto attached Annex VII.
Annex Description Qty ABC P (VAT Inclusive)
Total
VII-A
Supply, Delivery, Installation,
Splicing, Testing Commissioning,
Operation and Maintenance of Brand New Fiber Optic Cable in
Baguio City
1 lot 31,561,974.00
VII-B1 revised as
of 03 November
2015
Supply, Delivery, Installation, Splicing, Testing Commissioning,
Operation and Maintenance of Brand New Fiber Optic Cable in
Legazpi, Albay
1 lot 32,294,339.00
VII-C1
Supply, Delivery, Installation, Splicing, Testing Commissioning,
Operation and Maintenance of Brand New Fiber Optic Cable in
Palo, Leyte
1 lot 21,523,855.00
The ABC is inclusive of VAT. Any proposal with a financial component exceeding the ABC shall not be accepted. Further, the sum of bid for each item indicated in the Revised
Detailed Financial Breakdown per Annex VIII-A1, B1 as of 03 November 2015, C1 must be equal to the signed and submitted Financial Bid Form per Annex VII.
![Page 104: BIDS AND AWARDS COMMITTEE FOR THE …i.gov.ph/wp-content/uploads/2015/11/SBB-3-FOC-Baguio-Legaspi-and... · Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation,](https://reader031.fdocuments.net/reader031/viewer/2022030903/5b4413e77f8b9a64608b93a2/html5/thumbnails/104.jpg)
Supplemental Bid Bulletin No. 3 Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Band New
Fiber Optic Cable in Three (3) Regional Government Centers (Baguio, Legazpi, Palo) Bid Reference No. BAC4iGOV-2015-10-050
Pag
e10
4
Revised Detailed Financial Breakdown per Annex VIII-A1,B1as of 03 November
2015 , C1
Annex Description Qty ABC P (VAT Inclusive)
Total
VIII-A
Supply, Delivery, Installation,
Splicing, Testing Commissioning, Operation and Maintenance of
Brand New Fiber Optic Cable in
Baguio City
1 lot 31,561,974.00
VIII-B1
revised as
of 03 November
2015
Supply, Delivery, Installation,
Splicing, Testing Commissioning,
Operation and Maintenance of Brand New Fiber Optic Cable in
Legazpi, Albay
1 lot 32,294,339.00
VIII-C1
Supply, Delivery, Installation,
Splicing, Testing Commissioning,
Operation and Maintenance of Brand New Fiber Optic Cable in
Palo, Leyte
1 lot 21,523,855.00
13.1 (b)
If the Bidder claims preference as a Domestic Bidder or Domestic Entity, a Certification from the DTI, SEC or CDA to be enclosed pursuant to the Revised IRR of R.A. 9184.
15.4(a)(i) &
15.4(b)(ii)
Completed “For Goods Offered from Abroad” and/or “For Goods Offered From
Within the Philippine” Forms per Annex VIII-A and Annex VIII-B, whichever is applicable.
NOTE:
In case of inconsistency between the Checklist of Requirements for Bidders
and the provisions in the Instruction to Bidders/Bid Data Sheet, the Instruction to Bidders/Bid Data Sheet shall prevail