BFH The Path to Net Zero Energy Houses in Cold Climates
-
Upload
shawna-henderson -
Category
Business
-
view
758 -
download
1
description
Transcript of BFH The Path to Net Zero Energy Houses in Cold Climates
The Process of Progressions
Net Zero Energy
75% reduction
50% reduction
25% reduction
Current Practice
} The Path to Net Zero
A Net Zero Energy House produces as much energy as it uses on an annual basis.
This presentation focusses on how to get there.
Reductions most cost-effective in this order
Air tightness measures
Increase insulation
Water conservation
Mechanicals
Renewables
} Focus of measures in progressions
Capacity exceeds code requirements
Issues
Concerns
Challenges
Innovations on the horizon
} NRCan targets/goals for Industry
Energy Intensity vs. House Size
Issues
Concerns
Challenges
} Energy Intensity
Lighting 5% Appliances
13%
Water 17%
Space 65%
ERS80 (PRE-2012 R-2000)
Lighting 6%
Appliances 16%
Water 21%
Space 57%
ERS86 (conventional HVAC)
Series of challenges to reduce various loads
Reduce space heating load
Air tightness measures
Insulation Measures
Reduce water heating load
Fixtures
Drainwater Heat Recovery
Meeting DWH load becomes biggest challenge
Mechanicals designed around low temp hot water delivery
Minimal electrical loads @ fans/pumps
Small loads, can sacrifice efficiency @ blower
Electrical base loads
Primarily occupant driven
Builder has minimal impact
} Energy End Use Patterns
Lighting 13%
Appliances 46%
Water 8%
Space 33%
Net Zero Energy (solar thermal option)
Note: Ventilation included in ‘Space’ component in charts, ranges from 2% of overall energy load in ERS80 to 9% in NZE
Lighting 10%
Appliances 44%
Water 20%
Space 26%
Net Zero Energy (non-solar thermal)
Revisit, Revise, Rethink
Measures taken in initial progressions impact the types of measures (and associated costs) further down the path to Net Zero Energy.
} Energy Analysis & Financial Evaluation Work Flow
Excel worksheet
Revise ���to targets
IRR/ simple
payback
Costings Loads w/fuel equivalents
Energy contributions Incremental capital costs over baseline
Reductions in purchased fuel Contributions from Renewables
Offsets to purchased fuel (DWHR)
Select target reduction from baseline
Model for 25%, 50%, 75% ���and 100% reductions ���
from baseline
Select regionally appropriate assemblies to increase
insulation levels
Specify high performance mechanicals and renewables
Estimate regional fuel costs
Ramping it up
Air sealing & increasing insulation highest priorities for ERS80↓25% & ERS80↓50%
Mechanicals are the highest priorities for ERS80↓75%
Renewables are the highest priorities for NZE
} Progressions
ERS 80 (Existing R2000)
• Performance Path, NSBC 2010, OBC 2012, NBC 2012 • NOTE: R2000 requires 1.5ACH @ 50Pa but ERS80 does not
ERS80↓25% ESNH
• Air sealing: key for production builders – close in on 1.5 ACH • Increase insulation -- Use exterior air barriers/rigid board ins. to help reduce ACH • Higher efficiency conventional mechanicals (incl. HRV)
ERS80↓50% R-2000
• Envelope: Further air sealing (1.0 ACH vs. 1.5 ACH), increase insulation, upgrade windows • Hot water conservation – DWHR • Higher efficiency, smaller space heating equipment • Integrated mechanicals?
ERS80↓75%
• Last push @ envelope: emerging high-efficiency materials/windows • Mechanicals: Integrated, renewables, match load, supply temps to delivery • DHW is the load challenge • Emerging technologies: air to water heat pumps, solar thermal concentrators, co-generation
Net Zero Energy
• Choose mechanicals to reduce electrical loads as well as heating loads • Reduce all possible electrical loading (LEDs, Energy Star appliances, motion detectors) • Site-generated electricity production to match anticipated loads
Like standard practice, only better
Exterior insulation
Combinations
Innovative materials
Assembly Issues
Brick ledge
Fasteners
Window bucks & details
Drainage plane
Construction Issues
Trades scheduling
Inspectors
} Materials and Assemblies
Fig. 1
Fig. 2
Fig. 3
Like standard practice, only better
Tried & True
Air sealing interior VDR
Insulating with foam or fibre
Innovative
Quad glass with 2 suspended films, krypton fill
Vacuum Insulated panels: RSI 22.7/mm (R30/inch)
} Materials and Assemblies
Like standard practice, only better
Integrated systems
Space and water heating/cooling
Space/water & ventilation
Flexibility of energy sources
What types?
How many?
Issues
Preplanning
Servicing non-conventional systems
Distribution systems
} Mechanicals
Air handler
Hot water coil
Evaporator Coil (cooling) optional
Integrated Space Conditioning and Water Heating (forced air)
Air to Water Heat Pump (hydronic space conditioning and water heating)
Always cheaper to save a Watt than make a Watt
Reduce loads
Space heating
Water heating
Lighting
Appliances
Builder can only supply a house than can approach net zero energy
Energy usage dependent on occupant lifestyle
Preplanning
Solar thermal
PV
Micro co-generation
District energy
} Renewables
What works in different areas
Assemblies & materials
Mechanicals
Airtightness
Labour/Trades
Fuel Costs/Perceptions
} Regional Differences
Large/Mid-size Production or Custom
Scheduling issues
Labour/training issues
Client interaction
Market Dynamics
} Builder Type – Economies of Scale
Internal Rate of Return vs. Payback
What is Payback • The time required for the
return on an investment to “repay” the sum of the original investment.
What is Internal Rate of Return (IRR)? • Tells you how well your
money is working for you compared to other investments or costs of borrowing.
• Indicator of the efficiency,
quality or yield of an
investment.
} Financial Valuation of Premiums
Internal Rate of Return: the point on the graph where the costs of the investment equal the benefits of the investment. Expressed as a percentage that represents how well your investment is working for you each year after you have taken care of all of your costs.
Planning Horizon (years)
All
cash
flow
s (+
/-)
Years after capital expenditure
Capital Expenditure
Simple Payback: the point on the graph where the cost of the investment is recovered. Expressed in years or months
Perceptions of Costs
Simple Payback:
“The quicker the better”
vs.
long-term investment
How to talk about IRR?
• IRR of 10% over 10 years for
NZE construction/mechanicals can
be compared to interest on the
increased mortgage principal
needed for the premium to be
paid over and above the baseline
construction and mechanicals
} Communicating IRR to the Client
costs benefits
House Characteristics
325 m2 (3,500 s.f.) living space
2 storey house + finished basement
>15% glazing
Attached garage
Conventional mechanicals
} ESNH/R-2000 Upgrade Package (Ottawa) 2-storey w/basement ERS80 Baseline
ID
Library Part Na... D1 10 D1 Entrance 10 D1 Entrance 10 D1 Garage 1 10 D1 Pocket 10 D2 10
Quantity 5 1 1 1 1 1
W x H Size 0.813x2.000 1.067x2.100 1.219x2.100 3.048x2.134 0.762x2.100 1.800x2.100
2D Symbol
3D Front View
Door Legend
12
4
12
10
A5 HOUSE 3 DOOR SCHEDULE 1:1
A5 HOUSE 3 REAR ELEVATION 1:64A5 HOUSE 3 FRONT ELEVATION 1:64
ID
Library Part Na... D1 10 D1 Entrance 10 D1 Entrance 10 D1 Garage 1 10 D1 Pocket 10 D2 10
Quantity 5 1 1 1 1 1
W x H Size 0.813x2.000 1.067x2.100 1.219x2.100 3.048x2.134 0.762x2.100 1.800x2.100
2D Symbol
3D Front View
Door Legend
12
4
12
10
A5 HOUSE 3 DOOR SCHEDULE 1:1
A5 HOUSE 3 REAR ELEVATION 1:64A5 HOUSE 3 FRONT ELEVATION 1:64
98
5.11
46
8.88
2.93
2.09
2.42
2.42
4.83
8.60
BEDROOM
BEDROOM
38mm x 140mm framing @400mm O.C. drywall
INTERIOR AREA:41.538 m2
BEDROOM
HOUSE 3
HOUSE 3
HOUSE 3
HOUSE 3
HOUSE 3
A3 HOUSE 3 UPPER FLOOR PLAN 1:64
Total heated space = 3,500 s.f.
• Air tightness: 4.55 ACH
• ATTIC: RSI 8.8/R50 blown cellulose
• BELOW-GRADE WALLS: RSI 2.1/R12 fibreglass batt interior standoff wall
• ABOVE-GRADE WALLS: RSI 3.9/R22 fibreglass batt
• BELOW SLAB: RSI 1.8/R10
• WINDOWS: Low-e, argon-filled, insulating spacers, vinyl frames
• SPACE HEATING: 92% AFUE gas furnace
• WATER HEATING: 67% AFUE 60 gal tank
• VENTILATION: 60% sensible efficiency
} ESNH/R-2000 Upgrade Package (Ottawa) 2-storey w/basement ERS80 Baseline
W
1
2
3
4
5
6
7
8
9
10
11
12
13
5.11 61 3.66
5.11 4.27
8.29
4.53
8.88
618.
881.
65UNEXCAVATED
LAUNDRY
FINISHEDSLAB ONGRADE
SLAB ON GRADE
38 mmx235mm floor joists @ 400mm
O.C. 18.5mm T&G plywood
FINISHED BASEMENTAREA:
INTERIOR AREA:37.5537m2
45.3768 m2
HOUSE 3
HOUSE 3
HOUSE 3
HOUSE 3
HOUSE 3
A1 HOUSE 3 FOUNDATION 1:64
5'-11" by 6'-11"
3'-6"
6'-11"
3'by
6'3'
by6'
2'-8" by 6'-7"
10' by 7'
4'
6'-1
1"
1
2
3
4
5
6
7
8
9
10
11
12
13
F
1
2
3
4
5
6
7
8
9
10
11
12
13
2.56 3.17
5.72
1.65
5.11
3.84
5.64
9.49
1.27 2.59 1.26 4.27
1.65
45
11.1
3
61
1.65
8.88
61
8.60
612.89
4.83
2.31
2.95
INTERIOR AREA:48.9119 m2
LIVING
GARAGE
9'1" CEILINGHEIGHT
38m
m x
140
mm
fram
ing
@
400m
m O
.C. d
ryw
all
KITCHEN
38 mmx235mm floor joists @ 400mm
O.C. 18.5mm T&G plywood
HOUSE 3
HOUSE 3
HOUSE 3
HOUSE 3
HOUSE 3
A2 HOUSE 3 MAIN FLOOR 1:64
Changes from ERS80
ESNH Envelope (ERS80↓25%):
• Air tightness: 2.0 ACH
• ATTIC: RSI 10.6/R60 blown cellulose
• ABOVE-GRADE WALLS: RSI 3.9/R22 fibreglass batt plus 2” Type IV exterior (or 1.5” polyisocyanurate) 10” fdn wall for brick siding
• BELOW-GRADE WALLS: RSI 3.9/R22 fibreglass batt interior standoff wall
• BELOW SLAB: RSI 1.8/R10, no change from baseline
} ESNH (ERS80↓25%) Package, Ottawa
Measure Upgrade Cost
GJ saved
RSI 10.6/R60 attic RSI 6.3/R32 above grade walls RSI 3.9/R22 below grade walls
$540 $6815 $818
46.47 GJ
86% AFUE Instantaneous gas DHW
Rental vs. $1100
7.90 GJ
75% Efficient HRV $300 -1.82 GJ
DWHR $500 2.63 GJ
Changes from ERS80
R2000 Envelope (ERS80↓50%):
• AIR TIGHTNESS: 1.0 ACH
• ATTIC: RSI 10.6/R60 blown cellulose
• ABOVE-GRADE WALLS: RSI 3.9/R22 fibreglass batt plus 2.5” polyisocyanurate 10” fdn wall for brick siding
• BELOW-GRADE WALLS: RSI 3.9/R22 fibreglass batt interior standoff wall plus 1.5” Type IV exterior
• BELOW SLAB: RSI 1.8/R10, no change from baseline
} R-2000 (ERS80↓50%) Package, Ottawa
Measure Upgrade Cost
GJ saved
RSI 10.6/R60 attic RSI 7.0/R40 above grade walls RSI 4.9/R28 below grade walls
$540 $15744 $2314
63.99 GJ
86% AFUE Instantaneous gas DHW
Rental vs. $1100
7.90 GJ
75% Efficient HRV $300 -1.82 GJ
DWHR $500 2.63 GJ
Main upgrades from ESNH (ERS80↓25%): Air tightness from 2.0 to 1.0 Below Grade Walls from RSI 3.9/R22 to RSI 4.9/R28 Above Grade Walls from RSI 6.3/R32 to RSI 7.0/R40
Reductions from ERS80
Space heating • ERS80: 94% gas furnace ( AFUE) • ESNH: no change from baseline • R-2000: no change from baseline
Water heating • ERS80: .67 AFUE gas (tank) • ESNH: instantaneous gas water
heater 0.86 EF • R-2000: instantaneous gas water
heater 0.92 EF Hot water load reduced by: • ESNH: 33.05% • ERS86: 33.15%
Ventilation • ERS80: 60% EF HRV • ESNH: 75% EF HRV • R-2000: 75% EF HRV
} ESNH/R-2000 Upgrade Package (Ottawa)
ERS 80 ESNH R-2000
Space heating
108.41 GJ 61.93 GJ 44.42 GJ
Water heating
23.92 GJ 16.01 GJ 15.99 GJ
Base loads 31.53 GJ 31.53 GJ 31.53 GJ
ACH@50Pa 4.55 2.0 1.0
Reductions from ERS80
Cost increase
• ESNH – 25%
• Envelope - $8,173
• Mechanicals - $1,900
• Package - $10,073
• R-2000 – 50%
• Envelope - $18,598
• Mechanicals - $1,900
• Package - $20,498
IRR/Simple Payback – 10 years with annualized capital costs over the 10 years
• ESNH - none
• R2000 - none
} ESNH/R-2000 Upgrade Package (Ottawa)
$0"
$5,000"
$10,000"
$15,000"
$20,000"
$25,000"
Vancouver" Kamloops" GTA" Ottawa" Sudbury" Nova Scotia"
Estimated Median Cost Increase of Progression for ERS80↓50% (R-2000)!
$0"
$2,000"
$4,000"
$6,000"
$8,000"
$10,000"
$12,000"
Vancouver" Kamloops" GTA" Ottawa" Sudbury" Nova Scotia"
Estimated Median Cost Increase of Progression for ERS80↓25% (ESNH)!
ERS80↓75%
House Characteristics
214 m2 (2,300 s.f.) living space
2-storey slab-on-grade
No garage
3.76kW p Photovoltaics (PV)
(16 * 235W modules)
4 flat-plate solar thermal collectors
} Denim Homes/Nova Scotia Power Demonstration House: ERS96
ERS80↓75%
Final ERS = 96
Total heated space = 2,300 s.f.
• ATTIC: RSI 10.6/R60 blown cellulose
• ABOVE-GRADE WALLS: RSI 7.4/R42 wet sprayed cellulose & 75mm (1.5 inches) rigid board
• BELOW SLAB: RSI 4.4/R25 Type III
• WINDOWS: Low-e, argon-filled, insulating spacers, vinyl frames,
• SPACE CONDITIONING: Air-Source Heat Pump, with Solar Thermal in-floor
• WATER HEATING: Solar, DWHR, electric boost
• VENTILATION:
• High efficiency HRV
} Denim Homes/Nova Scotia Power Demonstration House: ERS96
This house features selective glazing. The south and west facing windows are double-pane units to take advantage of passive solar gain. The north facing windows, which don’t contribute to solar gain, are triple-pane units.
Measure ERS
Benchmark (NS Code) 80
Improved Envelope
Renewables 96
Mechanicals • Air-to-Air heat pump
(primary heating & cooling)
• Solar thermal and two drainwater heat recovery (DWHR) units
• Radiant heating system in floor is fed by excess from DWHR and two solar thermal collectors
ERS80↓75%
Wall Detail
Double 2x4 stud wall on 2x10 plate
Staggering eliminates thermal bridging
Rainscreen detail
Foil-faced rigid board to interior provides air barrier
Wet-spray cellulose stays in place, can have higher density, higher R-value per unit thickness
Headers are filled with RSI 7/R40 high-density spray foam
} Denim Homes/Nova Scotia Power Demonstration House: ERS96
Fibre-cement siding 3/8” vertical PT lath @
800mm (24”) o.c. (rainscreen) Housewrap
7/16” sheathing Double 2x4 staggered stud walls @ 800mm (24”)
o.c. on 2x10 plates RSI6.3/R36 wet-spray cellulose
RSI 1.3/R7.5 foil-faced rigid insulation Drywall, taped and sealed
Staggered Double Stud Wall, Corner Detail
Getting to Net Zero Energy
House Characteristics
301m2 (3,237 s.f.)
2storey with walkout basement
Attached garage
8.3 kWp Photovoltaics (PV)
(36 * 190W modules)
(8 * 190W modules)
2 evacuated tube solar thermal collectors
} BC Green Dream Home
Getting to Net Zero Energy
House Characteristics
Thermal Envelope = ERS85
Ceiling RSI 10.6 (R-60)
Main walls RSI 7.5 (R-44)
Foundation walls RSI 7.5 (R-44)
Slab RSI 3.5 (R-20)
Windows 3-pane, low-E 10 (soft coat), 13mm argon fill, insulating spacers, vinyl frames
0.68 ACH@50Pa (0.5ACH target)
Mechanicals
Space heating: Geothermal
Water Heating Solar DHW + HP preheat, DWHR, secondary electric boost as required
Ventilation: HRV
Space Cooling: Geothermal
} BC Green Dream Home
Measure ERS Estimated MJ
Benchmark (Envelope) 85 90,390
Improved Mechanicals 38,265
Renewables 101 (6,720)
Attic Insulation: 75mm (3 inches) urethane foam
400mm (16 inches) blown cellulose
Footing to Rafter ICF construction: Total 273mm (10 ¾ inches) foam
Getting to Net Zero Energy
Geothermal (5.1 COP per
manufacturer) feeds space
heating and pre-heats DHW
Solar thermal and drainwater
heat recovery (DWHR) unit reduce hot water load
Secondary electric tank boosts
DHW
Annual DHW energy
requirement = 4000 kWh
Solar contributes 2100 kWh-e
DWHR contributes 460 kWh-e
} BC Green Dream Home
Drainwater Heat Recovery
Secondary
Primary
Geothermal Heat Pump Desuperheater
Solar Water Heating System
Solar DHW Array
Getting to Net Zero Energy
Electrical load Lighting, appliances, electronics, exterior
CMHC default: 24 kWh/day
Actual Load: 11.5 kWh/day
PV: 8.3 kWpeak capacity
Modelled energy production
9940 kWh/yr
Monitored energy production
(Jun-Sep 2010) = -0.4% under
model
} BC Green Dream Home
6.8 kW Roof Mounted Array
1.5 kW Bi-Facial Balcony Array
Solar DHW Array
Getting to Net Zero Energy
PV optimized by using shadow modelling to determine array placement and ‘string’ arrangement.
Innovative ‘bi-facial’ PV panels used in vertical installation as balcony guard.
All energy used and produced is monitored.
} BC Green Dream Home
1 1 1 1
1 1 1 1 1 2 2 2 3 3 3
2 2 2 3 3 2 3 2 3
3 2 3
4 4 4 4 4 4 4 4 4
X X
XX
Strings 1 & 2 è (18 modules) Inverter 1 Strings 3 & 4 è (18 modules) Inverter 2
Photo courtesy: www.greendreamhome.ca
Getting to Net Zero Energy
33% Cost Increase over ERS80 baseline:
Envelope: $40,000
Mechanicals $10,000
PV: $50,000
Package: $100,000
Finish package = $200,000
Construction Cost = $600,000
Land cost = $150,000
ROI/payback unknown
} BC Green Dream Home
Photos courtesy: www.greendreamhome.ca