Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

16
ID Nome attività 245 Installation Unit 1 247 383 Dismantling of distributor blind flanges 384 385 Machining of adapting flanges 386 387 final control of injector alignment 388 Drilling of dowel pins 389 390 392 Cleaning Turbine Shaft and Oil Slinger 393 Installation of the Oil Slinger 394 Oil Slinger Leakage Test 395 Installation of Shaft Support on Wheel Pit Cover 396 397 398 Feed Back Mechanism (Injectors) 399 Turbine guide bearing assembly & Installation 400 Runner and Turbine Shaft (Coupling) 401 Hydraulic Pipe Arrangement 402 Final installation of turbine and instruments 604 Training Turbines 417 Erection of Governor system 418 Oil Pressure Unit and Governor 419 Installation of foundation for deflector servomotor 420 Deflector servomotor 421 Accumulator units 422 423 Overspeed device 424 Main Inlet Valve ready for water filling 606 Training Governor 425 Installation Unit 2 427 562 Dismantling of distributor blind flanges 563 564 Machining of adapting flanges 565 Surface treatment, i.e. sandblasting and painting of Turbine, Ready for Generator Installation Installation of injectors, adjusting of adapting flanges Re-assembly of injectors with machined adapting flanges Removal of marking plate for injector alignment, final drilling of inspection platform Blast cleaning and painting of turbine housing and distributor Installation and Aligment of the Turbine Shaft on Wheel Pit Cover Deflector mechanism, adjustment, test welding and drilling of dowel pins Adaption and installation of piping, Walform (piping to be flushed before final installation) Surface treatment, i.e. sandblasting and painting of Turbine, Ready for Generator Installation Installation of injectors, adjusting of adapting flanges Re-assembly of injectors with machined adapting flanges

Transcript of Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

Page 1: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

ID Nome attività Duration

245 Installation Unit 1 308.25

247 17

383 Dismantling of distributor blind flanges 10

384 Installation of injectors, adjusting of adapting flanges 30

385 Machining of adapting flanges 30

386 Re-assembly of injectors with machined adapting flanges 10

387 final control of injector alignment 15

388 Drilling of dowel pins 2

389 3

390 Blast cleaning and painting of turbine housing and distributor 4

392 Cleaning Turbine Shaft and Oil Slinger 1

393 Installation of the Oil Slinger 1

394 Oil Slinger Leakage Test 1

395 Installation of Shaft Support on Wheel Pit Cover 1

396 Installation and Aligment of the Turbine Shaft on Wheel Pit Cover 1

397 Deflector mechanism, adjustment, test welding and drilling of dowel pins 20

398 Feed Back Mechanism (Injectors) 5

399 Turbine guide bearing assembly & Installation 2

400 Runner and Turbine Shaft (Coupling) 2

401 Hydraulic Pipe Arrangement 5

402 Final installation of turbine and instruments 10

604 Training Turbines 3

417 Erection of Governor system 48

418 Oil Pressure Unit and Governor 3

419 Installation of foundation for deflector servomotor 3

420 Deflector servomotor 4

421 Accumulator units 4

422 30

423 Overspeed device 4

424 Main Inlet Valve ready for water filling 0

606 Training Governor 3

425 Installation Unit 2 318

427 17

562 Dismantling of distributor blind flanges 10

563 Installation of injectors, adjusting of adapting flanges 30

564 Machining of adapting flanges 30

565 Re-assembly of injectors with machined adapting flanges 10

Surface treatment, i.e. sandblasting and painting of Turbine, Ready for Generator Installation

Removal of marking plate for injector alignment, final drilling of inspection platform

Adaption and installation of piping, Walform (piping to be flushed before final installation)

Surface treatment, i.e. sandblasting and painting of Turbine, Ready for Generator Installation

Page 2: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

566 final control of injector alignment 15

567 Drilling of dowel pins 2

568 3

569 Blast cleaning and painting of turbine housing and distributor 4

571 Cleaning Turbine Shaft and Oil Slinger 1

572 Installation of the Oil Slinger 1

573 Oil Slinger Leakage Test 1

574 Installation of Shaft Support on Wheel Pit Cover 1

575 Installation and Aligment of the Turbine Shaft on Wheel Pit Cover 1

576 Deflector mechanism, adjustment, test welding and drilling of dowel pins 20

577 Feed Back Mechanism (Injectors) 4

578 Turbine guide bearing assembly & Installation 2

579 Runner and Turbine Shaft (Coupling) 2

580 Hydraulic Pipe Arrangement 5

581 Final installation of turbine and instruments 10

604 Training Turbines 3

596 Erection of Governor system 49

597 Oil Pressure Unit and Governor 3

598 Installation of foundation for deflector servomotor 3

599 Deflector servomotor 4

600 Accumulator units 4

601 30

602 Overspeed device 4

606 Training Governor 3

603 Main Inlet Valve ready for water filling 0

604 Training Turbines 3

606 Training Governor 3

Removal of marking plate for injector alignment, final drilling of inspection platform

Adaption and installation of piping, Walform (piping to be flushed before final installation)

Page 3: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

Start Finish % Complete Predecessors Successors

4/23/2014 4/17/2015 37%

4/23/2014 5/13/2014 100%

5/20/2014 5/30/2014 100% 384,562

5/31/2014 7/4/2014 100% 383

7/5/2014 8/8/2014 100% 384

8/9/2014 8/20/2014 100% 385 387,565

8/21/2014 9/6/2014 100% 386

9/8/2014 9/9/2014 0% 387 567FS-11 d

9/8/2014 9/10/2014 100% 387 390,568

9/11/2014 9/15/2014 80% 389 395,569

9/8/2014 9/8/2014 100% 387 393

9/9/2014 9/9/2014 100% 392 394

9/10/2014 9/10/2014 100% 393 396

9/16/2014 9/16/2014 100% 390 396

9/17/2014 9/17/2014 100% 395,394 397,399

10/11/2014 11/3/2014 70% 396,576SS 398

11/4/2014 11/8/2014 0% 397 402

3/28/2015 3/30/2015 0% 396,338 400

3/31/2015 4/1/2015 0% 399 1025

11/3/2014 11/7/2014 0% 414SS+12 d

11/10/2014 11/20/2014 0% 398 1025

2/5/2015 2/7/2015 0% 579

11/10/2014 1/3/2015 0%

11/10/2014 11/12/2014 0% 105 419,597

11/13/2014 11/15/2014 0% 418 420,598

11/17/2014 11/20/2014 0% 419 421,599

11/21/2014 11/25/2014 0% 420 422,600

11/26/2014 12/30/2014 0% 421,416SS 423,601SS

12/31/2014 1/3/2015 0% 422 602

11/12/2014 11/12/2014 0% 414FS+7 d

2/6/2015 2/9/2015 0% 602

2/15/2014 2/20/2015 52%

4/23/2014 5/13/2014 100%

5/31/2014 6/11/2014 100% 383 563

6/12/2014 7/16/2014 100% 564

7/17/2014 8/20/2014 100% 565

8/21/2014 9/1/2014 100% 564,386 566

385,563FS-22 d

386,564FS-22 d

388,389,392,566FS-5 d

562,384FS-22 d

563,385FS-22 d

Page 4: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

9/2/2014 9/18/2014 100% 567,568,571

9/19/2014 9/20/2014 0%

9/19/2014 9/22/2014 100% 566,389 569

9/23/2014 9/26/2014 80% 568,390 574

9/19/2014 9/19/2014 100% 566 572

9/20/2014 9/20/2014 100% 571 573

9/22/2014 9/22/2014 100% 572 575

9/27/2014 9/27/2014 100% 569 575

9/29/2014 9/29/2014 100% 574,573

10/11/2014 11/3/2014 90% 575FS+10 d 577,397SS

11/4/2014 11/7/2014 0% 576 581

1/31/2015 2/2/2015 0% 575,517 579

2/3/2015 2/4/2015 0% 578 1,013,604

11/3/2014 11/7/2014 0% 593SS+12 d

11/8/2014 11/19/2014 0% 577 1013

2/5/2015 2/7/2015 0% 579

11/13/2014 1/8/2015 0%

11/13/2014 11/15/2014 0% 418,105 598

11/17/2014 11/19/2014 0% 597,419 599

11/21/2014 11/25/2014 0% 598,420 600

11/26/2014 11/29/2014 0% 599,421 601

12/1/2014 1/3/2015 0% 600,422SS 602

1/5/2015 1/8/2015 0% 601,423 606

2/6/2015 2/9/2015 0% 602

11/27/2014 11/27/2014 0% 595 605

2/5/2015 2/7/2015 0% 579

2/6/2015 2/9/2015 0% 602

565,387FS-5 d

566,388FS-11 d

576FS+10 d,578

Page 5: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

ID Nome attività Duration

245 Installation Unit 1 308.25

403 Erection of Inlet valve (MIV), Valve Control System and expansion joint. 85

404 Mobilization and preparation for installation of inlet pipe 3

405 Cut off and grinding of bulk head (distributor) 3

406 Skid track for inlet pipe 12

407 20

408 Placement of Control desk 2

409 10

410 Painting of welding joint 4

411 Installation of inlet valve and expansion joint 4

412 Grouting under MIV base (by Others) 2

413 Installation of Counterweight and Hydraulic Cylinder 8

414 By pass valve adaption 14

415 Valves and pipes for drainage, air venting and control system 8

416 30

605 Training MIV 3

425 Installation Unit 2 318

582 Erection of Inlet valve (MIV), Valve Control System and expansion joint. 71.05

583 Mobilization and preparation for installation of inlet pipe 3

584 Cut off and grinding of bulk head (distributor) 3

585 Skid track for inlet pipe 10

586 20

587 Placement of Control desk 2

588 10

589 Painting of welding joint 4

590 Installation of inlet valve and expansion joint 4

591 Grouting under MIV base (by Others) 2

592 Installation of Counterweight and Hydraulic Cylinder 8

593 By pass valve adaption 14

594 Valves and pipes for drainage, air venting and control system 8

595 16

605 Training MIV 3

Installation and alignment, welding NDT and heat treatment of inlet pipe

Adaption of embedded pipes, drainage from penstock, MIV, aeration etc.

Adaption and installation of piping, Walform (piping to be flushed before final installation)

Installation and alignment, welding NDT and heat treatment of inlet pipe

Adaption of embedded pipes, drainage from penstock, MIV, aeration etc.

Adaption and installation of piping, Walform (piping to be flushed before final installation)

Page 6: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

603 Main Inlet Valve ready for water filling 0 d

605 Training MIV 3 d

Page 7: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

Start Finish % Complete Predecessors Successors

4/23/2014 4/17/2015 37%

9/5/2014 12/13/2014 51%

9/5/2014 9/9/2014 100% 106,107

9/9/2014 9/12/2014 100% 404 407

9/9/2014 9/23/2014 100% 404 407

9/23/2014 10/16/2014 100% 405,406

11/6/2014 11/8/2014 0% 411 416

10/16/2014 10/28/2014 100% 404,407 410FS+2 d

10/30/2014 11/4/2014 0% 409FS+2 d

9/24/2014 11/6/2014 80% 413,408

10/23/2014 10/25/2014 100% 407FS+6 d

11/6/2014 11/15/2014 0% 411

10/20/2014 11/4/2014 60% 412SS-4 d

11/5/2014 11/13/2014 0% 414

11/8/2014 12/13/2014 0% 408 1016,422SS

11/27/2014 12/1/2014 0% 603

2/15/2014 2/20/2015 52%

9/5/2014 11/27/2014 54%

9/5/2014 9/9/2014 100% 584,585,588

9/9/2014 9/12/2014 100% 583

9/9/2014 9/20/2014 100% 583

9/28/2014 10/21/2014 100% 407SS+5 d

11/6/2014 11/8/2014 0% 590 588,595

10/21/2014 11/10/2014 90% 587,583 589

11/10/2014 11/14/2014 0% 588

10/6/2014 11/6/2014 80% 592,587

10/23/2014 10/24/2014 0% 586FS+1 d

11/6/2014 11/15/2014 0% 590

10/20/2014 11/4/2014 60% 591SS-4 d

11/5/2014 11/13/2014 0% 593

11/8/2014 11/27/2014 0% 587 6,031,028

11/27/2014 12/1/2014 0% 603

405,406,409,583SS

409,586SS+5 d,411SS+1 d,412FS+6 d

407SS+1 d,412FF+10 d

411FF+10 d,414SS-4 d

415,424FS+7 d,401SS+12 d

404SS,106,107

591FS+1 d,590SS+6 d

586SS+6 d,591FS+10 d

590FS+10 d,593SS-4 d

594,580SS+12 d

Page 8: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

11/27/2014 11/27/2014 0% 595 605

11/27/2014 12/1/2014 0% 603

Page 9: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

ID TURBINE UNIT 1 Duration % Complete % Peso % Avance total N° Trabajadores

247 17 100% 10.00% 10.00%

383 Dismantling of distributor blind flanges 10 100% 5.88% 5.88%384 Installation of injectors, adjusting of adapting flanges 30 100% 17.65% 17.65%385 Machining of adapting flanges 30 100% 17.65% 17.65%386 Re-assembly of injectors with machined adapting flanges 10 100% 5.88% 5.88%387 final control of injector alignment 15 100% 8.82% 8.82%388 Drilling of dowel pins 2 100% 1.18% 1.18%

389 Removal of marking plate for injector alignment, final drilling of inspection platform 3 100% 1.76% 1.76%

390 Blast cleaning and painting of turbine housing and distributor 4 100% 2.35% 2.35%392 Cleaning Turbine Shaft and Oil Slinger 1 100% 0.59% 0.59%393 Installation of the Oil Slinger 1 100% 0.59% 0.59%394 Oil Slinger Leakage Test 1 100% 0.59% 0.59%395 Installation of Shaft Support on Wheel Pit Cover 1 100% 0.59% 0.59%396 Installation and Aligment of the Turbine Shaft on Wheel Pit Cover 1 100% 0.59% 0.59%

397 Deflector mechanism, adjustment, test welding and drilling of dowel pins 20 100% 11.76% 11.76%

398 Feed Back Mechanism (Injectors) 5 100% 2.94% 2.94%399 Turbine guide bearing assembly & Installation 2 100% 1.18% 1.18%400 Runner and Turbine Shaft (Coupling) 2 98% 1.18% 1.15%401 Hydraulic Pipe Arrangement 5 100% 2.94% 2.94%402 Final installation of turbine and instruments 10 60% 5.88% 3.53%604 Training Turbines

170 100.00% 97.62%

GOVERNOR SYSTEM. UNIT 1 Duration % Complete % Peso % Avance total N° Trabajadores

418 Oil Pressure Unit and Governor 3 100% 6.25% 6.25%419 Installation of foundation for deflector servomotor 3 100% 6.25% 6.25%420 Deflector servomotor 4 100% 8.33% 8.33%421 Accumulator units 4 100% 8.33% 8.33%

422 30 100% 62.50% 62.50%

423 Overspeed device 4 50% 8.33% 4.17%606 Training Governor

48 100.00% 95.83%

TURBINE UNIT 2 Duration % Complete % Peso % Avance total N° Trabajadores

427 17 100% 10.06% 10.06%

562 Dismantling of distributor blind flanges 10 100% 5.92% 5.92%563 Installation of injectors, adjusting of adapting flanges 30 100% 17.75% 17.75%564 Machining of adapting flanges 30 100% 17.75% 17.75%565 Re-assembly of injectors with machined adapting flanges 10 100% 5.92% 5.92%566 final control of injector alignment 15 100% 8.88% 8.88%567 Drilling of dowel pins 2 100% 1.18% 1.18%

568 Removal of marking plate for injector alignment, final drilling of inspection platform 3 100% 1.78% 1.78%

569 Blast cleaning and painting of turbine housing and distributor 4 80% 2.37% 1.89%571 Cleaning Turbine Shaft and Oil Slinger 1 100% 0.59% 0.59%572 Installation of the Oil Slinger 1 100% 0.59% 0.59%573 Oil Slinger Leakage Test 1 100% 0.59% 0.59%574 Installation of Shaft Support on Wheel Pit Cover 1 100% 0.59% 0.59%575 Installation and Aligment of the Turbine Shaft on Wheel Pit Cover 1 100% 0.59% 0.59%

576 Deflector mechanism, adjustment, test welding and drilling of dowel pins 20 100% 11.83% 11.83%

577 Feed Back Mechanism (Injectors) 4 100% 2.37% 2.37%578 Turbine guide bearing assembly & Installation 2 100% 1.18% 1.18%579 Runner and Turbine Shaft (Coupling) 2 0% 1.18% 0.00%580 Hydraulic Pipe Arrangement 5 100% 2.96% 2.96%581 Final installation of turbine and instruments 10 50% 5.92% 2.96%604 Training Turbines

169 100.00% 95.38%

GOVERNOR SYSTEM. UNIT 2 Duration % Complete % Peso % Avance total N° Trabajadores

597 Oil Pressure Unit and Governor 3 100% 6.25% 6.25%598 Installation of foundation for deflector servomotor 3 100% 6.25% 6.25%599 Deflector servomotor 4 100% 8.33% 8.33%600 Accumulator units 4 100% 8.33% 8.33%

601 30 100% 62.50% 62.50%

602 Overspeed device 4 50% 8.33% 4.17%606 Training Governor

48 100.00% 95.83%

Surface treatment, i.e. sandblasting and painting of Turbine, Ready for Generator Installation

Adaption and installation of piping, Walform (piping to be flushed before final installation)

Surface treatment, i.e. sandblasting and painting of Turbine, Ready for Generator Installation

Adaption and installation of piping, Walform (piping to be flushed before final installation)

Page 10: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

VALVE MIV _ Unit 1 Duration % Complete % Peso % Avance total N° Trabajadores

404 Mobilization and preparation for installation of inlet pipe 3 100% 2.50% 2.50%

405 Cut off and grinding of bulk head (distributor) 3 100% 2.50% 2.50%406 Skid track for inlet pipe 12 100% 10.00% 10.00%

407 20 100% 16.67% 16.67%

408 Placement of Control desk 2 100% 1.67% 1.67%

409 10 100% 8.33% 8.33%

410 Painting of welding joint 4 100% 3.33% 3.33%411 Installation of inlet valve and expansion joint 4 100% 3.33% 3.33%412 Grouting under MIV base (by Others) 2 100% 1.67% 1.67%413 Installation of Counterweight and Hydraulic Cylinder 8 100% 6.67% 6.67%414 By pass valve adaption 14 100% 11.67% 11.67%

415 Valves and pipes for drainage, air venting and control system 8 100% 6.67% 6.67%

416 30 100% 25.00% 25.00%

605 Training MIV

120 13 100.00% 100.00%

VALVE MIV _ Unit 2 Duration % Complete % Peso % Avance total N° Trabajadores

583 Mobilization and preparation for installation of inlet pipe 3 100% 2.88% 2.88%

584 Cut off and grinding of bulk head (distributor) 3 100% 2.88% 2.88%585 Skid track for inlet pipe 10 100% 9.62% 9.62%

586 20 100% 19.23% 19.23%

587 Placement of Control desk 2 100% 1.92% 1.92%

588 10 100% 9.62% 9.62%

589 Painting of welding joint 4 100% 3.85% 3.85%590 Installation of inlet valve and expansion joint 4 100% 3.85% 3.85%591 Grouting under MIV base (by Others) 2 100% 1.92% 1.92%592 Installation of Counterweight and Hydraulic Cylinder 8 100% 7.69% 7.69%593 By pass valve adaption 14 100% 13.46% 13.46%

594 Valves and pipes for drainage, air venting and control system 8 100% 7.69% 7.69%

595 16 100% 15.38% 15.38%

605 Training MIV

104 100.00% 100.00%

Installation and alignment, welding NDT and heat treatment of inlet pipe

Adaption of embedded pipes, drainage from penstock, MIV, aeration etc.

Adaption and installation of piping, Walform (piping to be flushed before final installation)

Installation and alignment, welding NDT and heat treatment of inlet pipe

Adaption of embedded pipes, drainage from penstock, MIV, aeration etc.

Adaption and installation of piping, Walform (piping to be flushed before final installation)

Page 11: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

ID TURBINE UNIT 1 Duration171.5

GOVERNOR SYSTEM. UNIT 1 Duration49.5

TURBINE UNIT 2 Duration170.5

GOVERNOR SYSTEM. UNIT 2 Duration49.5

TOTAL 441

Page 12: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

% Avance total % PESO % Avance total97.62% 38.89% 37.96%

% Avance total95.83% 11.22% 10.76%

% Avance total95.38% 38.66% 36.88%

% Avance total95.83% 11.22% 10.76%

96.36%

Page 13: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

VALVE MIV _ Unit 1 Duration123

VALVE MIV _ Unit 2 Duration107

Page 14: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

% Avance total100.00%

% Avance total100.00%

Page 15: Avance Fisico Turbinas y Válvulas 27-08-2015.xlsx

Duration

ITEM TURBINE UNIT 1 171.5 97.62%GOVERNOR SYSTEM. UNIT 1 49.5 95.83%

TURBINE UNIT 2 170.5 95.38%GOVERNOR SYSTEM. UNIT 2 49.5 95.83%

VALVE MIV _ Unit 1 123 100.00%VALVE MIV _ Unit 2 107 100.00%

% Avance total