ID Nome attività Duration
245 Installation Unit 1 308.25
247 17
383 Dismantling of distributor blind flanges 10
384 Installation of injectors, adjusting of adapting flanges 30
385 Machining of adapting flanges 30
386 Re-assembly of injectors with machined adapting flanges 10
387 final control of injector alignment 15
388 Drilling of dowel pins 2
389 3
390 Blast cleaning and painting of turbine housing and distributor 4
392 Cleaning Turbine Shaft and Oil Slinger 1
393 Installation of the Oil Slinger 1
394 Oil Slinger Leakage Test 1
395 Installation of Shaft Support on Wheel Pit Cover 1
396 Installation and Aligment of the Turbine Shaft on Wheel Pit Cover 1
397 Deflector mechanism, adjustment, test welding and drilling of dowel pins 20
398 Feed Back Mechanism (Injectors) 5
399 Turbine guide bearing assembly & Installation 2
400 Runner and Turbine Shaft (Coupling) 2
401 Hydraulic Pipe Arrangement 5
402 Final installation of turbine and instruments 10
604 Training Turbines 3
417 Erection of Governor system 48
418 Oil Pressure Unit and Governor 3
419 Installation of foundation for deflector servomotor 3
420 Deflector servomotor 4
421 Accumulator units 4
422 30
423 Overspeed device 4
424 Main Inlet Valve ready for water filling 0
606 Training Governor 3
425 Installation Unit 2 318
427 17
562 Dismantling of distributor blind flanges 10
563 Installation of injectors, adjusting of adapting flanges 30
564 Machining of adapting flanges 30
565 Re-assembly of injectors with machined adapting flanges 10
Surface treatment, i.e. sandblasting and painting of Turbine, Ready for Generator Installation
Removal of marking plate for injector alignment, final drilling of inspection platform
Adaption and installation of piping, Walform (piping to be flushed before final installation)
Surface treatment, i.e. sandblasting and painting of Turbine, Ready for Generator Installation
566 final control of injector alignment 15
567 Drilling of dowel pins 2
568 3
569 Blast cleaning and painting of turbine housing and distributor 4
571 Cleaning Turbine Shaft and Oil Slinger 1
572 Installation of the Oil Slinger 1
573 Oil Slinger Leakage Test 1
574 Installation of Shaft Support on Wheel Pit Cover 1
575 Installation and Aligment of the Turbine Shaft on Wheel Pit Cover 1
576 Deflector mechanism, adjustment, test welding and drilling of dowel pins 20
577 Feed Back Mechanism (Injectors) 4
578 Turbine guide bearing assembly & Installation 2
579 Runner and Turbine Shaft (Coupling) 2
580 Hydraulic Pipe Arrangement 5
581 Final installation of turbine and instruments 10
604 Training Turbines 3
596 Erection of Governor system 49
597 Oil Pressure Unit and Governor 3
598 Installation of foundation for deflector servomotor 3
599 Deflector servomotor 4
600 Accumulator units 4
601 30
602 Overspeed device 4
606 Training Governor 3
603 Main Inlet Valve ready for water filling 0
604 Training Turbines 3
606 Training Governor 3
Removal of marking plate for injector alignment, final drilling of inspection platform
Adaption and installation of piping, Walform (piping to be flushed before final installation)
Start Finish % Complete Predecessors Successors
4/23/2014 4/17/2015 37%
4/23/2014 5/13/2014 100%
5/20/2014 5/30/2014 100% 384,562
5/31/2014 7/4/2014 100% 383
7/5/2014 8/8/2014 100% 384
8/9/2014 8/20/2014 100% 385 387,565
8/21/2014 9/6/2014 100% 386
9/8/2014 9/9/2014 0% 387 567FS-11 d
9/8/2014 9/10/2014 100% 387 390,568
9/11/2014 9/15/2014 80% 389 395,569
9/8/2014 9/8/2014 100% 387 393
9/9/2014 9/9/2014 100% 392 394
9/10/2014 9/10/2014 100% 393 396
9/16/2014 9/16/2014 100% 390 396
9/17/2014 9/17/2014 100% 395,394 397,399
10/11/2014 11/3/2014 70% 396,576SS 398
11/4/2014 11/8/2014 0% 397 402
3/28/2015 3/30/2015 0% 396,338 400
3/31/2015 4/1/2015 0% 399 1025
11/3/2014 11/7/2014 0% 414SS+12 d
11/10/2014 11/20/2014 0% 398 1025
2/5/2015 2/7/2015 0% 579
11/10/2014 1/3/2015 0%
11/10/2014 11/12/2014 0% 105 419,597
11/13/2014 11/15/2014 0% 418 420,598
11/17/2014 11/20/2014 0% 419 421,599
11/21/2014 11/25/2014 0% 420 422,600
11/26/2014 12/30/2014 0% 421,416SS 423,601SS
12/31/2014 1/3/2015 0% 422 602
11/12/2014 11/12/2014 0% 414FS+7 d
2/6/2015 2/9/2015 0% 602
2/15/2014 2/20/2015 52%
4/23/2014 5/13/2014 100%
5/31/2014 6/11/2014 100% 383 563
6/12/2014 7/16/2014 100% 564
7/17/2014 8/20/2014 100% 565
8/21/2014 9/1/2014 100% 564,386 566
385,563FS-22 d
386,564FS-22 d
388,389,392,566FS-5 d
562,384FS-22 d
563,385FS-22 d
9/2/2014 9/18/2014 100% 567,568,571
9/19/2014 9/20/2014 0%
9/19/2014 9/22/2014 100% 566,389 569
9/23/2014 9/26/2014 80% 568,390 574
9/19/2014 9/19/2014 100% 566 572
9/20/2014 9/20/2014 100% 571 573
9/22/2014 9/22/2014 100% 572 575
9/27/2014 9/27/2014 100% 569 575
9/29/2014 9/29/2014 100% 574,573
10/11/2014 11/3/2014 90% 575FS+10 d 577,397SS
11/4/2014 11/7/2014 0% 576 581
1/31/2015 2/2/2015 0% 575,517 579
2/3/2015 2/4/2015 0% 578 1,013,604
11/3/2014 11/7/2014 0% 593SS+12 d
11/8/2014 11/19/2014 0% 577 1013
2/5/2015 2/7/2015 0% 579
11/13/2014 1/8/2015 0%
11/13/2014 11/15/2014 0% 418,105 598
11/17/2014 11/19/2014 0% 597,419 599
11/21/2014 11/25/2014 0% 598,420 600
11/26/2014 11/29/2014 0% 599,421 601
12/1/2014 1/3/2015 0% 600,422SS 602
1/5/2015 1/8/2015 0% 601,423 606
2/6/2015 2/9/2015 0% 602
11/27/2014 11/27/2014 0% 595 605
2/5/2015 2/7/2015 0% 579
2/6/2015 2/9/2015 0% 602
565,387FS-5 d
566,388FS-11 d
576FS+10 d,578
ID Nome attività Duration
245 Installation Unit 1 308.25
403 Erection of Inlet valve (MIV), Valve Control System and expansion joint. 85
404 Mobilization and preparation for installation of inlet pipe 3
405 Cut off and grinding of bulk head (distributor) 3
406 Skid track for inlet pipe 12
407 20
408 Placement of Control desk 2
409 10
410 Painting of welding joint 4
411 Installation of inlet valve and expansion joint 4
412 Grouting under MIV base (by Others) 2
413 Installation of Counterweight and Hydraulic Cylinder 8
414 By pass valve adaption 14
415 Valves and pipes for drainage, air venting and control system 8
416 30
605 Training MIV 3
425 Installation Unit 2 318
582 Erection of Inlet valve (MIV), Valve Control System and expansion joint. 71.05
583 Mobilization and preparation for installation of inlet pipe 3
584 Cut off and grinding of bulk head (distributor) 3
585 Skid track for inlet pipe 10
586 20
587 Placement of Control desk 2
588 10
589 Painting of welding joint 4
590 Installation of inlet valve and expansion joint 4
591 Grouting under MIV base (by Others) 2
592 Installation of Counterweight and Hydraulic Cylinder 8
593 By pass valve adaption 14
594 Valves and pipes for drainage, air venting and control system 8
595 16
605 Training MIV 3
Installation and alignment, welding NDT and heat treatment of inlet pipe
Adaption of embedded pipes, drainage from penstock, MIV, aeration etc.
Adaption and installation of piping, Walform (piping to be flushed before final installation)
Installation and alignment, welding NDT and heat treatment of inlet pipe
Adaption of embedded pipes, drainage from penstock, MIV, aeration etc.
Adaption and installation of piping, Walform (piping to be flushed before final installation)
603 Main Inlet Valve ready for water filling 0 d
605 Training MIV 3 d
Start Finish % Complete Predecessors Successors
4/23/2014 4/17/2015 37%
9/5/2014 12/13/2014 51%
9/5/2014 9/9/2014 100% 106,107
9/9/2014 9/12/2014 100% 404 407
9/9/2014 9/23/2014 100% 404 407
9/23/2014 10/16/2014 100% 405,406
11/6/2014 11/8/2014 0% 411 416
10/16/2014 10/28/2014 100% 404,407 410FS+2 d
10/30/2014 11/4/2014 0% 409FS+2 d
9/24/2014 11/6/2014 80% 413,408
10/23/2014 10/25/2014 100% 407FS+6 d
11/6/2014 11/15/2014 0% 411
10/20/2014 11/4/2014 60% 412SS-4 d
11/5/2014 11/13/2014 0% 414
11/8/2014 12/13/2014 0% 408 1016,422SS
11/27/2014 12/1/2014 0% 603
2/15/2014 2/20/2015 52%
9/5/2014 11/27/2014 54%
9/5/2014 9/9/2014 100% 584,585,588
9/9/2014 9/12/2014 100% 583
9/9/2014 9/20/2014 100% 583
9/28/2014 10/21/2014 100% 407SS+5 d
11/6/2014 11/8/2014 0% 590 588,595
10/21/2014 11/10/2014 90% 587,583 589
11/10/2014 11/14/2014 0% 588
10/6/2014 11/6/2014 80% 592,587
10/23/2014 10/24/2014 0% 586FS+1 d
11/6/2014 11/15/2014 0% 590
10/20/2014 11/4/2014 60% 591SS-4 d
11/5/2014 11/13/2014 0% 593
11/8/2014 11/27/2014 0% 587 6,031,028
11/27/2014 12/1/2014 0% 603
405,406,409,583SS
409,586SS+5 d,411SS+1 d,412FS+6 d
407SS+1 d,412FF+10 d
411FF+10 d,414SS-4 d
415,424FS+7 d,401SS+12 d
404SS,106,107
591FS+1 d,590SS+6 d
586SS+6 d,591FS+10 d
590FS+10 d,593SS-4 d
594,580SS+12 d
11/27/2014 11/27/2014 0% 595 605
11/27/2014 12/1/2014 0% 603
ID TURBINE UNIT 1 Duration % Complete % Peso % Avance total N° Trabajadores
247 17 100% 10.00% 10.00%
383 Dismantling of distributor blind flanges 10 100% 5.88% 5.88%384 Installation of injectors, adjusting of adapting flanges 30 100% 17.65% 17.65%385 Machining of adapting flanges 30 100% 17.65% 17.65%386 Re-assembly of injectors with machined adapting flanges 10 100% 5.88% 5.88%387 final control of injector alignment 15 100% 8.82% 8.82%388 Drilling of dowel pins 2 100% 1.18% 1.18%
389 Removal of marking plate for injector alignment, final drilling of inspection platform 3 100% 1.76% 1.76%
390 Blast cleaning and painting of turbine housing and distributor 4 100% 2.35% 2.35%392 Cleaning Turbine Shaft and Oil Slinger 1 100% 0.59% 0.59%393 Installation of the Oil Slinger 1 100% 0.59% 0.59%394 Oil Slinger Leakage Test 1 100% 0.59% 0.59%395 Installation of Shaft Support on Wheel Pit Cover 1 100% 0.59% 0.59%396 Installation and Aligment of the Turbine Shaft on Wheel Pit Cover 1 100% 0.59% 0.59%
397 Deflector mechanism, adjustment, test welding and drilling of dowel pins 20 100% 11.76% 11.76%
398 Feed Back Mechanism (Injectors) 5 100% 2.94% 2.94%399 Turbine guide bearing assembly & Installation 2 100% 1.18% 1.18%400 Runner and Turbine Shaft (Coupling) 2 98% 1.18% 1.15%401 Hydraulic Pipe Arrangement 5 100% 2.94% 2.94%402 Final installation of turbine and instruments 10 60% 5.88% 3.53%604 Training Turbines
170 100.00% 97.62%
GOVERNOR SYSTEM. UNIT 1 Duration % Complete % Peso % Avance total N° Trabajadores
418 Oil Pressure Unit and Governor 3 100% 6.25% 6.25%419 Installation of foundation for deflector servomotor 3 100% 6.25% 6.25%420 Deflector servomotor 4 100% 8.33% 8.33%421 Accumulator units 4 100% 8.33% 8.33%
422 30 100% 62.50% 62.50%
423 Overspeed device 4 50% 8.33% 4.17%606 Training Governor
48 100.00% 95.83%
TURBINE UNIT 2 Duration % Complete % Peso % Avance total N° Trabajadores
427 17 100% 10.06% 10.06%
562 Dismantling of distributor blind flanges 10 100% 5.92% 5.92%563 Installation of injectors, adjusting of adapting flanges 30 100% 17.75% 17.75%564 Machining of adapting flanges 30 100% 17.75% 17.75%565 Re-assembly of injectors with machined adapting flanges 10 100% 5.92% 5.92%566 final control of injector alignment 15 100% 8.88% 8.88%567 Drilling of dowel pins 2 100% 1.18% 1.18%
568 Removal of marking plate for injector alignment, final drilling of inspection platform 3 100% 1.78% 1.78%
569 Blast cleaning and painting of turbine housing and distributor 4 80% 2.37% 1.89%571 Cleaning Turbine Shaft and Oil Slinger 1 100% 0.59% 0.59%572 Installation of the Oil Slinger 1 100% 0.59% 0.59%573 Oil Slinger Leakage Test 1 100% 0.59% 0.59%574 Installation of Shaft Support on Wheel Pit Cover 1 100% 0.59% 0.59%575 Installation and Aligment of the Turbine Shaft on Wheel Pit Cover 1 100% 0.59% 0.59%
576 Deflector mechanism, adjustment, test welding and drilling of dowel pins 20 100% 11.83% 11.83%
577 Feed Back Mechanism (Injectors) 4 100% 2.37% 2.37%578 Turbine guide bearing assembly & Installation 2 100% 1.18% 1.18%579 Runner and Turbine Shaft (Coupling) 2 0% 1.18% 0.00%580 Hydraulic Pipe Arrangement 5 100% 2.96% 2.96%581 Final installation of turbine and instruments 10 50% 5.92% 2.96%604 Training Turbines
169 100.00% 95.38%
GOVERNOR SYSTEM. UNIT 2 Duration % Complete % Peso % Avance total N° Trabajadores
597 Oil Pressure Unit and Governor 3 100% 6.25% 6.25%598 Installation of foundation for deflector servomotor 3 100% 6.25% 6.25%599 Deflector servomotor 4 100% 8.33% 8.33%600 Accumulator units 4 100% 8.33% 8.33%
601 30 100% 62.50% 62.50%
602 Overspeed device 4 50% 8.33% 4.17%606 Training Governor
48 100.00% 95.83%
Surface treatment, i.e. sandblasting and painting of Turbine, Ready for Generator Installation
Adaption and installation of piping, Walform (piping to be flushed before final installation)
Surface treatment, i.e. sandblasting and painting of Turbine, Ready for Generator Installation
Adaption and installation of piping, Walform (piping to be flushed before final installation)
VALVE MIV _ Unit 1 Duration % Complete % Peso % Avance total N° Trabajadores
404 Mobilization and preparation for installation of inlet pipe 3 100% 2.50% 2.50%
405 Cut off and grinding of bulk head (distributor) 3 100% 2.50% 2.50%406 Skid track for inlet pipe 12 100% 10.00% 10.00%
407 20 100% 16.67% 16.67%
408 Placement of Control desk 2 100% 1.67% 1.67%
409 10 100% 8.33% 8.33%
410 Painting of welding joint 4 100% 3.33% 3.33%411 Installation of inlet valve and expansion joint 4 100% 3.33% 3.33%412 Grouting under MIV base (by Others) 2 100% 1.67% 1.67%413 Installation of Counterweight and Hydraulic Cylinder 8 100% 6.67% 6.67%414 By pass valve adaption 14 100% 11.67% 11.67%
415 Valves and pipes for drainage, air venting and control system 8 100% 6.67% 6.67%
416 30 100% 25.00% 25.00%
605 Training MIV
120 13 100.00% 100.00%
VALVE MIV _ Unit 2 Duration % Complete % Peso % Avance total N° Trabajadores
583 Mobilization and preparation for installation of inlet pipe 3 100% 2.88% 2.88%
584 Cut off and grinding of bulk head (distributor) 3 100% 2.88% 2.88%585 Skid track for inlet pipe 10 100% 9.62% 9.62%
586 20 100% 19.23% 19.23%
587 Placement of Control desk 2 100% 1.92% 1.92%
588 10 100% 9.62% 9.62%
589 Painting of welding joint 4 100% 3.85% 3.85%590 Installation of inlet valve and expansion joint 4 100% 3.85% 3.85%591 Grouting under MIV base (by Others) 2 100% 1.92% 1.92%592 Installation of Counterweight and Hydraulic Cylinder 8 100% 7.69% 7.69%593 By pass valve adaption 14 100% 13.46% 13.46%
594 Valves and pipes for drainage, air venting and control system 8 100% 7.69% 7.69%
595 16 100% 15.38% 15.38%
605 Training MIV
104 100.00% 100.00%
Installation and alignment, welding NDT and heat treatment of inlet pipe
Adaption of embedded pipes, drainage from penstock, MIV, aeration etc.
Adaption and installation of piping, Walform (piping to be flushed before final installation)
Installation and alignment, welding NDT and heat treatment of inlet pipe
Adaption of embedded pipes, drainage from penstock, MIV, aeration etc.
Adaption and installation of piping, Walform (piping to be flushed before final installation)
ID TURBINE UNIT 1 Duration171.5
GOVERNOR SYSTEM. UNIT 1 Duration49.5
TURBINE UNIT 2 Duration170.5
GOVERNOR SYSTEM. UNIT 2 Duration49.5
TOTAL 441
% Avance total % PESO % Avance total97.62% 38.89% 37.96%
% Avance total95.83% 11.22% 10.76%
% Avance total95.38% 38.66% 36.88%
% Avance total95.83% 11.22% 10.76%
96.36%
VALVE MIV _ Unit 1 Duration123
VALVE MIV _ Unit 2 Duration107
% Avance total100.00%
% Avance total100.00%
Duration
ITEM TURBINE UNIT 1 171.5 97.62%GOVERNOR SYSTEM. UNIT 1 49.5 95.83%
TURBINE UNIT 2 170.5 95.38%GOVERNOR SYSTEM. UNIT 2 49.5 95.83%
VALVE MIV _ Unit 1 123 100.00%VALVE MIV _ Unit 2 107 100.00%
% Avance total