AustralianConstructionLawNewsletter Footnotes (1) Goff ... · (10) Goff& Jones atp.44. (11)...
Transcript of AustralianConstructionLawNewsletter Footnotes (1) Goff ... · (10) Goff& Jones atp.44. (11)...
Australian Construction Law Newsletter
The view that the right to a quantum meruit is founded onan implied contract ... justified the conclusion, which theArbitratoradopted, that the measure ofthe entitlementofthe party doing the work and/or supplying the materials
was assessed by reference to the reasonable cOst to him
ofdoing that work or supplying those materials, but the
replacement of that view with the concept ofrestitution
or unjust enrichment as the basis of the entitlement to a
quantummeruit, leads to the differentconclusion that the
measureofthe entitlement is assessedby reference to the
value ofwhat the other party receives.
... the onus lies upon (the contractor) to prove that the
amount claimed is fair and reasonable, and the contractis evidence ofwhat rate is fair and reasonable.
An example might serve to show the conflict in the ap
proaches to quantum meruit adopted in the Jennings case (19)
and the Renard case (20). Assume that a contractor agreed to
supply 1,000 tonnes ofrock to the Principal at $1 per tonne, but
the rock proved to be more difficult to obtain than the contractorcontemplated and, in fact, it costs the contractor $2 per tonne to
obtain. If half way through the contract, the Principal were to
refuse to accept more rock and thereby repudiated the contract,the contractorcould elect to terminate the contract. The contrac
tor would have incurred costs of $1,000, but have been entitled
to only $500 under the contract. The Principal's wrongful
repudiation would have saved the contractor from a further $500
loss. The contractor could not recover damages for the Princi
pal's breach. The breach saved the contractor $500. Itwould be
anomalous if the contractor could elect to sue for restitution and
recover an extra $500 (based on $2 per tonne for the 500 tonnes
delivered less the $500 already paid by the Principal).
The decision in Jennings (19) would suggest that the contractorcouldrecover an extra$500on aquantum meruit, whereasthe decision in Renard (20) suggests that on a quantum meruit,
the contractorwould recoverno more than the$500 already paid.Logic dictates that the second approach is correct. The fact that
the Principal repudiated tile contract does not mean that the
Principal is enriched. The rock delivered does not suddenly
double in value because the Principal refused to take more rock.
It is submitted that Brownie J. in the Renard case correctlyinterpreted the Pavey decision when he said:
... it is the value to the recipient of the work which is to
be measured, rather than the cost to the party doing thework.
A consequence of the Pavey decision may be a reduction inthe number of restitutionary claims, particularly when the Prin
cipal had repudiated the contract, and a tendency to claim aquantum meruit based on an implied term, rather than a quantummeruit based on unjust enrichment. The former is a reasonable
price for the work done by the contractor, whereas the latter is areasonable price for the benefitreceived by the otherparty.·Often
the amounts willbe the same, butnot always. Inpleading aclaim,
itwill be important to make the distinctionbetween a claimunder
the contract for quantum meruit and a restitutionary claim forquantum meruit.
- Philip Davenport
Footnotes(1) Goff& Jones, The LawofRestitution,3rdEdition, Sweet
& Maxwell, London, 1986, p.29.(2) Pavey & Matthews Pty Ltd v Paul 162 CLR 221, (1987)
61 ALJR 151.
(3) Goff & Jones at p.16
(4) Goff & Jones at p.39(5) William Lacey (Hounslow) Ltd v Davis (1957) 1 WLR
932.(6) British Steel Corp v Cleveland Bridge and Engineering
(1984) 1 ALL ER 504.(7) Wegan Constructions v Wodonga Sewerage Authority
(1978) VR 67.(8) Codelfa Construction Pty Ltd v State Rail Authority of
New South Wales (1982) 149 CLR 337.
(9) Goff & Jones at p.42.
(10) Goff & Jones at p.44.(11) JenningsConstructionLtdvQH &MBirtPty Ltd (1986)
3 BCL 189.(12) Deane 1. at p.165 of Pavey & Matthews v Paul (2)
discusses the distinction.(13) Brooking on Building Contracts, 2nd Edition, Butter
worths, Melbourne, 1980 at pp.76-77 distinguishes 5
classes of cases where a quantum meruit lies. The first
two are examples ofwhere the entitlement to a quantum
meruit is based on an implied term in the contract that a
reasonable price will be paid. In the other 3 classes, the
claim is based on unjust enrichment.(14) Per Deane 1. in Pavey & Matthews v Paul (2) at p.168.
(15) Lodder & Slowey (1904) A C 442, Keating, Building
Contracts, 4th Edition, Sweet & Maxwell, London,
1978.(16) Boomer v Muir, 24 P.2d 570 (1933), Goff & Jones at
pp.465-468.(17) Goff & Jones at pp.467.(18) Goff& Jones, the LawofRestitution, 2ndEdition, Sweet
& Maxwell, London, 1978 at p.380.(19) Jennings Construction Limited v Q H & M Birt Pty
Limited, unreported, Cole J. N.S.W. Supreme Court,
16.12.88 atp.16.(20) The Minister for Public Works v Renard Constructions
(M.E.) Pty Limited, Brownie 1., N.S.W. Supreme Court,
15.2.89.
6. THE BUILDING CODE OF AUSTRALIA- A simple uniform system of regulation.
The Building Code of Australia is the result of some eightyears work by the Australian Uniform Building RegulationsCo-ordinating Council. In formally announcing the publication of the first edition of the Building Code of Australia,Barry Jones, the Minister for Science, Customs and SmallBusiness, said:
The code gently advances rationalisation ofbuildingregulations for aU States and Territories and provides uniform, cost effective building regulationsaddressing safety, health and amenity.
The Code is presented in such a way that it may be called upin building regulations by the Statesand Territories, as in the
Austr:alian Construction Law Newsletter
case of Australian Standards, without the need to Incorporate the actual detail in the building regulations. The Codecontains the core requirements that would be generallyapplicable to all regulations. Modffications or additions willbe included in a series ofappendices Issued from time to time.
It is expected that each State and Territory's building regulations would call up the core requirements and appendicesand then contain additional administrative and non-technical provisions covering that State or Territory's requirements. It Is expected that future amendments of the Codewould not Involve the lengthy procedures usually associatedwith the amendment of regulations.
The challenge now for the States and Territories Is to determinewhether the Building Code ofAustraliamay be adoptedIn Its entirety, or whether some of Its provisions requireamendment to deal with climatic, geographic or othercircumstances. It is to be hoped that uniformity prevails forthe sake of the efficiency of the Industry.
The article below on the Building Code of Australia wasprepared by Hugh Knox, Manager, Regulations, Accreditation and Standards with the National Building TechnologyCentre, CSIRO Division ofBuilding Construction and Engineering. The National Building Technology Centre Is Technical Advisor to the Australian Uniform Building Regulations Co-ordlnatlng Council which, as stated above, prepared the Code. The authoritative tone of the article Is notsurprising given that Mr Knox Is part ofa team responsiblefor managing and coordinating the National Building Technology Centre's Input Into the Building Code of Australia.
The present regulations system.Australia is a federation ofsovereign states, eachofwhich at
present has its own regulations to control building within itsjurisdiction. Legislation in each state authorizes each local cityor municipal council (Australia has 836) to administer the regulations and to accept innovations not explicitly covered by theregulations.
Some uniformity of regulation has already been achievedbecause nearly every state has adapted its present buildingregulations from a model code, the Australian Model UniformBuilding Code (AMUBC). The Australian Uniform BuildingRegulations Co-ordinating Council (AUBRCC) is now takingthis principle into a new phase by developing the code as a singlevolume oftechnical regulations - the Building Code ofAustralia(BCA) - to be adopted by each building control authority by asimple direct cross reference from legislation.
The requirements in the BCA are aimed at establishing andmaintaining safety, health and amenity at acceptable levels withits application leaning towards performancerather than prescription. The BCA excludes administrative regulations andAUBRCC is now putting togetherasetofuniform administrativerequirements to parallel the BCA.The emergence of uniformity.
The expansion in building activity in recent times demonstrated the need for uniform building regulations. (About$22,000 millionwas committed to building in Australia in 198788.) However, since this field is the prerogative of the states,political problems at first created a barrier. The InterstateStanding Committee on Uniform Building Regulations (lS-
9
CUBR) was established in 1964 to consider, amongst otherthings, a uniform approach to technical regulations. The secretariatofiSCUBRwas then Commonwealth Experimental Building Station, nowcalled the National BuildingTechnology Centre(NBTC).
ISCUBR produced the Australian Model Uniform BuildingCode (AMUBC) early in the 1970s and it was adapted (ratherthan adopted) by six states and territories by 1976 as the basis oftheir regulations. Originally, the AMUBC was a confidentialdocument and could be seen by the general public only in theform ofregulations promulgatedby each state. Much uniformitywas achieved this way, but the states still insistedon making theirown variations to the original documents.
ISCUBRwas supersededin 1980by the AustralianUniformBuildingRegulationsCo-ordinatingCouncil (AUBRCC)which,like ISCUBR, is an association of building control authorities,local government and the building industry. It is supported by anumberoftechnical committees, eachresponsible for aparticularsectionoftheBCA. An Industry Liaison Committeeprovides anadditional communication link:.
AUBRCC decided subsequently to produce a single set oftechnical regulations - the Building CodeofAustralia. The BCAcan be adopted by direct cross reference from legislation ratherthan be adapted as the basis for the regulations ofeach state andterritory. It was issued for public review in October 1986.The benefits of the BCA.
The benefits ofhaving a single setoftechnical regulations inthe form of the BCA are that:
greater uniformity and consistency will beachieved;it will be easier to keep up to date;itwill provide the basis for a single national systemof accreditation ofnew products and practices.
AUBRCC stillhas away to go to achieve these benefits. Forexample, most of the building control authorities have announced that they will still apply some variations and additionswithin theirjurisdictions. Thevariations will be published, stateby state, as asupplementto the BCA. They will thereforebecomeapparent and this in tum could lead to pressure to reduce oreliminate them.Support for the BCA.
The intention is to support the BCA with a number ofancillary documents and aids that must be coordinated closelywith the development of the BCA. However, the support functions are not meant to rectify problems inherent in the BCA.These must be solved first by proper attention to the BCA itself.
Support functions include:a commentary to explain the reasons for the regulations (but not to say what the BCA should havesaid in the first place);computer software to assist the Code user by leading him quickly through the BCA clauses that arerelevant to a particular building, i.e. to speed updesign and checking (but not to untangle unnecessary complexity);compendia of tested products and systems, thesummaries classified according to BCA requirements;a single national accreditation system in which a
Australian Construction Law Newsletter
productorbuilding systemis appraised for suitability for purpose and given legal recognition ofcompliance with regulations by AUBRCC.
Future development ofBCA.The issue in 1986 of the public review draft of the BCA was
a most significant achievement. Much simplification had been
introduced by grouping the AMUBC requirements into seven
major sections. While this tended to bring related requirements
together, the size and complexity ofthe code's technical content
indicated that there was still much more to be done.
The code covers every major discipline applicable to build
ing including structural, mechanical, hydraulic and electrical
engineering, fIre protection and architecture and will have acontrolling effect on the building industry. In such a document,
therefore, unnecessary complexity and restriction and require
ments that are inconsistent, conflicting, incomprehensible, re
dundant and out-of-date can be unnecessarily and prodigiously
costly and can have a harmful effect on the built environment.
The National Building Technology Centre (NBTC) is thetechnical adviser to AUBRCC and is committed by its charter to
ongoing support of AUBRCC.
As a part of this function, NBTC engaged a consulting
engineer to review the BCA, the review culminating in a series of
reports (now known as the Blackmore Reports) that range fromgeneralities to detailed analyses.
It became apparent that there was still much unnecessary
complexity and many anomalies in the BCA that were broughtaboutby a lack ofcoherence in the technical content. The reports
also recognized the fact that the development of the BCA is amulti-milliondollarproject thathas tobe managedand organizedlike any other major project. It was obvious that the BCA needa systematic structure based on design logic.
The important general conclusion from the review is that
support facilities such as commentaries and software mustnotbe
put in place in order to compensate for unnecessary complexity,
errors, obscurity, inconsistency, ambiguity or otherdefIcienciesin a code. The code must be corrected first and the reportsdescribe simple techniques andprocedures to do this quickly andeconomically.
The restructuringoftheBCAis aimed atpromotingsimplicity and performance as the basis ofregulation. Restructuring willtherefore assist in:
the process ofbuilding design and approval;
the developmentofperformance requirements andthe accreditation of new products;
the development ofa true plain-English code;
• the developmentofsimplecomputer software as anaid in working quickly through the Code.
The costofdevelopmentis reduced, ifa logical andcoherent
structure for the draft code under consideration is establishedbefore there is detailed consideration of technical content. The
structure then ensures that technical decisions are expedited
because issues are clarifIed. Errors, ambiguities, obscurities andinconsistencies become apparent quickly and 'lIe corrected
quickly, and confusion is avoided.
Other consequential benefits include the following:Increasing the probability to the point ofcertainty
that the basic intentions ofthe authority responsible
for the code will be achieved in every building and
10
will be achieved with maximum economy in design, approval and construction.Eliminating the unprofessional attitude that com
pliance with the letter of the law absolves thedesigner from his professional responsibilities.
The building must satisfy the objectives.
Removing barriers to evaluationandlegal approvalof innovations in that these can now be assessed as
satisfying the appropriate objectives if there are no
relevant detailed requirements or standards.Ease ofdevelopment ofcomputer software to help
the user work quickly through the code because
each requirement will be logically structured and
part of a logical sequence.
Ease oftranslation into a true plain-English code tohelp in quicker and more accurate understandingof
what the code requires, brought about by the
simple, logical structure.• Cost savings in construction as a result ofremoval
ofunnecessary stringency.Buildings functioning more satisfactorily as a re
sult ofbetter technical content of the code.
Reduction of litigation that can result from misin
terpretation of the code.
AvaIlabilityThe fIrst edition of the BCA was published 'in December
1988. It is available from NBTC, PO Box 30, Chatswood NSW
2067; phone (02) 888 8888, NBTC state branches, from some
state government bookshops and other selected outlets.
- Hugh Knox. ReprInted with permission from
Australian BuIlding News.
7. LEGIONNAIRE'S DISEASE-
NEW AUSTRALIAN STANDARD TO COMBAT
KILLER DISEASE
This article on the new SAA Standard AS3666-1989 AirHandling And Water Systems Of Buildings - MicrobialControl by Dr Peter Christopher, Special Adviser, Commu
nicable Diseases, DepartmentofHealth, NSW is tImely,giventhe recent out break of Legionnaire's disease in Tasmania.
As stated in the article, the Standard emphasises the importance of design of air-conditioning and water systems inbuIldings, in recognition that some aspects ofpresent design
make efficient maintenance difficult and may contribute in
the multiplication oflegionella. The Standard also provides
for specified regular cleaning and maintenance of air-han
dling and warm water systems.
The Importance ofthe new Standard cannot be over-emphasised, given the seriousness of outbreaks of Legionnaire'sdisease in death and serious Illness and the significant poten
tialliability which could attach.
It should be understood that, if there is a Standard in exIs
tence, the courtswUl use the requirements ofthe Standard asa benchmark in examining conduct to make a determination
on negligence and liability. Ifa departure from the require
ments of the Standard has occurred with respect to either