Attracting and Maintaining Institutional Investment: Solar PV
-
Upload
eversheds -
Category
Technology
-
view
1.072 -
download
2
Transcript of Attracting and Maintaining Institutional Investment: Solar PV
Presentation Outline
• Introduction to SgurrEnergy
• Resource & energy yield
• Technology
• Completion risk
• EPC and O&M contracts
• Financial modelling
• Key messages
SgurrEnergy
• Leading renewable energy consultancy
• Formed in 2002
• Joined Wood Group in 2010
• Global network of offices
• 100+ experienced consultants
• People and technology focused
• Company wide triple BSI accreditation & UKAS ISO/IEC accreditation for wind farm power curve analysis
Global track record
Europe • Belgium
• Bulgaria
• Estonia
• France
• Germany
• Greece
• Ireland
• Italy
• Malta
• Netherlands
• Norway
• Poland
• Portugal
• Russia
• Romania
• Slovakia
• Spain
• Sweden
• UK
• Ukraine
Africa • Angola
• Kenya
• South Africa
Oceania
• Australia
• New Zealand
We have consulted on over 65,000 MW of renewable energy in over 40
countries covering both project development and due diligence
Asia
• China
• India
• Israel
• Korea
• Mongolia
• Pakistan
• Philippines
• Sri Lanka
• Turkey
• United Arab Emirates
• Vietnam
North America • Canada
• Mexico
• USA
South America
• Brazil
• Chile
• Galapagos Islands (Ecuador)
Experience
Due Diligence – Owner, Lender & Acquisition • Acquisition due diligence for solar PV plant, Italy, 25 MW, 2012, confidential client
• Lenders due diligence of Charanka solar PV plant, India, 15 MW, 2012, Standard Chartered
• Technical due diligence of Lorraine solar PV plant, France, 36 MW, 2012, Marguerite Advisor
• Acquisition due diligence for European solar PV portfolio, 120+ MW, 2011, confidential client
• Technical due diligence for solar PV project, France, 36 MW, 2011, confidential client
• Provisional Acceptance and witnessing commissioning, UK, 4.4 MW, 2011, Low Carbon Solar
• Owner’s Engineer/ Solar Resource Assessment for proposed PV Plant, Pakistan, 2011, Sapphire
• Owners Engineer/ Design verification and handover acceptance support, Belgium, 6.5 MW, 2011
• Acquisition due diligence of Rete Rinnovabile Solar PV Portfolio, Italy, 150 MW, 2010, Terra Firma Capital Partners
• Acquisition due diligence for solar PV project, Spain, 6.7 MW, 2011, confidential client
• Lender’s Engineer/ Construction monitoring on three PV plants, UK, 15 MW, 2011, Low Carbon
• Solar Rooftop PV Portfolio Technical Due Diligence, France, 2.4 MW, 2010, confidential client
• Solar Rooftop and Ground mounted PV Portfolio technical due diligence, France, 170 MW+, 2010, confidential client
Due Diligence- Introduction
The due diligence phase of evaluating a project takes three main forms:
1. Legal due diligence – assessing the permits and contracts (EPC and O&M).
2. Insurance due diligence – assessing the adequacy of the insurance policies and gaps in cover.
3. Technical due diligence – assessing the technology, integration and technical aspects of the permits and contracts.
• Feasibility – Solar Resource & Energy Yield
• Planning & Permitting
• Technical development – Grid connection
– Design and Technology
• Contracts – EPC
– O&M
– Power Purchase Agreement (PPA)
• Financial Close
• Construction – Provisional Acceptance Test
• Operation - Revenue – Final Acceptance Test
Project Stages
• Losses • Shading • Soiling • AC/DC cable • Temperature • Inverter • Transformer • Downtime • Mismatch
• Module degradation
• Total prediction uncertainty
Energy Yield Prediction Accuracy
• Power is approximately proportional to the plane of array irradiance
• Uncertainty in the yield prediction is dominated by uncertainty in the solar irradiation
Effect of Solar Resource on Energy Yield
Solar Resource Assessment
• Require historical data close to site and over a long period of time
• Data sources typically provide global horizontal irradiation (GHI) in hourly intervals
• Use transposition algorithms to convert from the horizontal plane to the tilted plane
Which Data are Most Representative?
There is disparity between different information sources
• 20 km from a WMO MET station (France) good agreement
Key Messages – Resource and Yield
• Key to yield prediction is quantification of resource
• Use a variety of resource datasets
- Understand the uncertainty
- Obtain probability of exceedance energy yield prediction values (e.g. P90)
• Understanding the yield prediction uncertainty can help lenders give more favourable terms
• Uncertainty is site dependent (distance from ground measurements, accuracy of satellite data)
• On-site measurements may be used to calibrate satellite derived estimates for site location
Resource and Yield– Common Mistakes
• Only using one resource dataset
• No assessment of inter-annual variability in resource
• No assessment of the yield uncertainty (P90)
• No assessment of inter-row shading or horizon shading losses
• Ignoring shading from nearby obstructions including poles, control rooms and switch yard equipment
• AC losses and plant self consumption ignored
• Plant downtime and grid unavailability ignored
• Degradation of the modules and plant components over the lifetime of the plant ignored
Technology
Module Type: • Crystalline Silicon (mono or
multi) • Thin film (CdTe, a-si)
Inverter Type: • Central Inverter • String inverter System Design: • Row spacing • Electrical design • Orientation and tilt • Shading
Bankability of Modules
Performance Warranty Quality & Management Standards
End of life recycling
Product Warranty Third Party Warranty Insurance
Track Record Total Installed Capacity / Production Capacity
Length of time in production
Recommend factory inspection
Cell Manufacturer
IEC Certification
Module Technology (c-Si or TF)
• Reliability Issues – Quick connector reliability
– Corrosion
– Improper insulation
– Delamination
– Discolouration
– Moisture ingress
– Bypass diode failure
Technology risk- modules
• Is IEC 61215 or 61646 proof that a product is durable and reliable? No!
• Not intended, or capable of showing long term performance
• Some Accelerated Life Testing, but not representative of real field conditions
• IEC Proves that the module meets certain standards.
IEC Certification
Third Party Insurance
Not Backed by third party insurance Backed by third party insurance
Suntech
First Solar
Yingli
Trina
Sharp
Sunpower
Hanwha Solar One
Kyocera
Jinko
Chint (Astronergy)
LDK
Canadian Solar
Solar Frontier
Solairedirect SA
NexPower Technology Corp
Signet Solar Inc
SolFocus Inc.
China Sunergy
• Module manufacturing industry currently in period of consolidation. • Ther is uncertain whether suppliers will be around for lifetime of warranty. • Third-party warranty insurance provides security even if company becomes
insolvent. • Several mainly tier 2 manufacturers now offer this, although not industry
standard. • Expect more manufacturers to offer in the next year due to highly
competitive nature of the market.
Insurance Providers: PowerGuard, Zurich, SPIB, Chartis, Solarif
• Temperature factors – Derating
– Shutdown
• Enclosure ratings – Indoor / outdoor
• Cooling – Forced or natural
• Fans – dusty environments
• Matched to the modules and strings
• Efficiency (Eu η%)
• Lifetime – Mid term replacements
Inverters
Bankability of Inverters
Product Warranty and extensions
Track Record
Compatibility with site climatic conditions
Euro Efficiency
IP Rating
Number of MPP Trackers
Voltage Range
Harmonic current conformity with grid Conformity with
national grid (G59/2 for UK)
IEC Certification
Technology (2)
Module Risks
• IEC certification
• Power tolerance
• Track record
• Financial standing
• De-rate with temperature
• Degradation rate
• Guarantees for power
Inverter Risks • Temperature factors
– De-rating – Shutdown
• Enclosure IP ratings – Indoor / outdoor
• Cooling – Forced or natural – Fans – dusty environments
• Matched to the modules and strings
• Contract strategy (EPC or Multi-contract)
– Both have benefits & drawbacks
• Interfaces
• Design
• Construction
• Who handles them?
• Programme
• Realistic
• Lead times
• Critical path
• Weather delays
• Adequate liquidated damages
• Supply contracts
• EPC contract
Team Capability – Completion Risk
• Trial Operation (10 days - 4 weeks)
– Reliability of:
• Inverters
• Tracking
• Whole System
– Performance Ratio Tests
• Acceptance
– Provisional Acceptance
– Final Acceptance (12-24 months later?)
Completion
Typical Acceptance Procedure
Mechanical Completion
Commissioning/start-up
Test Operation Period
(couple of days)
Performance Testing for Provisional Acceptance
(around 10 days)
Performance Testing for Final Acceptance
(over 1 or 2 years)
Provisional Acceptance
• Provisional Acceptance Testing starts after a short test operation.
• Successful completion of the tests marks the Provisional Acceptance of the plant.
• Failure of Provisional Acceptance Testing may require remedial measures and repeat testing.
• If the Plant again fails the test then liquidated damages will be payable.
Provisional Acceptance Tests (1)
Performance Ratio Test:
• Checks if the power plant is performing at or above the PR agreed or warranted within the EPC contract.
• Standard testing period would be continuous testing for around 10 consecutive days.
• If there are significant differences between the contracted and actual PR, the EPC contractor should identify and rectify the problem before repeating the PR test.
• The quality of a PV power plant may be described by its Performance Ratio (PR). The PR, usually expressed as a percentage, can be used to compare PV systems independent of size and solar resource. It quantifies loss associated with electrical elements of the plant.
• PR is a measure of actual generation versus the maximum based on DC capacity and irradiation received over a given time period.
• Installed DC capacity is defined at: – 1,000W/m2 irradiance
– 25 degrees C
– A defined solar spectrum
Performance Ratio
Final Acceptance
• Final Acceptance takes place after a successful repeated PR test.
• The period of operation between Provisional Acceptance and Final Acceptance is dependent on the EPC contract and the level of risk that may be accepted.
• A two year PR Warranty provided by the EPC Contractor followed by Final Acceptance provides good comfort to Investors since it covers risk degradation of the modules.
Acceptance Testing: Lessons Learned
• Use good quality calibrated measuring devices- this is often not observed
• A two year PR Warranty followed by Final Acceptance is often not observed
• PR tests should be carried out using clean pyranometers- often soiled pyranometers are used
• Availability formulas should take into account the scenario when only a proportion of the plant is operational- this is often overlooked
Sensor Devices
Pyranometer
• Measures solar irradiation
• Typical manufacturers: Kipp & Zonen, Eppley.
• Calibrated at least every 2 years.
• Measures full solar spectrum compared to reference cell which only measures part of spectrum.
• Should be cleaned regularly.
• Within 3% inaccuracy.
Monitoring Requirements
Measurement Description
Plane of Array Irradiance (Pyranometer) W/m2
Ambient Temperature °C
Module Temperature °C
Array DC Voltage V
Array DC Current I
Inverter AC Power VA
Exported Power VA
Imported Power VA
Wind Speed & direction if detailed modelling of system required
Horizontal Irradiance for comparisons with resource data sources
Inverter Output Current & Voltage I, V
Inverter Temperature Additional ventilation/cooling required?
Humidity Can effect lifetime of low quality modules
Monitoring: Common Mistakes
• Monitoring systems not installed in representative locations.
• Pyranometers not kept clean.
• Pyranometers not installed at module tilt.
• Only one pyranometer used. For a 5 MWp plant would expect two plane of array pyranometers (3 for >20MW) and one pyranometer on the horizontal plane.
• Reference cells should not be used in place of pyranometers as they may under-estimate the irradiation
Financial Model: What are The Risks?
• Sensitivity Analysis: – Annual module degradation 0.3% - 0.5% - 0.8%
– O&M costs ±10%
– Inverter replacement- once over project life?
– Module soiling losses: 2% , 3%, 4% (O&M dependent)
– Unavailability: 99%, 98% and 97% (dependent on grid strength)
• Reduce the likelihood or impact of the risk – Module cleaning linked to performance monitoring
– Include a maintenance reserve account
• Yield is often skewed seasonally – Include additional financial reserves to ease financial strain
Key Messages
• The process of technical due diligence can require considerable effort from the developer to satisfy the requirements of the lender.
• When well performed the lenders will fully understand the technical risks associated with the project and can decide if these are acceptable.
• A robust technical due diligence prior to designs being implemented can also pick up errors the developers have missed, and save them money.
• With experienced project partners, effective due diligence and good technical advisors, solar PV can be a low risk investment.
Any questions? www.sgurrenergy.com [email protected]
2
Introduction to Zouk Capital
Private equity investor focused on renewable energy
infrastructure and cleantech growth companies
Over €400m under management in 4 funds
Largest cleantech growth capital fund in Europe
3
Zouk’s dual track approach to the cleantech market
Alternative & Renewable Energy
Environmental Services & Technologies
Resource Efficiency Technologies
Solar
Biomass
Wind
Smart grid
Energy efficiency
Energy storage
Recycling Water
Waste management
Emissions solutions Advanced materials
Transport
Clean Technology
Marine
Fuel cells
Market intelligence
Deal flow
Commercial insight
Sector knowledge
Cleantech networks
Resource EfficiencyInfrastructure
Renewable EnergyGeneration
Environmental Infrastructure
Solar PV
Waste-to-Energy
Wind
Smart grid
Water treatment
Energy storage
Recycling
Waste management
Clean Infrastructure
Hydro
Transportation
Biomass Transmission
Biogas
Geothermal
Building efficiency
Focus on European expansion-stage cleantech companiesFocus on European expansion-stage cleantech companies
12 cleantech investments made over 2 funds12 cleantech investments made over 2 funds
4
Zouk’s cleantech growth capital strategy
Cleantech Europe II raised €230m and is the largest fund of its type in EUCleantech Europe II raised €230m and is the largest fund of its type in EU
Targeting high growth companies with established revenues (>€10m)Targeting high growth companies with established revenues (>€10m)
Select cleantech company investments
5
Water Solutions
Rural / Semi-urban Solar Building-integrated Solar
Solar / Recycling
Waste to Energy
Advanced thermal insulation
Electrical contractor
Energy efficiency services
Smart Grid
6
Zouk Infrastructure Fund I
39 MWCapacity built from late-stage development
10 projectsPortfolio: 5 in Italy, 5 in UK
Italy: large scale UK: distributed solar
7
Zouk Infrastructure Fund II
Financing renewable energy and environmental assets
Focusing on late-stage development and operational (distressed)
Investing primarily in Europe
Diversified range of sectors: geothermal, wind, solar, waste, hydro, biomass
Projects with Predictable Cash Flows
8
� Long term feed-in tariff framework with no or limited price and volume risk
� Long-term take-or-pay offtake agreements
� Limited merchant risk, if any, in liquid, transparent markets
� Operation in countries with stable track-record in relation to regulatory regimes
� Creditworthy / diversified counterparties
� Insurance for operation disruptions due to unpredictable events
� Non- or limited-recourse financing with adequate contingencies built into project budget
� Long-term financing with no or very limited refinancing risk
� Reputable, experienced lenders ideally with relationship with Zouk
� Debt / revenues / costs currency matching
� Hedging (interest rates, inflation, etc)
� Predictable cost structure over the life of the project
� Fixed-price, fixed date, turn-key construction contracts
� Long-term fixed price operating and maintenance contracts
� Cost hedging over the life of the Project (to the extent possible)
� Insurance for unpredictable events
RevenuesRevenues
FinancingFinancing
CostsCosts
Typical Project Structure
9
Centralised MKTs
Land Owners
Sponsor
Project SPVProject SPV
Govt.Govt.
Lenders
Offtaker(s)
FITs, Subsidies
OfftakeContracts
EPC Contractor
O&MContractor
Fuel Supplier
Insurance Providers
Financing Contracts
Asset Manager
Service Providers
Authorities
Developer
ProjectAuthorisations
Land Rights Agreements
Development Agreements
Project SellerProject SPA
EPC Contract O&M ContractFuel Supply
ContractInsurance Contract
Asset MngmtContract
Service Contracts
Sponsor
Capitalisation Contract
SH Agreement
OfftakeContracts
Risk Allocation
10
Centralised MKTs
Sponsors
Project SPV(Residual Risks)
Project SPV(Residual Risks)
Govt.Govt.
Lenders
Offtaker(s)
Price / Volume Risk
EPC Contractor
O&MContractor
Fuel Supplier
Insurance Providers
Developer / Project Seller
Construction Risk
Operation Risk
Fuel Supply Risk
FM Risk Authorisation Risk
Financing Risks
Comments� Risks should be allocated
to the parties best able to manage them
� Project contracts are the means to transfer risks
� Tender processes for the assignment of Project contracts should ensure maximum risk transfer at lowest possible costs
� The Project company is left with the residual risks which were not transferred to other parties
� Recourse to the Sponsors, if any, is always limited in amount, scope and time
Some residual risk,
(if limited-recourse)
Legal notices
The information contained in this document (the "Information") is issued by Zouk Capital LLP (the "Issuer") on a confidential basis to a limited number of prospective investors ("ProspectiveInvestors") and their respective legal counsel and/or other advisers ("Advisers") for the sole purpose of providing information in relation to the potential investment by Prospective Investorsin interests ("Interests") in the fund to be known as Renewable Energy and Environmental Infrastructure Fund II (the "Fund"). Neither Prospective Investors nor their Advisers shouldconstrue the Information as legal, tax, financial, investment, accounting or other advice, or as a recommendation by the Issuer, any of its affiliates, advisers, directors, employees or agents,that any Prospective Investor should acquire any Interest. Prior to making any investment, potential investors should arrive at an independent evaluation of such investment opportunity.The Information is qualified in its entirety by reference to the subscription agreements, limited partnership agreement(s) and any other legal documents constituting the Fund (the "FundDocuments"). Each investor who acquires an Interest will be bound by the terms and conditions of the Fund Documents. In the event that the descriptions in, or terms of, the Informationare inconsistent with, or contrary to, the descriptions in, or terms of, the Fund Documents, the Fund Documents shall prevail. The Information is subject to withdrawal, cancellation,modification or updating without notice, and is subject to the approval of certain legal matters by counsel and certain other conditions. This document is strictly private, proprietary andconfidential. This document may not be distributed, published, reproduced or transmitted in whole or in part, and the information contained herein (including the potential investmentopportunity) may not be disclosed by a recipient to any third party. By accepting delivery of this document, the recipient agrees to keep the information it contains strictly private andconfidential, and to return this document to the Issuer at any time upon the Issuer's request. No representation or warranty, express or implied, is or will be given by the Issuer or itsaffiliates, advisers, directors, employees or agents, and, without prejudice to any liability for, or remedy in respect of, fraudulent misrepresentation, no responsibility or liability or duty of careis or will be accepted by the Issuer or its affiliates, advisers, directors, employees or agents, as to the fairness, accuracy, completeness, currency, reliability or reasonableness of theinformation or opinions contained in the Information or any other written or oral information made available to any Prospective Investor or its Advisers in connection with any application tosubscribe for interests in the Fund (a "Proposed Subscription") or otherwise in connection with the Information. In particular, but without prejudice to the generality of the foregoing, norepresentation or warranty is given as to the achievement or reasonableness of any future projections, forecasts, targeted or illustrative returns (“Forward-Looking Information”). Actualevents and circumstances are difficult or impossible to predict and will differ from assumptions. A number of factors could cause actual results to differ materially from those in any Forward-Looking Information. There can be no assurance that the Fund’s investment strategy or objective will be achieved or that investors will receive a return of the amount invested. To the fullestextent possible by receipt of, and using, the Information, you release the Issuer and each of its affiliates, advisers, directors, employees and agents, in all circumstances (other than fraud)from any liability whatsoever and howsoever arising from your use of the Information or any information or communications provided in connection with any Proposed Subscription. Inaddition, no responsibility or liability or duty of care is or will be accepted by the Issuer or its respective affiliates, advisers, directors, employees or agents, for updating the Information (orany additional information), correcting any inaccuracies in it or providing any additional information to any Prospective Investor or its Advisers. Accordingly, none of the Issuer or its affiliates,advisers, directors, employees or agents shall be liable (save in the case of fraud) for any loss (whether direct, indirect or consequential) or damage suffered by any person as a result ofrelying on any statement in, or omission from, the Information or in, or omitted from, any other information or communications provided in connection with any Proposed Subscription.Investment in the Interests will involve significant risks. An investment in the Fund is only suitable for sophisticated investors and requires the financial ability and willingness to accept thehigh risks and lack of liquidity inherent in an investment in the Fund. The Fund's investments may be difficult to value and involve an above-average level of risk. No assurance can begiven, and no representation is made herein, that the Fund's investment strategy will be achieved or that investors will receive a return of their capital. Any offer or sale of securities (orInterests such as those described in this Information) may in certain jurisdictions be restricted by law. Any Prospective Investors who are considering making an investment in the Fund arerequired to inform themselves about, and to observe, any such restrictions. It is the responsibility of each Prospective Investor to satisfy themselves as to full compliance with the applicablelaws and regulations of any relevant territory, including obtaining any requisite governmental or other consent and observing any other formality presented in such territory. No action hasbeen taken to permit a public offering of the Interests in any jurisdiction where action for that purpose would be required. This Information does not constitute an offer to sell or a solicitationof an offer to buy Interests in any jurisdiction to any person to whom it is unlawful to make such offer or solicitation in such jurisdiction.
11
Contact details
12
Zouk Capital LLP
100 Brompton Road
London
SW3 1ER
United Kingdom
+44 (0)20 7947 3400
www.zouk.com
Lead contacts
Lee Moscovitch [email protected] +44 (0)20 7947 3414
Ref: 1126192
The Ernst & Young Environmental Finance team
The solar PV investment opportunity
Navigating incentives
The funding backdrop
Summary
Agenda
Eversheds conference June 2012 2
Ref: 1126192
Ernst & Young Energy Infrastructure Advisory team
We are a market leading renewable energy
corporate finance team, with over 60
dedicated professionals advising on
energy and environmental finance
Ernst & Young acted as lead financial advisor to SeaEnergy Plc.
SeaEnergy Plc
This announcement appears as a matter of record only.
has disposed its offshore wind development subsidiary,
SeaEnergy Renewables
Ltd
Repsol
to
for £50 million
Ernst & Young acted as financial advisor to RES UK & Ireland Ltd.
has disposed of a majority stake of
Wadlow Energy Ltd
to
Barclays Infrastructure Funds
RES UK & Ireland Ltd
This announcement appears as a matter of record only. August 2011
3 Eversheds conference June 2012
Ernst & Young acted as financial advisor to the shareholders of Eco2 Lincs Limited.
Eco2 Lincs Limited
This announcement appears as a matter of record only.
has raised £115 million of senior debt funding to construct and operate the Lincolnshire based 38 MW straw fired
Sleaford Renewable
Energy Plant The lending club consisted of NIBC Bank NV, The Royal Bank of Scotland, Siemens Bank GmbH and Unicredit Bank AG
We are currently advising on:
► Over 5GW of renewable M&A
transactions in Europe
► Over £300m of project financing for
renewable projects in Europe
In the last 15 months, we have:
► Disposed of four consented onshore
wind farms in the UK
► Secured c.£115m senior debt and a
PPA for Sleaford biomass plant
► Advised on PPAs for over 130MW of
renewable energy capacity.
► Provided complex financial modelling
and structuring services to the largest
solar project finance facility in the UK
(Eaga - £225m)
Since 2005, we have:
► Raised project finance for over 785MW
of renewable energy assets
► Advised on PPAs for over 1.1GW of
renewable assets
Ernst & Young provided accounting, tax and modelling services to Eaga plc.
has provided accounting, tax and modelling services on Eaga's £300m project f inancing of a portfolio of social housing rooftop solar PV installations
Eaga plc
UK Solar PV project financing
This announcement appears as a matter of record only. March 2011 This announcement appears as a matter of record only.
Ongoing
Structuring and financing advice on £1.5bn major infrastructure roll out Financial Advisor
This announcement appears as a matter of record only.
Ongoing
£1.5bn Smart meter funding and commercial strategy Financial Advisor
Our EEIA team sits within the wider EMEIA Infrastructure Advisory team
currently advising on £10 billion of infrastructure project financings, allowing
us to understand financing trends across a broad range of asset classes.
Ref: 1126192
Sector thought leadership
Eversheds conference June 2012 4
Our market leading thought leadership and research addresses a broad spectrum of challenges, from industry-wide issues to specific technical, business, regulatory and compliance concerns
4
Country attractiveness indices
Our quarterly Country Attractiveness Indices have become a benchmark for all our clients. It provides scores for national renewable energy
markets, renewable energy infrastructures and their suitability for individual technologies (wind, solar and biomass).
The CAI has been reported in 107 different publications worldwide, spanning most forms of media including TV, global and national
mainstream press and trade press and is one of the leading publications in the global renewable energy market.
Utilities unbundled
Utilities Unbundled, Ernst & Young’s semi-annual global power and utilities magazine, features insight from leading industry figures,
comment on key industry issues and analysis of the latest trends. Read about what your peers around the world are thinking and doing
about common industry concerns.
Growing beyond
The EY Global Cleantech Centre produces its “Growing beyond: the cleantech growth journey” publication on an annual basis. It includes
the findings from our annual Cleantech CEO Growth Journey retreat. Developed with Bloomberg New Energy Finance, the event brings
together nearly 50 CEOs to address the industry's capital, partnership and expansion challenges.
.
Cleantech matters
The cleantech-enabled transformation to a resource-efficient and low carbon economy is characterised by many observers as the next
industrial revolution. Our quarterly “Cleantech Matters” publication includes material covering the sector’s key drivers, trends and issues.
INSTRUCTIONS
The font size on the slide master
has been increased by 1pt, so that
text sizes are applied to the
standard two column layout in the
correct font size.
Go to the View menu and select
Header and Footer… to update
the Proposal title and Date.
No.1 by Global and EMEA Mandates Won
2005 - 2009
No.1 by Global PFI/PPP Deals closed
2009 & 2011
Ernst & Young 2011 No.1 by Global
Mandates Won
2009 Renewable Energy Advisor of Choice
Ernst & Young 2010 No.1 by Global
Mandates Won
Financial Advisor of the Year – Renewables
2008
PPP Financial Advisor of the Year
2005, 2007 & 2009
2011 Best Project Finance Adviser in EMEA and CEE
2009 Best Project Finance House – Financial Advisor
Best Advisory Firm – Renewable Energy Europe
Financial Adviser of the Year - Renewable Energy Financial Adviser of the Year - Power Financial Adviser of the Year - Social Infrastructure
2011 Middle East Power Deal of the Year
Sur IPP
2011 Best Infrastructure Deal in CEE - Polish Airports State Enterprise’s PLN700mn fund
raising
2011 PPP Deal of the Year Suffolk Waste PFI
European Transmission Deal of the Year - Robin Rigg OFTO
2011 Best PPP Deal in the Middle East – Bahrain Housing
2011 Asia-Pacific PPP Deal of the Year
Adelaide Hospital
Infrastructure Advisory– our awards
5
Partnerships Awards 2012
Best Local Government Project Team Devon Waste Partnership
Partnerships Awards 2012 Partnerships Awards 2012
Best Waste/Energy/Water Project South West Devon Energy from Waste PFI
Project Grand Prix South West Devon Energy from Waste PFI
Overall Project Finance Firm of the Year: UK
Partnerships Awards 2012
Best Financial Adviser
Eversheds conference June 2012
Ref: XX00000
A snapshot of UK Solar PV
Eversheds conference June 2012 7
Greg Barker – 24 May 2012
► “We can now look with confidence to a future for solar which will see it go from a small cottage
industry, anticipated under the previous scheme, to playing a significant part in Britain's clean
energy economy”
DECC recognise solar in RE roadmap
► DECC 2020 solar power pathway central scenario delivers 22GW of solar PV
Buyers market
► Continued over supply with ever decreasing panel and EPC prices
► Falling tariff regimes across Europe
► Grid parity around the corner?
Consultation, consultation, consultation
► DECC RO Banding consultation (ongoing) 2.0 ROCs falling to1.8 ROC
► FIT consultations known for now, awaiting response on Phase 2B
Other policy Renewable Heat Incentive / Green deal
► First of its kind support for renewable heat generation including solar thermal
► Energy efficiency loan scheme, domestic market minimum EPC requirements
Ref: XX00000
Investment through the transaction lifecycle
Eversheds conference June 2012 8
Note:
1. Based on a limited number of UK transactions and Ernst & Young experience working with leading developers in the field who tend to apply
these percentages to estimate value once set milestones are achieved
0%
20%
40%
60%
80%
100%
Land/feasibility study
Planning/EIA
Grid
Solar irradiation
Planning fully consented Financial close Commercial operational date
Bank terms agreed at close Project Finance
Pyranometer
Principal contract suite
Construction
12 months wind data
c.1-6 months c.1-6 months
Indicative value
realisation1
(% of total
realisable site
value assuming
sale at given point
in time)
Leases signed and surveys complete
Informal offer agreed
Preliminary data
Offer signed including indicative grid live date
PPA and construction contracts agreed at close Estimated
construction
period and
grid live date
coincides
Ref: XX00000
0
200
400
600
800
1,000
1,200
1,400
Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12
Dep
loym
ent (
MW
)
Domestic Commercial Industrial Community
FiTs indexed linked revenues give stability, but in unstable regime
May 2012
Confirmed cut in FiT
in August 2012
March 2012
Supreme court
rejects DECC appeal
Feb2012
DECC issue publish
response to Phase 1
consultation and
issue Phase 2
consult
January 2012
DECC looses court
of appeal decision
December 2011
DECC issue publish
response to Phase 1
consultation and
issue Phase 2
consult
December 2012
Judicial review
rejected, high court
appeal granted to be
heard
October 2011
DECC publish
comprehensive
consultation to
reduce tariffs on 10
December
April 2010
FiT launched
March 2011
DECC publish fast
track review on FiTs
June 2011
Response to fast
track review
confirming cut to PV
tariffs >50kWp
August 2011
New rates for
installations <50kW
take effect
August 2012
20yr tariff
Quarterly degression
Deployment
dependant
90% multi installation
tariff (>25 systems)
Increased export
E EPC rating or get
standalone tariff
Ref: XX00000
So projects under ROC regime gaining traction
Suppliers
RE generators
Trade ROCs
2
Issue ROCs 1
Regulator
End user
Ofgem
Utilities
(e.g., E.ON, Scottish Power, Centrica, SSE, RWE)
Independent
developers
(e.g., RES, Falck)
Infrastructure
funds
(e.g., HG Capital)
Utilities
(e.g., Scottish
Power)
Su
rre
nd
er
RO
Cs
3
RO
C r
ecycle
4
How the ROC market works
1. Ofgem issues ROCs to generators
according to renewable MWh
generated.
2. Suppliers obtain ROCs by:
► Owning qualifying assets.
► Buying ROCs through a PPA with
a generator.
► Buying ROCs from another
supplier (with surplus ROCs), or
through the commodity market.
3. To comply with their obligation,
suppliers must surrender ROCs.
4. Where there is a ROC market
shortfall, under-compliance is fined
and the proceeds distributed to
compliers as a ‘recycle’.
The ROC market
Ref: XX00000
And the future for the proposed FiT CfD
► Will investors be turned off by lack of power price exposure?
► Will 15 year tenor attract investors seeking long term, low
risk returns?
► Strike price mechanism?
► Guarantor between generator and supplier
The key to achieving these objectives will be to bring forward the level of investment needed in
new low-carbon generation capacity and infrastructure at the required pace and through a
combination of measures.
Source: DECC
► Overlap of RO provides some continuity, but without
absolute certainty on revenue
► Gross margin indexation linkeage RO and FiT CFD –
loss of natural hedge?
► Competition against transport fuels (revenues linked to
oil price)
Ref: XX00000 03 July 2012
Renewable equity investors - typical risk-return profile
Existing
developers
UK/ International
utilities
Infrastructure
funds
Secondary funds
(e.g., pension)
► Appetite for development risk – increased risk for
higher returns
► Exit after construction to fund pipeline
► Strategic objective
► Project development chain
► Low WACC
► May take on construction risk
► Desire to place funds drives return
► Long-term predictable cash
flows
► Limited appetite for
construction risk
► Varying comfort with power
price risk
Eq
uity c
ost of capital
Fully consented Financial close Commercial operational date Stage of development
Deal size £5 – 10mn £10 – 50mn £100 – 500mn
Ref: XX00000
Debt finance
Eversheds conference June 2012 15
► Increasing trend towards:
1. Club lending
2. Credit committee decision making driven by
relationships and geography
3. Mini-perm structures
4. Aggressive cash sweeps and restrictions on
payments to equity
5. Rise in margins (although offset by recent fall in the
long-term swap rate
► Attitude towards long term strategy in the project
finance market will vary by bank, however major deals
continue to be done (see graphic)
► Role of ECAs and Multilaterals key for overall funding
strategy and market approach
► Limited appetite for rooftop UK solar PV beyond solar
► Future for Ground mounted under ROCs?
Source: Infrastructure Journal
0
50
100
150
200
250
300
350
2005 2006 2007 2008 2009 2010 2011
US
$ b
n
Global project f inance volume by funding source
Equity Bonds Loans IFI Suppor t
Ref: XX00000
Solar PV funding – the capital journey
Eversheds conference June 2012 16
Exit arranged whereby value of assets transferred to long-term owner
Equity capital at 15%
(business model inertia risk)
Ownership capital at 6 – 7% cost of funds
Time period (X months)
Installation
Spend Investment (X £m)
Capital increase realised through cost of funds arbitrage,
releasing capital for further installation programme
Installation spend funded unencumbered
with external capital, i.e. equity or corporate debt
Constraints:
► Pension funds/insurance funds/life funds do not have significant
capital allocations specifically for renewables investments
► Conduits do not exist that enable PV market to effectively
access this capital – these funds do not invest directly
► Inertia risk, technology performance risk, and resource risk
needs to be properly understood to access low-cost funds
► Large equity capital sources needed to build installation capex
to levels to attract such investors
Ideal world:
► Long-term ownership resides
with low cost, long-term cash
yield investors
(pension/insurance/life funds)
► Cost of funds: c 6 – 7%
► Deal size: £100mn plus
Ref: XX00000
The road to the PV financing future
Eversheds conference June 2012 17
► Aggregation and consolidation
► Flight to quality
► How do you deliver long term institutional capital?
► Right conduit
► Right portfolio
► Right structure
► Right management
► Right advisors
Ref: 1126192
Summary
Eversheds conference June 2012 19
Solar investment opportunity
► 22GW of deployment in UK
► Cost reductions look set to continue – 50% -70% cost reduction in few years
► Grid parity
► Low(er) risk renewable technology
Revenues – which TLA will you invest in?
► FiTs
► ROCs
► CfD
The funding backdrop
► Conventional financing solutions are not a perfect fit for highly aggregated portfolios
► Optimising finance is a major value lever of UK PV – how long will it take
► Aggregation and flight to quality likely
Ref: 1126192 Eversheds conference June 2012 20
Thank you Louise Shaw, Senior Executive,
Environmental Finance
Tel: +44 (0)20 7951 4806
Email: [email protected]
www.ey.com/renewables
Ref: 1126192
Ernst & Young LLP
Assurance | Tax | Transactions | Advisory
www.ey.com/uk
The UK firm Ernst & Young LLP is a limited liability
partnership registered in England and Wales
with registered number OC300001 and is a member firm
of Ernst & Young Global Limited.
Ernst & Young LLP, 1 More London Place, London SE1 2AF.
© Ernst & Young LLP 2012. Published in the UK.
All rights reserved.
This document has been prepared by Ernst & Young. The information and opinions contained in this document are derived from public
and private sources which we believe to be reliable and accurate but which, without further investigation, cannot be warranted as to their
accuracy, completeness or correctness. This information is supplied on the condition that Ernst & Young, and any partner or employee of
Ernst & Young, are not liable for any error or inaccuracy contained herein, whether negligently caused or otherwise, or for loss or damage
suffered by any person due to such error, omission or inaccuracy as a result of such supply. In particular any numbers, initial valuations
and schedules contained in this document are preliminary and are for discussion purposes only.