AREVA Reliance Project Snapshot May14 final.pdf
9
Site Overview Reliance CSP Project Snapshot May 2014
-
Upload
navneet-pandey -
Category
Documents
-
view
221 -
download
0
Transcript of AREVA Reliance Project Snapshot May14 final.pdf
-
Site Overview
Reliance CSP Project Snapshot
May 2014
-
100% Receivers lifted (35 in total)
-
Receiver with Boiler tube
-
ICP
ICP Line
Phase 2 ICP Steam blow
-
Power Block
-
Insulation Towers
Steam production
Steam column around 100m high
-
Safety Stand Down
-
Physical Progress on site (as of May 2014)
Mechanical completion
100%
Electrical completion
97%
I & C completion
97%
25 SSGs commissioned (out of 35) Preparing for the synchronization with grid