April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

17
April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting

Transcript of April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Page 1: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

April 15, 2015

Odd Fellows Road Interchange and Roadway Improvements

Citizen Information Meeting

Page 2: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Contract Information

Contractor: G.A. & F.C Wagman, Inc.

David Lyle Design-Build Project Manager

Paul Phillips Design-Build Construction Manager

Designer: Johnson, Mirmiran & Thompson, Inc.

Rodney Hayzlett, P.E Design Manager

Contract Price: $29,846,350

Awarded: January 2015

Notice to Proceed: February 18, 2015 (Design Start Date)

Construction Start: November 2015

Final Completion Date: August 3, 2018

Page 3: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Introductions

Contract Information

Project Overview

Roundabouts

Construction Schedule

Conclusion

Agenda

Page 4: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Project Overview

Page 5: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Project OverviewSegment A

Design Features: New interchange with US 29/460

New roundabout at Top Ridge Road

Segment A

Top Ridge Road Roundabout

Bradley D

rive

Segment B1

WBL R

oute 460

EBL Route 460

Page 6: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Project OverviewSegment B1

Design Features: Roadway improvements along Odd Fellows Road

New roundabout at Mayflower Drive

Segment B1

Mayflower Drive Roundabout

May

flo

wer

Dri

ve

Bradley D

rive

Segment A

Segment B2

Page 7: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Project OverviewSegment B2 (Design Only)

Design Features: Roadway improvements along Odd Fellows Road

New Roundabout at Albert Lankford Drive and Murray Place

Segment B2

Albert Lankford Drive Roundabout

Lynchburg

Expressway

Segment B1Norfo

lk-S

outher

n Rai

lway

Albert Lankford DriveM

urra

y Pl

ace

Page 8: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Roundabout Basics

Source: NCHRP Report 672, Roundabouts: An Informational Guide (Oct. 2010)

Typical Features

• Circular shape

• Traffic yields entering the circle

• Splitter islands direct traffic and

provide refuge for pedestrians

• Concrete apron permits turning

movements by large trucks

• Modern roundabout dates to

1960’s (U.K.)

• Virginia has 130± in its inventory

• 3 in Lynchburg District

Splitter Island

Apron

Diameter

Page 9: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Roundabouts

What benefits do roundabouts offer?

FUNCTIONAL

Keep traffic moving

Lower delays than a signalized

intersection

Lower costs to operate and

maintain

Reduced vehicle emissions

Source: NCHRP Report 672, Roundabouts: An Informational Guide (Oct. 2010)

Delay with Signal16 sec

Delay with Roundabout3 sec

1000 vehicles/hour

Page 10: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Roundabouts

What benefits do roundabouts offer?

SAFETY

• Significant safety improvement

Lowers vehicle speed

Eliminates red-light running

Eliminates most serious conflict points

Safer for pedestrians and cyclists

• Compared to Signalized Intersections

90% Reduction in Fatal Crashes

75% Reduction in Crashes with Injury

30% Reduction in Pedestrian Crashes

10% Reduction in Bicycle Crashes

Source: NCHRP Report 672, Roundabouts: An Informational Guide (Oct. 2010)

Page 11: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Roundabouts

What benefits do roundabouts offer?

SAFETY

Far fewer conflict points

Source: NCHRP Report 672, Roundabouts: An Informational Guide (Oct. 2010)

Page 12: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Roundabouts

3 Roundabouts Included on Project

1. Segment A: Top Ridge Road 80’ Diameter

2. Segment B1: Mayflower Drive 120’ Diameter

3. Segment B2: Albert Lankford Drive 85’ Diameter

How do these compare to existing roundabouts in Lynchburg District?

2

3

1

Page 13: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Roundabouts

5th StreetLynchburg, VA75’ Diameter

75’

Page 14: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Roundabouts

Routes 60 and 29Amherst, VA85’ Diameter

85’

15.9% Trucks

Page 15: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Roundabouts

Mayflower Drive

120’

8.6% Trucks

Page 16: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Construction Schedule

Targeting 2018 Delivery

Utility Relocations – June 2015 thru June 2016

Project Completion – August 2018

Traffic Impacts

Restrictions on Single Lane Closures

Odd Fellows Road: 7 AM – 9 AM; 4 PM – 6 PM

Route 29/460: 7 AM – 9 AM; 2 PM – 6 PM

Restrictions on Total Closure

6 AM – 7 PM (15 Minute Maximum)

Page 17: April 15, 2015 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting.

Please Join Us at the Displays For More Information