Honeywell Aerospace Management System Approach HSEMS Overview & SBG Governance
An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace...
Transcript of An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace...
![Page 1: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/1.jpg)
28-29 October 2002 Slide 1 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
An Heritage Approach to Aerospace Risk Based Design: With Application
Prepared at:SRA Workshop on Risk Analysis of Aerospace Systems II:
Mission success Starts with Safety28-29 October 2002
Prepared by:Joseph R. Fragola
Vice President and Principal Scientist
Science Applications International Corporation265 Sunrise Highway, Suite 22, Rockville Centre, NY 11570
![Page 2: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/2.jpg)
28-29 October 2002 Slide 2 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
• Historical Performance Assessment • Space Shuttle Analysis• Potential Safety Goals Review• Current Risk vs. Time (Risk Intensity)• Application of heritage approach to
risk-based design
Heritage Approach to Risk-Based DesignLauncher Architecture Application
![Page 3: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/3.jpg)
28-29 October 2002 Slide 3 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Historical Crew Safety
1 in 10
1 in 100
1 in 1,000
1 in 10,000
Mercury &Gemini
Apollo
Apollo (LunarLandings Only)
Apollo, Mercury& Gemini
All pre-Shuttleprograms
(including Skylab& Apollo-Soyuz)
Pre-Challenger
Post-Challenger(SAIC '95)
Current Shuttle(SAIC '99)
Apportionment
Estimate
Demonstrated
Loss
of C
rew
Pro
babi
lity
Estimate
![Page 4: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/4.jpg)
28-29 October 2002 Slide 4 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
0.1%
1.0%
10.0%
100.0%
Shuttle* Delta II Atlas I & II
Soyuz Proton Zenit Ariane 4 H-II Long March
Launch Vehicle
Loss
of V
ehic
le P
roba
bilit
y (p
er m
issi
on)
*Space Shuttle estimate is for ascent only (this allows a for a fair comparison with other launch vehicles)
Current Launch Vehicle Safety/Reliability
![Page 5: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/5.jpg)
28-29 October 2002 Slide 5 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Historical Performance Assessment
Safety and Mission Reliability Performance
![Page 6: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/6.jpg)
28-29 October 2002 Slide 6 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Mission Reliability vs. Safety
• Reliability related to Safety, but not identical
• Sometimes the two conflict, as in abort decisions
• Less reliable vehicles can even be safer if intact abort/crew survival options better
![Page 7: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/7.jpg)
28-29 October 2002 Slide 7 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Historical PerspectiveLV Safety and Reliability
• Space shuttle one of the most reliable demonstrated launchers: 1 in 100 or 99%
• Estimated current launch reliability over 1 in 400 or 99.7%. Best, by far of any other
• Crew survival capability limits safety. Estimated in same range as Apollo era Saturn, about 1 in 200
![Page 8: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/8.jpg)
28-29 October 2002 Slide 8 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Transportation System Safety “Pillars”
1 . Inherent Reliability: Safe and reliable in normal operation.
2 . Intact-Abort: Robust design allows return of vehicle and personnel, safely given mission loss.
3 . Survival: Personnel safety ensured with vehicle loss.
![Page 9: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/9.jpg)
28-29 October 2002 Slide 9 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Space Transportation Safety Improvements
• Inherent reliability• Abort success• Personnel survival
![Page 10: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/10.jpg)
28-29 October 2002 Slide 10 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
QRAS Cumulative Risk Intensity
![Page 11: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/11.jpg)
28-29 October 2002 Slide 11 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Current Shuttle Abort Capability
(Alt ~ 150kft)
![Page 12: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/12.jpg)
28-29 October 2002 Slide 12 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Abort Focus and Definition
• Inherent reliability and crew survival/escape potential discussed previously
• Focus here on “aborts”• Aborts include mission continuance or safe
return with “graceful” failures in major risk contributing areas
• Propulsion on ascent and landing on descent for example
![Page 13: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/13.jpg)
28-29 October 2002 Slide 13 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Abort Risk Reduction Value• Intact aborts valuable contributors to safety
and payload,risk reduction, but not mission reliability unless mission is continued
• Aborts provide mission continuance and vehicle return in ascent and assured return in descent
• Ascent value driven by ICF%,engine out, and benign failure detection capability
• Descent value driven by Go-around
![Page 14: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/14.jpg)
28-29 October 2002 Slide 14 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Ascent Risk Reduction Value
• Shuttle abort probability about 1 in 100 • Probability driven by single engine
failure for most of ascent• Mission continuance limited to only
small portion of ascent• Intact abort to landing success limited
by viable landing sites
![Page 15: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/15.jpg)
28-29 October 2002 Slide 15 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
SSME Benign Shutdown
DynamicProbability of: Safie
First Engine Shutdown 1 in 150 1 in 106 1 in 106Second Engine Shutdown 1 in 225 1 in 159 1 in 230
Two Engine Shutdown 1 in 33,750 1 in 16,854 1in 24,345
MaggioStaticModel Evaluation
•Dynamic calculates probability of second engine shutdown as a function of first engine time. •Determines the extended operation time required and probability of shutdown based on extended operation time and power level.
![Page 16: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/16.jpg)
28-29 October 2002 Slide 16 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Ascent Abort Risk Reduction Value
• 90% shuttle abort success, implies reduction in ascent safety from 1 in 400 to 1 in 290
• Abort success improvement factor of 10, at least, by increase in landing site options
![Page 17: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/17.jpg)
28-29 October 2002 Slide 17 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Ascent Risk Reduction Value
• Engine out capability allows single liftoff failure mission continuance and abort to landing with benign double failure
• Horizontal takeoff and flight to altitude also significant potential risk reducer
• Risk reduced to 1 in 100,000 by combining both at current engine inherent reliability levels. Factor of 10 increase approaches commercial air risk range of 1 in 1,000,000
![Page 18: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/18.jpg)
28-29 October 2002 Slide 18 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Risk Reduction Value of Aborts Descent
• Shuttle landing risk estimated in order of 1 in 2000, Dead stick
• Assuming majority of the landing risk alleviated by Go-Around, risk reduced to 1 in 4 million
• Reduced risk consistent with commercial air landing (assuming higher speed compensated by other factors)
![Page 19: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/19.jpg)
28-29 October 2002 Slide 19 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Final CommentsShuttle Safety
• The Space Shuttle is the world’s most reliable launch system in operation
• Inherent reliability growth, while important, is limited by the existing design of the Shuttle
• Process changes, while not analyzed, offer the potential for additional safety growth
• The safety impact of a 50% ascent crew survival system or RFS are approximately the same– Factor of 2 improvement– Potentially large difference in cost and schedule
• If significant ascent improvements are made, further safety improvements must address descent risk items– Examples: Landing, TPS, APU, Flight Controls(limited
work to date)
![Page 20: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/20.jpg)
28-29 October 2002 Slide 20 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Flight Failures vs. Altitude
![Page 21: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/21.jpg)
28-29 October 2002 Slide 21 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Personnel Survival Considerations
• Shuttle Risk insights• Re-visit of SRB Risk• Review of WSTF test results• Re-visit of 51-L event• Risk-based design perspective for
personnel survial
![Page 22: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/22.jpg)
28-29 October 2002 Slide 22 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
SRB Considerations
• SRBs continue to be the most risk intense element of shuttle system
• SRBs most likely initiator of ascent accident while attached
• However, SRB failure mode risk dominated by non-explosive modes– Historically only 1 in-flight explosion in the
last 20 years– Dominant failure scenarios lead to H2/O2
involvement and/or aerodynamic breakup
![Page 23: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/23.jpg)
28-29 October 2002 Slide 23 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
WSTF H2O2 Explosion Testing• WSTF Conducting Tests for NASA
Code Q as part of INSRP Activity
• Tests on Scale of Delta ELVindicate limiting effects even atground level
• Interaction zone appears limited tointertank surface area
• NASA lead and contractor expertsfeel 95% limit is 1,000lb (TNT) and50% limit (most probable) is 500lb
![Page 24: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/24.jpg)
28-29 October 2002 Slide 24 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Key Events Leading to 51-L Accident
Event MET (sec)
• First Evidence of plume 58.788
• LH2 Press. Deviates 66.764
• H2 Cloud RH of ET 73.188
• Bright spot bet. Orbiter & ET 73.173
• Localized small expl’n at intertank 73.213• Massive dump of H2 73.282• H2 leak from aft dome 73.290• Last Telemetry 73.631• Crew Module emerges from cloud 74.165• Nose and cargo bay severed 74.578
InsertChallenger Movie
*51L Explosion Working Group, KSC-00232,06/16/89
![Page 25: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/25.jpg)
28-29 October 2002 Slide 25 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Required Escape Warning TimesConstant 10G, 3 second escape acceleration, equivalent
Structural overpressure load for 14.7 psi internal pressure
Note: Does not account for initial vehicle flight velocity
![Page 26: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/26.jpg)
28-29 October 2002 Slide 26 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Observations from 51-L Applied to Crew Escape Activation
• Even with initiation of LH2 pressure deviations, only 6.5 secs would have been available to activate escape system
• Wait to loss of pressure maintenance would have allowed only 1 sec for activation
• Activation of escape system likely only if initiated without hesitation at first deviation
Unlikely that an escape system would have activated in a 51-L type event
![Page 27: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/27.jpg)
28-29 October 2002 Slide 27 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Observations from 51-L Applied to Crew Module Survival
• Only small local explosion in intertank - no pressure wave
• Breakup aerodynamic, failed in pure tension
• Crew cabin survived 51-L with minimal damage to integrity of system
• Crew loads (7-8 gs) were well within survival limits
Crew and cabin would likely survive initial insult if a 51-L type event were to reoccur
![Page 28: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/28.jpg)
28-29 October 2002 Slide 28 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Crew Survival Option Impact on Safety
Sf
0.05
0.07
0.40
TBD
0.30
0.80
0.80
Mean
349
353
438
TBD
470
1234
1512
Ascent Descent Total Pcs
Sf
0
0
0.05
TBD
0.25
0.65
0.75
Pcs
671
671
706
TBD
895
1917
Pcs
729
745
1155
TBD
990
3465
Median*
380
386
478
TBD
513
1350
16532684 3465
Survival OptionComments
Bailout
Walkaround Extract
Seat Extract
CM Stabilization and Bailout
CM Separation (Intact Recovery)
CM Separation (Extract/Eject)
Escape Pod
Current System
Current System with Stabilization
*Calculated using an error factor of 2
![Page 29: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/29.jpg)
28-29 October 2002 Slide 29 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
CFD Surface Mesh for Explosive Survivability Analysis
173,794 Boundary Points2,679,754 Points
15,197,690 Elements
173,794 Boundary Points2,679,754 Points
15,197,690 Elements
![Page 30: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/30.jpg)
28-29 October 2002 Slide 30 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Detonation Initiation and Early Time Propagation
• 500lb TNT Equivalent Charge
• Initiation as a spherical blast with radius of 32.15cm
• Typical Time-Step : DT = 3.1 m sec– About 13,000 Time-
Steps
![Page 31: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/31.jpg)
28-29 October 2002 Slide 31 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Steady State Conditions at 51-L Accident Point
7.98 psi
0.04 psi
Pressure Distribution
Alt. = 52,000 ftMa = 1.97
2.8
0.0
Velocity Distribution
![Page 32: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/32.jpg)
28-29 October 2002 Slide 32 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Space Shuttle Explosion Analysis500 lb. of TNT - Time = 0.4ms
126.2 psi
0.0 psi1.3e+5 cm/s
0.0 cm/s
Pressure Distribution
Velocity Distribution
![Page 33: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/33.jpg)
28-29 October 2002 Slide 33 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Space Shuttle Explosion Analysis 500 lb. of TNT - Time = 2.4ms
22.5 psi
0.1 psi 1.3e+5 cm/s
0.0 cm/s
Pressure Distribution
Velocity Distribution
![Page 34: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/34.jpg)
28-29 October 2002 Slide 34 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Space Shuttle Explosion Analysis 500 lb. of TNT - Time = 7.7ms
22.5 psi
0.0 psi1.3e+5 cm/s
0.0 cm/s
Pressure Distribution
Velocity Distribution
![Page 35: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/35.jpg)
28-29 October 2002 Slide 35 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Space Shuttle Explosion Analysis 500 lb. of TNT - Time = 11.4ms
22.5 psi
0.0 psi 1.3e+5 cm/s
0.0 cm/s
Pressure Distribution
Velocity Distribution
![Page 36: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/36.jpg)
28-29 October 2002 Slide 36 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Space Shuttle Explosion Analysis 500 lb. of TNT - Time = 14.7ms
22.5 psi
0.0 psi 1.3e+5 cm/s
0.0 cm/s
Pressure Distribution
Velocity Distribution
![Page 37: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/37.jpg)
28-29 October 2002 Slide 37 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Space Shuttle Explosion Analysis 500 lb. of TNT - Time = 29.5ms
7 psi
0.0 psi 2.7e+5 cm/s
0.0 cm/s
Pressure Distribution
Velocity Distribution
![Page 38: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/38.jpg)
28-29 October 2002 Slide 38 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Explosive Overpressure and Impulse on Orbiter
140
Approximate Location of 576 Bulkhead
134
135
136
137
138
139
Probable Range ofAcceptable Pressures
![Page 39: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/39.jpg)
28-29 October 2002 Slide 39 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Crew Survival System Concept
Initial Event Crew Cabin Separation Stabilization
DecelerationLanding
QuickTime™ and aCinepak Codec by Radius decompressor
are needed to see this picture.
![Page 40: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/40.jpg)
28-29 October 2002 Slide 40 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Historical Approaches to Personnel Survival
• Two approaches applied:– Escape from danger
• Military aircraft-ejection• Passenger ships-lifeboats
– Survive and recover• Military helicopters• Race cars
![Page 41: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/41.jpg)
28-29 October 2002 Slide 41 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Crew Safety Lessons Learned fromShuttle Design
• Launcher survival heritage in “escape from danger” technology
• Technology suitable for Apollo era launchers and others stacked in-line
• Escape systems may be non-viable for tandem vehicles as shuttle or others requiring in-stream ejection
• “Survival and recover” approach may be viable option especially for LOX/H2 fueled systems
![Page 42: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/42.jpg)
28-29 October 2002 Slide 42 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
Example Risk Allocation - 1:10,000
ImmediateCatastrophic
FailureGoal: 1 in 1,200
UnrecoverableAbort
SituationGoal: 1 in 6,000
Loss of VehicleGoal: 1 in 1,000
Crew SurvivalGoal: 1 in 13
Crew RecoveryGoal: 1 in 46
Crew ReturnGoal: 1 in 10
Crew SafetyGoal: 1 in 10,000
![Page 43: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/43.jpg)
28-29 October 2002 Slide 43 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning
![Page 44: An Heritage Approach to Aerospace Risk Based Design: With ... · A Heritage Approach to Aerospace Risk Based Design: With Application Day 1 Morning Abort Focus and Definition •](https://reader030.fdocuments.net/reader030/viewer/2022040401/5e788d607c25f227b01b4c6f/html5/thumbnails/44.jpg)
28-29 October 2002 Slide 44 of 44
A Heritage Approach to Aerospace Risk Based Design: With ApplicationDay 1 Morning