Alabama State Port Authority Serving Alabama Alabama Section of the American Water Resources...
-
Upload
kolby-giffin -
Category
Documents
-
view
241 -
download
0
Transcript of Alabama State Port Authority Serving Alabama Alabama Section of the American Water Resources...
Alabama State Port AuthorityServing Alabama
Alabama Sectionof the
American Water Resources Association
Alabama Water Resources ConferenceSeptember 4, 2013
Alabama’s SeaportOne of the Nation’s Largest In Total Trade
Alabama State Port Authority
Over $700+ Million Invested Since 2001
Record FY2012: $144+ Million in Revenues Handling More than 25
Million Tons of CargoGenerates 127,591 Jobs in
Alabama(direct, indirect, and related user
jobs)Generates $506+ million in direct
and indirect tax impact in AlabamaASPA Total Economic Value: $18.7
Billion to Alabama
Northern Region of AlabamaGREAT SOUTHERN IP MARSHALL DURBIN NUCOR PILGRIM’S ROCK TENNSOLUTIA TYSON FOODS VULCAN MATERIALSWAYNE FARMS WEYERHAEUSER
Central Region of AlabamaACIPCO ALABAMA POWER DRUMMONDHONDA KIA KRONOSPANMERCEDES WALTER ENERGY NUCORO’NEAL STEEL US PIPE
Southern Region of AlabamaAKER SOLUTIONS BERG / EUROPIPE DUPONTEVONIK GEORGIA PACIFIC HYUNDAIHYSCO INEOS MASLAND CARPETSMITSUBISHI OUTOKUMPU AMERICAS POSCOSSAB STANDARD FURNITURETHYSSENKRUPP
Serving Alabama IndustryListing Represents a Sampling of ASPA Customers by Region
ASPA Five Year Capital Program
Pier C North Rehabilitation $18MOngoing
Intermodal Rail (ICTF – Phase I) $36M 2013 Rail Bridge and Site Work
Pier D Steel Warehouse $36M 2013-2014 Container Terminal Phase II $68M 2014-2015 Garrows Bend Logistic Park $110M 2014-2016 New Shiploader/Rail Loop Track/Yard 5 $70M 2014-2016
@ McDuffie Coal Terminal Intermodal Rail (ICTF – Phase II) $44M 2015-2017
Truck/Vehicle Bridge Connector Automobile RO-RO Terminal $54M 2015-2018 Middle Bay Port Pier/Yard $21M 2015-2018 Interchange Rail Yard Expansion $5M 2015-2018 Axis Inland Dock Expansion $5M 2015-2018
Total Cost$467M
Project Cost Schedule
Choctaw Point ICTF Phase ISite Prep, Rail Bridge, Facility – $36M
New Steel Warehouse - $36M
Automobile Terminal - $54MTheodore Ship Channel
Choctaw Point Logistics Park - $110M
McDuffie - $70MExport Enhancements
New Steel Warehouse Underway
Complements $18 Million in Recent and Ongoing Investments for Iron/Steel Shippers
Serves High Growth in Steel Products
ThyssenKruppSSABNucorSeverstalOutokumpu NA
Public/Private Venture with Alabama Steel Terminals, LLC
Choctaw Point Complex
APM Terminals Mobile
ICTF
Logistics Park
Future Ro/Ro Terminal
Greenfield Project Located on Theodore Ship Channel
Highway / Rail Served
Phased Construction
Phase I: Ship Berth with ~ 100 Acres
Phase II: ~ 250 Additional Acres
Market Study and Preliminary Engineering Underway
Alabama State Port Authority
THANK YOU!James K. LyonsDirector / CEO
251-441-7200 / [email protected]
Serving Alabama