Akobo Construction Field Report-draft.doc PDF

download Akobo Construction Field Report-draft.doc PDF

of 19

Transcript of Akobo Construction Field Report-draft.doc PDF

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    1/19

    2012

    Akobo field construction Report Page 1

    ProjectCompound Improvement

    For

    Akobo Field Office

    Undertaken by

    Contractor: GASCO Limited

    Compiled by: Ladu George Lambu

    Construction Supervisor, SCI AKOBO.

    Checked by: Stephane K,

    Construction Consultant, SCI JUBA

    Date: 6th

    May 2012

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    2/19

    2012

    Akobo field construction Report Page 2

    SCOPE OF WORKS

    The Contractor was awarded the contract, number PB/135/11/UN on the first dayof February2012 to construct an office block, two separate latrines each with four

    stances and the Chain link fence, to be completed within 90 calendar days upon

    the date of the contract signature.

    IMPLEMENTATION

    From 8th

    march 2012 the contractor arrived and took over the site. From the 9th

    Between 10

    of March the SCI logistics manager was requested about the local material

    sources, whereby he had to assist in the local mobilization of sand and aggregatebut he was busy and could not make it for that day.

    thand 16

    th

    From 17

    of March (a duration of 6 days), there was no major activity

    going on for the reason being that land Boundaries for SCI compound had not yet

    been decided between the SCI and the local authority and the local materials had

    not yet been fully mobilized.

    th

    Foundation works had to go on for three consecutive days till 20

    of March, the foundation works started by setting out and excavation as

    per the drawings within the defined boundaries as it had been agreed by the local

    authorities and SCI management.

    th

    The foundation works proceeded immediately after the bulk materials had been

    secured and delivered on site.

    of March when

    it was stopped after a decision taken by the contractor through the foreman to

    switch to the mobilization of materials which had to do with the collection of sand

    from River Meer area and local aggregates from the same area.

    From the foreman, Tony, we were able to get information that all the rest of

    materials apart from sand and local aggregates, were to come from Juba

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    3/19

    2012

    Akobo field construction Report Page 3

    including; marrum / gravel , harder aggregates and the rest of the material to

    complete the works . This was to take only 3 days for all the materials to be

    delivered.

    We found out that all the walling was done by use of cement/sand blocks made in

    situ on site. Some of the blocks indicated that they were very weak and

    crumbling. Well, the foreman had to explain as to why as such was happening for

    the first batch of blocks before they were even used and he said that it was the

    first trial test that was done by a 1:4 ratio (cement bag: wheelbarrow of sand)

    instead of 1:3 mix ratio that is commonly used.

    On the same note, the wall thickness done on site for the foundation walls (plinth

    walls) for all the construction is 150mm compared to that in the drawing which is

    specified as 400mm for the Office block as per the drawing and 200mm thickness

    for the toilet walls.

    The foreman had defended himself that it was all about the mould that was

    delivered on site that gave him no option. The mould could make block sizes of

    150x200x400mm compared to the expected 200x200x400mm solid blocks.

    Basically the walls were built on edge instead of building on bed to achieve the

    200mm desired thickness.

    There was enough evidence that curing was not done effectively otherwise it

    could have been the ratio that was poor on top of the clay impurities in the sand

    that led to the poor quality of the first lot of the blocks that were made.

    THE PROJECT WAS DELAYED

    We looked at the time frame and got worried about the time left compared to the

    works left to be done. The contract was signed on the 1st

    of February 2012 and

    the project duration is for only 90 days. This means that the contractor has only

    the month of May to cover everything to turn key and handover.

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    4/19

    2012

    Akobo field construction Report Page 4

    When we tried to track backwards, it was found out that work started onthe 8

    th

    The project commencement was earmarked when a team of 5 Masons(skilled laborers) and 6(unskilled laborers) Helpers and their foreman

    arrived in Akobo.

    of May 2012, which was one month and a week late ever since the

    project was signed and we could not get any reason as to why this

    happened that way.

    On the other hand, the foreman explained that they had to wait foranother 6 days before the new SCI boundaries had to be negotiated

    between the SCI admin and the local authorities.

    That, rain had interrupted twice ever since the project started. This was inthe mid march when rain started at around 11:00 am and work came to a

    standstill until the next day. The other occasion was in the first week of

    April when it started raining at around 2:30pm and work couldnt proceed

    until the next day.

    The last delay was from the time when cement got finished and the workshad to come to a stand still waiting for the materials from Kampala. Our

    estimation was for about a week when these materials had to reach Juba

    and three days for the materials to reach Akobo from Juba. Fortunately,

    the consignment was sent on Wednesday 1st

    of May from juba and it

    reached on the 4th

    day of May 2012 to Akobo, the day after our arrival in

    Akobo.

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    5/19

    2012

    Akobo field construction Report Page 5

    TECHNICAL FINDINGS

    HOW IT WAS DONE ON SITE FROM THE CONTRACT DOCUMENT

    OFFICE BLOCK:

    The plinth wall thickness is150mm,

    The plinth wall thickness is400mm,

    The Stud columns are 150mmx200mm,

    The Stud columns are 400mmx400mm,

    The RCC ground beam is150mmx200mm,

    The RCC ground beam is300mmx300mm,

    The marrum / Gravel layerthickness is 65mm,

    The murrum / Gravel layerthicknesss is not indicated.

    The DPM Ga 1000 PVC membranewas not provided,

    The DPM Ga 1000 PVCmembrane was not

    documented,

    The BRC reinforcement Bars to theslab are R8 tied @ 370mm spacing,

    The BRC reinforcement Bars areindicated as Y10 to be tied @

    300mm spacing, The stirrups used are R6@300mm

    spacing

    The stirrups specified areR8@200mm spacing.

    FENCE

    The spacing of the angle line pits is3000mm c/c @ the depth of

    600mm with diameter of 250mmon average.

    121 pieces of 50x50x6mm AngleDelivered on site

    The spacing of the angle line pitswas not indicated and the depth

    of 400mm/ 500mm with a topcross section area of 300X300mm

    was specified in the BOQ.

    Required is 174 pieces of50x50x6mm Angle as per the

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    6/19

    2012

    Akobo field construction Report Page 6

    BOQ to cater for struts and

    Strainers for the fence

    VIP LATRINE, 2No @ 4-stance

    The deepest end of the pitexcavated is 4000mm from the

    ground level.

    The depth of the pit could not beread from the document i.e the

    section detailed drawing for the

    pit was missing from the

    document.

    The top section of the built pit is1500x4700mm internally and

    1600mm depth from the ground

    level. And the bottom section of

    just mere excavated pit separated

    by a 65mm thick slab is

    790mmx4000mm and 2600mm

    deep.

    Ditto but the drawing planspecifies 900x4000mm top areaof the pit which differs from the

    1300x2100x5000mm as per the

    BOQ ,

    The total excavated volume wascomputed to be 20m

    The total volume to beexcavated was 28m

    3

    3per 4stance

    pit as per the BOQ

    The slab thickness to one of thetoilets near the office block was

    made to be 65mm thick with Y12

    rebar @ 300mm spacing and

    covered by the welded wire mesh

    on top.

    The slab was specified to be100mm thickness for all the

    toilets as per the BOQ.

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    7/19

    2012

    Akobo field construction Report Page 7

    MATERIALS DELIVERED TO THE SITE

    The last batch of the materials for the completion of the work arrived yesterday4

    thMay 5, 2012 at around 3:00 pm, it took 3 days to reach AKOBO from Juba.

    These included:-

    Item Details Quantity Unit Remarks

    1 Portland Cement, Rhino

    Brand

    250 Bags Non was damaged

    2 Y12, Reinforcement bars 38 No

    3 Iron sheets, Ga 28 pre-

    painted maroon in color

    145 Pcs

    4 Welded Wire

    mesh,120x240mm

    3 Pcs

    5 Wooded Door frames 8 Pcs

    6 Softboards,122x244cm,10mm

    thick

    65 Pcs

    7 Sadolin paints, Emulsion,

    under coat

    Jkans

    8 Sadolin paints, Emulsion,

    Final coat , cream

    Jkans

    9 Sadolin paints, Gloss

    paint

    Jkans

    10 Sadolin paints weather 4 tins of Tin

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    8/19

    2012

    Akobo field construction Report Page 8

    guard 20Ltr @

    11 Metallic doors for VIPLatrines, 80cmx210cm

    8 pcs

    12 Flash Timber doors 4 pcs

    13 Barbed wires,25kg Roll 3 Rolls

    14 Main Gate

    Metallic,4000x2100

    1 No The small pedestrian gate

    was not provided

    15 Binding wire 10 Kg

    16 Putty for glasses 2 Tins

    17 50x50x6mm Angle bars 121 Pcs

    17 Wood preservative 3 Jkans

    18 Burnt clay Vent

    bricks,220x112x75mm,Z

    design

    20 Pcs

    19 Hand crashed Aggregate 10 Ton

    20 Chain link 20 Rolls

    21 Tension wire for the chain

    link

    3 Rolls

    22 Ridge caps 25 Pcs

    23 Valleys @ 2m long 5 pcs

    24 2x6 common timbers 45 pcs

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    9/19

    2012

    Akobo field construction Report Page 9

    25 2x4 common timbers 315 pcs

    26 2x3 common timbers 90 pcs

    27 1x9 Fascia boards 32 pcs One was damaged during

    delivery

    28 Metallic doors for the

    latrine 750x2100mm sizes

    8 pcs

    29 1200x2200mm Double

    door

    1 pcs

    30 Casement Windows

    ,1mx1.2m

    22 No 9 windows were damaged

    and need welding ,panel

    beating repairs & painting

    31 Assorted Wire Nails

    6 25 Kgs

    5 6 Kgs

    4 7 Kgs

    3 35 Kgs

    2 5 Kgs

    Roofing Nails 20 Kgs

    Rubber washers Are missing, not brought

    Hoop Iron 5 Rolls

    DPC 5 Rolls

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    10/19

    2012

    Akobo field construction Report Page 10

    Recommendations

    Latrines:

    We would recommend that the intended detailed section as part of the drawing

    to be delivered for comparison or, to give us the precedence and guidelines in

    controlling the already existing part. This would help us to make quick adjustment

    as soon as possible. For example its quick not clear about the specific guide

    concerning the pit depth and its top area. For the BOQ, it specifies1300x2100x5000mm and the drawing indicates 900x4000mm. The contractor

    decided to excavate 4000mm as the pit depth from the ground level but in steps

    as indicated in the table of observations above. Please find the attached sketches

    of the as built sections of the toilets.

    Office Block:

    The recommended BRC from the drawing was y10 bars @300mm spacing c/c

    fixed with binding wire contrary to what was done by the contractor where R8

    bars spaced @370mm c/c was used. This is the point dragging us to another level

    until we get a go ahead from the construction manager; the condition has already

    been raised to his attention.

    We had taken a quick decision of improvising by just reducing the spacing through

    addition of more bars but the foreman had to confirm from his boss first.

    And concerning the stirrups for the beams and columns, we were suggesting that

    the use of R6 bars instead of the specified R8 would call for a reduction in their

    spacing from the original 300mm to 150-200mm if only approved by the designer.

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    11/19

    2012

    Akobo field construction Report Page 11

    On the other hand, for the wall, we had suggested to use the hoop iron

    reinforcement @ every two courses to counter cracking.

    DPM

    The DPM, Damp proof Membrane was ignored by the contractor simply because

    it was not part of the drawing and in the BOQ. We thought that the DPM is the

    protective layer of the slab and the reinforcement against the raising moisture.

    On the same note, it was not procured. If we could ask for precedence from the

    designer, then we are safe.

    FENCE

    We would recommend that the fence needs more reinforcement in any way to

    provide sufficient support to it laterally. This could be archived by improvising

    more angle line bars for struts and the required strainers and terminal posts or

    additional Timber poles @ not < 10m with deeper excavation depth.

    WATER

    More water will be needed for future use especially for concrete works andcuring. Curing is mandatory and requires relatively more water. The only nearest

    water source point for clean water is the compound bore hole and it this calls for

    a maximum storage and water reservation from the contractor.

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    12/19

    2012

    Akobo field construction Report Page 12

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    13/19

    2012

    Akobo field construction Report Page 13

    akobo 1: This the Arial view of one of the toilets.

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    14/19

    2012

    Akobo field construction Report Page 14

    akobo 2: This side show how the soils are terrible, even up to the 2m depth, foundation cannot be guaranteed.

    So what the contractor did was to excavate below to a depth of 1500mm for the wall seated on a slab as seen in

    the photo, below this is a simple slab of 65mm made of 1:2:4 plain concrete according to the F/man.

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    15/19

    2012

    Akobo field construction Report Page 15

    akobo 3: The slab thickness is 65mm, reinforced as per the F/man. We thought maybe the strength is currently

    based on the formwork which is still below it.

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    16/19

    2012

    Akobo field construction Report Page 16

    akobo 4: This is the layout of the foundation and the interest was in the spacing of the Rebars, the raise of the

    plinth wall from the ground floor level.

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    17/19

    2012

    Akobo field construction Report Page 17

    akobo 5: These are some of the materials which were brought in the last consignment, of course some were

    damaged during transit especially the paint, windows and angle bars,

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    18/19

    2012

    Akobo field construction Report Page 18

    akobo 6: (Left) are the hand crashed aggregate fetched all the way from Juba. (Right) are the stones collected

    from the river banks.

  • 7/31/2019 Akobo Construction Field Report-draft.doc PDF

    19/19

    2012

    Akobo field construction Report Page 19

    akobo 7: This is one of the blocks that were molded on site. It shows that sand is impure with clay particles and

    rubbish. The quality could partially be improved by sieving sand before use.