AIAContractDocumentRelationshipDiagrams
-
Upload
mrgoldsmith23 -
Category
Documents
-
view
217 -
download
0
Transcript of AIAContractDocumentRelationshipDiagrams
-
8/3/2019 AIAContractDocumentRelationshipDiagrams
1/8
1
AIA Contract Documents
Contract Relationship DiagramsMay 2009
-
8/3/2019 AIAContractDocumentRelationshipDiagrams
2/8
2
Conventional (A201) Design-Bid-Build
For use when the owners project is divided into separate contracts fordesign (architect) and construction (contractor)
Suitable for conventional project delivery (design-bid-build)
Owner retains Architect
Architect and consultants prepare drawings and specifications
Architect assists Owner in obtaining bids/proposals and then Owner awardscontract(s) for construction
Contractor(s) and Surety(ies) obligate to owner for bid, performance andpayment bonds
Contractor and Subcontractors build the work
Key Attributes:
Conventional (A201) Design-Bid-BuildContract Relationship Diagram:
ConsultantConsultant
Owner
Sub-contractor
Sub-contractor
Contractor
Surety
B101Architect
B103
B104
C401
A101
A310A312
A102
A103
A107
Contracts used
A201 A201
A401A201
-
8/3/2019 AIAContractDocumentRelationshipDiagrams
3/8
3
Construction Manager as Adviser (CMa)
Key Attributes:
Construction Manager as Adviser (2009-CMa)
Contract Relationship Diagram:
Owner retains an Architect and a Construction Manager who acts as anindependent adviser to the owner
Prime contractor(s) responsible for construction, labor and materials
Construction Manager gives owner construction management advice throughdesign and construction phases. Increases expertise in managing a projectfrom start to finish
B132Architect
ConsultantConsultant
OwnerConst. Mgr.
Adviser (CMa)
ContractorContractor
C132
C401
A132 G732A232 G736
G737
Sub-contractor
Sub-contractor
A401
Contracts used
Multiple prime contractors
-
8/3/2019 AIAContractDocumentRelationshipDiagrams
4/8
4
Construction Manager as Constructor (CMc)
Key Attributes:
Construction Manager as Constructor (2009-CMc)Contract Relationship Diagram:
ConsultantConsultant
Const. Mgr.Constructor
(CMc)
Sub-contractor
Sub-contractor
Architect OwnerB103
C401 A401
A133
A134
Contracts used
Single party (Construction Manager) provides construction managementservices in pre-construction phase AND then completes construction(constructor)
Gives Construction Manager (constructor) responsibility and control overconstruction work via direct contracts with sub-contractors
Construction phase services paid on the basis of cost of work plus a fee eitherwith (A133) or without (A134) a Guaranteed Maximum Price
-
8/3/2019 AIAContractDocumentRelationshipDiagrams
5/8
5
Design-Build
Key Attributes:
Design-BuildContract Relationship Diagram:
Owner enters into a contract with a single entity Design-Builder
Design-Builder is then obligated to both design and construct the project
Design-Builder then enters into contracts with architect and constructioncontractor(s) if necessary
Design-Builder may be:
A Developer or Single Purpose Entity (design and construction in one shop)
An Architect-led organization
A Contractor-led organization (most often the case)
Owner
Design-BuilderArchitect
Consultant Consultant
Contractor
Sub-contractor
Sub-contractor
C441A441
B143
A141
A142
B142Consultant
Contracts used
-
8/3/2019 AIAContractDocumentRelationshipDiagrams
6/8
-
8/3/2019 AIAContractDocumentRelationshipDiagrams
7/8
7
Integrated Project Delivery:
Transitional Documents
Key Attributes:
Integrated Project Delivery:Transitional DocumentsContract Relationship Diagram:
Integrated Project Delivery is an emerging process and these TransitionalAgreements are a comfortable first step into IPD
A collaborative project delivery approach that utilizes the talents and insightsof all project participants through all phases of design and construction.
Structured similar to existing construction manager agreements.
B195Owner
A195
Architect
ConsultantConsultant
C401 A401
Contractor
Sub-ContractorSub-Contractor
A295
Contracts used
A295 A295
-
8/3/2019 AIAContractDocumentRelationshipDiagrams
8/8
8
Integrated Project Delivery:
Single Purpose Entity
Key Attributes:
Integrated Project Delivery:Single Purpose Entity Documents
Contract Relationship Diagram:
These Agreements more fully integrate the project parties into IPD
Creates a limited liability company for the purpose of planning, designing andconstructing the project.
The Single Purpose Entity (SPE) allows for complete sharing of risk andreward in a fully integrated collaborative process.
Contracts used
Owner
Architect
ConsultantConsultant
Construction
Manager
TradeContractor
TradeContractor
C197C197
C196
C198* C199*
Owner/Architect/CM/Other Members
C195
*Available in late 2009.