Agenda

• Introductions• Project Overview• What is a Turnaround?• Turnaround Solution Concepts:

– Schedule vs. Cost Management– Earned vs. Burned Hours (Tracking)– Field Change Orders– Turnaround Warehousing Practices

• Lessons Learned• Can the Turnaround Solution Help Me?

Page 3: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Placid Refining Co., LLC

• Independent & Privately Owned • Refinery located in Port Allen, Louisiana

– Produces: Unleaded Gasoline, Diesel Fuel , Commercial Jet Fuel, Military Jet Fuel, Heavy Fuel Oil, & Liquefied Petroleum Gas

– Processes 56,000 BPD of crude oil (over 98% of current capacity)– Is in a constant cycle of improvement and is currently being expanded to

increase the capacity of the refinery to 80,000 BPD• Awards:

– Principal Financial Group’s 10 Best Companies in US– OSHA Voluntary Protection Programs (VPP) "Star“ Level– Multiple Distinguished Safety Awards from the National Petroleum

Refiner's Association– Past winner of Independent Supplier of the Year Award presented by

the Petroleum Marketers Association of America

Page 4: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

EDI

• Florida Corporation Based Out of St. Petersburg• Founded in 1999• Specialists in:

– Maintenance Process and Technology Consulting– EAM Implementations– Asset/Facility Walkdowns and Data Collection– IBM-Certified Training Center

• Designers of Custom Maximo Add-Ons:– Turnaround Management– EDI SuiteReq

Page 5: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

What is a Turnaround?

• Shutdown of an entire plant or section of a plant for the purpose of executing:– Inspections– Preventive Maintenance– Deferred Corrective Maintenance– Capital Projects

• Goal: Achieve as much work as possible in tight time window to minimize impact to lost production.

Page 6: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Turnaround Challenges

• Managing a large number of outside contractors and temporary labor.

• Making effective use of Rental equipment.• Managing new, unplanned work that

arises from inspections during the Turnaround.

• Managing the tremendous amount of materials that are needed in a short amount of time.

Page 7: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Turnaround Phases

• Pre-Execution:– Physically preparing work-site and equipment.– Planning work activities.– Defining the schedule.– Procuring Parts, Labor & Equipment

• Execution:– Physically executing the work.– Reporting progress and actuals.– Creating/planning follow up work.– Managing Schedule and Cost.

• Post-Execution:– Physically disassembling work-site and activating equipment.– Actuals data reconciliation.– Invoice payments.– Material reconciliation.

Page 8: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Schedule vs. Cost Management

• Two major management concerns during a Turnaround:– Schedule– Cost Allocation/Tracking

• Managers must be able to easily manage a single schedule of all activities, but still track the separate cost roll-ups of individual funding sources.

Page 9: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Schedule vs. Cost Management

• Solution Features:– Enhanced Cost Management Application to

Included GL-Account Functionality.• Work Order inherits GL from Capital Project

associated• If no Capital Project assigned, GL comes from

Location or is set manually.– New App (Turnaround Tracking) Created for

Viewing WO Hierarchy to 4 Levels on 1 Screen.

Page 10: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Schedule vs. Cost Management

Page 11: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Earned vs. Burned Hrs. Tracking

• The most critical metric for day to day management of a Turnaround is Earned Value vs. Burned Hours.– Earned Value: Percent of Work Completed x

the Budgeted Cost of that Work. (WO Plans)– Burned Hours: Actual Cost to Complete the

Work. (WO Actuals)• Required for management to quickly see

where schedule slips or scope creep is jeopardizing budget or timeline.

Page 12: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Earned vs. Burned Hrs. Tracking

• Solution Features:– Percent Complete attribute was added to

Work Order tasks to be updated as actuals are reported.

– Reports were created to utilize percent complete, along with planned costs, for calculating Earned Value and comparing with Actual Costs.

Page 13: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Earned vs. Burned Hrs. Tracking

Page 14: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Field Change Orders

• One of the largest risks in Turnaround management is the impact of unplanned work that is discovered during a Turnaround.

• These “Field Change Orders” must be integrated into the project plan, but still identifiable separately so their impact on schedule and budget can be monitored.

• The cost/time associated with these WOs must supplement the Earned vs. Burned analysis.

Page 15: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Field Change Orders

• Solution Features:– Checkbox added to Work Orders for marking

as “Field Change Order”.– All other aspects of these Work Orders are

handled identical to other TAR work.– Reports created that allow the user to roll-up

Field Change Order costs and analyze them along with Earned vs. Burned metrics.

Page 16: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Field Change Orders

Page 17: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Turnaround Warehousing

• A Turnaround puts incredible strain on both the Physical Warehouse and Warehouse Management.

• An organization must have the ability to track the incredible in-flux of parts in a short amount of time without jeopardizing steady state operations.

• At end of TA, all inventories for Turnaround should be “0” or easy to identify and integrate back into central stores.

Page 18: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Turnaround Warehousing

• Solution Features:– Created separate virtual warehouse specifically for

Turnarounds.• Inventory procured for TA isolated from steady-state

inventory.• All standard Inventory processes still apply to these parts.• Bins for each temporary storeroom/yard.• Reorder points set to ‘-1’

– Created Pick Ticket application for creating storeroom reservation requests (regardless of WO status.)

Page 19: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Turnaround Warehousing

Page 20: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Summary of Solution Benefits

• Ability to Manage Cost and Schedule Concurrently.

• Ability to Track Earned vs. Burned Hours• Ability to Track Field Change Orders and

Their Impact on the Turnaround• Ability to Effectively Manage Turnaround

Inventories

Page 21: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Lessons Learned During Implementation

• Data Dependencies!– Tremendous data collection and organization effort– All metrics based off structured data which needs to

be kept up-to-date in real time

• Training!– Elegant solutions are only as good as the people

using them– Early identification and involvement of all affected

parties during implementation

Page 22: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Could the Turnaround Solution Work For You?

• Do You Manage Large Shutdowns or Overhauls Without an Effective Management/Tracking System?

• Do You Have Difficulty Managing Complex Projects With Dependent Tasks and Multiple Funding Sources?

• Do You Have Peaks in Your Workload and/or Inventories During Predictable Time-Periods?

• If Yes, you might benefit from the Turnaround Solution.

Page 23: Agenda - IBM€¦ · Turnarounds. • Inventory procured for TA isolated from steady-state inventory. • All standard Inventory processes still apply to these parts. • Bins for

Questions?