Agenda for the 138 - wrpc.gov.in · 400 kV Amreli-Hadala, 400 kV Amreli-Chorania, 400 kV...
Transcript of Agenda for the 138 - wrpc.gov.in · 400 kV Amreli-Hadala, 400 kV Amreli-Chorania, 400 kV...
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
1
Agenda for the 138th
Protection Committee Meeting (PCM) of WRPC
to be held on 17.10.2019 at WRPC Mumbai.
ITEM NO.1: Confirmation of Minutes of the 137th PCM The 137th meeting of protection sub-committee was held on 17th July 2019 at
WRPC Mumbai. The MoM was circulated vide letter WRPC/Protection/
PCM/Minutes/2019/9463 dated 31.07.2019.
No comments have been received on the MoM.
Committee may like to confirm the minutes of 137th Protection sub-
Committee meeting.
ITEM 2:- Major Occurrences/grid disturbances:
2A. Occurrences in Gujarat system:
2A.1. Grid Incidence at 400 kV Amreli-Hadala line on 16th July 2019.
Event Category: GI-2 Event Summary as per the WRLDC report:
On 16.07.2019 at 11.14 hrs there was a grid incidence at on 400 kV Amreli-Hadala line. R-B phase fault occurred on 400 kV Amreli-Hadala line and
the fault was not cleared by Amreli end CB, which led to LBB protection operation and tripping of all the elements connected to 400 kV Amreli Bus 2. 400 kV Amreli-Hadala, 400 kV Amreli-Chorania, 400 kV Amreli-Jetpur 2,
400/220 kV 315 MVA Amreli ICTs 1&4, 400 kV Kasor 1 LR charged as BR at Amreli and 50 MVAR Amreli Bus reactor tripped.
Details of Occurrence as per GETCO report:
At the time of occurrence, the bus position of the feeders/X’mers were as
under and all the 400KV Bays were running along with 400KV Bus coupler as
follows (Bus bar protection type: Numerical ALSTOM- MiCOM P741).
400KV BUS
BUS-A BUS-B
1. AMRELI-JETPUR LINE-1
2. 400/220KV, 315MVA ICT-2
3. 400/220KV, 500MVA ICT-3
4. 400KV 125MVAr Bus reactor
1.400KV AMRELI-HADALA
2. 400KV AMRELI- JETPUR LINE-2
3. 400/220KV, 315MVA ICT-1
4. 400/220KV, 315MVA ICT-4
5. 400KV 50MVAr BUS reactor
6. 400KV 50MVAr Kasor-1 reactor
7. 400KV AMRELI- CHORANIA
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
2
Sequence of Occurrence as per GETCO report
At 11:14:16:153 hrs. 400kV Amreli Hadala line fault occurred (Distance
protection R & B phase with carrier aided trip), but fault was not cleared on the
instant. After approx. 209 msec. i.e at 11:14:16:362 hrs, Int.LBB of 21-Main1
distance relay P444 operated. Which caused the 50BF-Bus-zone2 trip extend to
all adjacent CBKRs of BUS-2 along with 400kV Bus-coupler. 400kV Bus-bar
protection trip in zone 2 occurred due to LBB protection Optd., on 400kV
Amreli- Hadala line. Simultaneous to above Ext.LBB-96 scheme also optd.
The 50BF (LBB-prot.) signal was initiated only due to Main protection (distance)
of Hadala line failed to clear the fault as mentioned to above. At the time of fault
upgraded new data-base version loading in server was under process. During
such process of ALSTOMSDCADA Configuration all the bays’ control for NIT-
logic, A/R-status, Carrier selection (permissive/ direct-trip) goes on
disabled/default. Here in this case the prot. trip from distance relay Along with
“Normal” mode also became disable according to the relay configuration. The
400kv Amreli-Hadala line distance relay 21M1 (with correct phase & zone prot.)
operated. But master trip 86 didn’t operate which cause distance function base
internal LBB was operated after approx. 209 msec.(tBF2). Consequently 50 CB-
Fail1 prot. (tBF2) released as 50BF-bus zone2 trip command to whole 400kV
BUS-ZONE2 connected elements.
SLD/Event report is enclosed as Annexure 2A.1.
GETCO may inform OEM (ALSTOM) report available, if any, on the above
issue
Committee may like to discuss.
2A.2. Grid Incidence at 220kV KLTPS/Akrimota S/s on 21st July 2019.
Event Category: GD-1
Event Summary as per the WRLDC report:
On 21.07.2019 at 15.50 hrs there was a grid incidence at 220kV Akrimota S/S. At 220kV Akrimota, Bus 2 and Akrimota-Nakhtrana 2 were under shutdown. 220kV Bus 1 and Akrimota - Nakhtrana ckt 1 tripped due to heavy
chattering in PI of Bus. Since, both the buses tripped, ALTPS units 1 & 2 and 220kV ALTPS-KLTPS ckt 1&2 tripped and ALTPS station became dead. At the same time 220kV KLTPS - Kukma ckt 1&2 tripped on reflection fault. As 220kV
KLTPS-Nakhtrana ckt 1&2 were under outage due to tower collapse, units 1&4 at KLTPS tripped on loss of evacuation. 220 kV Kukma-Panandhro 1, 220 kV
Kukma-Panandhro 2, 220 kV Akrimota bus 1, 220 kV Akrimota-Nakharatna 1 and KLTPS Unit 1&4 tripped.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
3
Details of Occurrence (as per the report given by GETCO):
220KV Panandhro - Nakhatrana line - I & II under L/C by GETCO for
tower replacement work from 12.06.2019. 220KV Panandhro -Kukma- I & II
tripped at 15:50 Hrs. 220KV Panandhro-Akrimota line-I & II was hand trip from
KLTPS end On 21.07.2019, the status of both the bus at KLTPS (Pannandhro)
was as under:
BUS-I BUS-II
(a) GT#1 (a) GT#4
(b) ST#1 (b) ST #2
(c) Akari-II (c) Kukma-II
(d) ICT-1(on load ) (d) Akari-I
(e) Kukma-I (e) ICT-1(Soft Charged )
Relay and Indications:
Sr Name Of Feeder Relays –KLTPS end Relays Remote end
1 220 KV Panandhro -
Kukma- I
Distance Protection Zone-1,
(B-N), 40.67 Km,
IA – 89.81 A, IB – 1754 A, IC –
386 A,
Facia – Dist. Protection Optd.
Distance Protection Zone-
1, (B-N), 93.69 Km, IB –
1290 A,
Facia – Dist. Protection
Optd.
2 220 KV Panandhro -
Kukma- II
Distance Protection Zone-1,
(B-N), 45.8 Km,
IA – 88.59 A, IB – 1773 A, IC –
386.8 A,
Facia – Dist. Protection Optd.
Distance Protection Zone-
1, (B-N), 94.69 Km,
IB – 1310 A,
Facia – Dist. Protection
Optd.
3 220 KV Panandhro –
Akrimota – I
KLTPS end breaker not
tripped-hand trip
Facia – Under voltage and
under frequency
4 220 KV Panandhro –
Akrimota – II
KLTPS end breaker not
tripped-hand trip
Facia – Under voltage and
under frequency
4 70MW Unit#1 Relay:- Trip relay 86GA optd, under frequency trip relay
operated.
Facia:-415V USS Bus U/V alarm, V/Hz High alarm,
Channel in balance (Excitation), Under frequency protection
alarm, Under frequency protection trip, Metering PT fail
alarm, first rotor earth fault relay alarm 86GA Optd.
5 70MW Unit#2 Under shutdown
6 75MW Unit#3 Under shutdown
7 75MW Unit#4 Relay:-Group 1 GRP1-[Excitation CB + Turbine trip, VT fail
alarm, under frequency alarm and trip and over frequency
alarm. Group 2 GRP-3 [Excitation CB + turbine trip], under
frequency alarm and trip and over frequency alarm
Facia:-Gen trip relay optd.
GT Relay- over flux alarm(warning)
SLD/Event report is enclosed as Annexure 2A.2.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
4
2A.3. Grid Incidence at 400/220 kV Ukai S/s on 15th August 2019.
Event Category: GI-2
Event Summary as per the WRLDC report:
At 400/220 kV Ukai S/s, 400kV Ukai-Kosamba and Ukai-Navsari lines tripped
on over-voltage & 400/220kV ICT tripped on Overflux & differential protection
operation. Due to tripping of all the elements, 400kV Bus 1&2 at Ukai
substation de energized.
GETCO not uploaded the preliminary tripping report in the tripping portal.
Committee may like to discuss.
2A.4. Grid Incidence at 400/220 kV Ukai S/s on 16th August 2019.
Event Category: GI-2
Event Summary as per the WRLDC report:
At 400/220 kV Ukai S/s, 400kV Ukai-Kosamba tripped on over-voltage &
400/220kV ICT tripped on Over flux protection operation. 400kV Bus 1&2 at
Ukai substation de energized as 400kV Ukai -Navsari was already out on voltage
regulation.
As per GETCO report direct trip received from Ukai end and 86A and 86 B trip
operated.
Committee may like to discuss.
2A.5. Grid Incidence at 220 kV Panandhro S/s on 25th August 2019.
Event Category: GI-1
Event Summary as per the WRLDC report:
At 220 kV Panandhro, R-phase CT of 25MVAR BR caught fire and resulted in tripping of all the elements connected to 220 kV Panandhro Bus 2.
GETCO not uploaded the preliminary tripping report in the tripping portal.
Committee may like to discuss.
2B. Occurrences in Madhya Pradesh system:
Nil
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
5
2C. Occurrences in Maharashtra system
2C.1. Grid Incidence at 220 kV Kalwa S/s on 10th July 2019.
Event Category: GD-I
Event Summary as per the WRLDC report:
On 10.07.2019 at 09.04 hrs there was a grid incidence at 220 kV Kalwa S/S. 220 kV Padghe Bus 2 and 220 kV Padghe-Temghar 1&2 were under outage prior to the event. 220 kV Kalwa-Kalwa interconnecter 1&2 were in open
condition to reduce the fault level. 220 kV Apta-Taloja and 220 kV Kalwa-Apta tripped due to conductor snapping and resulted in overloading and tripping of 220 kV Kalwa-Colorchem and 220 kV Kalwa-AKP. 220 kV Kalwa 1,
colorchem,Themghar and Taloja got blackout due to the event. 220 kV Kalwa-Apta, 220 kV Kalwa-AKP, 220 kV Klawa-Colorchem and 220 kV Apta-Taloja
tripped. The Event Report (of WRLDC) is enclosed at Annexure 2C.1
Description of occurrence (As per MSETCL report):
On dated 10.07.19 at 05:33 hrs 220 kV Bus A outage was availed at Padghe
S/s as per approval from SLDC Kalwa. 220 kV Padghe –Temghar Line I & II were
under outage. The 220 kV Temghar S/s, 220 kV Colourchem S/s and 220 kV
Kalwa S/s were feed from 220 kV Kalwa II- Colourchem line, 220 kV Kalwa I –
Temghar, 220 kV Apta – Kalwa, 220 kV AKP - Kalwa & 220 kV Apta – Taloja –
Kalwa Line and these lines were acting as source lines. Inter-connector breaker
between 220 kV Kalwa I & II was kept off as per SLDC instruction for fault MVA
reduction.
At 08:58 hrs. Apta – Taloja line tripped on distance protection due to
conductor snapping at Tower No. 640 when carrying current @ 600 Amp. This
lead to increase in current on 220 kV Apta – Kalwa and 220 kV Kalwa –
Colourchem line. Loading of these lines reached @ 800 Amp., which is near to
the thermal limit of the conductor. At 09:04 hrs. 220 kV Kalwa –Apta line
tripped on distance protection due to conductor snapping at Tower No. 640 i.e.
same location. Apta source was been cut off which resulted in shifting the
complete load on 220 kV Kalwa – Colourchem Temghar – Kalwa link & AKP line
having distance source (Nasik). Due to this the 220 kV Kalwa – Colourchem line
current reached to 1300 Amp and got overloaded and tripped on back up over
current after approximately 4 sec. Due to this, the complete load of Colourchem,
Temghar, Kalwa & Taloja shifted to 220 kV Kalwa- AKP line. The 220 kV Kalwa -
AKP line's current reached to 1280 Amp and got overloaded and tripped on back
up over current approximately after 1.5 sec. This resulted in total failure of 220
kV sources. This caused shifting of total MSETCL load on TATA Netwok
(Through 100 kV TATA Lines viz 100 kV Kalyan, Salshette I & Salshette – II))
which caused disturbance in TATA network also.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
6
Initially system was normal catering the load of @610 MW at Colourchem,
Temghar, Taloja & Kalwa I S/s through 220 kV Kalwa II – Colourchem –
Temghar – Kalwa Link, Kalwa – AKP & Apta – Taloja – Kalwa D/C when 220 kV
Padghe Bus A outage availed with 220 kV Padghe – Temghar D/C kept off at
05:33 hrs. 220 kV Taloja – Apta Line tripped @ 08:58 hrs. The R-B ph fault
occurred @ Loc No. 640 due to conductor snapping when current is @ 600 Amp.
and line tripped on distance protection from both end. The complete load of 220
kV Taloja S/s were feed through 220 kV Kalwa S/s. Due to this, the 220 kV
Kalwa- Apta Line and 220 kV Kalwa – Colourchem line shared maximum load
above the thermal limit as being the strong source to the network. 220 kV
Kalwa-Apta Line tripped @ 09:04 hrs. The R-B ph fault occurred @ Loc No. 640
due to conductor snapping and the line tripped on distance protection from both
end. Now, the complete network were feed through 220 kV Kalwa-Colourchem –
Temghar – Kalwa I Link Line and 220 kV Kalwa – AKP Line. As being a strong
source, the 220 kV AKP Kalwa – Colourchem line got overloaded above thermal
limit i.e. 1300 A Approx. The contribution of 220 Kalwa – AKP line was very less
as being weak source. Due to the overloading of 220 kV Kalwa – Colourchem
line, the line tripped @09:04 hrs. from 220 kV Kalwa S/s end on over current
protection. Now, the only source available to the network is of 220 kV Kalwa –
AKP line which was also eventually got overloaded i.e. 1280 A approx. The 220
kV Kalwa – AKP Line tripped at 220 kV AKP S/s at 09:04 hrs end only due to
overloading. Now, the complete 220 kV source to the network lost. 100 kV
Kalwa- Kalyan line, 100 kV Kalwa – Kalyan-Salsette-1 & 2 Line (open at 100 kV
Salsette) were still in service which connected to generation at 100 kV Khopoli
S/s, 100 kV Bhivpuri S/s and 100 kV Bhira S/s (TATA NETWORK) & TPC –
MSETCL – AEML and 100 kV Khopoli Bhivpuri – 1 & 2 tripped on Zone -4 with 2
sec delay. Therefore, the 220 / 100 kV Kalwa I, 220 kV Colourchem, 220 kV
Temghar and 220 kV Taloja S/s suffered power failure.
Remedial Measures suggested & action taken in order to avoid recurrence.
1. Fours maintenance activities being old aged lines.
2. Thermo scanning to be done when loading is maximum.
3. Auto reclosing of Inter-connector under contingencies of overloading of
220kV Lines at Kalwa –I is kept ready and being taken into service on dtd.
12.07.2019.
4. Load trimming at Colourchem S/s is kept ready for contingency for Kalwa –
Colourchem line.
5. Kalwa – Mumbra – Pal – Taloja link to be kept on with load trimming
scheme for contingencies on 220 kV side at Kalwa, Taloja & Padghe to avoid
total failure of supply in coordination with MSLDC, Kalwa.
6. To avoid disturbance in either network of MSETCL & TATA network,
common contingencies to be devised in coordination with MSLDC Kalwa.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
7
Single Line Diagram:
MSETCL may give their views on (i) measures to control the overloadings
under such situations be explored and automatic load trimming schemes be
implemented. (ii) It may be explored whether the Bus Coupler can be
automatically put in service under such situations and then after
restoration of normalcy the B/B can be put out.
Committee may like to discuss.
2C.2. Grid Incidence at 220 kV Kalwa S/s on 19th July 2019.
Event Category: GD-I
Event Summary as per the WRLDC report:
On 19.07.2019 at 19.28 hrs there was a grid incidence at 220 kV Kalwa S/S. 220 kV Taloja-Apta and 220 kV Jambhul-Anandnagar were under outage
prior to the event. 220 kV ICTs at Pal S/s were hand tripped from 100 kV side to shift the load of 100 kV Dombivalli S/s to 100 kV Pal-Mumbra and 100 kV Pal-
Taloja. At 19:28 Hrs, 220 kV Kalwa-Taloja tripped due to the snapping of B phase conductor and no source was available at Taloja S/s. 100 kV Pal-Mumbra tripped on overload and led to the total failure of supply at 220kV Taloja, 100 kV
Dombivalli, Taloja, DFPCL, FGIL, BOC, Hindalco and Mumbra S/s. 220 kV Kalwa-Taloja and 100 kV Pal-Mumbra tripped.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
8
Description of occurrence(As per the MSETCL report):
At 200 kV Taloja S/s, 220 kV Taloja –Apta line was under outage and
subsequently, At 19:28 hrs 220 kV Kalwa –Taloja line tripped due to snapping of
B ph conductor – Anandnagar line was also under outage and at 220 kV Pal S/s
ICT –I & II was hand tripped from 100 kV side and total load 100 kV Dombivali
S/s was shifted to 100 kV Pal – Mumbra and 100 kV Pal – Taloja line. At 19:28
hrs 220 kV Kalwa –Taloja line tripped due to snapping of B ph conductor at Loc
No. 14-15 and no source available to substation Because of which 100 kV
Mumbra – Pal line tripped on overload. This lead to total failure supply to 100
kV Dombivali, 100 kV Taloja, 100 kV DFPCL, 100 kV FGIL, 100 kV BOC, 100 kV
Hindalco, 100 kV Mumbra substations.
At 200 kV Taloja S/s, 220 kV Taloja –Apta line was under outage. At 19:28
hrs, 220 kV Taloja -Kalwa line tripped due to B ph conductor snap and fall on B
ph conductor resulting in R-B to Earth fault. At 220 kV Jambhul S/s, 220 kV
Jambhul – Anandnagar line was under outage. At 220 kV Pal S/s 220/100 kV I
& II was hand tripped to divert 100 kV load on Taloja & Mumbra line. As 220
kV Taloja was in dark total 100 kV load shifted on 100 kV Mumbra – Pal line.
Due to which 100 kV Mumbra – Pal line tripped on over load at Mumba end. 220
kV Kalwa – Taloja line tripped from Kalwa end first in Zone – 2 and then tripped
from Taloja end in Zone – I to weak source available.
Single Line Diagram
The Event Report is enclosed at Annexure 2C.2.
MSLDC is requested to give the loading pattern at and around Kalwa S/s
network. Also load trimming schemes implemented/planned, if any, may be
submitted.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
9
2C.3. Grid Incidence at 400/220 kV Khargar S/s on 25th July 2019.
Event Category: GI-I
Event Summary as per the WRLDC report:
On 25.07.2019 at 03.48 hrs there was a grid incidence at 400/220 kV
Khargar S/S. At 400/220 kV Khargar S/s, 220 kV Bus 1 and all connected
elements tripped due to the B phase bus CVT blast on Bus bar protection
operation. The 220 kV Khargar Bus 1, 400/220 kV Khargar ICTs 1&3, 220 kV
Khargar-Nerul, 220 kV Khargar-Uran 1, 220 kV Khargar-Panvel, 220 kV
Khargar-Borivalli and 220/33 kV Khargar ICTs 1&3 tripped.
Description of occurrence (As per MSETCL report):
220 kV Bus 1 B phase PT failed at Khargar substation and resulted in
tripping of all the elements connected to 220 kV Bus 1 on Bus bar protection
operation. The fault current during the event was 45.7 kA and the fault
duration was 64 ms. There was a load loss of 35 MW due to the event.
Details of indication for occurrence on 220 Kv ‘A’ bus on Dt. 25.07.2019
Own Station: KHARGHAR Other Station:
Window indication Relay Indication Window
indication
Relay
Indication
1)220KV BUS COUPLER
**NR TYPE BUS BAR
PROTN. AND ABB
TRIP BUS OPERATED
N.A
N.A
2)220KV URAN-I
a) BUSBAR TRIP RELAY
OPERATED.
Nil NIL NIL
3)220KV TSS PANVEL
a) BUSBAR TRIP RELAY
OPERATED
NIL NIL NIL
4) 220KV BORIVALI-I
a) BUSBAR TRIP RELAY
OPERATED
Nil Nil Nil
5) 220KV NERUL
a) BUSBAR TRIP RELAY
OPERATED
Nil Nil Nil
6) 400/220/33KV 3X105
MVA ICT-I (HV/LV SIDE)
a) BUSBAR TRIP RELAY
OPERATED
b) OLTC Buchholtz Trip
OLTC Buchholtz Trip
30H
Nil Nil
7) 400/220/33KV 3X105
MVA ICT-III (HV/LV SIDE)
a) BUSBAR TRIP RELAY
OPERATED
Nil Nil Nil
8) 220/33KV 50MVA TF-I
(HV/LV SIDE)
a) BUSBAR TRIP RELAY
OPERATED
Nil Nil Nil
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
10
9) 220/33KV 50MVA TF-
III(HV/LV SIDE)
a) BUSBAR TRIP RELAY
OPERATED
Nil NIL Nil
400/220 kV Khargar ICT 3 was charged at 04:48 Hrs followed by the other
elements as given in the restoration table. 400/220 kV Khargar ICT 1 was
charged on 26-07-19 at 12:09 Hrs after complete testing. 220 kV Khargar-
Borivalli was charged on 26-07-19 at 00:02 Hrs after the replacement of rotary
insulator of Bus isolator.
Single Line Diagram of 220 KV side of Khargar
The Event Report is enclosed at Annexure 2C.3.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
11
2C.4. Grid Incidence at 220 kV Boisar S/s on 29th July 2019.
Event Category: GI-I
Event Summary as per the WRLDC report:
On 29.07.2019 at 17.48 hrs there was a grid incidence at 220 kV Boisar S/S.
Due to the snapping of earth wire of multi circuit tower, 220 kV Boisar-
Boisar(PG) T/C and 220 kV Boisar-Nallasopara tripped. 220 kV Boisar-TAPS
also tripped at the same time on Directional earth fault and 220 kV TAPS-
Borivali tripped later on over current protection operation. The 220 kV Boisar-
Boisar(PG) 1,2&3, 220 kV Boisar-Nallasopara, 220 kV Boisar-TAPS and 220 kV
TAPS-Borivalli tripped.
The Event Report of WRLDC is enclosed at Annexure 2C.4.
Description of occurrence (As per MSETCL report):
On date 29.07.2019, due to snapping of OPGW at Location no. 16-17A-17,
220 kV PGCIL Line 2 tripped from both end over Y ph-E over distance protection
and 220 kV PGCIL – Nalasopara line tripped over distance protection from both
end. Simultaneously 220 kV Boisar 2 – PGCIL line 1 tripped over distance
protection at PGCIL end only. At the same time, 220 kV PGCIL Line no 3 tripped
over Distance protection R ph –E in Zone 1 from both end due to R ph Jumper
broken at Location no. 18. As all three 220 kV PGCIL lines to Boisar 2 ss tripped,
220 kV Tarapur line tripped over current protection due to overloading from
Tarapur end only.
At Location no 17A (newly erected multi circuit tower where 220 kV Boisar 2
– PGCIL Line 1, 220 kV Nalasopara –PGCIL line located at upper cross arms and
220 kV PGCIL line no 3 at Bottom), the hanging (not fixed at peak) OPGW
snapped and might be came in the induction zone of Rph (bottom side) of the
220 kV Nalasopara –PGCIL line 1 causing tripping over Distance protection at
both end. (AR is not available at Both end). The snapped conductor then fell over
220 kV Boisar 2 – PGCIL Line 2 initially over Y ph and then R ph at Location no
16. From Boisar 2 end, the line auto reclosed over Y-E fault initially, but as the
fault was persisted AR lockout initiated to trip the line. At PGCIL end, AR is not
available so line tripped on 3 ph. Simultaneously, the same fault was also seen
by the distance relay of 220 kV Boisar 2 – PGCIL line no 1 in forward direction at
PGCIL end and line tripped at PGCIL end only. At same time, 220 kV PGCIL line
3 auto reclosed from Boisar 2 end over R-E fault, but after approx. 6s (as per
DR), as the R-E fault sensed in the reclaim time, AR Lockout initiated and line
tripped. At PGCIL end AR is not available, Line tripped over distance protection.
Rph jumper found broken at Location no 18. Due to above, as all three sources
to Boisar 2 from PGCIL ss, 220 kV Tarapur line tripped over Dir. over current
protection due to overloading at Tarapur end only. No LTS operation and also
Load affected was Nil, but restoration process required load restriction, hence
220 kV Ghodbunder and Versova Line hand tripped and local load shedding
(107.6MW) carried out.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
12
Single Line Diagram
Committee may like to discuss.
2C.5. Grid Incidence at 400/220 kV Padghe S/s on 31th July 2019.
Event Category: GI-2
Event Summary as per the WRLDC report:
On 23.06.2019 at 06.23 hrs there was a grid incidence at 400/220 kV
Padghe S/S. At 400/220 kV Padghe S/s, R phase CVT of 400 kV Bus 1 blasted
and resulted in tripping of all the elements connected to 400 kV Bus 1. The 400
kV Boisar-Padghe 1, 400 kV Tarapur-Padghe 2, 400 kV Nagothane-Padghe 1,
±500 kV HVDC Chandrapur-Padghe Pole 2, 400/220 kV 315 MVA ICT2,
400/220 kV 500 MVA ICT 3 and 400 kV Bableshwar-Padghe 1 tripped.
Description of occurrence (As per MSETCL report):
At 12:54 Hrs. Dated: 31.07.2019 400 kV Rph A bus CVT ABB Make burst &
caught fire. As the CVT was directly connected to the A bus, fault was seen by
Main Bus 1 Different Zone of 400 kV Bus bar Protection at Padghe Substation.
Hence Feeders and ICTs connected to Main bus A 400 kV HVDC-2, Tarapur-2,
Nagothane-1, Babhaleshwar-1, 315 MVA 400/220 kV ICT-2, 500 MVA 400/200
kV ICT 5 and Bus coupler tripped on operation of Main bus A differential zone of
400 kV Bus Bar protection. At the same time 400 kV Boisar line which was
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
13
connected to B Bus, tripped at both ends at Padghe on 87R reactor differential
protection and Boisar on DT received.
Conditions prior to Occurrence :
A-Bus Before tripping
1. 400 kV HVDC-2 0 MW (I)
2. 400 kV BBLR-I 415 MW (I) 3. 400 kV KALWA-I 0 MW (E) 4. 400 kV NAGOTHANE-I 62 MW (I) 5. 400 kV TARAPUR-2 256 MW (I) 6. 315 MVA ICT-2 240 MW (E) 7. 500 MVA ICT-5 344 MW €
B-Bus
1. 400 kV HVDC-I 0 MW (I)
2. 400 kV BBLR-2 420 MW (I)
3. 400 kV KALWA-2 555 MW (E)
4. 400 kV NAGOTHANE-2 182 MW (I)
5. 400 kV TARAPUR-I 261 MW (I)
6. 400 kV BOISAR(PGCIL) 168 MW (I)
7. 315 MVA ICT-3 250 MW (E)
8. 600 MVA ICT-4 460 MW (E)
Conditions after Occurrence
Feeders and ICTs connected to Main bus A 400 kV HVDC-2, Tarapur-2,
Nagothane-1, Babhaleshwar-I, 315 MVA 400/220 kV ICT-2, 500 MVA 400/200
kV ICT 5 and Bus coupler tripped on operation of Main bus A differential zone of
400 kV Bus Bar protection. 400 kV Boisar line which was connected to B Bus
tripped on 87 R reactor differential protection.
The sequence of tripping and restoration
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
14
Bus Configuration & load Prior to occurrence:
Sr.
No.
400 kV Main Bus – I ( A Bus) 400 kV Main Bus – I ( A Bus)
Name of bays (Feeder/
ICTs/ TFs)
Load (MW)
04.00 hrs
Name of bays (Feeder/
ICTs/ TFs)
Load (MW)
04.00 hrs
1. 400 kV HVDC-2 0 MW (I) 400 kV HVDC-I 0 MW (I)
2. 400 kV BBLR-I 415 MW (I) 400 kV BBLR-2 420 MW (I)
3. 400 kV KALWA-I 0 MW (E) 400 kV KALWA-2 555 MW (E)
4. 400 kV NAGOTHANE-I 62 MW (I) 400 kV NAGOTHANE-2 182 MW (I)
5. 400 kV TARAPUR-2 256 MW (I) 400 kV TARAPUR-I 261 MW (I)
6. 315 MVA ICT-2 240 MW (E) 400 kV BOISAR(PGCIL) 168 MW (I)
7. 500 MVA ICT-5 344 MW (E) 315 MVA ICT-3 250 MW (E)
8. 600 MVA ICT-4 460 MW (E)
Relay / Flag Indications
Sr.
No.
Name of Feeder / bays Local End Indication Remote End Indication
WI RI WI RI
1. 1. 400 kV TARAPUR-2 NIL 96 Trip Relay DT Received DT Received
86 optd
2. 500 MVA 400/220 kV
ICT-5
NIL 96 Trip Relay NA NA
3. 400 kV Babhaleswar –I NIL 96 Trip Relay DT Received DT Received
4. 400 kV Nagothane-I NIL 96 Trip Relay DT Received DT Received
5. HVDC-2 NIL 96 Trip Relay NIL Converter CB
trip Scheme
6. 315 MVA 400 / 220 kV
ICT-2
NIL 96 Trip Relay NIL NIL
7. Bus Coupler Bus zone –I
optd,
96 Trip Relay NA NA
8. 400 kV Boisar Reactor Diff
Prot optd.
TCI /TC2
faulty, CB
PDR optd
87 R, Group
A Trip
DT Received DT Received
These were Old CVTs in section I of 400 kV Main bus A. Out of these, R and Y
phase CVTs were showing abnormal voltages during the bus outage availed for
bus conductor replacement. Hence new CVTs were erected & commissioned in
section 2 of A bus on dtd. 23.03.2019. After transfer of load from old CVTs to
new CVTs old CVTs were kept disconnected from secondary sides. As these CVTs
were connected directly to the main bus with the help of jumper, it was not
possible to isolate them from bus without bus outage. The outage for the same
was proposed on dtd. 31.05.2019 but was not approved by LD Kalwa & hence
could not be availed, thus CVT were in service. However on Date 31.07.2019 at
12:54 Hrs, 400 kV Rph A bus CVT WS Make burst & caught fire. As the CVT
was directly connected to the A bus, fault was seen by Main Bus I Differential
zone of 400 kV Bus bar Protection at Padghe Substation. Hence Feeders and
ICTs connected to Main bus A (400 kV HVDC-2, Tarapur-2, Nagothane-I,
Babhaleshwar-Im 315 MVA 400 / 220 kV ICT-2, 500 MVA 400 / 220 kV ICT 5)
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
15
and Bus coupler tripped on operation of Main bus A differential zone of 400 kV
Bus Bar protection.
At the same time 400 kV Boisar line which was connected to B Bus tripped at
both ends, at Padghe on 87 R reactor differential protection and at Boisar on DT
received. As per instruction from PGCIL, Line reactor kept isolated and line
charged through TBC due to Own CB problem at Padghe (Y pole wiring burnt).
The CB problem is under investigation in coordination with PGCIL team & will
be rectified in due course.
400/220 kV Padghe ICT 2 was charged at 14:59 Hrs followed by the other
elements as given in the restoration table. The Y phase CB wiring of 400 kV
Boisar 1 found burnt and taken into service through TBC after isolating line
reactor. The bus old CVTs were removed from the bus.
The Event Report is enclosed at Annexure 2C.5.
Committee may like to discuss.
2C.6. Grid Incidence at 400/220 kV Deepnagar station on 12th July 2019.
Event Category: GI-2
Event Summary as per the WRLDC report:
On 12.07.2019 at 10.19 hrs there was a grid incidence at 400/220 kV
Deepnagar station. At 400/220 kV Deepnagar station, LBB of ST 4 & GT 5
operated which resulted in tripping of 400 kV Deepnagar Bus 1. The 400/21.75
kV 600 MVA Deepnagar GT-5, 400/21.75 kV 600 MVA Deepnagar GT-4,
400/11/6.6 kV Deepnagar ST 4, 500MW Deepnagar Unit 4&5 and 400 kV
Deepnagar Bus1 tripped.
Description of occurrence (As per MSETCL report):
Bus Configuration & load prior to occurrence
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
16
LBB prot. of GT-5 & STN 4B optd from GENCO. Due to that Main & Tie CB of
GT-5 & STN 4B Tripped is in order. Due to this LBB prot. (Optd. From GENCO)
Bus 1 -50Z1X LBB optd. (at 400kV BUSBAR Panel) and CB connected to 400kV
Main BUS-1 tripped is in order.
Bus wise tripping-
Present and past diagnostic testing (CB Timing and DCRM etc.) results are in
order.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
17
The Event Report is enclosed at Annexure 2C.6.
After details analysis with tripping events and equipment testing results, it is
confirmed that the relay operation at 400kV MSETCL Deepnagar S/s is correct
and in order. Hence it was requested to check or verify the correct operation of
LBB relay of GT-5 & STN-4B at MSPGCL Deepnagar end .
Committee may like to discuss.
2C.7. Grid Incidence at 220 kV Uran S/s on 3rd August 2019.
Event Category: GI-1
Event Summary as per the WRLDC report:
At 220 kV Uran S/s, flashover on Main Bus 2 R Phase Tension Disc Insulator
String at 220 KV ONGC Bay resulted in tripping of all the elements connected to
220 kV Uran Bus 2 on Busbar protection operation.
Description of occurrence (As per MSETCL report):
On 03.08.2019, at 20:29 Hrs, at 220 kV Uran S/s, Due to flashover and
bursting of Main Bus-2 R Phase tension disc insulator string over 220 kV ONGC
bay, resulting in a correct operation of 220 kV Busbar protection relay and
selective tripping of bus coupler and feeders on bus zone-B.
Relay and Flag indications as follows:
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
18
Single Line Diagram of 220 kV Uran S/s:
The Event Report is enclosed at Annexure 2C.7.
Committee may like to discuss.
2C.8. Grid Incidence at 220 kV Uran S/s on 3rd August 2019.
Event Category: GI-1
Event Summary as per the WRLDC report:
At 220 kV Uran S/s, 220 kV Bus 1 and all the connected elements tripped due
to spurious LBB signal generated due to the faulty Binary input module of REB
670.
Description of occurrence (As per MSETCL report):
On dated 03.08.2019, at 13:41 Hrs, at 220 kV Uran S/s, Due to malicious LBB
Trip command received from 220 kV Station tf-1 of GTPS Bay, resulting in
operation of 220 kV Busbar protection relay for external LBB signal and triping
of 220 kV Buscoupler and feeders on 220 kV Bus zone-A.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
19
During occurrence weather was stormy and cloudy with heavy rain, cable trenches were full of water with water level in yard was upto knee level.
Operational issues leading to Non-operation / Mal-operation of protection
system: Cable coming from OGM panel of 220 / 6.6 kV Stn. T.F. -1 of GTPS in yard to Bus Bar panel at 220 kV Uran Control Room found faulty due to insulation failure. Further, though Stn. T/F-1 of GTPS is out of service, A-Bus
isolator physically open but getting Close status in Bus Bar Panel due to improper contact in auxiliary relay in OGM Panel. Hence B/B/LBB trip signal extended to A-Bus trip relays
Relay and Flag indications:
Single line diagram of Uran S/s:
The Event Report is enclosed at Annexure 2C.8.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
20
2C.9. Grid Incidence at 220 kV Uran S/s on 4th August 2019.
Event Category: GI-1
Event Summary as per the WRLDC report:
At 220 kV Uran S/s, 220 kV Bus 1 and all the connected elements tripped due
to spurious LBB signal generated due to the faulty Binary input module of REB
670.
Description of occurrence (As per MSETCL report):
On dated 04.08.2019, at 03:57 Hrs, at 220 kV Uran S/s, Due to spurious signal
of LBB Trip command received from 220/6.6 kV Station TF-1 ( Bay 17 of Busbar
panel) of GTPS Bay, resulting in operation of 220 kV Busbar protection for
external LBB signal and tripping of bus coupler and feeders on bus zone-A.
During occurrence weather was stormy and cloudy with heavy rain, cable
trenches were full of water with water level in yard was upto knee level.
Operational issues leading to Non-operation / Mal-operation of protection
system: Cable coming from OGM panel of 220 / 6.6 kV Stn. T.F. -1 of GTPS in
yard to Bus Bar panel at 220 kV Uran Control Room found faulty due to
insulation failure. Further, though Stn. T/F-1 of GTPS is out of service, A-Bus
isolator physically open but getting Close status in Bus Bar Panel due to
improper contact in auxiliary relay in OGM Panel. Hence B/B/LBB trip signal
extended to A-Bus Bus-Bar trip relays.
Relay and Flag indications:
Single line diagram of Uran S/s:
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
21
The Event Report is enclosed at Annexure 2C.9.
Committee may like to discuss.
2C.10. Grid Incidence at 220 kV Uran S/s on 4th August 2019.
Event Category: GI-1
Event Summary as per the WRLDC report:
At 220 kV Uran S/s, 220 kV Bus 1 and all the connected elements tripped due
to spurious LBB signal generated due to the faulty Binary input module of REB
670.
Description of occurrence (As per MSETCL report):
On dated 04.08.2019, at 05:27 Hrs, at 220 kV Uran S/s, Due to spurious signal
of LBB Trip command received from 220/6.6 kV Station TF-1 ( Bay 17 of Busbar
panel) of GTPS Bay, resulting in operation of 220 kV Busbar protection for
external LBB signal and triping of buscoupler and feeders on bus zone-A. During
occurence weather was stormy and cloudy with heavy rain, cable trenches were
full of water with water level in yard was upto knee level.
Operational issues leading to Non-operation / Mal-operation of protection
system: Cable coming from OGM panel of 220 / 6.6 kV Stn. T.F. -1 of GTPS in
yard to Bus Bar panel at 220 kV Uran Control Room found faulty due to
insulation failure. Further, though Stn. T/F-1 of GTPS is out of service, A-Bus
isolator physically open but getting Close status in Bus Bar Panel due to
improper contact in auxiliary relay in OGM Panel. Hence B/B/LBB trip signal
extended to A-Bus Bus-Bar trip relays.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
22
Relay and Flag indications:
Single line diagram:
The Event Report is enclosed at Annexure 2C.10.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
23
2C.11. Grid Incidence at 220 kV Nashik S/s on 15th August 2019.
Event Category: GD-1
Event Summary as per the WRLDC report:
220 kV Nashik-Bableshwar 2 was taken on TBC at Nashik S/s for bus
sectionaliser 3 outage. Trip circuit faulty alarm appeared on the Nashik TBC. To
attend the problem the circuit was opened at Bableshwar end and the TBC
isolator was opened with charging current which rersulted in sparking of the
isolator and created R-E fault. As the trip circuit of the line was faulty, TBC not
opened and resulted in tripping of all the elements connected to 220 kV Nashik
Main Bus on LBB operation.
Description of occurrence (As per MSETCL report):
220kV LBB protection operated at 220kV GCR eklahare SS. Hence feeders
connected to bus Zone-1 and 3 tripped correctly. The 220kV Ghatghar line
which is in bus Zone-2, tripped from remote end.
Relay details
Control Panel Annunciation Dist prot. Optd.
Main-I Relay indications Dist. Relay: - A Ph-E, Zone-4, Loc. 112.20km, IR=1301A, IY=519A, IB=487A, IE=312A
The Event Report is enclosed at Annexure 2C.11.
Committee may like to discuss.
2C.12. Grid Incidence at 220/132 kV Dhule(MH) S/s on 22nd August 2019.
Event Category: GI-1
Event Summary as per the WRLDC report:
At 220/132 kV Dhule(MH) S/s, due to the sparking in 220 kV Bus Bar relay
panel on RQDA module of RADSS bus bar panel, Bus bar protection operated
and all elements connected to 220 kV Main Bus tripped.
Description of occurrence (As per MSETCL report):
On dt.22.08.2019 220 kv Bus Bar (old yard) operated at 220 kv Dhule S/st. @
12:36 hrs.
Following feeders tripped
1. 200 MVA ICT-1
2. 200 MVA ICT-2
3. 50 MVA T/F
4. 25 MVA T/F
5. 220 kV Chalisgaon
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
24
6. 220 kV IC-1
7. 220 kV IC-2
After yard & Bus Bar panel inspection carried out, Spark is observed on 220 kv
Bus Bar relay panel on RQDA module of RADSS bus bar panel. After card
cleaned and with Ld NGP permission Restoration carried out.
Relay operation details
Control Panel Annunciation 86 Relay Optd , 96 trip relay optd.
Main-I Relay indications BUSBAR OPTD, ‘U’ FLAG OPTD.(U-TRIPPING FLAG)
Main-II Relay indications BUSBAR OPTD, ‘U’ FLAG OPTD.(U-TRIPPING FLAG)
Other Relay indications
220 kV BUS BAR PANEL BUSBAR OPTD, ‘U’ FLAG OPTD.(U-
TRIPPING FLAG), 96 Trip relay of 220 kV Interconnector- 1 & 2,
220 kV Chalisgaon, 200 MVA ICT- 1 & 2, 50 MVA T/F, 25 MVA T/F optd.
The Event Report is enclosed at Annexure 2C.12.
Committee may like to discuss.
2D.Occurrences in Goa system:
2D.1. Grid Incidence at 220kV Ponda S/s on 29th July 2019.
Event Category: GD-1
Event Summary as per the WRLDC report:
On 29.07.2019 at 17.38 hrs there was a grid incidence at 220kV Ponda S/s. At 220kV Ponda, Bus 2 bus fault occurred due to the de-capping of bus insulator and resulted in tripping of all the elements connected to it.220 kV Mahalashmi-
Amona also tripped during the event. Tripping of 220 kV Ponda-Xeldem 1&2, led to black out at 220kV Xeldem S/S. The 220 kV Ponda Bus 2, 220 kV Ponda-Xeldem 1&2, 220 kV Mahalakshmi-Amona, 220/110 kV Ponda ICTs 2&3 and
220 kV Amona-Ponda 1&2 tripped.
The SLD/Event Report is enclosed at Annexure 2D.1
Goa Electricity Department may submit the detailed report.
Committee may like to discuss.
2D.2. Grid Incidence at 220 kV Amona S/s on 13th August 2019.
Event Category: GI-1
Event Summary as per the WRLDC report:
At 220 kV Ponda S/s, Dropper of 220KV Ponda-Xeldem-2 fell on 220KV Bus-1
and all the elements connected to 220 kV ponda Bus 1 tripped.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
25
Description of occurrence (As per Goa Electricity Department report):
The bus dropper of 220kV PXR-II line snapped and fallen on main Bus-I at
Ponda S/s and it pulled the 220kV Mapusa-Ponda I line and CB of 220kV Mahalaxmi-Amona at Amona S/s. Due to source tripping of above two lines the
main Bus-I having 2 nos. of 100MVA ICTs at Ponda Ss became dead. 220kV Mapusa-Ponda I line tripped and CB of 220kV Mahalaxmi-Amona at Amona S/s
The SLD/Event Report is enclosed at Annexure 2D.2.
Committee may like to discuss.
2D.3. Grid Incidence at 220 kV Amona S/s on 15th August 2019.
Event Category: GI-1
Event Summary as per the WRLDC report:
At 220 kV Amona S/s, due to failure of Y-ph LA of 220KV Tillari feeder all the
elements connected to 220 kV Amona Bus 2 tripped. Description of occurrence (As per Goa Electricity Department report):
Due to failure of 'R' phase LA at Amona connected of 220kV Tillari-Amona line,
the 220kV Halkarni-Tillari line tripped. The line CB of Tillari-Amona did not trip.
220 KV Mahalaxmi Amona breaker at Amona tripped.
Main-I Relay indications DPR, Zone I, Phase:- R-N, Fault current :- 6.9kA, distance 2.7 Kms.
The SLD/Event Report is enclosed at Annexure 2D.3.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
26
2E.Occurrences in Chhattisgarh system:
2E.1. Grid Incidence at 220/132 kV Bemetara S/s on 13th July 2019.
Event Category: GD-1
Event Summary as per the WRLDC report:
On 13.07.2019 at 22.22 hrs there was a grid incidence at 220/132 kV
Bemetara S/s. 220/132 kV 160 MVA Bemetara ICTs 1&2 and 220/132 kV 160
MVA Gendpur ICT 2 tripped on overload and led to the blackout of 220 kV
Gendpur S/s and 132 kV Kawardha,Pandariya and Saja S/s. The 220/132 kV
160 MVA Bemetara ICT 1, 220/132 kV 160 MVA Bemetara ICT 2, 220/132 kV
160 MVA Gendpur ICT and 220KV Urla –Siltara tripped.
Event Description (As per CSPTCL report) :
220/132kV 160MVA Bemetra ICTs have different impedance due to which there
is difference in sharing of their load. On 13.07.2019 at 22:20 hrs, Bemetra ICT 2
tripped on overload due to increase in agricultural load, causing tripping of ICT-
1 also on overload. With the tripping of both the ICTs, load of 132kV Kawardha
shifted on 132kV Gendpur-Kawardha D/C causing overload and tripping of
220/132kV Gendpur ICT-2. Gendpur ICT-1 was out of service. This led to
cascade tripping of 132kV feeders causing total blackout at 132kV Kawardha,
Pandariya and Saja.
Sequence of tripping and restoration :
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
27
SLD indicating network around 220/132 KV Bemetra S/S
The SLD/Event Report is enclosed at Annexure 2E.1.
Committee may like to discuss.
2E.2. Grid Incidence at 220 kV Raigarh S/s on 24th July 2019.
Event Category: GD-1
Event Summary as per the WRLDC report:
On 24.07.2019 at 18.11 hrs there was a grid incidence at 220 kV Raigarh S/s.
R-E fault occurred at 132 kV Raigarh-Salasar feeder at 2.3 km from Raigarh end
in Zone 1 and distance protection relay gave trip command to open the CB. The
CB got mechanically jammed and resulted in LBB operation and tripping of all
the elements connected to 132 kV Bus. 132 kV Raigarh-Raigarh Interconnector
1&2 tripped and 132 kV Raigarh,132KV Kodatarai, 132KV Dabhra and 132KV
S/S Baramkela supply got interrupted due to the event. There was a load loss of
125 MW due to the event. The detailed report submitted by the utility is attached
as annexure. The 220/132 kV 160 MVA Bemetara ICT 1, 220/132 kV 160 MVA
Bemetara ICT 2 and 220/132 kV 160 MVA Gendpur ICT 26.220KV Urla –Siltara
tripped.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
28
The sequence of tripping and restoration (As per CSPTCL report):
Single line diagram:-
The total interruptions occurred due to mechanical jamming in Circuit Breaker
of 132KV Salasar feeder at 220 KV S/S Raigarh.
The SLD/Event Report is enclosed at Annexure 2E.2
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
29
2E.3. Grid Incidence at 220/132 kV Siltara S/s on 28th August 2019.
Event Category: GI-1
Event Summary as per the WRLDC report:
Due to the R phase fault in 132 kV Siltara-Vandana feeder, 220/132 kV Siltara
ICTs 2&3 tripped.
CSPTCL not uploaded the preliminary tripping report in the tripping portal.
The SLD/Event Report is enclosed at Annexure 2E.3
Committee may like to discuss.
2F.Occurrences in Dadra and Nagar Haveli system:
Nil
2G.Occurrences in Daman and Diu system:
Nil
2H.Occurrences in PGCIL systems:
2H.1. Grid Incidence at 800 kV HVDC Champa-Kurukshetra Terminal on
05th July 2019.
Event Category: GI-2
Event Summary as per the WRLDC report:
On 05.07.2019 at 17.20 hrs there was a grid incidence at 800 kV HVDC
Champa-Kurukshetra Terminal. 800 kV HVDC Champa-Kurukshetra Pole 1&2
tripped on Metallic Return Line Differential(MRLD) protection and Earth over
current protection respectively due to Direct Metallic Return(DMR) line 1 short
circuit fault. The 800 kV HVDC Champa-Kurukshetra Pole 1, 800 kV HVDC
Champa-Kurukshetra Pole 2 tripped.
Event Description (As per PGCIL report) :
Pole-1& Pole-2 Tripped on DMR1 short circuit fault. MRLD Protection operated &
Earthover current protection operated.
The SLD/Event Report is enclosed at Annexure 2H.1
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
30
2I.Occurrences in NTPC systems:
Nil
2J. Occurrences in Green Infra Wind Energy Limited (GIWEL)
system:
2J.1. Grid Incidence at 220 kv Vadva S/s on 12th August 2019.
Event Category: GD-1
Event Summary as per the WRLDC report:
Due to the tripping of 220 kV Bhuj-Vadva S/C on B-E fault, 220/33 kV
Vadva ICTs 1,2& 3 deenergized at 220 kv Vadva S/s. B - phase temporary earth
Fault.
GIWEL may submit the detailed report.
Committee may like to discuss.
2J.2. Grid Incidence at 220 kv Vadva S/s on 24th August 2019.
Event Category: GD-1
Event Summary as per the WRLDC report:
Due to the tripping of 220 kV Bhuj-Vadva S/C on O/C current protection
operation, 220/33 kV Vadva Icts 1,2& 3 deenergized at 220 kv Vadva S/s. line
tripped in low set over current.
GIWEL may submit the detailed report.
Committee may like to discuss.
2K. Compliance of 128th PCM to 137th PCM recommendations:
The compliance status of the 128th to 137th PCM recommendations is enclosed at
Annexure-2K.1.
Utilities are requested to furnish the compliance in the PCM.
Committee may like to discuss/note.
ITEM NO. 3: Tripping of lines / ICTs : The minor incidences of tripping of lines and ICTs during the period 01-07-2019
to 31-07-2019 are to be discussed is enclosed at Annexure–3.
Committee may like to discuss/note.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
31
ITEM NO. 4: State Level Relay Co-ordination Groups:
4A.1.)Back ground: In the 128th& 129th PCM the issue of formation of “State
level Relay Co-ordination Group” (SRCG) was discussed in detail to review the
relay settings within the State, so that the settings are coordinated. It was
decided that SLDC shall be the convener of the group and the SRCG of the
States shall periodically review the relay coordination in their State. The
proposals for revision of relay settings then shall be put up to the PCM forum for
ratification.
4A.2.) 131st& 132nd PCM discussion:
Following critical areas were identified for relay protection co-ordination in the
131st PCM;
Maharashtra : Akola, Talegoan, APL Tirora and Mumbai-MSETCL
interconnections.
Gujarat : SSP, Kakrapar,Kawas&Gandhar.
MP : Omkareshwar&Damoh.
Chattisgarh: Korba (W) & Bhilai.
4A.3.) 136th PCM Discussions:
NPCIL representative informed that the implementation of revised distance relay
settings of 220kV TAPS-Borivali feeder at TAPS end has been done on
26.04.2019.
MSLDC representative informed that based on the action taken report of the first
and second meeting, they have proposed to conduct the third meeting most
probably in the month of June 2019.
GETCO representative informed that most of the relay setting coordination
issues were addressed during the first and second meetings and also informed
that the third meeting will be held in the month of June 2019 or July 2019.
MS,WRPC stressed that regular meetings of the State level Relay Co-ordination
groups be held for review of relay coordination of interconnections and the MoM
to be shared with PCM.
4A.4.) 137th PCM Discussions:
MSETCL representative informed that the relay settings for the critical areas
identified above have been done and a report would be put up in the next PCM.
GETCO representative informed the 2nd meeting of the group was conducted and
the 3rd meeting would be held in August 2019.
MPPTCL & CSPTCL representatives informed that they are also conducting
regular meetings and the findings would be put up in the next PCM.
MSETCL, MPPTCL & CSPTCL may appraise subcommittee with regards new
developments/report etc. as committed in 137th PCM.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
32
ITEM NO. 5: Hon’ble CERCs orders on the Grid
disturbance of 30.07.2012 & 31.07.2012 5.1: Compliance Status observations made in Protection Audit (Petition No.
220/MP/2012) BackGround:
5.1.1) Back ground:
CERC vide its order dated 21.02.2014 in respect to petition No. 220/MP/2012
filed by POWERGRID have directed that CTU and SLDCs shall submit quarterly
Protection Audit Report to the respective RPC latest by 15th day of the first
month of next quarter and RPCs shall submit the report to the Commission
latest by 15th day of the second month of next quarter. The Member Secretary of
Regional Power Committees shall monitor the protection related issues and
bring to the notice of the Commission any instance of non-compliance of the
Regulation 1.5 of the Grid Code in respect of the protection related issues
considered in the instant petition.
Maharashtra representative stated that they are taking up the protection audit in
a - Ø d manner and they have already identified the S/Ss to be taken up for
protection audit. Further the compliances are mainly pending for protection
audits carried out in the recent past.
Gujarat & MP representatives stated that they have also taken up identification of
the S/Ss for protection audit and the same shall be intimated to PCM as soon as
it is done.
5.1.2) Protection Audit of all critical S/Ss above 220kV level :
Protection audit of all the critical S/Ss above 220kV level has to be carried out.
Take up protection audit of newly commissioned S/Ss and S/Ss where protection
audit has been carried out 5 years back.
(Discussed in 132nd PCM)
5.1.3) Protection audit of second - phase :
The status regarding the taking up the protection audit of second - phase was
discussed and the update on the same is as follows;
PGCIL, GETCO & MPPTCL representatives informed they have already planned
the activity to be done through independent agency. MSETCL representative
informed that they are planning to carry out the protection audit through
independent agency. NSPCL representative informed that they have already
carried out PA of their S/S. NTPC & CSPTCL representative informed that they
will inform the status shortly.
(Discussed in 133rd PCM)
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
33
5.1.4) Submission of Protection audit status to Hon’ble CERC :
Protection Audit Report for the fourth quarter of 2018-19 (January 19 to March
2019) has not yet received from CTU and SLDCs excluding SLDC, Gujarat and
SLDC, MP and PGCIL.
SLDCs and CTU/WRLDC are requested to submit the data at the end of every
quarter to WRPC, in compliance to the above CERC order dated 21.02.2014, so
that the quarterly data submission can be made by WRPC to CERC.
5.1.5) Issue to be discussed :
The compliances of protection audit observations received from the states for the
quarter (January to March 2019) have been sent to CERC, the same is available
on WRPC web site http://wrpc.gov.in/pcm/PAR_March_2019.pdf.
It has been observed that except Gujarat, MP & PGCIL, none of the
other constituents are regularly submitting the updated status, hence
the status already received is being communicated to Hon’ble CERC.
From the following compilation it is observed that the category A &
category B observations are still to be complied, which is serious.
The updated status of the protection audit observations is as given below
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
34
As per the Hon’ble CERC order dated 21.02.2014 in respect to petition No.
220/MP/2012, SLDCs and CTU are requested to submit the data at the end
of every quarter to WRPC, so that the quarterly data submission can be
made by WRPC to CERC.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
35
5.2: Relay Setting Database:
5.2.1) Background:
Hon‟ble CERC‟s vide order dated 22.02.2014 in the matter o f grid
disturbance occurred on 30.07.2012 & 31.07.2012 in petition No. 167/Suo-
Motu/2012, have made certain observations and issued directions.
According to this order, all the RPCs have to maintain the relay settings data of
all the ISTS lines and lines emanating from interface S/Ss of Utilities to ISTS
(400 kV& above and 220 kV interfacing lines). Therefore, all utilities were
requested to submit relay setting data to WRPC/WRLDC.
5.2.2) 136th PCM Discussions:
MS,WRPC briefly explained the database that is being prepared by WRPC to the
forum. He further informed to the constituents to furnish the data as per the
preferred format so that the data import from Excel to the database can be made
smoothly. He also informed to the forum that the compiled data base in Excel
sheets will be circulated to all the constituents and requested all the
constituents to update the data (if any) and furnish the updated data to WRPC.
5.2.3) Data formats and regular updation of the data :
The formats for relay settings were re-aligned as per the requirement of WRPC and
the same was sent to all the constituents vide email dated 07.06.2019.
Constituents are requested to send and update the data, strictly in the formats
circulated by WRPC vide the above email.
All the IPPs/ISGS and State generators are also required to submit the switchyard
setting data in the above formats. The generating Unit setting data should be
submitted by all these generators in the format enclosed as Annexure 5.2.3.
5.2.4) 137th PCM Discussions:
MSETCL representative informed that they would submit the data within 15
days. GETCO representative informed that the work is in progress. Committee
noted that the data was received recently from CSPTCL and is exactly as per
requirement of WRPC.
Committee requested the Generating utilities to submit the data in the format at
the earliest.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
36
ITEM NO. 6: Task Force report Report of the Task Force on Power System Analysis Under
Contingencies:
Background:
Ministry of Power, GoI constituted a “Task Force on Power System Analysis
under Contingencies”, in December 2012 under the chairmanship of Shri
V. Ramakrishna as per the recommendation made by Enquiry Committee
headed by Chairman, CEA on grid disturbances that took place in NEW grid
on 30th and 31
st July 2012. The terms of reference of Task Force broadly cover
analysis of the network behavior under normal conditions and contingencies,
review of operational philosophy of protection relays, review of islanding
schemes and technological options to improve the performance of the grid. The
report of the Task Force was discussed briefly in 122nd PCM and subsequently
discussed in detail in a special meeting held on 18.12.2014. Thereafter the
recommendations were discussed in the previous PCMs. A brief on suggestions
given by Ramakrishna Committee, discussions/observations of the group and
PCM are as follows.
6.1) Formulation of Special groups for studies and protection coordination:
The Task Force recommended forming a group for studies, protection
coordination and relay settings. It also recommended that each utility should
establish a protection application department with adequate man power &
skills. The members of protection team shall undergo regular training to
enhance their skills.
6.2) Tuning of power electronic devices & PSS: The Task Force recommended
carrying out studies & reviewing the network at regular intervals (3-4 years) with
introduction of newer power electronic devices. The results may be implemented
within next 3-4 years. It also suggested that as this requires specialized dynamic
modeling, the task may be entrusted to reputed independent agency and
implementation of tuning be entrusted to respective manufacturer.
A meeting was held on 03.01.2017 at WRPC Mumbai, wherein representatives of
all the generating companies, SLDCs and expert from IIT-B attended the meeting.
WRP Committee in the 33rd WRPC meeting held on 01.02.2017, agreed and gave
approval for funding the studies software as above from WRPC fund for
developing the software through IIT-B. GETCO, CSPTCL, PGCIL WR-I & II
representatives informed that they would confirm their representation for the
study group shortly.
The 1st meeting of the WR Study Group was held on 29.10.2018 at WRPC,
wherein it was stressed that the updated network upto 31.09.2018 and the
planned network and system data upto March-2019 be submitted to WRPC for
taking up the Capacitor Studies.
Committee requested to submit the updated network upto 31.09.2018 and the
planned network and system data upto March-2019 to WRPC for taking up the
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
37
Capacitor Studies.
6.3) 136th PCM Discussions:
As regards to carrying out capacitor requirement studies, the data is still not
received from constituents and therefore all constituents are once again
requested to furnish updated network upto 30.04.2019 and the planned network
and system data upto March-2020 to WRPC for taking up the Capacitor Studies
The PSS tuning status received from WRLDC is enclosed at Annexure-6.
6.4) 137th PCM Discussions:
It was decided that nominations details will be made available to WRPC.
Subsequently, the contact details have been received which is tabulated
below.
Sl
No.
Name Organization Contact
Number
Mail ID
1 Shri. SSS Srinivas NTPC Solapur 9422508195 [email protected]
n
2 Shri Sachin Lomate SLDC Maharashtra 9029800895 [email protected]
3 Shri Vekhade
MSETCL testing
4 Shri G. T. Jawale
TPC 9223311419
om
5 Shri Sandeep
APL
6 Shri Sonu W. Korekar
Reliance
9324216663
sonu.korekar@relian
ceada.com
7 Smt.Pushpa Sheshadri
WRLDC 9869404482
8 Shri. Pradeep Sachan
SLDC MPPTCL 9425805277
p.sachan@mptransco
.nic.in
9 Shri. Kuleshwar Sahu Power Grid
Corporation of India
Ltd -WR-I
6260169298 kuleshwar@powergri
dindia.com
10 Shri Sanjoy Das Power Grid
Corporation of India
Ltd - WR-2
9429976244
sanjoydas@powergrid
india.com
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
38
National Power Committee(NPC) items:
ITEM NO.7: Violation of CEA Protection (Grid)
Standards-( NPC item): 7.1.1) CEA vide letter dated 30.08.2017, have intimated that following
protection standards were reportedly violated in respect of following cases;
(1) Non-availability of A/R at both ends of 220kV lines
(2) Non-submission of DR/EL data to RLDC within 24 hours of the event.
(3) Non-intimation of main reason for the events after its complete analysis.
(4) Higher fault clearance time than prescribed in the standards.
CEA has further directed that if the non-compliance of Grid/Standards/ Grid
Code continues, the matter may be reported to CERC under provisions of the
Grid Code, with a copy of the report to CEA. Committee (131 to 136th PCM)
requested all the utilities of WR to strictly follow the CEA’s protection standard
in future in order to ensure safe grid operation. A report of WRLDC on the above
subject covering details from July 19 to August 19 is enclosed at Annexure 7.
All the constituents are requested to submit the compliance report on the report
of WRLDC indicating violation of CEA Protection (Grid) Standard in case of
tripping of inter-regional lines of voltage class 220 kV and above level of WR
7.1.2) 137th PCM Discussions:
Committee requested all the constituents to submit the compliance report
on the report at annexure indicating violation of CEA Protection (Grid)
Standard of voltage class 220 kV and above level of WR.
7.2.1) Non-Auto recloser operation at RGPPL end (WRLDC item):
It is observed from the events in May ‘19 and June ’19 that the A/R at RGPPL
end did not operate and the lines tripped on transient faults. In all the events,
A/R was attempted and successful at remote end only and in each event the line
was holding.
The events are mentioned in the table below
Element name outdate out
time in date in time comments
400 kV RGPPL-
New Koyna 2 21-05-19 02:41 21-05-19 03:16
Line tripped from Dabhol end
only due to Y phase fault. A/R
successful at New Koyna end.
400 kV RGPPL-
New Koyna 2 22-05-19 01:10 22-05-19 10:35
Line tripped from Dabhol end
only due to R phase fault.
400 kV RGPPL-
Nagothane 1 26-05-19 02:47 26-05-19 03:22
Tripped at Dabhol only; Y
phase fault; A/R successful at
Nagothane
400 kV RGPPL-
New Koyna 1 29-05-19 23:52 30-05-19 00:32
B Phase fault, A/R successful
at New Koyna end. Line
tripped at Dabhol end only.
400 kV RGPPL-
Nagothane 2 30-05-19 03:08 30-05-19 09:44
Line tripped from Dabhol end
only. A/R successful at
Nagothane end.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
39
400 kV RGPPL-
New Koyna 1 03-06-19 06:23 03-06-19 06:56
Y phase fault, A/R successful
at New Koyna tripped at
Dabhol end only
RGPPL may kindly update the status of A/R of 400kV transmission lines at
their end.
Committee may like to discuss.
7.2.2) 137th PCM Discussions:
It was decided that a letter regarding the A/R issue be sent to RGPPL.
Committee requested all the utilities to attend the violations given in the
Annexure.
7.3) Status of Auto recloser of 220 kV Malanpur-Auraiya and 220 kV
Mehgaon-Auraiya (WRLDC item)
Due to the non-availability of phase segregated LBB relay at Auraiya end, A/R of
Malanpur and Mehgaon lines were kept off at Auraiya and MPPTCL ends from
September 2016.
As per letter dated 26.03.19 from MPPTCL to NTPC Auraiya, MPPTCL has made
request to Auraiya authority to procure the LBB relay as per their requirement
and the cost in this regard shall be paid by MPPTCL. As per mail dated 08-04-
2019, MPPTCL informed that ‘Auraiya has procured the LBB relay and the same
is being commissioned shortly’.
MOM of the meeting between MPPTCL and Auraiya regarding this issue and
letter given by MPPTCL to NTPC Auraiya are enclosed as Annexure-7.3.
7.3.2) 137th PCM Discussions:
Committee suggested that NTPC & MPPTCL would resolve the issue
mutually.
NTPC & MPPTCL may kindly update the status.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
40
ITEM NO. 8: Details of Protection Audit and
Implemented Defence Mechanism –Reg (NPC Item).
8.1) National Power Committee Division (NPC) / CEA vide letter dated
10.09.2018 informed that a meeting was taken by Hon’ble MoSP (IC) on
20.08.2018 to discuss the draft National Electricity Plan. During the discussions
CEA has been asked to prepare report and presentations covering aspects of grid
reliability and security,especially with respect to grid failure and remedial
measures including mechanisms such as is-landing schemes,SPS,UFR,Third
Part Protection Audit etc.
NPC/CEA vide letter dated 10.09.2018 requested WRPC, the details in
prescribed formats on the following may please be furnished
i. Protection Audit Carried out so far and its observations
ii. Islanding scheme implemented in the region.
iii. SPS implemented in the region.
iv. Status of implementation of AUFLS in the region .
v. Status of implementation of df/dt relays & its settings in the region.
WRPC vide mail dated 12.10.2018 and dated 26.10.2018 requested
MSETCL,MPPTCL,CSPTCL,GETCO,Goa Electricity Department (GED), DD,
PGCIL , NTPC and DNH to furnish the information sought by NPC vide letter
dated 10.09.2018 to WRPC at the earliest. However, information was not
received from constituents except WRLDC and MSETCL. The letter & formats
received from NPC,CEA is enclosed at Annexure 8.
MPPTCL, CSPTCL, GETCO, GED,DD,DNH, NTPC is requested to submit the
information before the PCM or in the PCM.
The details sought by NPC have been received from WRLDC, MSETCL and PGCIL.
8.2) 137th PCM Discussions:
Committee requested MPPTCL, CSPTCL, GETCO, GED,DD,DNH & NTPC to
submit the data immediately.
MPPTCL, CSPTCL, GETCO, GED,DD,DNH, NTPC is again requested to submit
the status.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
41
ITEM NO. 9: Enquiry Committee recommendations-
( NPC Item).
9.1)NPC, CEA vide letter no 7/GSC/NPC/CEA/2019/87-93 dated 16.01.2019
requested to submit the updated status of implementation of Enquiry Committee
recommendations. The last updated information of all constituents is enclosed
as Annexure -9.1. All the constituents are requested to update information and
submit the updated information (in excel format) to WRPC, so that the same
can be furnished to NPC, CEA. WRPC, vide mail dated 25.01.2019 (prc-
[email protected]) requested the constituents to submit the updated status of
implementation of Enquiry Committee recommendations at the earliest to WRPC.
9.2)135th PCM Discussions:
All the constituents are requested to submit the updated status of
implementation of Enquiry Committee recommendations at the earliest to
WRPC.
However, the data has not received from the constituents except PGCIL WR-I
and SLDC Gujarat.
9.3) 136th PCM Discussions:
WRPC representative informed that the data has not received from the
constituents except PGCIL WR-I and SLDC Gujarat.
MS, WRPC informed to the forum that NPC,CEA consistently following up
the subject matter with WRPC.
MS,WRPC requested all the constituents consider the subject matter as
priority and to submit the updated status of implementation of Enquiry
Committee recommendations at the earliest to WRPC.
WRLDC has furnished the latest status of implementation of Enquiry
Committee recommendations.
Constituents are requested to regularly update the data. Chattisgarh,
Goa, DD & DNH, and IPPs have not submitted the data so far. They may
submit the data immediately.
9.4) 137th PCM Discussions:
Committee requested Chattisgarh, Goa, DD & DNH to submit the data.
Chattisgarh, Goa, DD & DNH are again requested to update the status.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
42
ITEM NO. 10:- Recommendations of M/s PLI. Canada-
NPC Item.
10.1.)Ministry of Power, Government of India constituted a “Taskforce on Power
System Analysis under Contingencies” in December 2012 as a follow-up of the
recommendations of Enquiry Committee under Chairperson, Central Electricity
Authority (CEA) on Grid Disturbances of 2012 in Indian Grid.
The Taskforce broadly made recommendations regarding analysis of the network
behavior under normal as well as contingency scenarios, review of the
philosophy of operation of protection relays, review of islanding schemes, review
of tuning of power electronic controlled devices, review of relay coordination and
technological options to improve the performance of the grid. The Taskforce
further recommended the appointment of consultants for the above.
To fulfill part of the above recommendations, Powertech Labs, Inc. (PLI) was
contracted to perform the following tasks:
Task I: Examination and recommendation of methodology for
optimum calculation of transfer capability in the planning
and the operational horizons.
Task II: Calculation of transfer capability for the entire country.
Task III:
Guidelines for developing and implementing system
protection schemes and islanding schemes, and
review of existing schemes.
Task IV:
Operational planning and long term planning for the
secure and efficient operation of the grid.
Task V:
Suitable suggestions in the Regulatory framework to
ensure secure and efficient grid operation.
Task VI: Review of the tuning of all power electronic devices and
suggesting retuning of setting of these devices, as per
“Taskforce Report on Power System Analysis”.
A meeting of officials from CEA,CERC,CTU and NLDC was held on 22.03.2019 in
the O/o Chief Engineer (NPC) for finalization of action plan of all the
recommendations in the report of the Tasks I to VI of the M/s Powertech Labs
Inc. Canada under Package B ( Review Transmission System Transfer Capability
and Review of Operational and Long Term Planning). During the meeting action
plan of the recommendations of Tasks were finalized.
NPC vide letter dated 15.05.2019 forwarded the finalized action plan of the
recommendations of Tasks and the same is enclosed as Annexure 10.1.
The recommendations that are required to be implemented by RPCs has been
highlighted by adding extra columns in the recommendation sheets of PLI and is
enclosed at Annexure 10.2.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
43
Western Region Islanding schemes:
ITEM NO. 11: Islanding scheme for KAPP - 3&4, Nuclear
Power Units of NPCIL. 12.1) NPCIL letter no. NPCIL/Trans/2018/M/29 dated 10.10.2018 have
requested WRPC for evolving an Islanding scheme for KAPS 3 & 4 so that it can
be implemented before the unit start up. WRPC vide letter dated 07.12.2018
requested GETCO,NPCIL,WRLDC to furnish the required information for doing
detailed study to evolve the islanding scheme for KAPS 3 & 4. The data required
as follows:
1) Data/details/information to be furnished by NPCIL/KAPS:
a) Generation details
i. Generation trip details.
ii. Speed control operation of governor.
iii. UF/LF trip settings.
iv. Other relevant requirements.
b) Load details- load to be included in Island.
2) Data/details/information to be furnished by GETCO:
The downstream network & feeder wise loads at the next bus and further
downstream low voltage network.
3) Data/details/information to be furnished by WRLDC:
Latest network & peak &off-peak loadings of lines emanating from KAPS &
adjacent buses.
A meeting was held at KAPS NPCIL on 14.11.2018 to discuss the Islanding
scheme. Generator data was received from KAPS NPCIL vide their letter dated
04.01.2019. Data has been received from GETCO by mail.
12.2)135th PCM Discussions:
SE (P), WRPC suggested that a separate meeting would be better to discuss and
formulate the Islanding scheme for Kakrapar Atomic Power Project (KAPP - 3&4)
2x700 MW capacity Nuclear Power Units of NPCIL and the date of the meeting
could be decided and intimated to NPCIL,GECTO& WRLDC later on.
12.3) KAPS Islanding meeting held on 24.04.2019 at WRPC Mumbai.
A meeting was held on 24.04.2019 at WRPC Mumbai (copy of MoM enclosed at
Annexure-15.5) to discuss Islanding scheme for Kakrapar Atomic Power Project
(KAPP - 3&4) 2x700 MW capacity Nuclear Power Units of NPCIL.
During the meeting all the participants discussed about the option 1 and option
2 proposed by GETCO.
After detailed discussion, all the participants, agreed to choose option-II for
KAPS 3 & 4 islanding out of two options proposed by GETCO. It was also agreed
to put up the decision of choosing option –II in next PCM for further direction (if
any).
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
44
12.4) 136th PCM Discussions:
A meeting was held on 24.04.2019 at WRPC Mumbai (copy of MoM enclosed at
Annexure-12.4) to discuss Islanding scheme for Kakrapar Atomic Power Project
(KAPP - 3&4) 2x700 MW capacity Nuclear Power Units of NPCIL.
During the meeting all the participants discussed about the option 1 and option
2 proposed by GETCO.
After detailed discussion, all the participants, agreed to choose option-II for
KAPS 3 & 4 islanding out of two options proposed by GETCO.
DNH representative was not present during the meeting.
12.5) 137th PCM Discussions:
DNH representative informed that they in-principle agree with the option-2 given
above. They would discuss with their management and revert back. As regards
to the seasonal variation of load on the identified lines, they informed that the
same would be submitted shortly.
NPCIL representative informed that the protection setting data would be shared
with GETCO, as desired by GETCO.
Committee felt that with the above data GETCO would carry out detailing of the
Islanding scheme and forward the same to WRPC. After receipt of the detailed
scheme, a meeting would be arranged to finalize the Islanding scheme.
DNH & NPCIL has furnished the data as above to GETCO.
GETCO vide mail dated 07.08.2019 (copy enclosed as annexure 12.5) has
requested for additional data and the same was forwarded to NPCIL and
DNH. A separate meeting has been arranged on 16.10.2019 at WRPC
Mumbai. The out come would be informed in the PCM.
Committee may like to discuss.
ITEM NO. 13: Certificate for Healthiness of Batteries
13.1) Background:
As per the MoP direction given in pursuant to recommendations of the Enquiry
Committee (NEW grid disturbance on 30th & 31st July, 2012), RPCs are
required to obtain from their respective Constituents the monthly certificate for
healthiness of batteries, installed at 220 KV and above voltage level Substations
(for power supply to Relays, RTUs and PLCC equipment) and furnish the same to
CEA/MoP.
With reference to above, the Constituents are requested to submit the certificate
on healthiness of batteries on monthly basis (i.e. status for a month shall be
sent by the 7th day of the following month) to WRPC Secretariat.
The certificates have been received from KSK Mahanadi, TRN Energy,
GSECL/GETCO, MSETCL, TATA Power, Essar Power, Rinfra, NCA, SKS, CGPL,
PGCIL WR#2, LANCO, Jaypee Nigrie, NSPCL, GSEL, MCCPL.
Constituents other than above may submit the certificates on regular basis.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
45
ITEM NO. 14: Third-Party Protection Audit Teams (TPPAT).
14.1) The issue of "Formation of Third-Party Protection Audit Teams(TPPAT) for
carrying out third party protection audit in WR" was discussed in the 37th
WRPC meeting held on 18.12.2018 and it was agreed to form protection audit
teams in WR for carrying out the protection audit of S/Ss in WR.
Table –A: Number of members to be nominated with relay testing and
coordination background.
Utility No. of members to be nominated
with relay testing & coordination
background
Nomination status
Genco Transco Others
Maharashtra 1 1 - TRANSCO
1. Mr- R. H. Satpute
Superintending Engineer
Design and Protection Dept.
GENCO
1. Mr R S Alone EE(Testing)
Madhya Pradesh 1 1 - GENCO
Shri. Hapreet Singh Bomrah,
AE. (O &M)
Gujarat 1 1 - Shri. R.A. Patel DyEE(T)
Mehasana
GSECL
Shri.P.A.Parekh,DE,CHPH
EMD, Ph no. 9687663077
Mail :-
Chhattisgarh 1 1 -
PGCIL: W-1 - 3 - 1. Shri Dinesh Reddy, Dy
Manager
2. Shri S Naveen, Asst
Manager
PGCIL:WR – II - 3 - 1. Sh. SachinSavke, Asst.
Manager – Jabalpur PS
2. Sh. Pramod Pathak, Asst.
Manager – Navsari
3. Sh. Kumar Siddhant, Asst.
Manager – Navsari
NTPC 3 - - 1.Shri R K Aash
9429408449
2.Shri S K Waryani
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
46
8275045135
3.Shri Umesh Kumar
6265530641
IPP : APL 1 - -
IPP : CGPL/TATA 1 - - Shri G.T.Jawale
IPP: SASAN 1 - -
SSP/NCA 1 - -
WRLDC - - 2 Shri. Selvamani Prabaharan
M and Shri. M. Venkateswara
Rao
Table-B : Number of teams, its composition and duties.
Sl No. Team Composition System to be audited
1 Team -I 1. Gujarat Transco -1
2. Gujarat Genco – 1
3. PGCIL – 1
4. NTPC -1
5. DNH-1
Maharashtra
IIP S/Ss
2 Team – II 1. MP Transco – 1
2. MP Genco -1
3. PGCIL – 2
4. NTPC -2
5. APL
Gujarat
Chhattisgarh
3 Team – III 1. Maharashtra Transco -1
2. Maharashtra Genco -2
3. PGCIL 2
4. NTPC-3
5. SASAN
6. Goa
Madhya Pradesh
PGCIL
4 Team – IV 1. Chhattisgarh Transco – 1
2. Chhattisgarh Genco – 2
3. CGPL/TATA
4. DD -1
5. SSP – 1 & NPCIL - 1
Goa
DD
DNH
NHPC
NPCIL
NTPC
WRPC vide mail dated 08.01.2019 requested all constituents to give the
nomination so that the work of protection audit can be initiated latest by
15.01.2019. Nominations have been received from MSETCL,PGCIL WR-II &
NTPC only. The other constituents in Table-A may give the nominations at the
earliest.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
47
14.2) 136th PCM Discussions:
WRPC representative informed that the details of protection audit teams in WR
for carrying out the protection audit of S/Ss in WR has been circulated to the
constituents by mail ([email protected]) dated 08.01.2019 and 19.03.2019.
However, nominations are still awaited from all constituents except PGCIL and
NTPC.
MS,WRPC requested all the constituents to furnish their nominations at the
earliest to WRPC so that the third party protection audit in WR can be started.
14.3) 137th PCM Discussions:
Constituents were requested to give the nominations at the earliest.
Committee in reference to queries whether the utilities can carry out the third
party protection audit by hiring/appointing out side agency, Committee
recommended that utilities can proceed by hiring/appointing out side agency for
carrying out third party protection audit. However the protection audit should be
carried out strictly as per the guidelines given in the “Report of task Force” and
Tractable.
The list of critical sub stations and Sub stations where protection audit has
been carried out 5 years back is enclosed as Annexure 14.3
Committee may like to discuss the plan for third party protection audit of
the critical sub stations through above formulated teams.
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
48
WRLDC Items :
ITEM NO.15:
15.1 ) Mock Testing of Local and Wide area System Protection Schemes
(SPS) in Western Region
15.1.1) Background:
The details of local SPS are as follows: -
1. CGPL SPS
2. Sasan SPS
3. JPL Stage 1 & 2 SPS
4. Essar Mahan SPS
5. Sipat SPS
6. 220 kV Vapi-Kharadpada
7. APL Mundra SPS
8. APL Tiroda SPS
9. Mouda SPS
10. High Frequency SPS (tripping of Korba Unit 7 , Vindhyachal Unit 7,
CGPL Unit 40)
Details of Inter-regional SPS Schemes (Wide Area) are as follows:
11. Agra-Gwalior SPS at Gwalior end.
12. HVDC Mundra Mohindergarh SPS
In the 129th PCM it was decided that mock testing of the local SPS can be
done without much coordination and therefore WRLDC may prepare a
schedule for mock testing of local SPS and carry out the mock testing as
per the schedule in coordination with the generators concerned. The Wide
Area SPS requires coordination among the inter region, therefore these shall
be scheduled in consultation with the NLDC and respective RLDCs.
It was decided that wherever the SPS has operated successfully in the
recent past, it would not be required to carry out the mock testing of SPS.
15.1.2) Updates:
1. The updated status of recent successful operation of SPS received from
WRLDC is enclosed at Annexure-15.1.2 (A).
2. Schedule of mock testing of SPS along with SPS operations (2016-19) as
received from WRLDC is enclosed at Annexure-15.1.2 (B).
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
49
15.2) Revision of SPS implemented at JPL:
The SPS for safe evacuation of generation at JPL was implement in Sept 2011
and later on reviewed in April 2015. It was formulated for N-1-1 stability of JPL
Stage-I (4X250 MW+2X135 MW) and JPL Stage-II(4X600 MW) TPS.
The implemented scheme is as follows:
If Generation at JPL Stage-I (4 * 250), JPL Stage-II (2X600 MW) & DCPP (2 * 135
MW) in service, Net Generation 2180 MW.
1. One circuit of 400 kV JPL-Raipur line and 400 kV JPL Stage-I to JPL Stage-
II inter connector or One of the line is out of service and other circuit trips:
a. Ex Bus Generation at JPL Stage-1 to be brought to 590 MW (Trip one
unit of 250 MW & 2-Unit of 135 MW along with 60 MW of Generation
reduction in 3-4 Minutes.)
2. Tripping of 765 kV Tamnar-Kotra D/c lines or One circuit on outage and
other line trips: a. Trip one unit of 600 MW and immediate backing down
other unit such that Ex Bus generation of JPL Stage-I + JPL Stage-II should
not exceed 1160 MW.
WRLDC vide email have informed that M/S JPL has requested for revision of
SPS after commissioning of 765 kV Tamnar-Kotra-D/C lines. TRN Energy
(2X300 MW) is connected to 400 kV Tamnar PS and is evacuating through 765
kV Tamnar-Kotra-D/C lines. Therefore, in case of N-1-1 contingency i.e.,
tripping of 765 kV Tamnar-Kotra-D/C lines, TRN Energy also has to be included
in SPS along with JPL.
15.2) 137th PCM Discussions:
Committee observed that since the representatives of TRN & Jindal power are
not present in the meeting, it would be discussed in special meeting/next PCM
Committee may like to discuss.
Agenda for the 138th PCM to be held on 17.10.2019 at WRPC Mumbai.
50
ITEM NO. 16:- WRLDC Tripping report portal
16.1) Indian Electricity Grid Code (IEGC),2010 part 5, operating code, clause 5.2
( r ) stipulated the timeline for submission of grid incident reports to WRLDC and
WRPC which is as follows:
“ All the users, STU/SLDC and CTU shall send information/data including
disturbance recorded/sequential event recorder output to RLDC within ( 24
hours ) for the purpose of analysis of any grid disturbance/event. No user,
SLDC/STU or CTU shall block any data/information required by the RLDC
and RPC for maintaining reliability and security of the grid and for
analysis of the event.”
CEA (Grid standards) regulations, 2010 clause 15. (3) Stipulated the timeline for
submission of grid incident reports to WRLDC and WRPC which is as follows:
“All operational data, including disturbance recorder and event logger
reports, for analysing the grid incidents and grid disturbance and any
other data which in its view can be of help for analysing grid incident or
grid disturbance shall be furnished by all the Entities within twenty four
hours to the Regional Load Despatch Centre and concerned Regional
Power Committee.”
WRLDC tripping portal was operationalized from 01-06-2019 for uploading FIR,
DR/EL and other details related to the tripping.
User IDs and password were issued to utilities to upload the tripping details in
the following link.
http://103.7.130.115/Trippingnew//Account/Login.aspx
As per IEGC 54.2(r), utilities need to submit the data within 24 hours of the
event.
In the 137th PCM, all Utilities are requested to use the WRLDC tripping
portal and submit the data through the same. However, it is found that
utilities are not uploading the data on the above link.
Committee may like to discuss.
ITEM NO. 17: Date and venue of the next meeting
Committee may like to decide the next PCM (139th PCM) date and venue.