ACCIONA WINDPOWER WIND POWER PLANTS AND GRID INTEGRATION EXPERIENCE 2010 –Friday 23 th April...
-
Upload
edwina-shelton -
Category
Documents
-
view
214 -
download
0
Transcript of ACCIONA WINDPOWER WIND POWER PLANTS AND GRID INTEGRATION EXPERIENCE 2010 –Friday 23 th April...
ACCIONA WINDPOWER WIND POWER PLANTS AND GRID INTEGRATION EXPERIENCE
2010 –Friday 23th April
Óscar Alonso Teresa ArlabánAlberto GarcíaAlejandro González
Authors statement
As a consequence of the Island volcano ash any author of the present paper has been attending the 2010 EWEC conference in Warsaw. Our commitment with the attendees and conference organizers has lead us to prepare a new presentation with audio tracks where you will hear the voices of Oscar Alonso and Teresa Arlaban introducing and highlighting the most important aspects of our work.
We apologize for any inconvenience and hope you find our work interesting and useful. At the end of the presentation you will see our contact email. Feel free to contact us for any question or doubt.
Our Best Regards.
Óscar Teresa Alberto Alejandro
Introduction- TSO – DSO Grid Requirements:
- Voltage support: Normal and Transients.- International approach.- Compliance of: turbines and subs controls
- AW turbine capabilities (AW1500/3000)
- Reactive power & LV/HV RT capabilities
- Substation level voltage control.
- Last experience: Waubra - Australia.
- Future trends: Preliminary research results.
1GRID SUPPORT REQUIREMENTS
- Every country establishes distinct specs.
- Different requirements for transmission or distribution lines.
- Current demands mainly focused on following aspects:
- Normal operation – small voltage variations.
- Transients: LVRT and HVRT.
- Quality: Flicker, harmonics, unbalance, etc
- Protections.
- Metering .
1 .- Scope of the current operator demands
1GRID SUPPORT REQUIREMENTS
- Normal demands:
- 5% voltage steps response in 1 to 5 s.
- Reactive power range: +/- 35% Rated Power.
- Operation on voltage range (PCC): +/- 15%.
- Set point accuracy higher than 0.5 %.
2 .- Voltage Controls
3.- LVRT – International Comparison – Balance/unbalance
AWP technology
1GRID SUPPORT REQUIREMENTS
4.- Implications
1GRID SUPPORT REQUIREMENTS
- Turbine level:
- Increased reactive power range (40%).
- Efficient reactive power management.
- Improved LVRT/HVRT techniques.
- Substation Level:
- Improved technology (control & comms).
2- Variable Speed – Low loads
- Rated Power: 1500 / 3000 kW
- IGBT-Based Power converter.
- Doubly Fed Induction generator:
- 6 pole – 1000 rpm.
- 50 / 60 Hz
- Pitch Control – Hydraulic
- Three-bladed. Horizontal Shaft.
- High Efficiency: 12 kV supply.
ACCIONA WINDPOWER TURBINES: AW1500 / 3000
1 .- General Characteristics
2ACCIONA WINDPOWER TURBINES: AW1500 / 3000
Design - Robust – Reliable - Efficient
AW1500
AW3000
2ACCIONA WINDPOWER TURBINES: AW1500 / 3000
2.- Extended Reactive Power Range: 40%
Curva Nominal Potencia Activa - Potencia Reactiva/Rated Active - Reactive Power curve
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
1600
-700 -600 -500 -400 -300 -200 -100 0 100 200 300 400 500 600 700
Q [kVAr]
P [k
W]
Curva Nominal Potencia Activa - Potencia Reactiva/Rated Active - Reactive Power curve
0
500
1000
1500
2000
2500
3000
-14
00
-12
00
-10
00
-80
0
-60
0
-40
0
-20
0 0
20
0
40
0
60
0
80
0
10
00
12
00
14
00
Q [kVAr]
P [
kW
]
AW1500 AW3000
Increased Reactive Power capability implies:
Increased power converter & generator ratings
3 .- LVRT / HVRT New Torque and Pitch strategy
- Based on “available active power” (depends on the remaining voltage and reactive current injection)
- Available torque is used to damp oscillations.
- Fast Pitching to get pre-calculated steady angle.
2ACCIONA WINDPOWER TURBINES: AW1500 / 3000
Max = 1272.12 rpmMax = 1246.5 rpm
88 rpm 38 rpm
2ACCIONA WINDPOWER TURBINES: AW1500 / 3000
Example (LVRT test)- 90% Volt depth and 2s long.-Turbine load 90%.
2ACCIONA WINDPOWER TURBINES: AW1500 / 3000
3 .- LVRT / HVRT New Torque and Pitch strategy
Old Techniques New Techniques
Consequences- Longer and deeper
voltage dips.- Reduction of
oscillations and mechanical loads.
3VOLTAGE CONTROL – WAUBRA (AUS)
1 .- WAUBRA (AUS) Characteristics & Requirements
- 128 wind turbines model AW1500.
- POI at 220 kV – 2 transformers 220 kV / 66 kV / 150 MW
- Five substations 66 kV / 12 kV.
- Two voltage controllers:
- Transformer 1. 66 kV side.
- Transformer 2. 66 kV side.
- Requirements:
- Response for voltage steps of 5% in less than 5 secs.
- Reactive capacity +/- 30% Rated Power.
2 .- Voltage Control Principles
Comms: 200 ms polling cycle
Parameters:KpTiFilter
3VOLTAGE CONTROL – WAUBRA (AUS)
3 .- Set point step tests
Set Point steps
Pink – Substation Reactive powerBlue – Substation Voltage
Saturation
3VOLTAGE CONTROL – WAUBRA (AUS)
4.- Transformer Tap changer tests
Transformer Tap changer test
Pink – Substation Reactive powerBlue – Substation Voltage
2 - 3 s max response time
3VOLTAGE CONTROL – WAUBRA (AUS)
5 .- Coordination after LV or HV faults (Now, standard)
Smoothed reactive power restorationRamp up/down 30 to 50 kVAr/s
LV event – 0.5 s (real measurement)
Sub Control Sub ControlTurb Control
3VOLTAGE CONTROL – WAUBRA (AUS)
1 .- Improved Voltage control
- Same control for weak (SCR<2) or strong grids (SCR>10).
- Detection of the grid characteristics:
- Fast grid impedance selection method.
- Fast estimation algorithm of the Thevenin grid voltage.
- Principle of operation: Steady-state pre-calculated response.
- Accurate, robust and safe even with long polling times.
- Patents pending.
4FUTURE DEVELOPMENTS
4FUTURE DEVELOPMENTS
1 .- Improved Voltage control (1 – 2 s response)
Set Point changes
RX grid change (SCR 20 to less than 4!)
Grid voltage changes
4FUTURE DEVELOPMENTS
2 .- Accredited Grid Integration field test report
Field tests to demonstrate grid code compliance.
Certified Laboratory testing and accredited procedure
(international acceptability).
- Turbine level:
- LVRT and HVRT according to most exigent grid codes.
- Active power management: Primary, inertial response, power reserve.
- Protections. Harmonics. Flicker. Islanding. Etc.
- Substation level:
- Voltage control.
- Global active power controls: Frequency, others.
- Protections. Harmonics. Flicker. Islanding. Etc.
CONCLUSSIONS
AWP Grid Voltage support :
AW1500 and AW3000 Turbines:
Improved LVRT / HVRT behavior.
Extended Reactive Power range.
Substation: Accurate and reliable hardware and controls
(improved close future solutions, R&D benefits).
Acciona WindPower commitment to demonstrate Full Grid
Code compliance through real and accredited field testing.
THANK YOU SO MUCH FOR YOUR ATTENTION
• Contact Email:
• And visit our stand for personal assistance or guidance.