AASHTO SCoC 2007 -...
Transcript of AASHTO SCoC 2007 -...
AASHTO SCoC 2007AASHTO SCoC 2007
Tools for Making Decisions in Project Selection and DeliveryTools for Making Decisions in Project Selection and Delivery
Sid Scott, P.E.Trauner Consulting Services, Inc.
Hosted by MDOTJuly 29 - August 2, 2007
Beau Rivage Resort, Biloxi, Mississippi
2
OverviewOverview
TrendsCaltrans Innovative Procurement Program• Project Delivery Systems• Decision Drivers for Project Delivery• Selection Tools
Lessons LearnedResources
3
DOT RealityDOT Reality
High attrition (loss of experience)Limited resources (changing environment)Growing funding gapChanging capital programsPublic expectations
4
Project DeliveryProject Delivery
Overall process by which a project is:Designed, Constructed, and/orMaintained, Operated, Financed
5
Project Delivery SystemsProject Delivery Systems
Design-Bid-Build (Traditional)Innovative Alternatives (Caltrans):• Design Sequencing• CM @ Risk • Design-Build
• Low Bid• Best-Value
6
Project Delivery SystemsProject Delivery Systems
Design-Bid-Build ID/IQ
Design-Build
CM at-Risk
Public Sector Model: Private Sector Model:• Separation of Services for Design and Construction
• Owner retains risk of performance
• Single Entity provides Integrated Services
• Design• Construct• Operate• Maintain• Finance
• Contractor assumes greater risk of performance
AlliancingDesign-Sequencing
Public-Private PartnershipsAgency CM
7
Decision Drivers for Alternative Project DeliveryDecision Drivers for Alternative Project Delivery
Accelerate DeliverySingle Point ResponsibilityReduce Owner StaffingEarly Cost CertaintyReallocate riskMinimize impacts to publicPotential for lower costs or lower maintenance (Life Cycle Cost)Increase qualityInnovate
8
Design-Bid-BuildDesign-Bid-Build
Design must be 100% complete to begin constructionOwner can best manage risk (third party coordination, etc.)Prescriptive specifications
Well established and understoodClearly defined rolesSuitable for competitive biddingNo legal barriers in procurement
Owner
Designer Constructor
Advantages
Project Criteria
9
Design SequencingDesign Sequencing
Linear projects or repetitive design featuresConcurrent design and construction possibleMinimal third party issues
Fast-tracking (early construction)
Owner
Designer Constructor
Advantages
Project Criteria
10
CM at-RiskCM at-Risk
Complex projects with multiple phasesLimited time or funding constraintsProjects that are difficult to define or subject to change
Transfer construction cost/performance risks to CM (GC)Opportunity for fast-trackingGMP w/ shared savings provides incentive to control cost/time
Owner
Designer CM
Advantages
Project Criteria
Sub Sub Sub
11
Design-Build (Low Bid)Design-Build (Low Bid)
Small to medium projectsMinimal third party (ROW, utility) complicationsTime sensitive (user impacts)Greater design detail (more prescriptive specifications)
Accelerate (fast-track) deliverySingle point responsibility for final design, construction, and other services
Owner
Design-Builder
Advantages
Project Criteria
12
Design-Build (B-V)Design-Build (B-V)
Medium to large projectsOpportunity for innovation Time sensitive (user impacts)Less design detail (scope can be defined using performance requirements)More time/cost for procurement (two-step)
Accelerate (fast-track) deliveryEarlier cost and schedule certaintySingle point responsibilityMore risk allocated to D-BuilderPotential for innovation and reduced life-cycle $
Owner
Design Builder
Advantages
Project Criteria
18
Worksheet 2Worksheet 2
Align project success criteria with project delivery objectives or drivers
21
Lessons LearnedLessons Learned1. Alternative delivery methods not appropriate for
every project2. If used for the right project, alternative delivery
methods can help achieve project goals• Reduced Cost• Accelerated delivery• Innovation• Enhanced quality/performance
3. Systematic decision making improves potential for success
22
Additional ResourcesAdditional ResourcesNHI Course No. 134058 – Alternative ContractingFHWA Websites:• Program Administration
• http://www.fhwa.dot.gov/programadmin/contracts/• Alternative Contracting Community of Practice
• http://knowledge.fhwa.dot.gov/cops/hcx.nsf/home?openform&Group=Alternative%20Contracting
• National Highway Specification Website• http://www.specs.fhwa.dot.gov
The Fifth Edition of the AASHTO Primer on Contracting for the 21st Century
• http://construction.transportationAASHTO D-B Taskforce website http://designbuild.transportation.org/?siteid=63
23
Additional Resources (cont’d)Additional Resources (cont’d)
Caltrans Innovative Procurement project websitehttp://construction.colorado.edu/Caltrans-Ipp/Desktop.aspx?tabId=5
Representative alternative contracting websites
• Florida DOT http://www.dot.state.fl.us/construction/altcontract.htm
• North Carolina http://www.ncdot.org/doh/preconstruct/altern/design_build/default.html
• Oregon DOT http://www.oregon.gov/ODOT/HWY/OPD/DBprojects.shtml
• Virginia DOT http://www.virginiadot.org/business/design-build.asp
• Washington State DOT http://www.wsdot.wa.gov/Projects/delivery/alternative/
• Minnesota DOT www.dot.state.mn.us/const/tools/innovativecontract.html
• Arizona DOT http://www.azdot.gov/Highways/ConstGrp/DesignBuildGuide.asp
AASHTO SCoC 2007AASHTO SCoC 2007
Questions?
Sidney Scott, P.E.Trauner Consulting Services, [email protected]