A Model for Sustainable Development of Grid Connected ...reee.sacities.net/sites/default/files/Tech...
Transcript of A Model for Sustainable Development of Grid Connected ...reee.sacities.net/sites/default/files/Tech...
“ A Model for Sustainable Development of Grid Connected Renewable Energy in Vietnam ”
submitted by
Tran Hong Ky
M.Sc.-Thesis submitted as a partial fulfilment of the requirements for the degree
of
“ Master of Science (M.Sc.) in Energy Systems and Management “
SESAM - Sustainable Energy Systems and Management International Institute of Management
University of Flensburg, Germany
March 2003
ii
TABLE OF CONTENTS
CURRENCY EQUIVALENTS AND UNITS OF MEASURE .................................................................. VI
ACRONYMS AND ABBREVIATIONS.................................................................................................... VII
ACKNOWLEDGEMENTS.......................................................................................................................VIII
SUMMARY REPORT .................................................................................................................................. IX
ZUSAMMENFASSUNG............................................................................................................................. XII
1 BACKGROUND................................................................................................................................... 1
2 OBJECTIVE......................................................................................................................................... 3
3 METHOD AND METHODOLOGY .................................................................................................. 3
3.1 FIELD RESEARCH ............................................................................................................................... 3
3.2 METHOD AND METHODOLOGY........................................................................................................... 4
4 SOCIO - ECONOMIC SITUATION OF GIAP TRUNG COMMUNE.......................................... 7
5 LOAD DEMAND FORECAST......................................................................................................... 15
PRODUCTIVE USE ..................................................................................................................................... 18
6 HYDROPOWER POTENTIAL, SCHEME COMPONENTS AND COST ESTIMATION....... 22
6.1 HYDROPOWER POTENTIAL............................................................................................................... 22
6.2 HYDROPOWER COMPONENTS........................................................................................................... 26
6.3 COST ESTIMATION ........................................................................................................................... 29
7 OPTIMIZATION OF HYDROPOWER SCHEME........................................................................ 31
7.1 EXCEL MODEL ................................................................................................................................. 32
7.2 ECONOMIC ELECTRIFICATION COST ................................................................................................ 34
7.3 ECONOMIC BENEFIT OF INVESTMENT............................................................................................... 38
7.4 SUM UP ............................................................................................................................................ 40
8 ALLOCATION AND MOBILIZATION OF CAPITAL INVESTMENT.................................... 40
8.1 ALLOCATION OF INVESTMENT ......................................................................................................... 40
8.2 MOBILIZATION OF INVESTMENT CAPITAL ........................................................................................ 42
9 INSTITUTIONAL ISSUES............................................................................................................... 45
9.1 INSTITUTIONAL FRAMEWORK FOR POWER SECTOR .......................................................................... 45
9.2 NEW ELECTRICITY LAW AND THE IMPACT........................................................................................ 46
9.3 APPLICATIONS AND APPROVALS ...................................................................................................... 47
9.4 INSTITUTIONAL DEVELOPMENT ....................................................................................................... 48
iii
10 LEGAL FRAMEWORK FOR SETTING UP ENTERPRISE....................................................... 49
11 ECONOMIC AND FINANCIAL EVALUATION.......................................................................... 53
11.1 TARIFF STRUCTURE.................................................................................................................... 53
11.2 ECONOMIC EVALUATION............................................................................................................ 57
11.3 FINANCIAL ANALYSIS ................................................................................................................ 59
12 BUSINESS PLAN............................................................................................................................... 64
12.1 MARKETING PLAN ..................................................................................................................... 64
12.2 PRODUCTION PLAN .................................................................................................................... 65
12.3 ORGANIZATION & MANAGEMENT PLAN .................................................................................... 69
12.4 FINANCIAL PLAN........................................................................................................................ 69
12.5 COMMUNITY MOBILIZATION ...................................................................................................... 75
13 EXPECTED SOCIAL IMPACT OF HYDRO POWER SYSTEM ............................................... 76
14 RISK AND MEASURES TO OVERCOME RISK ......................................................................... 79
15 CONCLUSION AND RECOMMENDATION................................................................................ 81
BIBLIOGRAPHY ......................................................................................................................................... 84
APPENDIX 1 ................................................................................................................................................. 86
APPENDIX 2 ............................................................................................................................................... 103
APPENDIX 3 ............................................................................................................................................... 106
APPENDIX 4 ............................................................................................................................................... 118
APPENDIX 5 ............................................................................................................................................... 129
APPENDIX 6 ............................................................................................................................................... 146
iv
LIST OF TABLES
Table 4.1: Ranking of Development Priorities.................................................................... 12
Table 5.1: Typical household's electricity consumption profile.......................................... 17
Table 5.2: Electricity demand for Public/ services use ....................................................... 17
Table 5.3: Power demand for wood processing .................................................................. 18
Table 6.1: Main hydrology parameters................................................................................ 25
Table 6.2: Cost estimation................................................................................................... 30
Table 7.1: Economic Electrification Cost ........................................................................... 37
Table 7.2: Economic Benefit for Investment....................................................................... 39
Table 11.1: Purchasing tariff for Srok Phu Mieng hydropower .......................................... 57
Table 11.2: Economic avoided cost to EVN ...................................................................... 58
Table 11.3: Economic Sensitivity Analysis......................................................................... 59
Table 11.4: Financial Sensitivity Analysis .......................................................................... 63
Table 12.1: Maintenance Schedule for Civil Work............................................................. 66
Table 12.2: Investment Capital Contribution ...................................................................... 70
Table 12.3: Loan payment schedule .................................................................................... 71
Table 12.4: Yearly Cash Flow Statement............................................................................ 72
Table 12.5: Profit and Loss Statement ................................................................................ 73
Table 12.6: Balance Sheet ................................................................................................... 74
Table 12.7: Break-even point .............................................................................................. 75
v
LIST OF FIGURES
Figure 3.1: Location map of Giap Trung commune.............................................................. 6
Figure 4.1: Village map of Giap Trung ................................................................................. 7
Figure 4.2: Distribution of Ethnic group ............................................................................... 8
Figure 4.3: Paddy rice in Giap Trung.................................................................................. 10
Figure 4.4: Proportion of household by well-ranking ......................................................... 10
Figure 4.5: Household Income Distribution........................................................................ 11
Figure 4.6: Pico using in Giap Trung .................................................................................. 13
Figure 4.7: Time for wood collecting of women................................................................. 14
Figure 5.1: Electricity demand for Giap Trung commune .................................................. 19
Figure 5.2: Daily load curve for the commune................................................................... 20
Figure 5.3: Energy demand projection ................................................................................ 21
Figure 5.4: Peak load projection.......................................................................................... 21
Figure 6.1: Catchment area of Giap Trung hydropower ..................................................... 23
Figure 6.2: Hydrological data for Giap Trung Hydropower ............................................... 24
Figure 6.3: Head loss and Turbine Efficiency..................................................................... 24
Figure 6.4: Power duration curve ........................................................................................ 25
Figure 6.5: Longitudinal cross section of Giap Trung hydropower .................................... 27
Figure 6.6: Location diagram of mini hydropower and transmission/distribution.............. 29
Figure 6.7: Comparison unit cost of small hydropower in Vietnam ................................... 30
Figure 6.8: Breakdown of Investment Cost......................................................................... 31
Figure 7.1: Excel Model Diagram .................................................................................... 33
Figure 7.2: Economic Electrification Cost .......................................................................... 38
Figure 7.3: Economic Benefit for investment ..................................................................... 40
Figure 8.1: Allocation of Investment Cost .......................................................................... 41
vi
Figure 10.1: Organization structure of Jointly Owning Utility ........................................... 50
Figure 10.2: Organization structure of Liability Limited Company ................................... 51
Figure 11.1: Economic Sensitivity Analysis ....................................................................... 59
Figure 11.2: Financial Sensitivity Analysis......................................................................... 64
Figure 12.1: Investment Capital contribution...................................................................... 69
Figure 12.2: Company capital requirement ......................................................................... 70
Currency Equivalents and Units of Measure
Currency Unit = Vietnamese Dong (VND)
VND 1,000 = US$0.065
US$1 = VND 15,400
Kg Kilogram
kVA Kilovolt Amp。
kW Kilowatt
km Kilometer
km2 Square Kilometer
m Meter
m2 Square meter
m3 Cubic meter
Mw Megawatt
ton Metric ton
vii
Acronyms and Abbreviations
BARD Bank for Agriculture and Rural Development EIRR Economic Internal Rate of Return EVN Electricity of Vietnam FID Fund for Investment Development FIRR Financial Internal Rate of Return GEF Global Environmental Facility GOV Government of Vietnam IOE Institute of Energy IPP(s) Independent Power Producer(s) FIRR Financial Internal Rate of Return JICA Japan International Cooperation Agency JIBIC Japan International Bank for International Cooperation LV Low Voltage MOI Ministry of Industry MOU Memorandum of Understanding MV Medium Voltage NPV Net Present Value O&M Operation and Maintenance PBP Pay Back Period PCF Protocol Carbon Fund PECC1 Power Engineering Consulting Company 1 PPA Power Purchasing Agreement SIDA Swedish international Development Agency SPP(s) Small Power Producers SPPA Standard Power Purchasing Agreement US$ U.S. dollar VND Vietnamese Dong WB World Bank
viii
Acknowledgements
I would like to convey my sincere gratitude to the German Academic Exchange Service
(DAAD) for the their support, which enabled me to pursue my post graduate on the
master’s course “Sustainable Energy Systems and Management” (SESAM), University of
Flensburg, Germany.
I would like to extend my deep appreciation to Professor Uwe Rehling for invaluable
contribution provided during my Master Dissertation work.
My sincere thanks goes to Dip. Ing. Wulf Boie for his regular guide, suggestion and
constructive feedback in my Master Dissertation work.
I would like to thank my teachers Dipl. Soz. Dorsi Germann, Ms. Christiane Delfs, Dr.
Roland Menges and Dr. Olav Hohmeyer for the knowledge I gained from them.
I specifically want to thank Mr. Alex Arter (Director of Entec AG), Mr. Ho Hao (PECC1),
Mrs. Tran Hai Anh (PECC1), and all my friends in Vietnam for their support during my
field research.
My thanks also goes to all my classmates and German students namely Stefan, Matthias
for their friendship provided to me during my staying in Germany.
Finally, I deeply thank my family members for always being with me, providing me their
support and encouragement for the study.
ix
Summary report
Vietnam is well endowed with hydropower resources, of which small hydropower is
experienced the cheapest and most reliable renewable energy sources, currently available
in Vietnam. However, exploitation of the renewable energy is still limited.
Renewable could play a significant role in electricity generating to provide to rural areas
aiming to improve their standard of living and encourage income generating activities. One
part of the ambitious Rural Electrification Program, which is carried out by Government of
Vietnam (GOV) and World Bank (WB), is to develop grid connected small hydropower.
The hydropower will provide electricity at relatively low price to local residents who are
not being able to access to electricity or are supplied by diesel generation with high cost,
and feed supplemental electricity into the national grid. GOV expects these projects will be
developed by non-utility investors. Participation of private sector will create a new form of
ownership and investment to Vietnam’s power sector that concerns investors, local
residents and GOV/Electricity of Vietnam (EVN).
The objective of the study is (i) to verify the feasibility and sustainability of the new
investment model in Vietnam in meaning of technical, legal and institutional, social-
economic and financial, and (ii) to analyze role of participants to assure sustainable
development of the model. Furthermore, the needed measure to promote development and
minimize the risk to the investment also discussed and recommended in detail.
To facilitate the study a hydropower potential site at Giap Trung commune, Northern
province of Ha Giang, Vietnam is taken into consideration.
Giap Trung is one of the poorest communes in Ha Giang province that listed among
communes being connected to national grid after 20101. While the power demand is very
low, the commune has considerable hydropower potential, which could be exploited to
provide electricity to the commune and feed supplementary energy into national grid.
To answer the question which option should be selected to electrify the commune, a
comparison is made for four possible options namely “Grid connected hydropower”, “Off
grid hydropower”, “connection to national grid” and “diesel generator”. The selected
1 According to the Master Plan Study in Rural Electrification, IoE, 1999,
x
option should have the lowest cost for electrifying the commune. Based on the criterion the
option “grid connected hydropower” is selected since requiring the lowest cost (unit cost
3,980 VND/kWh and economic cost for electrification VND 6,012 million). From
investment point of view, however, the best option means creating maximum benefit to
society. Two alternatives, “grid connected hydropower” and “off grid hydropower”, which
could be used to exploit hydropower potential, were considered to find out the optimum
option for investment. The option “grid connected hydropower” is one time again to be the
better one (NPV = VND1, 593 million, IRR = 12.2% and unit cost 936 VND/kWh, 5 times
lower than that of compared alternative). Therefore, a grid-connected hydropower, which
will supply electricity to the commune and feed surplus power to national grid, is selected
for Giap Trung site.
According to Decree 45/2001/ND-CP2, of total VND 1,006.5 million investment cost for
the project, the investor, who acts as Small Power Producer (SPP) will contribute VND
5,852 million for hydropower plant and transmission lines to national grid. GOV and local
households will contribute the remaining, for the commune grid. To maximize benefit to
local households and assure the project could be well implemented, the commune grid is
supposed to be constructed and managed by the SPP. In order to meet investment capital
born by investor, SPP could mobilize from any possible source. The study, base on the
current situation in Vietnam, has dealt with the issue to find out the most possible financial
arrangement for the project.
Participation of private investors in power sector is new in Vietnam. This creates new form
of ownership and investment. Therefore, legal and institutional issues have been touched
upon. A number of legal company form are analyzed to find out the most suitable for the
project, that is Jointly Owning Utility forming by private investor and Ha Giang People
Committee. Basis points, processes, procedures, and approval for setting up a private
enterprise doing business in power field are also dealt with.
In order to evaluate the feasibility of the project on economic and financial aspect, a
comprehensive economic and financial appraisal has been done. Tariffs for retail sale to
local households is determined at level 1200 VND/kWh, which bases on willingness and
able to pay for the service of the local households and should cover the production cost of
2 Construction Publish House, Hanoi 2001, p. 39
xi
supplier. The economic benefit of power fed into national grid is valued equal to avoided
cost of EVN. Due to no SPPA available at present then the tariff at the rate of 582
VND/kWh on average, that is applied to other existing SPP in Vietnam, is used for Giap
Trung project Calculation results show that the project is economically viable (NPV =
VND 3,070.6 million, EIRR = 15.2% and Unit cost = 850.8 VND/kWh) bringing high
benefit to the whole economy. From financial view, the project is attractive investor since
having quite high financial indicators (NPV = VND 306.7 million, FIRR = 13.8% and Unit
cost = 618 VND/kWh). However the project will more attractive to investor if the tariff is
set equal to avoided cost for energy of EVN. In additional, sensitivity analysis also has
been done to verify the viability of project in reference cases.
In order to have a closer sight to the project, a business plan for the enterprise is set up.
Due to connect to national grid then project can sell 100% annual output at any year. Issues
on operation, repair and maintenance, training, billing and money collection have been
concerned. Especially, PPA(s) to households and to EVN are also dealt with. Financial
plan bring a more detail picture of financial statement presenting quite strong and stable
situation of the enterprise.
Along with development of the power project, community mobilization has to be done in
order to (i) maximize socio-economic benefit of the power plant; (ii) minimize risk. It
requires local resident, who are real beneficiaries, to participate in project promotion,
project preparation and project implementation actively and positively.
The social impacts of the project are generally positive. The project is seen to improve
standard of living of local households, and a key component in promoting the local
economic development. The people are provided a better service with lower cost compared
the energy sources currently used in the commune. Furthermore, they do not have to wait
for at least 7 year to connect to national grid.
In conclusion, the development model for Giap Trung grid connected hydropower is
feasible and sustainable, expected to be extended to other projects in Vietnam. It is
recommended that GOV, one of the participants and also market enabler, need to play
more active role, balancing interest among participants and have necessary measures to
promote the development model.
xii
Zusammenfassung
Vietnam ist mit Wasserkraft-Ressourcen gut ausgestattet, wobei eine Mikro-
Wasserkraftnutzung sich als die günstigste und verlässlichste Art der erneuerbaren
Energien, die zur Zeit in Vietnam realisierbar sind, herausgestellt hat. Allerdings sind die
Nutzungsmöglichkeiten erneuerbarer Energien dort immer noch begrenzt.
Erneuerbarkeit könnte eine wichtige Rolle bei der Energie-Erzeugung zur Versorgung
ländlicher Gebiete spielen. Dies soll dem Ziel dienen, eine Verbesserung der
Lebenssituation der Menschen in diesen Regionen zu erreichen. Eine Ziel des ehrgeizigen
Programms zur Elektrifizierung der ländlichen Gebiete, das von der vietnamesischen
Regierung und der Weltbank durchgeführt wird, ist es, ein durch Mikro-
Wasserkraftnutzung gespeistes Stromnetz aufzubauen. Dieses soll Haushalte, die ansonsten
keinen Zugang zum Stromnetz haben bzw. durch teuren Dieselkraftstoff versorgt werden,
und zusätzlich das nationale Stromnetz speisen. Die vietnamesische Regierung geht davon
aus, dass diese Vorhaben durch Investoren außerhalb der
Elektrizitätsversorgungsunternehmen entstehen wird. Die Beteiligung der Privatwirtschaft
wird für neue Eigentums- und Investitionsstrukturen im Bereich der vietnamesischen
Stromversorgung sorgen.
Die Zielsetzung der Untersuchung ist es (i), die Durchführbarkeit und die
Zukunftsfähigkeit des neuen Investitionsmodells in Bezug auf technische, gesetzliche,
institutionelle, sozio-ökonomische und finanzielle Belange und (ii) die Funktionen der
Beteiligten zu analysieren, um eine zukunftsfähige Entwicklung des Modells sicher zu
stellen. Des weiteren werden das notwendige Ausmaß an Förderung für die Entwicklung
und die Minimierung der Investitionsrisiken detailliert erörtert.
Um die Untersuchung zu stützen, wird ein Gelände mit Wasserkraftpotential bei der Giap
Trung-Kommune, der nördlichen Provinz von Ha Giang in Vietnam genauer betrachtet.
Giap Trung ist eine der ärmsten Kommunen der Ha Giang-Provinz und eine der
Kommunen, die erst im Jahr 2010 für den Anschluss an das nationale Stromnetz
vorgesehen ist. Da der Energiebedarf sehr gering ist, hat diese Kommune ein beträchtliches
Wasserkraft-Potential, was genutzt werden könnte, um die Kommune zu versorgen und
damit zusätzlich das nationale Stromnetz zu speisen.
xiii
Um die Frage zu beantworten, welche Möglichkeit gewählt werden sollte, un die
Kommune zu elektrifizieren wird ein Vergleich der vier Möglichkeiten erstellt. Diese sind
"Wasserkraftnutzung mit Anschluss ans Stromnetz", "Wasserkraftnutzung ohne Anschluss
ans Stromnetz", "Anschluss an das nationale Stromnetz" und "Nutzung eines
Dieselgenerators". Die gewählte Alternative sollte die geringsten Kosten für eine
Elektrifizierung der Kommune aufweisen. Basierend auf diesem Kriterium wurde die
"Wasserkraft mit Anschluss ans Stromnetz" gewählt(Kosten der Einheiten: 3.980
VND/kWh und Kosten für die Elektrifizierung VDN 6,012 Millionen. Aus dem
Blickwinkel der Investitionsmaßnahmen ist die beste Möglichkeit jedoch der
größtmögliche Nutzen für die Gesellschaft. In Bezug auf diesen Gesichtspunkt sind die
"Wasserkraftnutzung mit Anschluss ans Stromnetz" sowie "Wasserkraftnutzung ohne
Anschluss ans Stromnetz" die geeignetsten. Wiederum ist die erstgenannte Alternative die
beste (NPV= VND1,593 Millionen, IRR= 12,2% und Kosten der Einheiten: 936
VND/kWh, fünfmal weniger als bei den verglichenen Möglichkeiten). Daher wurde die
"Wasserkraftnutzung mit Anschluss ans Stromnetz" mit Nutzung der überschüssigen
Energie für das nationale Stromnetz als die geeignetste für das Giap Trung-Gelände
gewählt.
Gemäß der Verfügung 45/2001/ND-CP , von insgesamt 1,006.5 Millionen VND
Investitionskosten für das Projekt wird der Investor, der als "Small Power Producer" agiert,
5,852 Millionen VND für Wasserkraftanlagen und Fernleitungen zum nationalen
Stromnetz SPP) beisteuern. Die restliche Summe wird von der Regierung und den lokalen
Haushalten geleistet. Um den Nutzen für die lokalen Haushalte zu maximieren und
sicherzustellen, dass das Projekt gut umsetzbar ist, soll das kommunale Stromnetz offenbar
von der SPP erläutert und gemanagt werden. Die Untersuchung, die auf der momentanen
Situation in Vietnam basiert, hat sich mit dem Sachverhalt beschäftigt, wie man das
bestmögliche finanzielle Arrangement für das Projekt schafft.
Die Beteiligung privater Investoren auf dem Energiesektor ist neu in Vietnam. Diese führt
zu neuen Formen von Eigentum und Investition. Daher wurden im Anschluss auch
rechtliche und institutionelle Voraussetzungen angerissen. Es werden verschiedene
Rechtsformen analysiert, um die geeignetste für das Projekt zu finden. Als sinnvollste
stellte sich die "Jointly Owning Utility" heraus, bei der es mehrere Teilhaber gibt. In
diesem Fall sind dies mehrere Privatinvestoren und das Ha Giang People Committee.
xiv
Verschiedene Arbeitsverfahren und das Erhalten einer Genehmigung für ein Unternehmen,
das Geschäfte auf dem Energiesektor macht, wurden ebenfalls behandelt.
Um die Umsetzbarkeit des Projekts hinsichtlich der finanziellen und ökonomischen
Aspekte zu bewerten, wurde eine umfassende ökonomische und finanzielle Einschätzung
vorgenommen. Die Tarife für den Einzelhandelsverkauf an die lokalen Haushalte wurde
auf den Level 1200 VND/kWh, die auf der Bereitschaft und Zahlungsfähigkeit der lokalen
Haushalte basiert, für den Service zu bezahlen. Dies sollte die Produktionskosten der
Lieferanten abdecken. Der ökonomische Nutzen der ins nationale Stromnetz gespeisten
Energie wird gleich hoch bewertet wie die vermiedenen Kosten von EVN. Infolge der
Tatsache, dass dort zur Zeit kein SPPA verfügbar ist, wurde die Tarifrate von 582
VND/kWh, die im Durchschnitt für die in Vietnam existierenden SPPs gelten, für die
Berechnungen bezüglich Giap Trung zugrunde gelegt. Die Kalkulationen zeigen, dass das
Projekt machbar ist und für die ganze Wirtschaft von Nutzen sind (NPV =VND 3,070.6
Millionen, EIRR =15.2% und Einheitskosten = 850.8 VND/kWh). Unter finanziellen
Gesichtspunkten ist das Projekt ebenfalls attraktiv, da die Investoren hohe finanzielle
Indikatoren haben (NPV =VND 306.7 Millionen, FIRR =13.8% und Einheitskosten
VND/kWh). Zusätzlich wurde auch eine Anfälligkeits-Analyse erstellt, um die
Zukunftschancen des Projekts auch in dieser Hinsicht zu erörtern.
Um einen noch genaueren Blick auf das Projekt zu haben wurde ein Geschäftsplan erstellt.
Da es an das nationale Stromnetz angeschlossen ist, kann es 100 % der Leistung in jedem
Jahr absetzen. Arbeitsverfahren , Reparaturen, Schulungen, Instandhaltung, Abrechnungen
und das Sammeln von Geld sind weitere Gesichtspunkte, unter denen das Projekt
beleuchtet wird. Ein Finanzplan führt zu einem noch detaillierteren Bild von einem starken
und stabilen Unternehmen.
Einhergehend mit der Entwicklung des Energieprojekts, muss auch das gesamte Umfeld
mobilisiert werden, um den sozio-ökonomischen Nutzen der Energiekraft-Anlage zu
maximieren (i) und das Risiko zu minimieren (ii). Es bedarf des aktiven und positiven
Einsatzes der Beteiligten und Begünstigten für dieses Projekt hinsichtlich der Werbung,
der Vorbereitung und der Durchführung.
Die sozialen Auswirkungen des Projekts sind allgemein positiv. Das Projekt soll den
Lebensstandard der privaten Haushalte verbessern und eine Schlüsselkomponente beim
Antreiben der lokalen ökonomischen Entwicklung sein. Den Menschen wird ein besserer
xv
Service mit niedrigeren Kosten geboten, wenn man sie mit der derzeit üblichen
Energieversorgungen in der Kommune vergleicht. Des weiteren müssen die Betroffenen
nicht mindestens sieben Jahre warten, um an das nationale Stromnetz angeschlossen zu
werden. Abschließend lässt sich feststellen, dass das
Entwicklungsmodell von Wasserkraft mit Anschluss ans Stromnetz für Giap Trung
umsetzbar und zukunftsträchtig ist. Man kann davon ausgehen, dass es auf weitere Teile
Vietnams ausgedehnt wird. Es wird empfohlen, dass die Regierung Vietnams, einer der
Mitwirkenden und gleichzeitig Markt-Ermöglicher, eine aktivere Rolle einnimmt, um die
Interessenlagen unter den Beteiligten auszubalancieren und die Entwicklung des Modells
mit dem notwendigen Ausmaß zu unterstützen.
1
1 Background
Vietnam is well endowed with hydropower resources, particularly in the hilly and
mountainous areas in the northwest of the country. Small hydropower is experienced the
cheapest and most reliable renewable energy sources, currently available in Vietnam that
likely will form a major part of the Renewable Energy Component. The technical potential
for small-scale hydro generation (under 10 MW per site) is estimated about 800 -1400MW,
of which 400-600 MW could be connected to the national grid. However only 10% of the
potential has been exploited so far3.
Renewable could play a significant role in electricity generating to provide to rural areas
aiming to improve their standard of living and encourage income generating activities. One
part of the ambitious Rural Electrification Program, which is carried out by Government of
Vietnam (GOV) and World Bank (WB) aiming to electrify 90% of ten million households
living in rural area by 2010, is to develop grid connected small power plants based on
Renewable Energy, especially on small and mini hydropower. These hydropower plants will
provide electricity at high quality to local residents who are not being able to access to
electricity or are supplied by diesel generation with high cost, and feed supplemental
electricity to the national grid.
GOV expects these projects, based on commercial manner, will attract participation of non-
utility investors such as local authorities, local enterprises or private investors. By promoting
the involving of non-utility investor in these small grid connected hydropower projects,
GOV aims (i) To exploit the renewable energy potential to provide electricity to local
household at relatively low cost, and to supplement grid supply, (ii) To reduce financial
burden to state budget for rural electrification and extension of generation capacity4, (iii) To
involve private sector in promoting renewable energy development in Vietnam, and (iv) to
replace the existing model, which has bad reputation in developing small and mini
hydropower in the past due to not clear ownership, poor operation and maintenance, and
high cost resulting from very low demand in rural areas.
3 Bogach, 2000, p. 7
4 Annually EVN needs about US$ 2 billion investment capital during period 2002-2010. Sources www.vnexpress.net. Printed on 15.11.2002
2
In order to realize the target, GOV with great effort, is going to approve a new Law of
Electricity by the end of 2003 that will generate a solid legal ground and institutional issues
for such kind of investment. Particularly, a Standard Power Purchasing Agreement (SPPA)
for Small Power Producers (SPPs), which deals with purchase tariff, term of agreement and
other related issues, will be published and applied for all SPPs. Preferential policy on tax,
capital mobilization, etc is also expected to be touched upon.
In fact such kind of the projects has been received interest of quite a lot of private investors.
Participation of private sector will create a new form of ownership and investment to
Vietnam’s power sector that concerns investors, local residents and GOV/Electricity of
Vietnam (EVN). Attractiveness of the projects to investors is scaled by gained profit, while
for the local resident is impacts of the project to their life and GOV/EVN is to exploit
renewable energy potential available and using efficiently scarce national resources.
Sustainability of a development model is archived only when having feasible project and
satisfying interests of its participants.
In that context, the study is carried out to (i) evaluate the feasibility and sustainability of the
new development model in meaning of legal and institutional, social, and economic and
financial aspects, and (ii) to analyze role of the participants to assure sustainable
development of the model. Furthermore, the needed measure to promote development and
minimize the risk to the investment also discussed and recommended in detail.
To support the study, a potential hydropower site located at Giap Trung Commune, Bac Me
district, North province of Ha Giang was selected as a case study. Giap Trung is one of the
poorest communes in Ha Giang province that listed among communes being connected to
national grid after 20105. It is supposed that a mini hydropower scheme with 244 kW
installed capacity will be constructed by private investor aiming to electrify the commune
and feed supplementary electricity to national grid, 7.5 km distance. Electrifying 564
households in the commune will help to improve their living condition and promote
economic development in the area.
5 According to the Master Plan Study in Rural Electrification, IoE, 1999,
3
2 Objective
The objective of the study is to evaluate feasibility and sustainability of Giap Trung grid
connected hydropower scheme, which is supposed to be developed by private investor to
electrify the commune in order to improve their standard of living and encourage income-
generating activities and to feed supplementary electricity to national grid. In addition the
role of participants, possibility to extend the model in Vietnam and necessary measures to
promote the development model will be studied and recommended as well.
More specifically, the objectives of the study as follows:
(i) To optimize exploitation of the available hydropower potential in term of
economic cost for electrification and economic benefit of investment
(ii) To analyze legal and institutional issues related to Independent Power Producers
(IPPs) in Vietnam, these impact and development.
(iii) To set up a management model for the hydropower project
(iv) Economic and financial appraisal under present situation in Vietnam.
(v) To set up primary business plant for the project aiming has closer sight to
operation and management of the project.
(vi) To anticipate possible social impact of the project to Giap Trung commune, and
(vii) Lesson learned and possibility to apply the model in Vietnam.
3 Method and Methodology
3.1 Field research
Field research had begun officially from October 01st 2002 to December 31st 2002 in Hanoi
and other provinces in Vietnam. A number of field trips have been carried as follows:
(i) One week-visiting un-electrified commune of Giap Trung in Ha Giang province
on the last week of October 2002. Carrying questionnaire and key interview with
community mobilization experts, and site investigation with foreign experts
(ii) Visiting un-electrified commune of Bat Mot in Thanh Hoa province in
November, 2002
4
(iii) Visiting un-electrified commune of Thong Thu in Nghe An province in
November, 2002
(iv) Visiting 3 MW grid connected small hydropower of Yajun Ha, which went in to
commercial operation since 1999 in Gia Lai province
Desk studying and data collection have been carried out in the following organizations:
(i) Power Engineering Consulting Company 1, Hanoi
(ii) Electricity of Vietnam, Hanoi
(iii) Institute of Energy, Hanoi
(iv) Ministry of industry, Hanoi
(v) World bank office in Hanoi
(vi) Department of Industry of Ha Giang Province
(vii) ENTEC AG office in Hanoi
(viii) Workshop on Small Power Project, Hanoi6
3.2 Method and methodology
To conduct the study the following methods and methodology have been used:
(i) Data collection7
(ii) Household questionnaire survey: Household questionnaire was performed in
cooperation with social expert of MOI for 33 households in Giap Trung
commune. The objective of the questionnaire survey is to collect baseline data for
RARE program, which mainly focus on mini hydropower development. The
6 The workshop was organized by MOI & World bank Vietnam with participation of MOI, WB, EVN, Investors and other interests. The workshop is conducted by Steven Ferrey, the Professor of Law at Boston, USA. The main objective of the workshop are (i) Examine the role PPA, (ii) Examine the concept of Avoided Cost in SPP transaction, (iii) To share how other nations designed and implemented PPAs and avoided cost, (iv) To examine opportunities now to use additional available international funds for renewable SPP development in Vietnam, and (v) To share the idea what process and next step would best allow SPP development in Vietnam
7 See Field Research
5
format of the questionnaire for general data is designed by social expert, and for
electricity use is designed by myself.
(iii) Key interview has been done to leaders of “Giap Trung” local Peoples
Committee (a) to have a general picture of the whole commune;(b) to have data
of using energy for productive and public purpose, and; (c) to find out the
development plan of the commune for the coming time. The questionnaire format
was built up by International social expert in cooperation with MOI, PECC1
experts. Several informal “ Key informant interview” have also been done to
experts from IPPs department of MOI, EVN’s department of Business and Rural
Electrification, EVN’s department of Law and Regulation, non-utility investors
and consultants.
(iv) “Appliance saturated method” is used to forecast load demand.
(v) Excel spread sheet is widely used for (1) household data processing, (2)
hydropower potential assessment, (3) Selection of the optimum development
option of the hydro scheme, (4) Economic and financial analysis, and (5)
Financial Plan for Power Enterprise.
(vi) Economic and financial appraisal
6
Figure 3.1: Location map of Giap Trung commune
7
4 Socio - economic situation of Giap Trung Commune
Giap Trung commune is situated 10 km from the district center on a dirty road in poor
condition (passable by four-wheeled vehicle only in the dry season). The national grid runs
along the district road 6.5 km to the south of Giap Trung. The commune is made up
primarily of households relocated here from areas further north (due to the war with China
1979 -1980).
Figure 4.1: Village map of Giap Trung
Giap Trung is a multi-ethnic commune that comprises 5 ethnic minority groups. According
to Ha Giang local authorities, Giap trung is one of the poorest communes in the area that is
given priority to invest on infrastructures such as school, road and electricity in order to
improve livelihood of local people. The total population of the commune is 4490 persons, in
590 households. The Dao are the largest ethnic group (76%) of the population. Tay: 10%;
H’mong: 14%; Kinh: 1%; Hoa: 0.3%.
8
Figure 4.2: Distribution of Ethnic group
Dao75%
Tay10%
H'mong14%
Kinh1%
Hoa0%
The Dao and Tay in Giap Trung commune are quite assimilated with the way of life in the
lowlands, although Kinh language is not widely used and traditional customs continue to be
respected. Despite the distance from village to village is far, people have close relations. It is
quite common to find three generations living in the same house e.g. Grandparent, Parent
and children. The population is relatively young with 52% of people under 18 and the
remaining is 48%.
The literacy rate is reported quite high at 75% and 90% can communicate Kinh language.
Almost children go to school in the commune center or located in villages. However, very
few of them could continue to high school.
The eleven villages are closely linked through both economic relations and marriage ties.
Families and neighbors assist each other during times of hardship, such as lending food on a
no-interest basis. Traditions of communal work are also strong and continue to be
maintained in the villages. Villagers often work together to repair inter-village roads and
pathways, and help each other or exchange labor in building houses.
In all villages of Giap Trung, the role of the village patriarch is not very strong, whereas the
role of the village heads is very apparent. Villagers tend believe in the heads of their villages
and to follow the decision of these leaders. Most village heads are young, have been well
educated compared to the average level in the village or commune (they are also exclusively
male in Giap Trung, not unlike other rural areas of Vietnam). They speak fluently Kinh
language and are officially elected by the villagers. All information to be conveyed between
commune authorities and villagers is transmitted through village heads.
9
All of the villages have branches of the three basic mass organizations of Vietnam: the Party,
Youth Union and Women’s Union. Unlike some other communes where the Women’s
Union is quite strong and influential, the Women’s Union in Giap Trung seems not as active
as the Youth Union branch. The village officials maintain a good and close relationship with
the village heads and the mass organizations, especially the Party. In the administrative task,
the Party plays the most significant role and dominates the operation of the Commune
People’s Committee. The political power of the agricultural co-operatives has been
diminished in the last decade. However, they still play a significant role in reporting the
crop, insect situation and selling agricultural inputs (fertilizer, seeds, etc.).
Similar to other mountainous communes, Giap Trung 's infrastructure is not developed. The
road connecting to the district is in poor condition that cannot access by vehicle in rainy
season. Inter-village roads are earth road and there are some sections cannot access by car.
A primary school locates in Khau Nhoa village with a number of classrooms distributed in
other villages. Kindergartens are seen in several villages. Both school and kindergartens
were constructed by governmental budget. Besides, a commune clinic and commune office
locates also in Khau Nhoa village that is considered as commune center. The market, opens
two times a month in the commune center, does not attract people from surrounding
communes, but only serves local needs. People from all twelve villages come to exchange
basic produce here. There are some small shops in the commune center selling basic general
goods such as fish sauce, batteries, notebooks etc.
The economic activities of the commune focus mainly on agriculture (rice and corn
production), forest product exploitation, cattle breeding and trade. Almost of households
(97%) have agricultural land and have been allocated forest area under protection contracts
in accordance with State regulations. According to local authorities, 25 households are
involved in trade, and 40 households run shops (30 of whom are from outside the commune).
All other households are involved in agriculture and forestry. Khau Nhoa, Na Bo, and Na
Vieng villages have conditions to plant paddy rice in the river valleys. In the other villages
people plant at upland agriculture and collect forest products. Livestock rising is not as
developed as it has been in the past, due to widespread disease in the region.
10
Figure 4.3: Paddy rice in Giap Trung
Source: Oliver, Entec AG, 2002.
Average agricultural land area per capita varies greatly from village to village. It is highest in
Khau Nhoa (260 m2 per capita), and lowest in Lung Cao, Khuoi Phung and Lung Nhoa
(about 80 m2 per capita ). Income from agriculture in the four more remote villages is lower
than in the centrally located villages due to less pretty land and water shortages in those
villages. Average rice productivity in the commune for 2001 was 190kg/360m28.
Several households in the commune are traders, mostly trading in household items and some
running food services. Most of them locate in Khau Nhoa and Na Vieng village. Households
in trade have incomes significantly higher than those purely dependent on agriculture.
Figure 4.4: Proportion of household by well-ranking
30%
46%
24%
Poor Average better-off
8 360m2 is one sau, a standard land measurement.
11
Average income per household in the commune in 2001 was 7,740,000 VND. The
distribution of income is significantly uneven (see the figure 4.4) ranging from 840000 to
19000000 VND. The ratio of poor households is still high, accounting for about one third or
178 households9. Among the poor households, 85 households faced food shortage at least 2
months/year. The number of average income households is 268 households, accounting for
45.5% of the total number of households. The number of better-off households is 143,
equivalent to 24.2%. Households considered to be “better-off” are mostly concentrated in
Khau Nhoa, Na Bo and Na Vieng villages.
Figure 4.5: Household Income Distribution
0%
10%
20%
30%
40%
50%
Prop
ortio
n (%
)
<1 1 to 5 5 to 10 10 to 15 >15
Household Income (mil. VND)
Informants gave several reasons for why some households are more successful
economically. Among the better-off are households of commune officials, who have stable
incomes and allowances. Other better-off households are skilled in animal husbandry,
especially ox husbandry, which is a good income source in the area. Other households are
better-off due to trading and some have high income because of hard work and good
knowledge of cultivation, resulting in higher productivity. Living standards vary from
village to village. This is attributed to more favorable conditions for agriculture in some
villages, and better access to trade and commercial activities. Commune leaders ranked the
living standard of the five centrally located villages in descending order as follows: Khau
9 The classification follows the national standard. “poor” household are those have monthly income less than 1,000000 VND, “average” household have income between 1,000,000 – 5,000,000 and “better-off” have income more than 10,000,000 VND.
12
Nhoa, Na Vien, Na Bo, Than Khien, Na Den, Phia Booc, Lung Ngoa, Na Pong, Khuoi
Phung, Lung Cao.
Three wealthy groups, a group of women in Phong village, a group of residents in Khau
Nhoa village, and commune leaders were asked to rank development priorities. While there
were differences in the results of their rankings, all ranked an improved access road to the
commune and electricity among the top three development priorities.
Table 4.1: Ranking of Development Priorities10
Local Authority
Residents in commune center (Can village) .
Women’s group
Income generation 3 2
Water 4 4
Health 4 (‘better clinic’)
Education 5 (‘better school’)
Access Road 1 3 1
Electricity 2 1 2
Irrigation 5 5 3
Existing energy generation facilities
The most common energy sources in Giap Trung are Pico-hydro, kerosene, wood, candles,
batteries and diesel motors. Diesel engines are used for rice husking /polishing, and wood
processing.
Pico hydro use is relatively high with 72% of total households (402 households) either own
or share the use of a Pico hydro generator. Pico is used primarily for lighting, black and
white televisions, electric fans, radios and cassette players. Households in the villages
surveyed reported that they run standard light bulbs as well as fluorescent tubes for lighting
powered by their Pico generators. Complaints given by local people about Pico hydro energy
were mainly to their quality. The quality of the machines is low and therefore they do not
have a long life span (local people in Giap Trung did not expect their Pico generators to last
10 The scale of ranking is from 1 to 5. 1 is considered the highest priority and 5 is lowest priority
13
more than 4 years) and the machines require constant maintenance. A common problem in
Giap Trung was the frequent theft of Pico hydro generators in the night.
Figure 4.6: Pico using in Giap Trung
Source: Oliver, Entec AG, 2002.
Purchase price for Pico units can vary greatly. People reported buying second hand units for
as little as 40,000 VND, while new units can cost up to 1,200,000 VND. Average cost is
about 350,000 VND per unit. Everyone interviewed said they installed the units by
themselves. Almost of households say they keep their Pico units running 24 hours a day
(This means that they keep the unit in the flow of the stream and not necessarily imply that
they are drawing power off of the unit for the full 24 hours.). Monthly maintenance expenses
are from 10,000 VND to 15,000 VND per month.
Besides Pico, kerosene is one of the main sources of energy for lighting in Giap Trung. In
the questionnaire survey, 97% of households surveyed reported using kerosene for lighting.
Many of these households use kerosene lamps in addition (or as a backup) for Pico hydro.
On average, households reported using about 1.5 lit/month, cost 12000 VND per month.
There is sometimes a shortage of kerosene in the commune (when road conditions are bad
and it cannot be transported). At those times, household use candles for lighting.
Kerosene is supplied to the commune through two sources. One is the state supply system
run by the General Corporation for Mountainous Areas Development; the other is private
supply through private suppliers. State run stations sell kerosene at 4500 VND/liter (they
have state subsidy for transportation). The private stations sell at a higher price, usually
14
around 5000 VND/liter, although this may go up to 5500 VND/liter at times when no
kerosene is available through the state supply. State run stations tend to close earlier than
private suppliers; therefore private businesses rely on custom from households running short
of kerosene after hours and at times when state supply runs dry.
Wood is mainly used for cooking and heating. 100% of households are using wood for
cooking. Fires tend to burn throughout the day and night, especially in winter if people are at
home and are stoked and rekindled when needed to prepare meals or prepare feed for some
animals. Alcohol is also distilled over wood fires.
One household, on average, uses 380 kg wood per month. They collect firewood freely in
the surrounding hills, and purchase of firewood is unknown. For interviewed household,
wood collecting is completely done by women. The women spend 1.8 hours in average for
wood collecting.
Figure 4.7: Time for wood collecting of women
79% of household in the commune use dry cell batteries regularly. Dry cell batteries are
used primarily for running cassette players, radios, and flashlights. On average, each
household in the commune uses about 4 batteries per month, spending an average of 5,000
VND for batteries every month. Flashlights are used outside of the house, so batteries are a
current source of energy that cannot be entirely replaced by hydropower or other sources of
electricity within the home. Dry cell batteries may be purchased at the small private shops
with cost of 2,500 VND/pair.
There are 14 diesel motors, which are used to run machines for rice husking and polishing
and two wood processing stations running in the commune.
0%
10%
20%
30%
40%
50%
60%
Prop
ortio
n (%
)
0.5 1 1.5 2 3 4
Hours
15
Other energy source is candle. Candles are used mostly by teachers (in villages), for lighting
at night after school hours, or in households when there is a shortage of kerosene.
Current energy use and household well-being
There were no considerable distinctions in the ways of using energy among different well-
being. Use of Pico hydro generators is only slightly lower for poor households (60%) than
for households ranked average (80%) or better off (75%)11. A number of households in any
of these categories are sharing Pico with other households.
Kerosene was much less widely used by richer households (22%) than by average (95%) or
poorer households (89%). One possible explanation is that better off households may be able
to afford more modern forms of lighting (such as neon strips, or rechargeable ‘flash’ lamps)
that they can recharge or use Pico systems, rather than using simple kerosene lamps for
lighting. Differences in the use of wood for fuel could be neglect among wealth ranking
groups.
As seen from the communes, there is little possibility to change from wood to electricity for
cooking and heating It may be possible to convince some rich households to use electric
kettles or rice cookers but this still need actively campaign. However, there is a high
possibility to convert energy demand for milling/husking and wood processing to electricity
and the number of televisions is also likely to increase.
It can be concluded that electricity is not new to Giap Trung, many households have owned
or share Pico hydro systems for several years already. The anticipated social impact of the
project in the commune is mainly in terms of what kinds of advantages may be offered to
local people through using power from mini hydro power rather than their current sources of
energy.
5 Load Demand Forecast
Similar to other rural areas, electricity demand for Giap Trung commune can be divided in
three groups by the purpose of electricity using (i) domestic use (by households), (ii) public
11 A number of better-off household involving in trading and living far away from stream therefore percentage
of those using Pico is lower than that figure of average group.
16
and service use, and (iii) productive use. Load demand for the whole commune is total
demand of these groups.
Domestic use
Electricity demand for domestic use purpose is forecasted based on information collected
from field surveys12 and actual situation of using electricity in Vietnamese rural areas. It is
clear that for such rural area like Giap Trung commune the demand for lighting accounts for
the largest part of household’s electricity consumption, following by entertainment and
others. The peak load occurs at from 19 to 20 o'clock resulting from electricity demand for
lighting.
To estimate domestic electricity demand a "typical household's electricity consumption
profile" for the commune is identified. The profile is not a profile of a household in reality,
but is an assumed household profile, which expresses electricity-using characteristic of all
households in average. Followings are basics to identify the typical profile:
(i) It is assumed that after electrified, all substitutable energy sources for domestic
use purpose will be replaced by electricity provided from hydropower scheme,
that are electricity comes from Pico, kerosene, dry cell battery for radio and
cassette players.
(ii) Each household has from 1 to 3 lamps for lighting with assumption there is a
correlation between proportion of household having 2 or 3 lamps and medium
and rich households13
(iii) Penetration rates of other electrical appliances such as TV, radio, etc come from
survey data result.
(iv) Using time of the appliances gained from survey data and taking experience of
similar electrified villages in Vietnam in consideration.
The typical profile is identified with total power of 150.3 W and monthly energy
consumption of 17.8 kWh. The typical profile is presented in table 5.1
12 Field survey includes (i) household survey; (ii) productive use survey (iii) electricity use. See appendix 1 and 2 for more detail.
13 See chapter 4 "Socio-economic situation of Giap Trung commune"
17
There will be 546 households connected to the mini hydropower scheme in Giap Trung
commune. Correspondingly, monthly electricity demand for domestic use is 9734 kWh
equivalent to 116806 kWh/year.
Table 5.1: Typical household's electricity consumption profile
Appliance Power Penetrate rate
Power Daily using
Monthly consumption
(Watts) Unit (%) (Watts) (hour) (kWh)
Bulb 1 60 1 100% 60.0 4.5 8.1
Bulb 2 40 1 60% 24.0 4.0 2.9
Fluorescent lamps 40 1 30% 12.0 4.0 1.4
Radio/Cassette 15 1 70% 10.5 3.0 0.9
TV 75 1 40% 30.0 3.5 3.2
Video Recorder 35 1 5% 1.8 1.0 0.1
Rice cooker 1000 1 0% 0.0 1.0 0.0
Refrigerator 85 1 0% 0.0 6.0 0.0
Fans 40 1 30% 12.0 3.5 1.3
Sum 150.3
Monthly consumption 17.8
Public and service uses
Group of consumers using electricity for public/service use consists of the district's general
heath clinic, the Giap Trung secondary and primary schools, the Commune Office, shops
and services. Total energy demand for public/service use is estimated 795 kWh/month,
equivalent to 9538 kWh/year. The power and yearly energy consumption of the customer
group are shown on table 5.2. Detail calculation is on appendix 2.
Table 5.2: Electricity demand for Public/ services use
Customer Power
(W)
Annual consumption
(kWh)
Consumption time
District's heath clinic 2585 3329 Round day
Giap Trung school 2340 2967 Round day
Commune Office 1410 1994 Round day
Shops and Services 840 1248 Round day
Sum 7175 9538
18
Productive use
Electricity demand for productive use in Giap Trung commune is mainly for rice husker and
wood processing machines currently powered by diesel engine, which potentially could be
replaced by electrical motors. Most of diesel engines are old, low efficiency with capacity of
12 kW. Technically, the engine can be replaced by electrical engine with capacity of 7.5 kW
that requires a large investment cost of 1.5 to 3 million VND. Electricity demand for
productive use considerably depends on number of consumers willing to convert to electrical
motor. Among 14 rice huskers, two commits to convert to electricity, one say no and the
remains do not give final decision yet. Therefore, it is expected that at the beginning 2 rice
huskers will convert to electrical engine with total capacity of 15 kW (7.5 kW x 2).
According to field survey, annually diesel consumption for husking and milling rice in the
whole commune is 4620 liter. Assume that the efficiency of diesel engine and electrical
engine are 20% and 75% respectively, the total electricity demand for rice husking is
estimated at 12409 kWh/year if all amount of rice is husked by the electrical engines.
However, even though electric engines offer lower husking fee, it is expected that only 40%
of Giap Trung’s demand of rice husking will be done by electrical engines due to remoteness
and habit that accounts for 4964 kWh/year.
At present two wood processing machines are working in Giap Trung commune. The
visiting to two processors during the filed trip observed they were quite busy at that time.
The owners are very interested in shifting from diesel motor to electrical motor and aware of
benefit from shifting as well. However they still concerned about the electricity quality that
might affect to their business. It is expected that two wood processor will convert from using
diesel to electricity when the commune electrified. Electricity consumption and power of the
processors are presented in table 5.3. The figure of 37084 kWh/year is calculated for
productive use demand.
Table 5.3: Power demand for wood processing
Appliance Power
(W)
Unit
(Set)
Daily using
(Hour)
Annual consumption
(kWh)
Power-saw 5000 5 2.5 22812.5
Planer 1500 5 3 8213
Bulb 60 10 5 1095
Sum 32120
19
Total load demand at first year of electrified for Giap Trung commune is, therefore,
forecasted as follows:
- Electrical energy demand: 163428 kWh/year
- The peak load: 62.9 kW
- Load factor: 29.6%
Figure 5.1: Electricity demand for Giap Trung commune
Daily load curve
The daily load curve of the commune is set up based on following parameters:
(i) Typical household's electricity consumption profile
(ii) Electricity using characteristic of households
(iii) Electrical appliance and electricity using characteristic of public/services use and
productive use with assumption that power demand of productive use will occur
in daytime only.
Domestic use71%
Public and services use
6%
Productive use20%
20
Figure 5.2: Daily load curve for the commune
Load Demand Growth
On the long term, the growth rate of the electricity demand primarily depends on population
growth rate and economic development. During the first years after electrification, however,
a higher demand growth is to be expected, as more new electrical appliances will be
purchased. Experience in electrified villages in Vietnam like Na Bo and Na Tra shows that
the electricity demand grows annually by 1% to 4%14.
Based on the above considerations, an average growth rate of the electricity demand of 2.5%
for the first three years, and an average of 1.5% for the following years is assumed for the
computation of the load forecast in the Giap Trung commune. The electricity demand will
thus increase from 163428 kWh to 223334 kWh after 20 years
The average growth rate of the peak load is estimated at 1.5% on average for the next 20
years. The peak load will thus gradually increase over the next 20 years from 62.9 kW to
76.8 kW.
14 PECC1, EVN
0
10
20
30
40
50
60
70
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time
pow
er (k
W)
Domestic use Public and services Productive use
21
Figure 5.3: Energy demand projection
0
50
100
150
200
250
300
2002
2004
2006
2008
2010
2012
2014
2016
2018
2020
2022
Elec
trici
ty d
eman
d (k
Wh/
a)
Domestic use Public and service use Productive use
Figure 5.4: Peak load projection
0102030405060708090
2002
2004
2006
2008
2010
2012
2014
2016
2018
2020
2022
Peak
load
(kW
)
Similar to other remote rural areas in Vietnam, electricity demand in Giap Trung is very low
compared to average electricity consumption for the whole country. The demand is
characterized by low load factor (29%), one peak load at 19-20 o’clock (that time is also
peak load of Vietnam’s power system) caused primarily by lighting and entertainment. In
additional, scattered resettlement of the households will likely lead to very high cost to
electrify the commune.
22
6 Hydropower potential, scheme components and cost estimation
The proposed mini hydropower plant is located on Nam Nung stream, about 4 km from the
central of Giap Trung commune. At present there is a track which can access to the power
house round year. The topographical condition allows to build a run-off-river scheme which
comprises of a small weir, a 710 m length canal to create a generate head of about 65 m.
Local material for building the plant is found very near the site with quite good quality that
will help to reduce the cost of the power plant.
6.1 Hydropower potential
Hydrological assessment15
The mini hydropower scheme will exploit the hydropower potential of the Nam Nung
stream. The catchment area at the intake is 28.7 km2 stretching from Northeast to Southwest
over a length of 7.5 km at a mean elevation of 740 m a.s.l. The area is mainly covered with
forest, some rice paddies and widely spread settlements with agricultural land use.
Because there is no observed hydrological data for the site is available then average annual
discharge and duration of flow at Giap Trung site was determined by the Tank Model
Program16. This program was developed to estimate and simulate monthly and annual river
discharges. Rainfall data and other characteristics of the catchment area are used in
comparison with data from neighboring rivers to model the flow characteristics of a stream.
Parameters for the Tank Model in the calculation were rainfall data and river flows observed
at the Bao Lac station, which is 10 km from the site for the years from 1963 to 1972
The annual runoff at the proposed site is simulated from the monthly rainfall data, which
was available for the last 38 years. The characteristic figures are shown below:
• Mean annual stream flow: Q0 = 0.967 m3/s
• Mean annual specific discharge: M0 = 33.64 l/s.km2
15 HEC1 (Hydraulic Engineering Construction Company 1, Hanoi, Vietnam) 16 Adopted from the Tank Model of M. Sugawara, developed at the of National Flood Protection Center of Japan in 1956.
23
Figure 6.1: Catchment area of Giap Trung hydropower
Beside that discharge measurement by salt and cross methods was done during the field
research to check the data gained from interpolation. The measurements November 2002
revealed an average flow of 600 l/s seems suitable with interpolation result.
Estimated hydrological data for Giap Trung site, illustrated on the hydrograph and flow
duration curve in figure 6.2. Detail hydrological data see appendix 3.
24
Figure 6.2: Hydrological data for Giap Trung Hydropower
Hydropower potential estimation
The gross head of the hydropower is measured by total station during the field research
resulting in gross head of Giap Trung hydropower is 68 m.
Head loss estimation and turbine technical parameters are done based on the measured gross
head and supposed rated discharge of 0.6 m3/s, penstock internal diameter of 0.45 m. The
results of the calculation are shown on figure 6.3.
Figure 6.3: Head loss and Turbine Efficiency
The hydropower potential available is much more greater than the power demand from Giap
Trung commune. Therefore, the option to construct an off grid hydropower to provide power
to the commune is likely not economical compared to a grid connected hydropower, which is
connected to national grid about 7.5 km distance17. Because the Giap Trung hydropower is
17 See “Optimization of the hydropower scheme”
Hydrograh
0
1
23
4
5
6
0 96 192 288 384
Month
Dis
char
ge (m
3/s)
Flow Duration Curve
0123456
0% 20% 40% 60% 80% 100%
Prequency
Dis
char
ge (m
3/s)
Head loss curve(penstock diameter of 0.45 m)
02
46
810
12
0 0.2 0.4 0.6 0.8
Discharge (m3/s)
Hea
d lo
ss (m
)
Turbine efiiciency(Rated dischrge of 0. 6m 3/s)
0
0.2
0.4
0.6
0.8
1
0 0.2 0.4 0.6 0.8
Discharge (m3/s)
Turb
ine
effic
ienc
y (%
)
25
supposed to connect to national grid then there is no limitation in the demand for the project.
The project, therefore, will be developed at large level to benefit from economic of scale.
From that point of view, install capacity of 244 kW is selected for the mini hydropower
resulting in annual output of 1451092 kWh, firm energy 502458 kWh (frequency of 90%).
Main hydrology parameters of the hydropower are presented in table 6.1. Duration curve of
the hydropower plant see figure 6.4. Detail calculation see appendix 3.
Table 6.1: Main hydrology parameters
Items Unit Value
High water level m 325.00
Fore bay elevation m 323.00
Rated discharge m3/s 0.60
Rated head m 63.71
Firm Capacity kW 57.5
Firm energy kWh 503574
Installed capacity kW 244.1
Annual output kWh 1452354
- Wet season kWh 522755
- Dry season kWh 929599
Plant factor % 68%
Figure 6.4: Power duration curve
0
50
100
150
200
250
300
0% 20% 40% 60% 80% 100%
Pow
er (k
W)
26
6.2 Hydropower components
6.2.1 Civil work
Civil work comprises of an over-spill weir, intake, head race canal, fore bay, penstock and
power house.
A stone masonry over-spill weir will be constructed to accumulate water for intake with the
length of over-spill section of 15 m. The weir have dimension length x height = 20 (m) x
2(m). The width of the weir crest is 0.8, while the bottom width is 3 m. A cut-off is designed
under weir to prevent seepage and a downstream yard to prevent erosion in downstream.
The intake structures comprise of the weir body, a flushing opening, an intake orifice and a
side wall out of stone masonry on the right river bank, preventing water from bypassing the
weir. The intake is designed as a side intake. During normal plant operation the slide gate at
the flushing canal (width: 1.2m, height: 2.0m) is closed, whereas the intake orifice (0.7m x
1.0m) is opened. During flood events with heavy bed load transport and voluminous floating
debris the intake orifice can be closed and the flushing canal be opened.
The settling basin (or sand trap) made of stone masonry and covered with mortar is located
behind the water intake and has the following dimensions: width = 2.0m, length = 10.0m,
and depth = 1.7m. A discharging outlet (width 0.5m, height 1.0m) is located at the end of the
basin
The headrace structure begins with the outlet at the settling basin and ends at the fore bay.
The total length of the headrace together is 710m. The headrace is designed as an open canal
made out of stone masonry and leading along the right riverside. The standard cross-section
of the headrace canal is 1.0m wide and 1.2m high. The slope of the canal is 0.1%, resulting
in an average water depth of 0.9m for the design flow of the plant.
The fore bay forms the transition from the headrace to the penstock pipe and is built out of
stone masonry. The fore bay has the following dimensions: width 2.7m, length 10.0m, depth
2.0m, and a 5m long transition part. A trash rack prevents gravel and debris from entering
the penstock. The inlet to the penstock can be closed with a sliding gate (width 0.80m, height
0.8m). The fore bay can be emptied through an opening at the bottom of the basin, which
can be closed by a sliding gate (width 0.4m; height 1.3m).
A spillway conveys any water discharged from the fore bay safely away from the basin.
From the overspill section of the fore bay the water is diverted through an open channel
27
directly down to the river. The spillway has a length of approximately 50m and is lined with
stone masonry.
The total length of the penstock is 79m. The penstock consists of rolled welded steel pipes
with an internal diameter of 0.45m. The flanged pipes are welded on site. There is one
expansion joint and one butterfly valve at the powerhouse. The penstock is supported by one
anchor block out of reinforced concrete, located behind the powerhouse, and 10 saddles out
of stone masonry (approximately every 8m).
The powerhouse is located at the right riverbank of the river and has a reinforced concrete
base with a ground size of 10 x 15m and brick walls. The roof is covered with corrugated
zincalum sheets.
The total length of the tailrace structure conveying the water from the powerhouse back into
the river is approximately 30m. The tailrace is made of stone masonry and has a trapezoid
cross-section with a bottom width of 1.0m, a top width of 2.0m, and a depth of 1.0m.
Figure 6.5: Longitudinal cross section of Giap Trung hydropower
6.2.2 Electrical and mechanical equipment
Regarding the hydraulic data of the Giap Trung hydropower site (net head: 65 m, design
flow: 600 l/s), basically a Cross flow turbine or a Francis turbine is suitable. Whereas today
cross-flow turbines are successfully being manufactured in developing countries (e.g.
Indonesia, Nepal) having higher efficiency quality and longer lifetime expectancy.
Furthermore good quality Francis turbines need to be imported from industrialized countries
at considerably higher cost. Therefore, cross-flow turbine is selected.
Weir
Intake
Headrace
Fore bay
Penstock
Powerhouse
Tailrace
28
It is proposed to use an internal pole three phase synchronous generator with integrated
exciter machine in brushless design, self-regulated, internally ventilated squirrel-cage rotor,
with roller bearings, including relubricating device and grease regulation.
Either a digital turbine controller or an electro-hydraulic governor is proposed to use. This
control systems allow to regulate the speed of the turbine and generator and thus to keep the
frequency of the electricity at a constant value of 50 Hz.
6.2.3 Transmission and Distribution System
To connect the mini hydropower to the local households and national grid a transmission and
distribution system consisting of medium voltage (MV) 35 kV lines, low voltage (LV) 0.4
kV backbones and low voltage 220 V household connections will be set up. Location
diagram of mini hydropower and transmission/distribution are provided in figure 6.6.
Transformer at Powerhouse (step-up): A three phase 320kVA step-up transformer is
installed at the powerhouse to step up voltage from 0.4 kV to 35 kV.
35 kV Transmission Line to the National grid: A three phase 35kV transmission line will be
installed from the power house to the EVN's 10000 kVA substation in Bac Me district
center. The length of the lines is about 6.5 km
35 kV Transmission line to the commune: A three phase 35kV transmission line, 14.2 km
length, from the mentioned transmission line to villages will be built to connect the connect
the commune to the power house.
Transformers in Villages (step-down): Four 3-phase 25 kVA step-down transformers will be
used for villages to reduce power supply to 0.4 kV.
0.4 kV Distribution Line (Distribution Backbone):0.4 kV distribution lines with AC25
conductors will be set up with round steel poles to distribute the electricity within the village
(13.2 km).
220 V Household Connections: 220 V low voltage, single phase distribution lines with AC15
conductors will be used for the 546 household connections, whereby the total length of this
distribution network is estimated at 20.5 km.
The length of the lines is calculated base on the topographical data collected by GMS done
by PECC1 staffs.
29
Figure 6.6: Location diagram of mini hydropower and transmission/distribution
6.3 Cost estimation
Cost estimation is done based on the primary design for the mini hydropower scheme. Unit
cost price comes from Vietnam regulation on cost estimation18 and experience of PECC1
experts on some similar project in the region19. The investment cost of VND10, 006.5
million, equivalent to US$649770 is calculate for Giap Trung hydropower scheme. With the
unit cost of 1322 US$/kW and 264 USD/kWh, the hydropower is ranked at average level of
small and mini hydropower in Vietnam. The comparison is shown on figure 6.7 (unit cost of
other mini hydropower is took from Vietnam Renewable Energy Action Plant20 at the price
of the year 1999). To support for calculation of economic electrification cost and allocation
of the investment cost to beneficiaries, the project’s investment cost is divided into
investment cost for the commune grid and for hydropower plant21. Breakdown of investment
cost shown in table 6.2 and figure 6.7.
18 Construction Publish House, Hanoi, 2000. 19 See appendix 3 for detail. 20 Bogach, 2000, p. 52 21 Investment cost of hydropower comprises of investment cost for hydropower plant and transmission lines to EVN’s substation.
0.8 km
7.5 km
6.8 km
Powerhouse
Commune
National Grid
2.3 km
30
Figure 6.7: Comparison unit cost of small hydropower in Vietnam
0 500 1000 1500 2000 2500 3000
Nam Mou
Dan Sach 1
Na Loi
Giap Trung
Da Dang
Na Loa
Da Cho Mo
Nam He
Dan Sach 2
Pa Khoang
Thac Voi
Sa Deung
USD/kWhUSD/kW
Detail cost estimation of the Giap Trung mini hydropower is illustrated in appendix 3
Table 6.2: Cost estimation
Unit: million VND
No. Item / Specification Value
Summary Whole project Hydropower Commune Grid
A Civil Works 1,813.5 1,813.5 0.0
B Electro-mechanical Equipment 2,025.2 2,025.2 0.0
C Transmission/Distribution Lines 5,039.2 1,265.0 3,774.2
D Land Lease / Compensation Payments 15.0 15.0 0.0
E Project Planning, Engineering Design, Site Supervision and Administration 395.0 276.5 118.5
G Contingencies 718.5 503.0 215.6
Total 10,006.5 5,898.2 4,108.3
31
Figure 6.8: Breakdown of Investment Cost
7 Optimization of hydropower scheme
It is expected that private investor will develop Giap Trung hydropower plant aiming to
provide power to Giap Trung commune, and to sell supplementary energy to national grid.
The two purposes (i) Electrification of the commune, and (ii) Investment have different
criteria for the best hydropower scheme. For the former the option which requires the lowest
cost to electrify the commune is the best one but the option, which brings the maximum
turnover is considered the best one from latter’s interest. Therefore, selection of the optimum
option for the hydropower will be considered from two points of view (i) Cost of
electrification for the commune and (ii) Economic benefit of investment.
Economic Electrification Cost comprises of following indicators:
1) Economic Cost of Electricity (VND/kWh) that is the cost of one kWh electricity
provided to the commune (including investment and annual cost).
2) Economic Cost of Electrification for the whole commune means Net Present Value
of total cost paid to electrify the commune including investment cost and annual cost
for the period of 25 years.
3) Economic Cost of Electrification for one household (million VND/household) is
Economic Cost of Electrification for one household in average.
For Economic Benefit of Investment, following indicators are put into consideration:
1) Unit Cost of Electricity (VND/kWh) means production cost of one kWh electricity.
(including the commune's grid)
Civil Works18%
E/M Equipment20%
T&D Lines49%
Engineering5%
Contingencies8%
Land Acquisition
0%
(Excluding the commune's grid)
Civil Works30%
E/M Equipment33%
Engineering6%
T&D Lines21%
Land Acquisition
0%
Contingencies10%
32
2) Economic Net Present Value of the project (million VND), and
3) Internal Rate of Return (%)
7.1 Excel model
To facilitate the selection a excel model is set up to calculate economic indicators. The
model comprises:
(i) Module A – “Cost for electrification” used to calculate Economic Electrification
Cost indicators, and
(ii) Module B – “Investment Benefit” to compute Economic benefit indicators of the
investment.
Module A comprises of 7 worksheets (see figure 7.1)
- “Tariff estimation” worksheet is used to estimate economic tariff for power provided
from national grid to the commune.
- “Input data” worksheet comprises information of load demand of Giap Trung
commune, unit cost and investment cost of all considered options.
- “Grid Connected Hydropower”, “Off Grid Hydropower“, “Connection to National
Grid „, and “Diesel generators“ worksheets are used to calculate Economic
Electrification Cost Indicators for mentioned options.
- “EC result” worksheet to sum up the calculation results
Module B consists of 4 worksheets as follows:
- “Invest Data” worksheet comprises information on load demand of the commune,
economic and financial condition such as discount rate applied, analysis period, etc,
investment and annual cost of considered options.
- “Invest Grid connected” and “Invest Off Grid” worksheets are used to calculate
Economic Investment Indicators for the two options.
- “Invest result” worksheet to sum up the calculation results
33
Figure 7.1: Excel Model Diagram
Module A Module B
Excel Model
EC Result
Input data
Grid Connected
Off grid hydropower
Connect to national grid
Diesel Generators
Tariff Estimation
Invest data
Invest grid connected
Invest off grid
Invest Result
34
7.2 Economic Electrification Cost
The commune might be electrified by (i) exploiting the rich hydropower potential available,
(ii) Connect to national grid, and (iii) install diesel generators. Generation power from wind
or solar radiation is not mentioned due to very high cost compared to said power sources.
Therefore, to select the optimum option to electrify the commune, following options are put
into consideration:
"Grid connected hydropower"
If the option is selected one grid connected hydropower plant will be built at economically
maximum size to supply electricity to the commune and feed power into the national grid.
The project comprises of:
(i) Hydropower plant, 244 kW capacity
(ii) 35kV/0.4 kV 320 KVA transformers located at power house
(iii) MV transmission lines from powerhouse to national grid, 7.5 km length
(iv) The commune grid which includes (i) 14.2 km MV transmission lines from the
main MV lines to villages, (ii) four 35kV/0.4 kV 30 KVA transformers located at
villages, (iii) 13.2 km LV backbone lines, and (iv) connection lines to
households, 20.5 km length.
The investment cost to electrify the commune, however, is considered as the cost for the
commune grid only. That is estimated VND 4, 108.3 million.
In addition, the commune needs to pay for annual cost, which includes: (i) maintenance cost
estimated 1.5% of the investment cost, and (ii) Payment for electricity provided from the
power plant at the tariff supposed at 1200 VND/kWh22.
Cost breakdown of the option is presented in appendix 4.
"Off grid hydropower"
In the option the power plant is constructed to meet the power demand of the commune only.
To meet the demand peak load of 62.9 kW at year of electrification, an 82 kW hydropower
22See 11.1 “Tariff structure”.
35
plant will be built in combination with a mini grid to supply electricity to the commune.
Following components will be constructed for the option:
(v) Hydropower plant, 82 kW capacity
(vi) A 35kV/0.4 kV 110 KVA transformer at powerhouse
(vii) The commune grid which includes (i) 15.7 km MV transmission lines from the
powerhouse to villages, (ii) four 35kV/0.4 kV 30 KVA transformers at villages,
(iii) 13.2 km LV backbone lines, and (iv) connection lines to households, 20.5 km
length
Investment cost is VND 7,239.2 million. Annual cost of 3% and 1.5% of investment cost are
assumed for the O&M cost of hydropower and transmission/distribution, respectively.
Detail cost structure of the option is on appendix 4.
"Connection to the national grid"
The commune is connected to the national grid by MV transmission lines. The cost for
electrification comprise of investment cost for the transmission lines and payment for power
provided from the national grid. The tariff is calculated based on the avoided cost of EVN23.
Electricity consumption during peak load is estimated 50% and 65% in dry season and wet
season respectively and, to simplify, it is assumed no different electricity consumption
between wet and dry season days. Thus the economic tariff of 822 VND/kWh for the power
provided to the commune is estimated 24. The main components of the option are:
(i) 35 kV MV transmission lines connecting national grid to the commune grid with
the length of 6.8 km.
(ii) A 35kV/0.4 kV 110 KVA transformer.
(iii) The commune grid which includes (i) 14.2 km MV transmission lines from the
main MV lines to villages, (ii) Three 35kV/0.4 kV 30 KVA transformers at
23 Avoided cost of EVN is considered the cost EVN can be avoid if they do not have to generate and transmit an additional one unit electricity to customers.
24 Detail calculation is presented in appendix 4.
36
villages, (iii) 13.2 km LV backbone lines, and (iv) connection lines to
households, 20.5 km length.
Total investment cost of VND 5,058.9 million is calculated for the option. The annual O&M
cost of 1.5% of investment cost is assumed.
Detail cost structure of the option is presented in appendix 4.
"Diesel generator"
The power will be provided to the commune by a number of diesel generators installed in
villages with total capacity of 80 kW to meet the peak demand of 62.9 kW. In this case, the
commune does not need to build MV transmission lines due to the generation is located at
center of the villages. The option comprises of:
(i) Diesel generators with total capacity of 80 kW, about 20 kW - 30 kW each
(ii) LV backbone distribution lines within the villages, 13.2 km
(iii) Connection lines to each household, 20.5 km length
At present 25 kW capacity diesel generator costs 6.5 million VND/kW including transport
and installation25 resulting in 520 million VND for investment. O&M cost for the diesel
generator is assumed 5%.
Fuel cost accounts for the heavy proportion of the generation cost. For most diesel generator
in Vietnam the average efficiency observed at 22% then the unit fuel consumption is
calculated of 0.45 liter/kWh. Diesel fuel cost is recorded 5500 VND/liter at the commune
during the field trips.
Breaking down of cost estimation is shown in appendix 4.
Selection
Results of Economic Electrification Cost calculation presented in table 7.1 and figure 7.2
show that “Grid connected hydropower” is the cheapest option with Electrified Cost of VND
6,201.1 million and Electricity Cost of 3,980.4 VND/kWh, follows by options “connection
25 PECC 1
37
to national grid”. Options “Off grid hydropower” and “Diesel generator” are far more
expensive when have electrified costs 1.5 times higher than that of the cheapest option.
Regarding to economic cost for electrification, the two options "Grid connected
hydropower" and “connection to national grid” have similar cost. However the former has
advantage over the latter due to that will exploit the renewable energy potential available, be
environmental friendly, reduce the financial burden for extension generating capacity and
transmission grid. Furthermore this will help to promote participation of private sector in
renewable energy development in Vietnam that is worldwide experienced as the key factor
for the success of renewable energy development. From the arguments, the option "Grid
connected hydropower" is selected for electrifying the commune.
Detail calculation of Economic Electrification Cost is presented in appendix 4.
Table 7.1: Economic Electrification Cost
Option Electrified cost for the commune
Electricity cost
Electrified cost per household
(Million VND) (VND/kWh) (Million VND)
Grid connected hydropower 6,201.1 3,980.4 11.4
Connection to national grid 6,563.1 4,212.8 12.0
Diesel generator 7,109.4 4,563.4 13.0
Off grid hydropower 7,513.8 4,823.1 13.8
38
Figure 7.2: Economic Electrification Cost
7.3 Economic benefit of investment
From investment point of view, there are two development options for the hydropower plant
are put into consideration as follows:
"Grid connected hydropower"
In that option a grid-connected hydropower will be constructed with annual output of
1452354 kWh. The power plant firstly, will provide power to the commune and, secondly,
feed into national grid all surplus electricity. The economic benefit unit of one kWh
electricity provided to the commune is valued equal to the electricity unit cost of the
cheapest option to electrify the commune if no hydropower scheme will be constructed. The
said cheapest option for Giap Trung commune, as calculated in “Economic Electrification
Cost” is connect the commune to national grid with unit cost of 4,212.8 VND/kWh. Tariff
for electricity feeding into national grid is considered as avoided cost of EVN resulting the
average value of 606 VND/kWh26.
"Off grid hydropower"
26 See 11.1 “Tariff structure”
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
Grid connectedhydropower
Connection tothe grid
Diesel generator Off gridhydropower
Ele
ctrif
ied
cost
(mil
VN
D)
0
1,000
2,000
3,000
4,000
5,000
6,000
Ele
ctric
ity c
ost (
VN
D/k
Wh)
Electrified cost for the commune Electricity cost
39
In the option, the hydropower will supply power to the commune only. Even though the
power plant has considerably higher energy output than its electricity demand of the
commune but benefit-create electricity is just equal to demand. Economic benefit of
electricity provided to commune values 4,212.8 VND/kWh as mentioned above.
The component of the two options presented in "Economic Electrification Cost". Total
investment cost for the two options are VND 10,006.5 million and VND 6,873.4 million,
respectively.
Input data and detail calculation are presented in appendix 4. Summary results are presented
in table 7.2 and figure 7.3
Table 7.2: Economic Benefit for Investment
Option Net Present Value
Internal Rate of Return
Electricity Cost
(mil VND) (%) (VND/kWh)
Grid connected hydropower 1592.7 12.2% 936.5
Off grid hydropower -950.8 8.0% 4823.1
From investment point of view, only option “grid connected hydropower” is acceptable since
benefit gained from project can cover the cost and generate profit with net present value and
internal rate of return are VND 1,592.7 million and 12.2%, respectively. The option “off
grid” should not be selected due to poor economic indicators (NPV<0 and IRR<10%) and
the unit cost is 5 times higher than that of “grid connected hydropower”. The reason leading
to economic viability of “grid connected hydropower” can be understood that, even though
the option has higher investment cost (due to larger size and additional transmission lines to
national grid) but the connection help to increase the demand for the power plant then
increase benefit-create electricity. The additional benefit coming from increasing benefit-
create energy is greater the addition cost compensating losses and generating benefit.
Therefore, from investment point of view, only the grid-connected hydropower option could
be selected.
40
Figure 7.3: Economic Benefit for investment
7.4 Sum up
Consideration made to select optimum option for developing Giap Trung hydropower from
two points of view shows that option "Grid connected hydropower" is the best option.
Therefore the hydropower with install capacity of 244 kW, connected to national grid is
selected to exploit the hydropower potential available in order to electrify the commune of
Giap Trung and feed power to national grid.
8 Allocation and mobilization of capital investment
8.1 Allocation of investment
Private investor, who is interested in developing Giap Trung mini hydropower, will act as an
Independent Power Producer (IPP) not a retain seller. According to clause 15, chapter III,
Decree 45/2001/ND-CP issued 02.08.2001 by GOV the IPP is responsible for power plant to
generate and transmit power to customer’s grid. The domain of the power plant, which is
invested by IPP, is defined as whole power plant and transmission lines to the grid of
customer27. Follow that, the investor will bear the cost for Giap Trung hydropower and MV
27 Construction Publish House, Hanoi 2001, p. 39
-1,500
-1,000
-500
0
500
1,000
1,500
2,000
Grid connected hydropower Off grid hydropower
Net
Pre
sent
Val
ue (m
il V
ND
)
0%
2%
4%
6%
8%
10%
12%
14%
Inte
rnal
Rat
e of
Ret
urn
(%)
Net Present Value Internal Rate of Return
41
transmission lines to national grid (to nearest EVN’s substation, which is 7.5 km distance),
hereafter called “hydropower plant”. The investment cost of investor is estimated VND
5,898.2 million. The remaining of the scheme, hereafter called “commune grid”, which
includes MV lines to the commune, transformers located in villages, LV
transmission/distribution lines and connection fee, will be cover by GOV and local
household’s contribution in accordant with clause 5, chapter VI, Decree 45/2001/ND-CP28.
The figure of 4,108.3 million VND is calculated for investment cost of the commune grid.
Figure 8.1: Allocation of Investment Cost
Government and
households38%
Investor62%
At present, there is no existing power utility available to take over the commune grid. The
organization or individual, who will operate the grid should involve into the project from
preparation stage to implement the investment, which is considered as a part of the whole
hydropower scheme. There are 2 options for the management of the commune grid are put
into consideration as follows:
1) The grid will be constructed and operated independently from the power plant by a
entity such as electrical cooperative or electricity group, which may comprises of
members of the commune or any interests individual. The entity will act as a retail
dealer buying electricity from the power plant to deliver to every household.
Wholesale tariff applied to the retail dealer and retail tariff to households will be
defined by negotiating between investor and the entity, and between the entity and
28 Construction Publish House, Hanoi 2001, p. 63
42
households, respectively. Clear ownership and operation responsibility is an
advantage of the option. The investor will responsible for the power plant only,
avoiding complication of contracting and collecting money from every household.
However the option has following disadvantages (i) the retail tariff charged to the
households is likely very high29; (ii) Poor maintenance to the grid due to lack of
trained staffs; and (iii) Difficulty in construction caused by lack comprehensive
management, lack of cooperation among constructors, etc that may lead to longer
period of the construction.
2) The investor will construct and operate the grid as a part of the hydropower scheme.
The power plant sells electricity directly to households and responsible for repair and
maintenance of the grid. Investment cost for the grid will be transfer to the investor
as a grant during construction period. The retail tariff will be defined by discussion
among the investor, representative of the commune and the Department of Industry
of Ha Giang province. The option might terminate all disadvantages of the previous
option, therefore supposed to applied for Giap Trung hydropower project.
8.2 Mobilization of investment capital
8.2.1 Capital for Commune grid
According to clause 5, chapter VI, Decree 45/2001/ND-CP issued 02.08.2001 by GOV 30
Investment cost for transmission and distribution facilities including 04 kV backbone and
branch lines will be cover by state budget. Connected households should be responsible for
connection to their house including meter. In additional, they need to pay a connection fee,
which is stated by EVN of VND 450000/connection, and other contribution in kind depends
on the practical situation. Total capital contributed by GOV and household is VND 4,108.3
million.
8.2.2 Capital for power plant
Investor contributes an investment cost of VND 5,898.2 million for hydropower. The
investor can mobilize all possible financial sources for the project. Specific financial sources
29 High tariff is experienced in most rural areas that has grid operated by electricity cooperative or electricity group. The reasons are (i) high losses including technical and non-technical reasons, (ii) corruption, and (iii) The cooperative or group have advantage to force households pay for higher tariff. 30 Construction Publish House, Hanoi 2001, p. 39
43
as well as financial condition will be defined at further stage by investors. Hereafter are
possible financial sources might be put into consideration to mobilize for the project:
Grant
Grant is the capital contributed to project without repayment. Grant or subsidies from
government may be targeted towards a particular aspect such as non-polluting generation or
rural electrification. Grant help to reduce borrowing requirement then benefit investors and
customers. Under present circumstance in Vietnam, Giap Trung hydropower investors can
expect grants from following sources:
(i) From GOV/province of Ha Giang: Since Giap Trung is one of the poorest
communes in the province then support is needed to improve living standard of
the people. In addition, the project belongs to rural electrification program then
investors can apply for the grant from GOV ’s as stated in clause 50, chapter VI,
Decree 45/2001/ND-CP31. In fact, however, the grant appears not realistic since
GOV are expressing not willing to subsidy for grid connected power project but
support by committing to purchase all the energy output from these projects at
reasonable price.
(ii) From multilateral or bilateral agencies for development support: The grant is
more realistic since there are several organizations are willing to fund for such
the project in Vietnam on Project Planning, Engineering Design stage such as
Japan International Cooperation Agency (JICA), Swedish international
Development Agency (SIDA), etc. In order to get the grant, investor should
summit a proposal to the organizations and/or Vietnamese authorities for
approval.
Subsidy from Prototype Carbon Fund (PCF) and Global Environment Facility
(GEF) also might be put into consideration. PCF’s subsidy comes from purchase
credits based on calculated emissions from baseline carbon emissions with the
price paid to SPPs at US$ 3 – 4/ton. 25% of the amount will be paid upfront, 75%
over term years (the term last from 10 to 21 year)32.
31 Construction Publisher, Hanoi 2001, p. 63
32 Steven Ferrey, 2002, p. 18
44
(iii) From non-governmental organization as contribution towards socio-economic
advancement
Equity
Equity is the investment capital contributed by investors. At present no regulation states
proportion of equity for investment capital for IPPs in Vietnam. Investors tend to reduce
their contribution due to lack of capital available and bank’s interest rates are often lower
than their opportunity cost. In addition, investors think this also reduces their risk in
investment. However, the banks and financial funds always expect a high equity rate from
investor to ensure that they really involve in the investment. As a rule of thumb, a rate of 20-
30% from equity to investment capital is acceptable in Vietnam. A figure of 30% investment
cost equivalent to VND 1,769.5 million VND is assumed to be contributed by investor on
equity.
Loans
Investor can mobilize investment capital from two kind of loan (i) Concessionary loan, and
(ii) commercial loan.
Concessionary loans
Concessionary loan is understood as “soft loan” which has low interest rate and long grace
and repayment period. For Giap Trung hydropower the loan can be obtained from fund for
rural electrification program which is conducting in Vietnam with the interest rate about
3%/a – 6.5%/a33. Investor also could search Concessionary loan directly from multilateral or
bilateral agencies such as World Bank, PCF, GEF, SIDA, JICA, JBIC, etc. At present World
Bank in Vietnam has an available fund for SPP program development34. To get the loan
investor need to submit proposal to World Bank Vietnam and MOI for approval.
Concessionary loans also may come from electrical and mechanical equipment suppliers
who offer the payment by installment with very low interest rate (from 1% to 3%)35. It is
33 Interview by author with Mr. Pham, MOI, 28.10.2002
34 Steven Ferrey, 2002, p. 19
35 PECC 1
45
assumed that investor will get 30% investment cost, equivalent to VND 1,769.5 million on
concessionary loan with interest of 6.0% in average36.
Commercial loans
The most favor commercial fund for the projects is Fund for Investment Promotion (FIP)37.
The interest rate of the fund is regulated at 9%/year but might be lower in some cases. It is
expected that the investor can borrow the remaining 40% investment cost from the fund with
interest rate of 9%, grace and repayment periods are 1 and 10 years, respectively. In case, the
fund refuse to provide all required investment investor can search other loans from the Bank
for Agriculture and Rural Development (BARD), Bank for Investment and Development
(BID), etc with a little higher interest rate.
9 Institutional issues
9.1 Institutional framework for power sector
Vietnams energy sector is owned and controlled by the central government. The Ministry of
Industry (formerly the Ministry of Energy) is responsible for policy and oversight of the
power sector. Electricity Corporation of Vietnam (EVN) is responsible for all the industry
development and regulation.
EVN is a State Corporation established in 1995 under the State Enterprise Law. Under the
current regulations (Government Decree No 80), EVN is responsible for the management,
operation and development of Vietnam's entire power generation, transmission and
distribution system. This is done through a number of power sector entities. Those that may
play a part in the establishment and operation of small hydropower stations are:
1) The Institute of Energy (IOE) in identification and planning.
2) The Power Engineering Consulting Companies (PECC1, 2 and 3) in investigation
and design.
36 The similar proportion is obtained by Ta Liec grid connected hydropower in 2000. Source PECC1.
37 Fund for Investment Promotion is non-profit fund formed and run by GOV aiming to finance for development projects especially key and preferential projects. The fund offers lower interest rate and longer amortization period compared to other funds.
46
3) Transmission business unit (National Load Dispatch Center and 4 Transmission
Companies) in load dispatch though small hydro could be treated as part of the load
and not require central dispatch.
4) The three Power Companies (PC1, PC2 and PC3) in distributing power in the rural
areas.
5) The construction companies.
The retail tariff applied for electrified areas under direct management of EVN is regulated by
GOV based on the proposal by EVN. At present the retail tariff is about 2/3 of the long-term
marginal cost38 (LRMC) representing heavy subsidy from GOV to power sector. For areas
out of the EVN's grid, the tariff is defined through negotiating between seller and buyer.
9.2 New electricity law and the impact39
A Draft Electricity Law is currently in circulation amongst government agencies. However,
it is expected that there will be considerable change in the law and eventually supersede
Decree No.80.
The draft Electricity Law is understood to have the following aims:
(i) Establish a regulatory framework for the power sector
(ii) Protect the autonomy and commercialized operations of enterprises.
(iii) Specify rights and obligations of construction enterprises and consumers.
(iv) Establish regulatory functions of the Government agencies in planning,
licensing, pricing formulation, management and inspection of electricity
activities.
(v) Specify the principles for electricity price determination, one of which is non-
monopoly pricing.
38 Bogash, 2000, p. 5
39 Worley, 1999, p27
47
(vi) Encourage private sector investment in the power sector, especially rural
electrification, and help to reduce barriers to the functioning of market
forces.
(vii) Commercialize and corporatise the power sector, including distribution
utilities
(viii) Allow and ensure fair competition in electricity production and trading.
(ix) Allow various forms of investment and ownership in the generation sector.
(x) Minimize and simplify administrative controls on IPPs.
The final Draft Electricity Law is submitted to the National Assembly at the end of 2000 and
is expected to become law by the end of 2003. In the mean time, Decree No.80 is to be
adjusted by three decrees40 currently at different stages of preparation.
Under the existing Decree No.80, small hydropower projects would be planned, constructed
and operated by EVN, the work at each stage being allocated to the appropriate entity. The
expansion required to meet growth in demand and government objectives is greater than can
be met by EVN and GOV resources. Institutional growth to meet this expansion is not a
practical option. The Electricity Law will allow the shortfall to be met by IPPs based on
commercial mechanism. GOV supposes that local interests will develop the small
hydropower projects with the assistance of commercial companies. The prospective
Electricity Law will provide a legal framework for this. In the interim, until the Electricity
Law becomes law, it is expected that interim decrees will be made to meet specific cases.
These are likely to conform to the draft Electricity Law.
9.3 Applications and approvals
In addition to electricity law, project rights must be obtained under laws governing foreign
investment and environmental protection and compensation.
According to clause 12, chapter II, Decree 45/2001/ND-CP 41 and experience from
implemented projects, development of a small hydropower project by local and commercial
interests will involve the following steps:
40 Latest Decree is 45/2001/ND-CP issued August, 02nd , 2001 by GOV 41 Construction Publisher, Hanoi 2001, p. 37
48
1) Preparation or purchase a pre-feasibility study.
2) Signing of a Memorandum of Understanding (MOU) with EVN. MOU can be
obtained only by a licensed and registered business entity.
3) Preparation of a feasibility study, and environmental and social impact assessment
for approval.
4) Approval is granted by an Evaluation Committee comprising representatives of
relevant authorities and other agencies in accordant with clause 3, chapter I, Decree
45/2001/ND-CP42 assigned to review the proposed development.
5) Investment approval must be obtained from the appropriate Ministry-Prime
Ministerial approval is required in the case of foreign investment.
6) The power purchase agreement with EVN can be finalized once the above steps have
been completed. Power can be sold only to EVN.
7) Applications to the appropriate authorities for:
- Construction approval.
- Approval of land use, clearance and compensation.
- Import licenses for imported plant and equipment.
- A grid interconnection.
The project may proceed once these authorities are obtained.
9.4 Institutional development
Experience in developing IPP in Vietnam 43 has reported reluctance of some investors
involved in the process. For most of them the process is seen as too complex and lengthy
requiring negotiation at many stages and have stressed a need for simplification.
Theory, most of the steps listed above can be routine applications for authority from
government agencies once the planning approval has been obtained. If investors can provide
42 Construction Publisher, Hanoi 2001, p. 31
43 Information gained in workshop on PPA in Hanoi, December 2002
49
the project, which is developed with the appropriate consultation, and has obtained the
planning approval and meets GOV objectives as well as EVN regulations, It seems no reason
why these approvals should not be expeditiously granted. In fact, however, the process is
complicated and time consuming. The main reason is lack of comprehensive regulations and
criteria for approval and no clear responsibility of concerned authorities as well.
The procedures are new and have been applied in only a few small hydropower cases so far.
The system should improve with practice. Test cases need to go through to test the system
and show where improvements should be made. Lack of confidence will inhibit investment
at the outset and delay the opportunity for investment.
To meet the objective of GOV in promoting renewable energy development and rural
development, the number of the projects need to increase markedly. To support that, the
development process needs to be simplified and clear. Standard criteria and requirement
need to be set up for approval.
10 Legal framework for setting up enterprise
At present, IPPs/SPPs are investment models to be encouraged to develop in Vietnam in
order to (i) meet increasing demand of electricity and electrify local households; (ii) lessen
financial burden of stage budget on investment of power project and; (iii) increasing
efficiency of natural resource utilization to generate electricity.
It is intended that local utility will be set up to develop Giap Trung hydropower project as a
SPP with the purpose of (i) Provide electricity directly to local people and (ii) selling
electricity to national grid. According to enterprise models stated in “Laws of Enterprises44”
the local utility can be either (i) Jointly -Owned Utility (Share Holding Company) or (ii)
Liability Limited Company.
In general, Joint Owned Utility or Liability Limited Company is owned by a number of
shareholders 45 who hold either shares (in case of Jointly Owned Utility) or capital
contribution certificate (in case of Liability Limited Company). Shares can be sold freely
while capital contribution certificate can be sold to a non-member only after having offered
44 National Political Publish House, Hanoi 1999
50
these first to the co-members for purchase. Jointly Owned Utility's organization structure
consists of three level: General Meeting of Shareholders, The Board of Management and the
general director, and his management team while a Limited Liability Company's structures
consists of a members' Council (in case of Limited Liability Company has more than one
member), a Chairman of the Member's council and a General Director, who can be identical
the Chairman. The detail organization structure of Jointly Owned Utility and Electricity
Liability Limited Company are illustrated in figures 10.1 and 10.2.
Figure 10.1: Organization structure of Jointly Owning Utility
45 Maximum 50 shareholders for Liability Limited Company and unlimited number of shareholders for share holding company.
General meetings of shareholder
Board of Management
General Director
Operators Accountant Treasurer Supervision and billing team
51
Figure 10.2: Organization structure of Liability Limited Company
Due to limits on membership, the management structure of a Liability Limited Company is
slightly simpler and more direct than in a Jointly Owning Utility. The Member Council
resembles the Assembly of Shareholders, but has more in-depth discussion on company
policy and strategy due to the absence of a management Board. The Chairman of the
Members Council can, if he is different from the Director, perform some of the supervisory
functions on daily management, which a Board performs in JSC. However, flexibility to
adjust of jointly owning utility is greater due to their corporate governance structure, which
eases decision taking on restructuring issues and due to their broader range of financing
option.
The investor will decide which model is suitable in the later stage. However, according to
experience on similar project in the Center of Vietnam, it is auspicious to get involve of Ha
Giang People Committee as a jointly - owner to facilitate project development process. This
will help to simple project approval process; reduce time for clearance and compensation,
etc. It is also advantageous to employ local people to work for the local utility.
According to " Laws of Enterprises46", Provincial Planning and Investment Department of
Ha Giang province is authority to grant business license to the local utility. To establish a
electricity utility in Giap Trung commune, the follow steps must be followed:
46 National Political Publish House, Hanoi 1999
Member of Council
Chairman of Members Council
General Director
Operators Accountant Treasurer Supervision and billing team
52
1. A founding assembly of shareholders/ council members must be held. List of
shareholders/ members with contributed capital proportion and its terms.
2. A Board of Management will be nominated (in case of jointly owning utility),
and a utility general director, the plant operators, the accountant, treasurer must
be appointed, the supervisory and billing team must be set up.
3. A bank account must be opened for the founding capital of the company, which
must be paid in.
4. The paper work for the official registration of the utility as a company (officially
recognized, independent legal person) must be completed and processed that
consists of:
- Business registration application
- Utility Charter
- Founding shareholders/ jointly - owners Agreement
- List of founders/ jointly - owners
- Bank statement confirming legal capital
5. The paper work for the licensing of the company as an electricity utility in power
generation and distribution must be completed and processed that includes:
- An investment license or investment decision granted by Ha Giang Peoples
Committee.
- A license for electricity activities granted by Provincial Department of
Industry.
- A tariff approval and Power Purchasing Agreement (PPA) with EVN that
include identifying the connection point with the national grid, approval on
operational procedure of the Power Plant.
Besides, the local utility has to sign PPAs with local consumers in the serving area that
include households and productive loads.
According to Laws of Enterprises, the Local Utility has to declare on its establishment on
local newspaper within 30 days since the date of granting business licensee.
53
11 Economic and financial evaluation
11.1 Tariff structure
11.1.1 Ability and willingness to pay for service
The price of the main alternative fuel tends to benchmark the willingness and ability of
consumers to pay for electricity. It is assumed that after electrified the households will shift
from using substitutable energy sources to using electricity. The following energy sources
are expected to be replaced by electricity in Giap Trung commune:
(i) Pico for lighting and TV, Radio
(ii) Kerosene and paraffin for lighting
(iii) Dry cell for touch, radio and cassette player
(iv) Diesel for productive and services use
Pico
Pico is reported the most popular energy sources for lighting with 72% of household owning
or sharing a Pico. These Picos mainly comes from China and installed by the residents
themselves. These have a rated, though probably not actual, output of 300-1000 kW, and
cost VND 250,000-700,000 each. They are most commonly used for lighting, TV and Radio.
The Pico often last 2-3 years and could not be used round year, especially in dry season due
to stream flows drop below operating parameters. When asked why all residents in the
commune do not purchase a Pico-hydro, the reason cited is usually that they are too far
distant from a stream, not that residents cannot afford it. As the bearings are of poor quality,
and windings are not sealed, operation and maintenance of Pico-hydro typically costs each
year the capital cost of replacement. The monthly maintenance cost of Pico is ranging from
VND 5000 to 40000 resulting average of VND 13000. The yearly cost for 1 Pico, therefore,
is estimated VND 298743 and for the whole commune is VND 121.0 million/year.
Kerosene and paraffin
Even 72% of households own or share a Pico but kerosene is still widely used in the
commune with 97% of households using kerosene for lighting with monthly consumption
ranging from 0.2 liter and 4 liter per household. The considerable variation in Kerosene
consumption among the households can be understood as the result of “with” and “without”
54
Pico for lighting and entertainment. Average monthly consumption is calculated 1.4
liter/households resulting in yearly fuel cost for kerosene of VND 45.1 million for the whole
commune based on the fuel cost VND 5000 per liter47.
Fuel cost for paraffin is very small that can be neglected.
Dry cell battery
Dry cell battery is used for torches and powering radio and cassette player. The average cost
is about 2500 VND/pair (1.5 V type). Calculation of 4.4 pairs per month adds 9600 VND to
the monthly energy budget. With assumption of the figure 50% is consumed for radio and
cassette player that is can be replaced be electricity from the grid. Then cost for dry cell
batteries is calculated VND 28.3 million/year for the whole commune.
Diesel fuel
Diesel fuel consumed for rice husking and wood processing will be considered as the
substitute energy source for electricity.
Total diesel consumption for rice husking is reported 4620 liters of which 1848 liter
equivalent to 40% is expected be replaced by electricity due to difficulty in transportation
and the people's habits.
The figure of 12045 liter48 is calculated for diesel fuel for wood processing based on
projected electricity consumption and assumed efficiency of diesel motor and electrical
motor are 25% and 75% respectively.
Total cost for diesel is, therefore, estimated VND 76.4 million with the price of 5500
VND/liter49.
Ability and willingness to pay for service
From calculation above total annual expense for energy sources that can be replaced by
electricity when the commune is electrified is VND 268.0 million. Detail calculation is
illustrated in appendix 5.
47 Recorded during field trips at the commune
48 Due to no actual consumption was recorded.
49 Recorded during field trips at the commune
55
11.1.2 Tariff for the commune
According to clause 38, chapter IV, Decree 45/2001/ND-CP50 the retail electricity tariffs for
domestic use are as follows:
(i) The standard tariff structure51 will be applied for area supplied by national grid.
The lowest level of the tariff is 660 VND/kWh and up to 2000 VND/kWh.
(ii) For the areas, which are supplied by non-utility, the tariff is defined by
negotiating between seller and buyer.
Follows the regulation, tariff supposed to be applied in Giap Trung commune is set up by
negotiating between investors, acting as seller and local households, the buyer. The tariff
should be meet two criteria (1) Affordable for the households, and (2) Cover the production
cost of the supplier.
As estimated on “Ability and willingness to pas for the service” the annual total fuel cost for
Giap Trung commune is VND 268.0 million. The service can be met by 163428 kWh
electricity provided by the hydropower scheme then the willingness to pay for 1 kWh
electricity of the commune can be estimated at 1640 VND/kWh (that is total present fuel
cost divided by electricity demand). From the supply side, the investor can sell electricity at
the price of 582 VND/kWh to national grid52. To sell electricity to the commune, supplier
need to cover O&M cost of the commune grid, which is estimated 61.6 million VND,
equivalent to 1.5% of investment cost, plus cost of 25 – 30 million VND for monthly record,
billing, collecting money, etc means the supplier pays additional cost of 85 – 90 million
VND in total, equivalent to 530 to 560 VND/kWh. The price, which can cover production
cost for supplier, therefore, is estimated 1100 to 1200/kWh lower than ability to pay of
households. Therefore the price of 1200 VND/kWh is rational and supposed to apply for
Giap Trung commune.
The proposed tariff is higher than average tariff applied for electricity provided from
national grid. However, the gap will be decrease dramatically when the average national
grid’s tariff likely increases from 5.2 US cent/kWh (800 VND) to 7.0 US cent/kWh (1100
50 Construction Publisher, Hanoi 2001, p. 52
51 Issued by GOV which is a stair tariff increasing with the amount of electricity consumed.
52 See 11.1.3 “tariff to national grid”
56
VND) by the year 200553. At present tariff ranging from 1000 to 1300 VND/kWh are
applied in some areas provided by off grid connected hydropower and even national grid54.
The fact shows that the price is affordable for the households since the monthly cost for
electricity ranging from 13000 to 40000 VND for 12 - 30 kWh consumption. The reason
caused difficulty in rural electrification is the costs of connection, not the costs of electricity
use. Interviewed people in the commune also expressed their willing to pay for such amount
of money for their consumption based on the tariff 1200-13000 VND/kWh.
11.1.3 Tariff for electricity feeding into national grid
Even after great effort of GOV, particularly MOI and EVN as well as support from WB and
other international organization, a Standard Power Purchasing Agreement has not been
established yet. The purchase tariff applied for SPPs, which is conducting in Vietnam, is
defined through negotiation between EVN and SPPs. Hopefully; however, the Standard
Power Purchasing Agreement will be published very soon.
In the workshop on PPAs hold in Hanoi on 20th December 2002, representative of EVN, Mr
Do Quang Tri, vice director of EVN, one again stated EVN's support to SPPs by buying all
electricity generated by SPPs following a standard Power Purchasing Agreement, in which
the purchasing tariff, in principle, will be defined based on the avoided cost of EVN. For
coming time, due to no SPPA available, the tariff will be defined at reasonable level that can
compensate cost and create profit to IPPs through negotiation between IPPs and EVN.
In practice, some IPPs have contracted to EVN selling electricity to the national grid at the
tariff ranging from 3.5 US cent/kWh to 4.5 US cent/kWh55. One of the investors, Urban and
Industry Zone Investment Company, in 2002 have signed a contract to feed electricity to the
national grid from 1040 kW Sork Phu Mieng small hydropower at the tariff presented in
table 11.1.
The actual purchasing tariff for Giap Trung hydropower will be definded by its owner and
EVN at next step. However, in the study to facilitate calculation, the tariff for Srok Phu
Mieng is assumed to be applied for Giap Trung hydropower.
53 www.vnexpress.net, printed on 10.02.2003
54 Union Newspaper, issued on 18.08.2002
55 EVN
57
Table 11.1: Purchasing tariff for Srok Phu Mieng hydropower56
(The tariff excluding VAT tax)
Currency Wet season
(July 1st to October, 30th)
Dry season
(October, 1st to June, 30th)
US$ cent 2.5 4.5
VND 385 693
11.2 Economic evaluation
Economic evaluation is done from the economy point of view that allows assessing
efficiency of allocation of scarce national resources. An investment is considered efficient if
benefit created by the investment is greater than the paid cost. To evaluate economic
visibility of Giap Trung project, method "Cost and Benefit comparison" is used with
economic indicators as follows:
(i) Net present value (NPV)
(ii) Economic internal rate of return (EIRR)
(iii) Product unit cost (Pc)
Economic cost is all expenses to set up the project excluding tax and internal transfers. To
simplify a conversion of 0.9, which is accepted in Vietnam57 is used to convert financial cost
to economic cost resulting the figure of VND 9005.8 million for economic cost of the
hydropower scheme.
Economic benefit of the projects comprises of:
(i) Benefit of electrification for the Giap Trung commune. Economic benefit is
calculated at 4213 VND/kWh electricity provided to the commune58.
56 Official dispatch number 3429 CV-EVN-KD&DNT
57 EVN, PECC 1
58 See 7.3 “Economic benefit of investment”
58
(ii) Electricity feeding into the national grid. Monetary value of the benefit is
calculated equal to economic avoided cost59 of Vietnam's power system which is
presented in table 11.2
Table 11.2: Economic avoided cost to EVN 60
Tariff Dry season Wet season
US$ cent VND US$ cent VND
Energy 4.73 710 2.81 422
Energy plus capacity 6.73 1010 4.81 722
Result done by the Project Analysis Model show the Economic Net Present Value of the
project is VND 3070.6 million, equivalent to US$ 201410, Economic Internal Rate of Return
reaches at high levet at 15.2%, and the unit cost of 850.8 VND/kWh or US 5.5 cent/kWh. It
is concluded that the project is economically viable. Detail calculation is presented in
appendix 5.
Sensitivity analysis
Sensitivity analysis is done to verify the project viability in unfavorable circumstances as
follows:
1) The investment cost increases 10%
2) The annual output decrease 10%
3) Load demand of the commune decrease 10%
Sensitivity analysis result illustrated in table 11.3 and figure 11.1 shows that even in the
considered unfavorable circumstances Giap Trung mini hydropower still economically
feasible. It is efficient to allocate national resource to develop the hydropower
59 Avoided cost for energy only
60 Tran, 2001, p 26
59
Table 11.3: Economic Sensitivity Analysis
Sensitivity cases
Indicator Base case Investment increase 10%
Output decrease 10%
Commune demand
decrease 10%
NPV (mil. VND) 3,070.6 2,103.9 2,407.6 2,559.5
IRR (%) 15.2% 13.3% 14.1% 14.4%
Unit cost (VND/kWh) 850.8 934.5 945.9 850.4
.
Figure 11.1: Economic Sensitivity Analysis
11.3 Financial Analysis
Financial analysis is done from the investor interest to the project. Financial viability is the
most important factor deciding the attractiveness of a project to investor. Investor is willing
to develop the project only the investment could bring profit to them. Financial analysis on
equity, therefore, is carried out for Giap Trung hydropower. Financial indicators are taken
into consideration as follows:
0
500
1000
1500
2000
2500
3000
3500
Base case Investmentincrease 10%
Output decrease10%
Commune demanddecease 10%
12%
13%
13%
14%
14%
15%
15%
16%
NPV EIRR
60
(i) Net present value NPV
(ii) Internal rate of Return FIRR
(iii) Unit cost before tax Pc
(iv) Payback period PBP
Discount rate of 12%/year is used in the calculation that reflects the opportunity cost in
Vietnam and risk in hydropower development.
Analysis period is 25 years from the project go into commercial operation.
Costs of the project comprises of:
(i) Investment capital: Total capital investment for the project is estimated VND
10,006.5 million, equivalent to US$ 649,770. Of which VND 1,769.5 million
(30% investment cost) will be contributed by the investor as equity, VND 1,769.5
million comes from foreign loan with interest rate of 6.0%, amortization period
of 10 years. The rest of VND 2,359.3 million will be mobilized from local loan
with interest rate of 9.0%, amortization period of 10 years.
(ii) Operation and maintenance costs, which comprises of employee's wage,
maintenance and repair of electro-mechanical equipment, civil works and
transmission lines, insurance against electrical and mechanical equipment
breakdown and administration costs, is estimated 3% and 1.5% of investment
cost for hydropower plant and transmission/distribution lines, respectively. In
additional, the plant need to pay for money collection done by local labor and
billing. The cost is estimated VND 20.0 million. In total, the O&M is VND 236.2
million.
(iii) Water use fee is 1% of total turnover of the power plant.61
(iv) Taxes: According to Ordinance of Management of Investment and Construction,
Regulations on promotion of investment and developments, the local utility is
exempted from land tax. Enterprise tax imposes on profit of enterprise. The tax
rate varies to location, business field, size of impose enterprise. For Giap Trung
61 Stipulated on Natural Resources Utilization Law issued on August 12th 1995
61
project, the plant is exempted for first 4 years sine profit occurs, pays
concessionary rate of 7.5% for next 7 years and 15% for the following years62.
VAT rate is 10% of turnover applied in Vietnam for electricity commodity.
However, the tariff excluding VAT tax is considered then the VAT is not
considered in the calculation.
Revenue of the project comprise of:
(i) Revenue comes from selling electricity to the commune grid. The annual
turnover is calculated based on power demand projection for the commune and
the tariff of 1200 VND/kWh63. The revenue is increasing over years due to
increasing of the commune demand.
(ii) EVN will purchase all the remaining energy from the power plant after the power
plant has supplied electricity to the commune. The tariff to the electricity fed into
national grid is estimated at 582 VND/kWh.
(iii) Return input VAT: The plant will receive the input VAT tax from GOV. It is
assumed plant receive the money at the end of construction period, values VND
500.3 million, equivalent to 5%64 of investment cost.
Detail input data and calculation for financial analysis is presented in appendix 5.
Financial analysis calculation done by Project Analysis Model gives the results as follows:
Net present value VND 305.7 million
Internal rate of Return 13.8 %
Payback period 10 years
Unit cost before tax 617.6 VND/kWh
The project is financially feasible. However, if take risk in hydropower investment into
consideration, the project is attractive to investor but not at high level. To encourage private
62 Construction Publish House, 1999, p. 96, 99, 132,136
63 See 11.1 “Tariff structure”
64 PECC1. The figure is accepted in Vietnam to estimate input VAT for hydropower.
62
investor to invest in the project, promote measures are needed from GOV such as accept the
purchase tariff equal to avoided cost of EVN, exempt enterprise tax or “soft” loan with lower
interest tare and longer amortization period, etc. The effect of the measures will be discussed
in sensitivity analysis.
Sensitivity Analysis
Sensitivity analysis is done aiming to verify the viability of the project incase there is
fluctuation of factors, which affect to the project. The fluctuations affect to project viability
into two trends (i) Advantage and (ii) disadvantage. For that purpose, sensitivity analysis is
done for following alternatives:
Advantage trend:
- Tariff to national grid increase 10% near to energy avoided cost of EVN.
- The commune electricity demand increase 10%.
- Investor gets the local loan with interest rate lower to 7%.
- Proportion of foreign increase to 70%, no local loan needed.
Disadvantage cases:
- The investment cost increases 10%.
- Annual output decreases 10%.
- The commune electricity demand increase 10%.
- All loans need to mobilize from local loan.
Sensitivity analysis results show that tariff to national grid and financial
arrangements are the most sensitive factors coming from outside, while investment
cost and energy output are from the project. Investors, therefore, need to verify the
technical data. It is suggested that a reputed consultant should be hired to carry
further stage of the project. Beside that, result of negotiating to EVN and practice
capital mobilization also need to put into consideration to come up a final decision
for Giap Trung hydropower project.
63
Table 11.4: Financial Sensitivity Analysis
Indicator Base case Tariff
increase
10%
Commune
demand
Increase
10%
Foreign
loan reach
to 70%
Interest
rate 7%,
Investment
increase
10%
Output
decrease
10%
Commune
demand
decrease
10%
Local loan
account
for 70%
NPV (mil. VND) 306.7 781.2 380.4 562.4 478.2 (263.9) (247.6) 233.0 113.6
IRR (%) 13.8% 16.7% 14.3% 15.6% 15.0% 10.6% 10.6% 13.4% 12.6%
Payback period (year) 10 8 10 9 10 11 11 10 11
Unit cost (VND/kWh) 618 618 618 591.6 600 676 685 618 637
64
Figure 11.2: Financial Sensitivity Analysis
-400
-200
0
200
400
600
800
1,000
Tariffincrease
10%
CommunedemandIncrease
10%
Foreign loanreach to
70%
Interest rate7%,
Base case Investmentincrease
10%
Outputdecrease
10%
Communedemanddecrease
10%
Local loan account for
70%
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
NPV FIRR
12 Business plan
12.1 Marketing Plan
Giap Trung hydropower will be built at river Nam Nung, 2.5 km distance from Giap Trung
commune, Bac Me district, Northern province of Ha Giang. The power plant with capacity
of 244 kW, annual output of 1.452 106kWh will supply electricity to the commune and
selling surplus electricity to national grid.
Since to be connected to national grid, the project can sell all energy output to the
commune and national grid with the tariff are 1200 VND/kWh and 582 VND/kWh,
respectively. Most revenue of the power plant will come from selling to national grid but
the figure will reduce over the year because of growing of the commune electricity
demand. That means that the turnover of the project will increase over the year due to
higher tariff charged to commune than that to national grid.
(i) It is clear that the proportion of electricity sold to commune in total selling
affects to revenue of the project, a decreasing of the selling means a reduction
in revenue and vice-verse. Therefore, promotional measure should focus on the
market. Followings are measures need to do to increase selling to the commune:
65
(ii) To sign commitment of electricity using with possible connected households.
(iii) Assure operation of the transmission/distribution system always in good
condition.
(iv) Encourage households using electricity by campaigns on benefit of using
electricity, safety in using, etc.
(v) Promote productive use by offering lower tariff
12.2 Production Plan
Electricity generated at powerhouse will be transmitted to EVN’s 35 kV substation (7.5 km
distance) and village center (0.8 km length) by MV 35 kV transmission lines. In the
commune, power is reduced to 0.4 kV by transformers to backbone lines and then
connected to households. The losses on transmission lines to EVN’s substation and on the
commune grid is estimated at 1% and 5% respectively.
The project comprises of hydropower plant and transmission/distribution grid system that
has life span expected 25 year. Total investment for the project is VND10, 006.5 million.
The construction of civil work and equipment supply will be implemented by tendering.
Since the scheme is connected to national grid then the plant can generated at 100% its
capacity with average annual output of 1.452 106kWh for every year.
Generally, the proposed hydropower scheme will be operated 24 hours a day. The plant
will occasionally be shut down in order to carry out necessary maintenance or repair work
at the plant. Whenever possible such work will be executed during dry periods, when the
limited river flow restricts hydropower operation anyway. Six employees will be
contracted as operators of the hydropower scheme. They will work in shifts of 8 hours. All
operators will be instructed and trained in the operation and maintenance of the
hydropower plant. The training of the operators starts during the construction of the
scheme. On-the-job training is provided throughout the commissioning and testing of the
plant leading to a smooth transition to normal operation of the plant. Operation and
maintenance procedures will be described in the special manuals for the micro hydropower
plant, which are prepared by the project engineer as part of the project implementation, or
provided by the equipment suppliers.
66
Maintenance schedule for civil work is presented in table 12.165. The suppliers of the
equipment, together with the operation manuals, will provide maintenance schedules for
the electro-mechanical equipment. The maintenance schedule for the transmission and
distribution facilities will be elaborated in close cooperation with EVN, whose standards
will be applied.
Table 12.1: Maintenance Schedule for Civil Work
Maintenance Schedule Civil Works All year Drought Flood Weir and Intake Check for boulder damage Monthly Daily Check for leaks, undercutting Once Flushing Sluice, Intake Gate Check operation Monthly Grease screw Monthly Adjust As needed As needed Settling Basin Grease flushing sluice screw Monthly Drain and clean Monthly Weekly Sealing leaks and general repairs Annually Headrace Canal Inspect for leaks, overflowing Weekly Daily Drain and Clean Every 3 months Clean culverts Monthly Daily Sealing leaks and general repairs Annually Fore bay Clean screen Daily Check screen Weekly Daily Grease valves Monthly Drain and clean Monthly Monthly Weekly Sealing leaks and general repairs Annually Penstock Visual check for leaks Monthly Repaint Every 2 years Visual corrosion check Once Inspection of supports Annually Powerhouse Check roof Annually
65 Source ENTEC AG, 2002
67
Power purchasing Agreement
(i) Power purchasing Agreement to Households
A contract on selling/buying electricity need to be signed between the investor and each
connected households in the commune. The contract should be in accordance with chapter
IV, Decree 45/2001/ND-CP 66 on selling/buying and using electricity. The main
components of the contracts are as follows:
- General information of seller and buyer.
- Purpose of electricity using, agreement on installation and equipment.
- Legal requirement to seller and buyer.
- Quality of electricity provided.
- Electricity measurement and record.
- Electricity tariff and form of payment.
- Right and obligation of seller.
- Right and obligation of buyer.
- Other agreements.
(ii) Power Purchasing Agreement to EVN
In order to sell electricity to the national grid the producer need to gain a PPA with EVN.
The investor and EVN will define the detail of the PPA in further stage. The PPA should
comprises main contents as follows67:
- General information of seller and buyer
- Period of the PPA and possibility to renew.
- Facility development/operation and interconnection.
- Testing and inspection.
66 Construction Publisher, Hanoi 2001, p. 44-60
67 Summarized by author from Draft Standard Agreement for Purchase of Electrical Energy from Small Power Producer which is prepared by MOI, EVN
68
- Tariff and term of payment
- Forecasts and meters
- Disruptions and outages
- Insurance
- Indemnification and limitation of liability
- Force majeure
- Default
- Dispute resolution
- Delegation and assignment
- Notices
- Miscellaneous provisions
Electricity fee collection procedure
With the purpose of saving time and facilitate the work, it is recommended that billing and
electricity fee collection will be done by heads of village, teachers or other prestigious
people in the respective village. After fee collection, those people will return the amount of
money to the accountant of the plant and get a small amount of money (VND 100,000 per
month) as gratuity.
Production cost:
- Employee' wage: There will be 10 operators and staffs employed for the power
plant. The monthly salary of VND 600,000 per person is estimated resulting the
annual wage for employee of VND 72 million.
- Maintenance and repair of Electro-mechanical equipment, civil works and
transmission lines: The figure of VND 10.0 million is considered for the
maintenance and repair, equivalent to VND120 million per year.
- Insurance against electrical and mechanical equipment breakdown is
calculated equivalent to 0.2% of the investment cost for the equipment. That is
VND 4.1 million.
- Administration and overhead is VND 20 million per year.
- Money collection cost is assumed VND 20 million per year
69
The figure of VND 236.2 million is, therefore, estimated for O&M cost of the hydropower
scheme.
12.3 Organization & Management Plan
It is expected that a Jointly Owning Utility company (investor and Ha Giang People
Committee) will be set up to run the power plant. Organization structure of the company
and related issues are illustrated in figure 10.1 and chapter 10 “Legal framework for setting
up enterprise”.
Director and management board allocates Right and responsibility of employed staff.
Pre-Operating expenditure is estimated at VND 50.0 million.
12.4 Financial plan
A financial plan for the first 5 years is set up for the company that includes estimation of
capital requirement; calculation on monthly cash flow statement and yearly cash flow
statement, profit and losses statement and balance sheet; and break-even point calculation.
12.4.1 Investment Capital requirements of the scheme
Total investment capital cost of Giap Trung mini hydropower is VND 10,006.5 million or
about US$ 649,770. Of this figure, grant from GOV for the commune grid is VND 4,108
million accounting for 40.6%, of the rest the investor will provide 30% equivalent to VND
1,769.5 million and mobilize from banks VND 4,128.7 million VND (70%). It is assumed
that the loan comes from two sources (i) Foreign loan VND 1,769.5 million (30%) with
interest rate of 6.0%, and (ii) local loan VND 2,359.3 million (40%) at interest rate of
9.0%. The level of contributions in capital is shown in table 12.2 and figure 12.1.
Figure 12.1: Investment Capital contribution
40%
18%18%
24%
Grant Equity Foreign loan Local loan
70
Table 12.2: Investment Capital Contribution
Unit: mill. VND
Particulars Total Grant Equity Foreign loan Local loan
Contribution 10006 1769 4108 1769 2359
Percentage 100% 18% 41% 18% 24%
12.4.2 Capital requirement
At the time of establishing the company, the following capitals are required:
(i) Pre-operation expense: pre-operation expense is registration fee (about VND
5,000,000), cost of purchased office facilities, administrative cost, etc. that is
estimated at VND 50,000,000.
(ii) Working capital: working capital is running cost of the company includes
wages, O&M cost of the scheme, administration cost, re-investment cost, etc.
that is estimated for 3 months. For Giap Trung hydropower, working capital is
estimated at VND 50,000,000.
Figure 12.2: Company capital requirement
12.4.3 Borrowed loan
As mentioned above, the loan comes from two sources, e.g. foreign and local loans. Both
loans have grace period during construction time (1 year) and installment period of 10
100%
0% 0%
Fixed Assets Pre-Operating ExpensesWorking Capital
71
years. Loan payment schedule for the project is presented in the table 12.3. Analysis of
yearly cash-flow shows that the company is able to pay both principal and interest within
10 years, as scheduled with total payment reaches to VND 5880 million.
Table 12.3: Loan payment schedule
Unit: mill. VND
Year Amount of Principal
Outstanding Installment Interest Total
1 4129 -413 -319 -731
2 3716 -413 -287 -700
3 3303 -413 -255 -668
4 2890 -413 -223 -636
5 2477 -413 -191 -604
6 2064 -413 -159 -572
7 1651 -413 -127 -540
8 1239 -413 -96 -508
9 826 -413 -64 -477
10 413 -413 -32 -445
Total -4129 -1752 -5880
12.4.4 Cash-flow statement, profit/loss and balance
Yearly cash-flow statement, profit and losses statement and balance sheet are shown in
tables 12.4, 12.5 and 12.6. During first 5 years, the company has to face lost due to revenue
could not cover the production cost. The profit will occur from the year 6th and then
increase steadily. Even bearing the loss during the first 5 year, the company still has strong
cash flow statement. First, company will receive input VAT tax return from GOV that
increase cash available up to VND 481 million in the first year. Secondly, because
depreciation value of fixed assets is greater than yearly installment then the company’s
increase over the year up to VND 520 million at the end of the year 5th. It can be concluded
that the company has stable cash-flow statement.
72
Table 12.4: Yearly Cash Flow Statement
Unit: million VND
Pre-operatingYear
Particulars Activity 1st 2nd 3rd 4th 5th
Cash Inflow
Equity 1919
Loans 50
Cash Sales 936 939 942 943 945
Collection A/R 936 939 942 943 945
Other income 500 0 0 0 0
Total cash Inflow 1969 1437 939 942 943 945
Cash outflow
Pre-operation Expenses 100
Fixed assets 10006
Salary -72 -72 -72 -72 -72
Running cost -120 -120 -120 -120 -120
Administration -24 -24 -24 -24 -24
Water using fee -9 -9 -9 -9 -9
VAT tax 0 0 0 0 0
Interest -331 -298 -265 -232 -199
Loan amortization -429 -429 -429 -429 -429
Enterprise Tax 0 0 0 0 -39
Other expenses -20 -20 -20 -20 -20
Owners withdrawels 0 0 0 0 0
Total cash outflow 10106 -1005 -972 -939 -906 -912
Net cash inflow 50 431 -33 2 37 33
Cash balance beginning 50 50 481 448 450 487
Cash balance end 481 448 450 487 520
73
Table 12.5: Profit and Loss Statement
Unit: million VND
Year Year 1st Year 2nd Year 3rd Year 4th Year 5th
Sales 1437 939 942 943 945
Less
Salary -72 -72 -72 -72 -72
Running cost -120 -120 -120 -120 -120
Water using fee -9 -9 -9 -9 -9
VAT tax 0 0 0 0 0
Depreciation -500 -500 -500 -500 -500
other Overheads -20 -20 -20 -20 -20
gross profit 715 217 220 221 223
Marketing 0 0 0 0 0
Administration -24 -24 -24 -24 -24
Operating profit 691 193 196 197 199
Interest -331 -298 -265 -232 -199
Net profit before tax 360 -105 -69 -35 0
Taxes 0 0 0 0 -39
Net Profit 360 -105 -69 -35 -39
74
Table 12.6: Balance Sheet Unit: million VND
Pre- YEAR Period 1 2 3 4 5
ASSETS
Current Assets Cash 50 481 448 450 487 520 Raw Materials Inventory 0 0 0 0 0 0 Work in process 0 0 0 0 0 0 Finished Goods 0 0 0 0 0 0 Accounts receivable 0 0 0 0 0 0
Total Current Assets 50 481 448 450 487 520 Fixed Assets Other Equipment 10006 10006 10006 10006 10006 10006 Less Depreciation 0 500 1001 1501 2001 2502 Net fixed assets 10006 9506 9006 8505 8005 7505
Total fixed assets 10006 9506 9006 8505 8005 7505
Other assets 100 100 100 100 100 100 Total 10156 10088 9554 9056 8593 8125
LIABILITY
Current liabilities Accounts payable 0 0 0 0 0 0 Loans payable 0 0 0 0 0 0
Total Current liabilities 0 0 0 0 0 0 Long term liabilities 0 Loans payable 4129 3700 3271 2842 2414 1985
Total Long term liabilities 4129 3700 3271 2842 2414 1985
Owners equity Capital beginning 1919 6028 6388 6283 6214 6179 Accumulated Capital 1919 6028 6388 6283 6214 6179 plus net profit 0 360 -105 -69 -35 -39 Grant 4108 minus withdrawels
Total Owners equity 6028 6388 6283 6214 6179 6140 Total Liabilities and Equity 10156 10088 9554 9056 8593 8125
BALANCE 0 0 0 0 0 0
75
12.4.5 Break event point
Break-even point calculation is shown in the table 12.7. The Company will have lost for
the first two years. After that company start gain profit if the revenue is not smaller 621
million VND for the 3rd year and so on.
Table 12.7: Break-even point
Break-even Point (BEP) 1st Year 2nd Year 3rd Year 4th Year 5th Year
BEP (revenue) (mill. VND) 986 953 921 888 821
BEP (%) 105 102 98 94 87
12.5 Community mobilization
Community mobilization needs to be done aiming to get local community involving in
project actively and positively. Active participation of community in the project will help
to maximize benefit to community and reduce any negative impact, if happens. The
community mobilization could be divided into several stages in accordant with project
processes.
Stage 1 (at project preparation)
The objective of the stage is to raise awareness within the commune of the project and the
benefit of electricity provided from the hydropower. A community mobilization team
comprising social and hydropower expert will be sent to the commune to have meeting
with the commune leaders, perform questionnaire and gather needed information.
During the first meeting, community will be informed of the objective of the project,
benefit of using electricity from the hydropower scheme compared to other energy sources
and requirement for households to connect to the scheme. The feedback of community will
be recorded for designing.
After have draft feasibility study, the community mobilization will come back to the
commune to inform them supposed tariff and total of payment for household after
connection to the scheme. Draft design of the power plant, particularly location and layout
of the distribution system, arrangement for installation of consumer connection and meters,
location and routing of hydro weir, intake, headrace canal and powerhouse, etc. will be
published in order to find out obstacles for land acquisition and resettlement aspects.
76
Potential social impact of the project to the commune is to be informed and discussed. Any
feedback from the commune will be recorded to improve final design. A campaign on
electricity safety is done at the stage as well. Finally, households are required to sign a
commitment of using electricity provided by the hydropower scheme.
Stage 2 (at construction period)
In the stage, community is encourage to actively involve in monitoring the construction
work, assure that construction component is followed the approved design at good quality.
Any insufficient element or complain needs to inform to investors. To support that one of
the members of the commune might be appointed into controlled board acting a link
between the community and investor.
Households are required to sign to Electricity buying/selling contract. This will be legal
basic for connection to the mini grid, billing and payment. Households are also consulted
in wiring in their houses, buying electricity appliances. A group of local residents will be
selected to hired by hydropower plant to recording and collect money from households in
their villages.
Stage 3 (at operation of project)
Campaigns on electricity safety will be continued regularly. A custom service will be
established to deal with any breakdown or support to households. The community is
required to be active in protecting the grid facilities, prevent any violation to the grid, for
example to build house to near the grid, etc.
13 Expected social impact of hydro power system
As already mentioned, Electricity is not new to Giap Trung, households started using
electricity for several years ago since the first Pico was installed in the commune.
Therefore, the benefit of the project to local people need to be considered what is
advantages may be offered to local people through using power from mini hydro power
rather than their current sources of energy.
First of all, the project will electrify the commune 7 years earlier than waiting for
connection the commune to the national grid.
77
Thanks to construction of the hydropower scheme, the access road from District to Giap
Trung will be improved that create favorable condition for transportation of local people as
well as to promote possible income generating and trade activities. The track from the
commune to the hydropower is also upgraded.
The scheme will require a small amount of land for construction of powerhouse and
associated facilities. The land, crop and tree lost will be compensated. The level of
compensation will be subject to consent of project-affected people, local authorities and
contractor. There is no water diversion for irrigation or domestic use along river from weir
to powerhouse then construction has no effect on water using.
Despite the fact that many people in Giap Trung own TV sets and radios, people
interviewed repeatedly stressed the importance of having a regular information source as a
means of ‘knowing what is happening in the outside world.’ Watching television is an
enjoyable time for local people and also a very important means for accessing news and
information from outside the commune. Electricity provides potential to regularly access to
information source. There is a potentially negative rose from accessing information from
outside that cultural values and indigenous culture may be affected and changed. But as
stated by local people, access to outside information is very important to them.
At present in the commune there is a total of 85 TV sets. Although some of these
televisions are colors TV, it is not possible to get color due to low quality of power
supplied from Picos. People expressed that, if the project could provide stable source of
electricity they would purchase more TVs, particularly color TVs.
Local people seemed fervent with possible of having good lighting at home. It is likely that
a stable source of energy in the evening will allow their children to study better. It is also
stated that the use of electricity in the evening would allow adults to carry on activities
such as sewing, weaving and housework more effectively. Currently, most of people stated
having a rest at evening. This does not mean they have no work to do but because they
could not do due to lack of lighting.
There are several ways in which the project offers opportunities for reducing labor loads.
Certainly, men and women can be expected to be affected differently.
There are already rice milling and husking machines in the commune, but fee for husking
by the machines is expensive. It may be anticipated that these services will become more
78
affordable, and people would use them more regularly, if the owners of the mills could
access to a cheaper, but reliable, source of energy. Currently women do milling and
husking, when it is done by hand, so this is a key way by which the project might bring
real improvements to women’s lives.
The project also has potential to reduce the current burden for women of collecting
firewood. (The survey and interviews show that firewood mainly done by women).
Currently, local women spend up to 2 hours every day to collect firewood. If households
could use electricity for cooking (e.g. electric kettles and rice cookers), women’s labor
loads will be reduced, and less wood will need to be cut from the surrounding hills.
However, the change from firewood to electricity for cooking could not happen
spontaneously. Currently, people can collect wood free from surrounding hills so they will
not be wiling to change to electricity. Furthermore, the use of electric kettles and rice
cookers is virtually unknown in the commune. Some effort could have to be made to
convince local people of the potential benefits of cooking with electricity and the changing
might be initiated by rich households when they start using electricity for cooking.
Households who owning pico hydro generators are expected likely to convert to use
electricity from the hydropower scheme. The main reason for this, as they said, is that pico
generators require almost constant maintenance and attention and costly. This is usually a
man’s job, and then the project might free men from this daily task.
Positive impact of the project to health of the inhabitants might be expected. Currently, the
health clinic in Giap Trung commune center is running two light bulbs up to 10:30pm
powered by the generator of the frontier guard post. Health professionals have two to three
years' training, but often cannot put it into practice because the lack of facilities. The head
of this clinic confirmed that electricity from the hydropower scheme would be an
improvement on the current situation. Improved lighting can be expected to improve the
conditions of care within the clinics. However electricity in commune clinic does not mean
leading to equip electrical equipment such as refrigerators, electrical sterilization facilities,
etc to clinic.
Changes from the use of firewood in households to the use of electricity for cooking can be
expected to bring improvements in the respiratory health of people within Giap Trung
commune. However, as stated above, it would need additional effort to convince people
using electricity instead of firewood.
79
The risks associated with improper use of electricity could be a negative impact. However,
as mentioned already, the use of Pico in the commune is very popular and local people
already have experience with using electricity. But a campaign on safety in using
electricity is still needed to both adults and children to prevent accidents from happening or
lessen their impact.
Currently, classrooms in the commune are not electrified and teachers use candles for
lighting in the evenings. Interviewed teachers do not think lighting for daytime classes is
necessary and stated no classes held in the evening. However, electricity could help
children do their homework at night and improve teachers living conditions. It is unlikely
that school budgets in the remote area could afford for electronic teaching aids (such as
audio visual equipment) but the presence of electricity in classrooms would certainly create
possibility for the future.
Long-term job opportunities created directly by the project are small since very small staff
needed for the hydropower scheme. Several people will be hired to collect money from
households living in the villages. However, during construction period, project requires
large unskilled labor, mainly for clearance, excavation, damping and transportation that
can be qualified by the local people. Day's wage about 40000 VND for unskilled labor,
found in the similar projects, will increase considerably household income during that
time. In order to assure that local people will be hired at reasonable wage, an agreement
between the commune and contractors might be needed giving preference to local people.
In additional, part time job might be offered to local people during operation time such as
clearing sand trap or mud accumulated in the canal, etc.
Finally, widening use of electricity for productive purpose will create more jobs and
increase income of the people in long-term. Electrification do support to development of
other carrier in the commune such as mechanical repair, battery recharging, sewing and
shops.
14 Risk and measures to overcome risk
Infrastructure development in general or hydropower development in particular entails a
range of uncertainties and risk. The risk analysis and possible measures to over come the
risk are very important to investors, assuring fusibility and sustainability of projects.
Following are possible risk the investors may face and measures to over come the risks.
80
Risk occurs during project preparation
One of the most common risk in the hydropower concerns to water availability, especially
to small hydropower. The risk might because of no data record available for the site or
limitation in the record. Models or methods used to estimate flow series still contain error.
And even a long-term record is available no assurance that the hydrology will not change
cyclically or even permanently. Vietnam has experienced not very few small or mini
hydropower could not operate due to lack of water. The reported reasons are inaccurate
design and deforestation in catchment area. Risk also happens in assessment of the
potential demand, which tend to over estimate. Na Po hydropower is an example, after 3
years operation the demand is only half of power potential68. To over come the risk, a
reputed consultant should be selected to conduct feasibility study. The cost for consulting
might increase but the cost is compensated by more reliable feasibility study.
Risk in Construction
The risk may come from lack of fully cooperation or understanding between designer and
contractors, from different between design and particular or simply from contractors. That
may lead to longer construction period and increase investment cost of project. It is
recorded that almost hydropower project in Vietnam, which is invested by EVN, have real
investment cost greater that designed cost from 5% to 20%69. The increasing is primary
caused by non-technical reasons. Turnkey approach might be a solution for the risk. In
addition, strictly monitoring and supervising activity should be done and long-term
warranty is recommended
Risk in Operation
The risk may be caused by faulty design, construction or manufactures that often occur
after a certain time, several years after the first commissioning. The risk also may come
due to decreasing in water available in short term of long term, especially for small
hydropower due to small catchment area. To minimize the risk necessary measures are as
follows:
- Long-term warranty from contractors, suppliers and designers
68 Interviewed with Mr. Ho Hao, PECC1, 25.10.2002
81
- The low proportion of equity in investment capital
- Protect catchment area.
For Giap Trung hydropower, extension of national grid to the commune also could be seen
as a risk during operation. National grid likely offered lower tariff to households due to
received subsidy from GOV. Therefore, local households will prefer to buy electricity
provided by national grid. To solve the problem, investor should require agreement from
GOV/EVN to feed all energy output to national grid.
Institutional, financial and commercial risks: The risk may come from changing in tax, fee
policy and/or regulations related to the investment. For example GOV gives up promoting
renewable energy development then supports to the project might be terminated. Of course,
difficulty will arise and the project will less attractive to investors. To avoid or lessen the
risk, investor needs to truly understand regulations and policy of the government, able to
foreseen and react flexible to any possible changing. In addition, investor could involve
public sector into project aiming to reduce the effect of changing and to share the risk.
15 Conclusion and Recommendation
Giap Trung commune is one of the poorest communes in Vietnam. Electrification the
commune is necessary to improve their standard of living and give they a tool to increase
their income.
Similar to other remote rural areas in Vietnam, power demand in Giap Trung is
characterized by very low load factor due to electricity demand is primary for lighting and
entertainment. In additional, scattered resettlement of the households will likely lead to
very high cost to electrify the commune.
To answer the question which option should be selected for the project to electrify the
commune and maximize benefit to national economy, a comprehensive comparison among
four possible options namely, “Grid connected hydropower”, “Off grid hydropower”,
“connection to national grid” and “diesel generator” has been done from two points of
view (i) Electrification of the commune, and (ii) Economic benefit of the investment. The
option “Grid connected hydropower” is proved to be the best one when has the lowest cost
69 EVN
82
for electrifying the commune and brings highest benefit to national economy. Connection
to the national grid might be a promising solution to promote small hydropower
development where economically. This helps to overcome the low demand for off grid
hydropower, which is one of the main reasons leading to high cost of rural electrification,
and create possibility to exploit hydropower potential to benefit from economic of scale.
Participation of private investors in power sector is new in Vietnam. This creates new form
of ownership and investment. Investor owns the hydropower plant and he is fully
responsible for his decisions as well as result of business that is strong believed to improve
the current situation of small hydropower (out of date technology, poor operation and
maintenance, and loose financial control).
Legal and institutional frame for the investment model is in process of development in
Vietnam. Private ownership in infrastructure just accepted not more than 20 years and
much shorter time is known for power sector, which was totally under the control of the
government. “Law of Enterprises” has established solid legal ground for private business.
Institutional frame for development of grid-connected hydropower is available even be
considered complicated and not efficient. Institutional improvement then is needed to meet
practice and promote development of the investment.
Electricity provided by the hydropower scheme likely improves standard of living of local
people, the primary target of the project. High quality electricity provided from
hydropower scheme gives them better service with lower cost compared to their present
energy source. For affordable cost, local people can benefit from the modern service,
which affects positively to all aspect of their life, e.g. health, education, culture and
custom, etc. Electrification also could be the tool to promote local economic development.
The project is economically and financially feasible and satisfies interest of the all
participants. This assures sustainable development of the new model in developing
renewable energy in Vietnam.
Investor certainly is the decisive factor for the success of the model. However, GOV, who
acts as market enabler and also participant, should actively participate in the market
assuring balance between interest of beneficiaries and having necessary measures to
promote the development model. Local resident, the main target of project, need to active
and positive participate in the development that is, surely, to maximize the turnover from
project and really meet their expectations.
83
The model absolutely could be extended to apply for other areas in Vietnam, where has
low electricity demand but is endowed with rich hydropower potential and economically to
connect to national grid.
More specific, it is recommended:
(i) The investment model could be extended to apply for other hydropower
projects in Vietnam.
(ii) Legal and institutional frame should be simplified and more efficient. Standard
criteria for approval need to be set up and published.
(iii) Standard Power Purchasing Agreement should be approved as soon as possible.
This will avoid lengthy and result-unknown negotiation between EVN and
developers.
(iv) Purchase tariff should be defined based on avoided cost (energy and capacity)
of EVN and balancing interests of SPP(s), EVN and other stakeholders.
(v) Promote measures on tax, financing and other support need to be provided from
GOV to the investment.
84
Bibliography
Bogach V. Susan (2000), Vietnam Renewable Energy Action Plan, Hanoi
Boie, Wulf. 2000. Hydropower for rural Electrification Seminar Document
Colonco, 2000, Technical Assistance for Preparation of Proposed Rural Energy Project, Hanoi
Construction Publish House (1999), Ordinance of Management of Investment and Construction, Regulations on promotion of investment and developments, Hanoi
Construction Publish House (2000), Vietnam regulation on cost estimation, Hanoi
Construction Publisher House (2001), Guiding documents for implementation of power investment, management and using, Hanoi
Entec AG (2000), Package C: Techno-Economic Assessment Model. Consultant Report To World Bank Washington, D.C
ESMAP (2000), Best Practice For Sustainable Development Of Micro Hydropower in Developing Countries, Washington, D.C
EVN (1999), Training workshop on “Small Hydropower Project for Rural Development”, Hanoi
EVN, IOE (1999), Master Plan Study in Rural Electrification, Hanoi
Harvey, Adam. 1998. Micro- Hydropower Design Manual
Hifab International AB (2000), Vietnam Rural Energy Study (final report), Hanoi
JICA (2001), Renewable Energy Master Plan for Northern Part, Hand out for Workshop in Hanoi.
K. Goldsmith (1995), The role of the private sector in the small-scale hydropower field, ST. Gallen
Meritec. August 2000. REAP Package E - Vietnam, Feasibility Study of a Program to Develop (and/or rehabilitate) Community Scale Hydro- Based Mini Grid, Final Draft, Hanoi
MOI, EVN (2001), Standard Agreement For Purchase of Electrical Energy From Small Power Producer (draft), Hanoi
MOI, WB, GEF (2002), Brief RARE Organization and Operational Manual, Hanoi
MOI, PECC1, ENTEC AG (2002), Micro Hydro Power Scheme for the Giap Trung Commune, Ha Giang Province (Draft report), Hanoi
85
Mostert, Wolfgang (2002), Design of Remote Area Renewable Electricity Fund, Inception Report. Hanoi
Natasha Pairaudeau (2002), Training Manual for Community Mobilization, Hanoi
National Political publish house (1999), Laws of Enterprises, Hanoi
PECC1, (2000), Feasibility Study of Na Loa Small Hydropower, Hanoi
PECC1, (2000), Feasibility Study of Keo Bac Small Hydropower, Hanoi
PECC1, (2000), Feasibility Study of Yadrang Small Hydropower, Hanoi
PECC1&ENTEC AG, (2000), Feasibility Study of Na Loa Small Hydropower, Hanoi
Rehling, Uwe (2000), Mini-grid Seminar Document, SESAM.
Robert Vermstom and Stephen Graham (1999), Financial and Economic Justification
Steven Ferrey (2002), Workshop presentation in Hanoi “ Small power Projects (SPPs)”, Hanoi
Tran Hai Anh (2002), Renewable Energy as an Option for Rural Electrification of “Quang Khe” Commune, “ Dak Lak” Province (Vietnam), Flensburg
Tran Hong Ky (2002), Purchasing Tariffs for Renewable Energy Small Power Plants in Vietnam, Term paper, Flensburg
Worley (1999), Vietnam Rural Energy Project, Volume 1, Hanoi
http://www. laodong.com.vn
http://www. vnexpress.net
Union Newspaper, Vietnam
86
APPENDIX 1
SURVEY DATA FOR GIAP TRUNG COMMUNE
87
HOUSEHOLD SURVEY DATA
General statistic: Giap Trung Names of villages
Total of hh
No. of poor hh
30% of poor hh
No. of middle hh.
30% of middle hh
No. of rich hh
30% of rich hh
Na Poong Khuoi Khung Lung Nhoa Na Po Thom khieu Khau Nhoa Phia booc Na Vieng
30 58 38 69 36 68 91 63
11 21 19 19 12 28 23 19
3 6 6 6 4 8 7 6
13 28 12 43 18 32 54 41
4 8 4 13 5 10 16 12
6 9 7 7 6 8 14 3
2 3 2 2 2 2 4 1
Questionnaire counted Names of villages
30% of poor hh
20% of asked questionnaires
30% of middle hh
20% of asked questionnaires
30% of rich hh
20% of asked questionares
Na Poong Khuoi Khung Lung Nhoa Na Po Thom khieu Khau Nhoa Phia booc Na Vieng
3 6 6 6 4 8 7 6
1 1 1 1 1 2 2 1
4 8 4 13 5 10 16 12
1 2 1 3 1 2 3 2
2 3 2 2 2 2 4 1
1 1 1 1 1 1 1 1
Total 10 15 8 33 Q1.5. Commune: Valid Count Percent Giap Trung 33 100 Total 33 100 Q1.6. Village: Valid Count Percent Na Poong 3 9.1 Khuoi Khung 4 12.1 Lung Nhoa 3 9.1 Na Po 5 15.1 Thom khieu 3 9.1 Khau Nhoa 5 15.1 Phia booc 6 18.2 Na Vieng 4 12.1 Total 33 100 Well-ranking Valid Count Percent Poor 10 30.3 Middle 15 45.5 Rich 8 24.2 Total 33 100
88
Household profile and socio-economic indicators Q2.2. Ethnicity: Valid Count Percent Tay 5 15.1 Dao 23 69.7 H’mong 5 15.1 Total 33 100 Q2.3. No. of people in household (total): Valid Count Percent 3 1 3.0 4 2 6.0 5 6 18.2 6 8 24.2 7 4 12.1 8 3 9.1 9 1 3.0 10 2 6.0 11 3 9.1 14 2 6.0 15 1 3.0 Total 33 100 Q2.4. Male adults 18 and over (number): Valid Count Percent 1 15 45.5 2 11 33.3 3 6 18.2 4 1 3.0 Total 33 100 Q2.5. Male children under 18 (number): Valid Count Percent 0 5 15.1 1 10 30.3 2 11 33.3 3 3 9.1 4 2 6.0 5 2 6.0 Total 33 100 Q2.6. Female adults 18 and over (number): Valid Count Percent 1 16 48.5 2 10 30.3 3 5 15.1 4 2 6.0 Total 33 100 Q2.7. Female children under 18 (number): Valid Count Percent 0 3 9.1 1 7 21.2 2 12 36.4 3 7 21.2 4 3 9.1 5 1 3.0 Total 33 100
89
Q2.8. Family’s main sources of income (list): Valid Count Percent From Agriculture 33 100 From Animal Breeding 16 48.6 Hired Working 3 9.1 Total 33 100 Q2.9. Yearly total income of household (in VND, estimate): Valid Count Percent 840000 1 3.0 890000 1 3.0 1140000 1 3.0 1400000 1 3.0 1800000 1 3.0 2250000 1 3.0 2850000 1 3.0 3500000 1 3.0 3560000 2 6.0 5000000 1 3.0 6000000 1 3.0 6350000 1 3.0 6850000 1 3.0 7100000 1 3.0 7500000 2 6.0 8230000 1 3.0 8620000 1 3.0 8700000 1 3.0 9000000 2 6.0 9100000 1 3.0 9820000 1 3.0 10000000 1 3.0 12000000 1 3.0 12300000 1 3.0 12700000 1 3.0 12850000 1 3.0 13500000 1 3.0 14300000 1 3.0 18250000 1 3.0 19000000 1 3.0 Total 33 100 Q2.10. How many hours a day to household members spend collecting firewood?: Valid Count Percent 0.5 1 3.0 1 8 24.2 1.5 3 9.1 2 19 57.6 3 1 3.0 4 1 3.0 Total 33 100 How many hours a day to household members spend collecting firewood by well-ranking: Well-ranking Average time (hours) Poor 1,5 Middle 1,83 Rich 1,94
90
Q2.11. Which household members usually do this work? Valid Count Percent Woman 33 100 Total 33 100 Q2.12. What activities do children usually engage in the evening after dark? Valid Count Percent Doing assignments 26 78.8 Have a rest 7 21.2 Total 33 100 Q2.13. What activities do men usually engage in the evenings after dark? Valid Count Percent Have a rest 33 100 Total 33 100 Q2.14. What activities do women usually engage in the evenings after dark? Valid Count Percent Have a rest 29 87.9 Doing Housework 4 12.1 Total 33 100 Existing fuel use Which types of fuel does your household currently use, for what purpose, and approximately how do you spend per month on each fuel? Q3.1. Does your household currently use kerosene? Valid Count Percent Yes 32 97.0 No 1 3.0 Total 33 100 Q3.1.1. Uses Valid Count Percent Lighting 32 100 Total 32 100 Q3.1.2. How much of this fuel do you use each month (litre)? Valid Count Percent 0.2 1 3.2 0.5 3 9.3 0.75 1 3.2 1 15 46.9 1.5 2 6.2 2 6 18.7 3 3 9.3 4 1 3.2 Total 32 100 Average kerosene use each month by well-ranking: Well-ranking Average kerosene Poor 1,32 Middle 1,589 Rich 1,25
91
Q3.1.3. How much do you spend on this fuel each month (VND)? Valid Count Percent 1.200 1 3.2 3.000 3 9.3 4.000 3 9.3 4.500 7 21.9 5.000 4 12.6 6.000 2 6.2 7.000 1 3.2 8.000 1 3.2 9.000 2 6.2 10.000 2 6.2 12.000 2 6.2 15.000 2 6.2 24.000 2 6.2 Total 32 100 Average payment each month by well-ranking: Well-ranking Average payment (VND) Poor 6.420 Middle 8.000 Rich 6.000 Q3.2. Does your household currently use Diesel? Valid Count Percent No 33 100 Total 33 100 Q3.3. Does your household currently use Gas (LPG)? Valid Count Percent No 33 100 Total 33 100 Q3.4. Does your household currently use Wood? Valid Count Percent Yes 33 100 Total 33 100 Q3.4.1. Uses Valid Count Percent Cooking 33 100 Total 33 100 Q3.4.2. How much of this fuel do you use each month (kg)? )?( Self- estimated) Valid Count Percent 120 2 6.0 125 1 3.0 150 2 6.0 180 4 12.1 190 1 3.0 200 1 3.0 300 6 18.2 360 1 3.0 400 5 15.1 450 2 6.0 500 5 15.1 600 2 6.0 800 1 3.0 Total 33 100
92
Average wood use each month by well-ranking: Well-ranking Average wood (kg) Poor 289,5 Middle 346,667 Rich 405,0 Q3.4.3. How much do you spend on this fuel each month (VND)?( Self- estimated) Valid Count Percent 60.000 2 6.1 65.000 1 3.0 75.000 1 3.0 80.000 1 3.0 90.000 4 12.1 100.000 2 6.1 150.000 4 12.1 160.000 2 6.1 180.000 1 3.0 200.000 5 15.1 225.000 2 6.1 250.000 5 15.1 300.000 2 6.1 400.000 1 3.0 Total 33 100 Average payment each month by well-ranking: Well-ranking Average payment (VND) Poor 145.500 Middle 175.000 Rich 202.500 Q3.5. Does your household currently use Straw? Valid Count Percent No 33 100 Total 33 100 Q3.6. Does your household currently use Husks? Valid Count Percent No 33 100 Total 33 100 Q3.7. Does your household currently use Coal briquette? Valid Count Percent No 33 100 Total 33 100 Q3.8. Does your household currently use Charcoal? Valid Count Percent No 33 100 Total 33 100 Q3.9. Does your household currently use Bio-mass (including gas from dung or dung itself)? Valid Count Percent No 33 100 Total 33 100
93
Other energy sources Does your household obtain energy from any of the following sources? Please provide details: Pico hydro systems Q4.1. Do you own or share the use of a pico hydro system? Valid Count Percent Own 14 42.4 Share 10 30.3 Do not use 9 27.3 Total 33 100 Well-ranking * Do you own or share the use of a pico hydro system? Crosstabulation Well-ranking Own Share Do not use Total Poor Count 3 3 4 10 % of Total 9.1% 9.1% 12.1% 30.3% Middle Count 7 5 3 15 % of Total 21.2% 15.2% 9.1% 45.5% Rich Count 4 2 2 8 % of Total 12.1% 6.1% 6.1% 24.2% Total Count 14 10 9 33 % of Total 42.4% 30.3% 27.3% 100.0% Q4.2. If you share, how many households do you share with? (number): Valid Count Percent 1 2 20.0 2 7 70.0 3 1 10.0 Total 10 100 Q4.3. What is the capacity of the system? (W) Valid Count Percent 300 14 58.3 600 9 37.5 1000 1 4.17 Total 24 100 Q4.4. How many light bulbs does it provide for in your house? Valid Count Percent 2 1 7.14 3 9 64.3 4 3 21.4 6 1 7.14 Total 14 100 Q4.5. If shared, how many light bulbs does it run in total?: Valid Count Percent 2 4 40.0 3 1 10.0 4 3 30.0 5 1 10.0 9 1 10.0 Total 10 100
94
Q4.6. What was the cost to your hh of purchase (VND)? Valid Count Percent 250.000 1 7.14 300.000 4 28.5 330.000 1 7.14 350.000 2 14.3 360.000 1 7.14 380.000 1 7.14 400.000 2 14.3 700.000 2 14.3 Total 14 100 If own, average purchase by well-ranking: Well-ranking Average purchase (VND) Poor 300.000 Middle 460.000 Rich 325.000 Q4.7. If shared, what was the total cost of purchase (VND)?: Valid Count Percent 100.000 1 10.0 280.000 1 10.0 300.000 2 20.0 380.000 4 40.0 500.000 1 10.0 600.000 1 10.0 Total 10 100 Average payment each month by well-ranking: Well-ranking Average payment (VND) Poor 360.000 Middle 368.000 Rich 340.000 Q4.8. What was the cost to your hh of installation (VND)?: Valid Count Percent 9.000 1 7.14 15.000 3 21.4 20.000 1 7.14 25.000 1 7.14 30.000 1 7.14 50.000 1 7.14 85.000 1 7.14 90.000 1 7.14 100.000 1 7.14 140.000 1 7.14 200.000 1 7.14 300.000 1 7.14 Total 14 100 If own, average installation by well-ranking: Well-ranking Average installation (VND) Poor 81.666,67 Middle 44.142,86 Rich 135.000
95
Q4.9. If shared, what was the total cost of installation?: Valid Count Percent 15.000 2 20.0 30.000 1 10.0 50.000 2 20.0 60.000 1 10.0 100.000 1 10.0 160.000 1 10.0 180.000 1 10.0 300.000 1 10.0 Total 10 100 If shared, average installation by well-ranking: Well-ranking Average installation (VND) Poor 180.000 Middle 54.000 Rich 75.000 Q4.10. What is the cost to your hh of monthly maintenance (VND)? Valid Count Percent 3.000 2 14.3 5.000 4 28.6 10.000 5 35.7 18.000 3 21.4 Total 14 100 If own, average maintenance by well-ranking: Well-ranking Average maintenance (VND) Poor 8.333,33 Middle 9.571,43 Rich 9.500 Q4.11. If shared, what is the total cost of monthly maintenance (VND)? Valid Count Percent 5.000 2 20.0 10.000 3 30.0 13.000 1 10.0 18.000 1 10.0 20.000 1 10.0 25.000 1 10.0 40.000 1 10.0 Total 10 100 If shared, average maintenance by well-ranking: Well-ranking Average maintenance (VND) Poor 13.333,33 Middle 17.000 Rich 15.500 Q4.12. How many hours a day do you use the pico hydro system?: Valid Count Percent 6 4 16.7 24 20 83.3 Total 24 100
96
Car or motorcycle batteries: Q5.1. Do you own a car or motorcycle battery for power? Valid Count Percent No 33 100 Total 33 100 Small generators set (Diesel powered Genset) Q6.1. Do you own a Genset? Valid Count Percent No 33 100 Total 33 100 Candles Q7.1. How many candles does your household use each day? Valid Count Percent Do not use 33 100 Total 33 100 Dry cell batteries Q8.1. How many dry cell batteries do you use? (count up total in all appliances in household) Valid Count Percent 2 24 72.7 3 1 3.0 6 1 3.0 Do not use 7 21.2 Total 33 100 Q8.2. How many batteries do you use per month?: Valid Count Percent 2 5 19.2 4 14 53.8 6 6 23.1 12 1 3.8 Total 26 100 Average dry cell batteries by well-ranking: Well-ranking Average dry cell batteries (VND) Poor 3,5 Middle 4,67 Rich 5,0 Q8.3. Cost per month (VND)?: Valid Count Percent 2.500 5 19.2 5.000 14 53.8 7.500 6 23.1 15.000 1 19.2 Total 26 100 Average payment by well-ranking: Well-ranking Average payment (VND) Poor 4.375 Middle 5.833,33 Rich 6.250
97
Powered machinery and appliances: Please indicate which (and how many) of the following appliances and machines your households owns and how they are powered. Q9.1. Number of light bulb Valid Count Percent 0 10 30.3 1 5 15.2 2 15 45.4 3 2 6.1 4 1 3.0 Total 33 100 Q9.1.1. Powered by… Valid Count Percent Pico 23 100 Total 23 100 Q9.2. Number of Fluorescent tube Valid Count Percent 0 9 21.2 1 15 45.5 2 9 27.3 Total 33 100 Q9.2.1. Powered by… Valid Count Percent Pico 24 100 Total 24 100 Q9.3. Number of Colour TV Valid Count Percent 0 33 100 Total 33 100 Q9.4. Number of Black and white TV Valid Count Percent 0 24 72.7 1 9 27.3 Total 33 100 Q9.4.1. Powered by… Valid Count Percent Pico 9 100 Total 9 100 Q9.5. Number of Radio/cassette/cd players Valid Count Percent 0 12 71.4 1 21 28.6 Total 33 100 Q9.5.1. Powered by… Valid Count Percent Pico 10 47.6 Battery 11 52.4 Total 21 100
98
Q9.6. Number of Karaoke player Valid Count Percent 0 33 100 Total 33 100 Q9.7. Number of Video recorder Valid Count Percent 0 33 100 Total 33 100 Q9.8. Number of Electric fan Valid Count Percent 0 27 81.8 1 6 18.2 Total 33 100 Q9.8.1. Powered by… Valid Count Percent Pico 6 100 Total 6 100 Q9.9. Number of Refrigerator Valid Count Percent 0 33 100 Total 33 100 Q9.10. Number of Pressurized lamp Valid Count Percent 0 33 100 Total 33 100 Q9.11. Number of Water pump Valid Count Percent 0 33 100 Total 33 100 Q9.12. Number of Electric kettle Valid Count Percent 0 33 85.7 Total 33 100 Q9.13. Number of Rice mill/ husker Valid Count Percent 0 33 100 Total 33 100 Q9.14. Number of Rice cooker Valid Count Percent 0 33 100 Total 21 100 Q9.15. Number of Crop dryer Valid Count Percent 0 33 100 Total 33 100
99
Productive uses Which of the following activities does your household engage in? Q10.1. Does your household engage in rice milling/ husking? Valid Count Percent Yes 33 100 Total 33 100 Q10.1.1. Source of energy? (if any) Valid Count Percent Diezel 5 15.1 By hands and feet 28 84.9 Total 33 100 Q10.1.2. How often does the household engage in this activity (per month?) Valid Count Percent 1 13 39.4 2 9 27.3 3 11 33.3 Total 33 100 Q10.1.3. Would you consider converting existing machinery to hydro power or beginning to use electricity for this activity? Valid Count Percent Yes 33 100 Total 33 100 Q10.2. Does your household engage in welding/mechanical repairs? Valid Count Percent No 33 100 Total 33 100 Q10.3. Does your household engage in Wood working/furniture making? Valid Count Percent No 33 100 Total 33 100 Q10.4. Does your household engage in Sewing/weaving/tailoring? Valid Count Percent No 33 100 Total 33 100 Q10.5. Does your household engage in Electronic equipment repairs? Valid Count Percent No 33 100 Total 33 100 Q10.6. Does your household engage in Alcohol making? Valid Count Percent Yes 3 9.1 No 30 90.9 Total 33 100 Q10.6.1. Source of energy? (if any) Valid Count Percent Wood 3 100 Total 3 100
100
Q10.6.2. How often does the household engage in this activity (per month)? Valid Count Percent 1 3 100 Total 3 100 Q10.6.3. Would you consider converting existing machinery to hydro power or beginning to use electricity for this activity? Valid Count Percent No 3 100 Total 3 100 Q10.7. Does your household engage in Chicken hatching/rearing? Valid Count Percent No 33 100 Total 33 100 Q10.8. Does your household engage in Pumping - irrigation? Valid Count Percent No 33 100 Total 33 100 Q10.9. Does your household engage in Pumping – water supply? Valid Count Percent No 33 100 Total 33 100 Q10.10. Does your household engage in Entertainment Valid Count Percent No 33 100 Total 33 100 Expected use: Q11.1. If a mini hydro system is constructed in your commune what would you expect your electricity use pattern to be? Valid Count Percent Use evenings only 16 48.5 Use both daylight and evening hours 17 51.5 Total 33 100 Well-ranking * If a mini hydro system is constructed in your commune what would you expect your electricity use pattern to be * Cross tabulation Well-ranking Use evenings only use both daylight and evening hours Total Poor Count 8 2 10 % of Total 24.2% 6.1% 30.3% Middle Count 8 7 15 % of Total 24.2% 21.2% 45.5% Rich Count 8 8 % of Total 24.2% 24.2% Total Count 16 17 33 % of Total 48.5% 51.5% 100.0% Q11.2. If you connect to electricity would you consider starting other income generating activities which use electricity? Which ones? Valid Count Percent Do not know 33 90.5 Total 33 100 Q11.3. If you connect to electricity, which activities in your household will progress? Valid Count Percent Do not know 33 90.5 Total 33 100
101
DATA SURVEY FOR PRODUCTIVE USE 1. Rice husker
Name Power Monthly diesel consumption (lit) Total
Convert to using electricity (Yes/No)
If Yes, when (year from present)
Cost for convert (a, b or c)
Signature
T 1 T 2 T 3 T 4 T 5 T 6 T 7 T 8 T 9 T 10 T 11 T 12 Husker
I. Na Po village 1. Hoang Van Ngam 12 KW 40 40 40 40 40 40 40 40 40 40 40 40 480 Don’t know 2. Duong Van Khang 12KW 20 20 20 20 20 20 20 20 20 20 20 20 240 Don’t know II. Khau Nhoa village 1. Trieu Van Sinh 12 KW 35 35 35 35 35 35 35 35 35 35 35 35 420 Yes 1 b 2. Hoang Van San 12KW 20 20 20 20 20 20 20 20 20 20 20 20 240 Don’t know 3.Bon Van Niem 12KW 30 30 30 30 30 30 30 30 30 30 30 30 360 Don’t know 4. Bon Van Lanh 12KW 20 20 20 20 20 20 20 20 20 20 20 20 240 No III. Na Vieng village 1.Bon Van Noi 12 KW 40 40 40 40 40 40 40 40 40 40 40 40 480 Don’t know 2. Bon Van Chan 12 KW 20 20 20 20 20 20 20 20 20 20 20 20 240 Don’t know 3. Dang Van Pinh 12 KW 30 30 30 30 30 30 30 30 30 30 30 30 360 Don’t know IV Phia Booc village 1.Truong Duc Can 12 KW 20 20 20 20 20 20 20 20 20 20 20 20 240 Don’t know 2. Dang Giao Hung 12KW 20 20 20 20 20 20 20 20 20 20 20 20 240 Don’t know 3.Bong Van Kien 12KW 30 30 30 30 30 30 30 30 30 30 30 30 360 Don’t know 4. Trieu Quang Hung 12 KW 15 15 15 15 15 15 15 15 15 15 15 15 180 Don’t know 5. Truong Ngoc Tuan 8KW 15 15 15 15 15 15 15 15 15 15 15 15 180 Yes 1 b Cost for converting a – Cash available b – from selling pigs/ Pico/ diesel genset c – Borrow d –Can not afford
102
2. Giap Trung Commune Clinic Item Power (w) Number Daily using Lamp 100 30 10 60 6 10 40 8 10 Autoclave 2000 Fan 80 12 Refrigerator 85 1
3. Giap Trung secondary school Item Power (w) Number Daily using Lamp 60 110 8 40 32 8 25 16 8 Fan 80 45 Refrigerator 85 2
4. Commune Office Item Power (w) Number Daily using Lamp 100 10 6 60 18 8 40 10 8 Fan 80 12 Refrigerator 85 1
5. Shops and services Name of owner Do you intend lighting
during day time after electrified (Yea/No)
Do you intend use fans during day time after electrified (Yea/No)
Refrigerator (Yea/No)
set Daily use set Daily use Nguyen Nhu Hoa N 2 40 6 N 2 40 4 Y Le Hong Thai Y 2 40 6 Y 2 40 6 Y Nong Thi Thiet Y 3 40 6 Y 3 40 4 Y Nguyen Duc Nguyen Y 2 40 6 Y 2 40 6 Y 6. Other potential for productive use (According to interview with the commune leaders) Water supply: No Wood processing Name of owner
Lighting daytime Using power-saw during day time
Using power-planer during day time
Y/N
Set Power (W)
Daily use
Y/N
Set Power (W)
Daily use
Y/N
Set Power (W)
Daily use
Trac Van Trai
Y 4 60 8 Y 2 7500 3 Y 2 1500 3
Sam Van Lam
Y 6 60 8 Y 3 5500 3 Y 3 1500 3
Mechanical repair : Yes Shops Demand to increase shops: Yes
Number of additional shops in next 5 year: 7 Food service Demand to increase food service: Yes Number of additional food service in next 5 year: 8 Market: No Others 1. Tofu making 2. Recharging batteries 3. Sawing shops
103
APPENDIX 2
LOAD ESTIMATION FOR GIAP TRUNG COMMUNE
104
Electricity demand for public/service use
Customer Power
(W)
Monthly consumption
(kWh)
Yearly consumption
(kWh) Consumption time District’s General heath clinic 2585 277 3329 whole dayGiap Trung school 2340 247 2967 whole dayGiap Trung Commune Office 1410 166 1994 whole dayShops and Services 840 104 1248 whole day Sum 7175 795 9538
Customers Power Unit daily using time Monthly consumption (W) (hours) (kWh) District’s General heath clinic Office lighting 150.0 6 3 82Patient room lighting 80.0 3 4.5 33Employee room lighting 100.0 3 4.5 41Protection lighting 100.0 1 6 18Fan for office 80.0 6 3 44Fan for employee and patient 80.0 6 3 44Refrigerator 85.0 1 6 16Sum 277 Giap Trung school Power Unit daily using time Monthly consumption (W) (hours) (kWh) Class room lighting 80.0 8 3 58Office lighting 100.0 3 2 18Living room for pupil 80.0 3 4.5 33Living room for teacher 100.0 5 4.5 68Protect light 100.0 1 6 18Fan for office 80.0 3 3 22Fan for living room 40 8 3 29Sum 247 Giap Trung Commune Office Power Unit daily using time Monthly consumption (W) (hours) (kWh) Office lighting 100.0 8 3.5 85Staff lighting 100.0 2 4.5 27Protection lighting 80.0 1 6 15Radio 80.0 2 3.5 17TV 85.0 1 2.5 6Refrigerator 85.0 1 6 16Sum 166 Shops and Services Power Unit daily using time Monthly consumption (W) (hours) (kWh) Bulb 3 40.0 9 4 44Fan 1 40.0 9 3.5 38Refrigerator 60.0 2 6 22Sum 104
105
Electricity demand for public/service use
De-husking machine
Item Monthly
consumption Yearly
consumption
(kWh) (kWh)
Diesel
Diesel consumption 4620
Energy consumption 46534
Efficiency 20%
Electrical motor
Efficiency 75%
Total electricity demand 12409
Realistic 40%
Real electricity demand 414 4964
Wood Processing
Item Power Unit Time of
using Monthly
consumption Yearly
consumption
(W) Hour (kWh) (kWh)
Power-saw 5000 5 2.5 1901 22812.5
Planer 1500 5 3 684 8213
Bulb 60 10 5 91 1095
Sum 2677 32120
Total productive use demand 3090 37084
106
APPENDIX 3
TECHNICAL DESIGN
107
Monthly Runoff at Giap Trung Site
Year I II III IV V VI VII VIII IX X XI XII
1964 0.18 0.14 0.18 0.27 0.35 3.69 3.49 2.82 1.75 1.21 0.47 0.37
1965 0.26 0.2 0.16 0.3 0.97 1.8 2.46 1.63 0.66 0.81 0.82 0.38
1966 0.29 0.22 0.18 0.16 0.48 3.42 4.9 1.92 0.78 0.38 0.27 0.2
1967 0.16 0.13 0.11 0.24 1.67 1.55 1.94 3.22 1.78 0.94 0.41 0.28
1968 0.21 0.17 0.14 0.13 1.35 1.74 3.65 3.34 1.61 0.63 0.55 0.31
1969 0.23 0.18 0.15 0.13 0.27 1.4 2.85 3.78 1.31 0.65 0.35 0.24
1970 0.18 0.14 0.11 0.17 0.43 1.39 4.54 2.05 0.91 0.37 0.25 0.18
1971 0.14 0.12 0.1 0.09 0.31 2.56 3.31 5.55 2.34 0.84 0.35 0.34
1972 0.23 0.17 0.13 0.11 1.44 1.34 2.19 3.2 1.21 0.77 0.42 0.28
1973 0.21 0.16 0.32 0.53 1.86 3.54 3.9 1.92 1.4 0.56 0.32 0.24
1974 0.23 0.18 0.15 0.25 1.79 2.05 3.39 1.35 1.91 1.04 0.58 0.32
1975 0.25 0.2 0.16 0.26 3.85 3.46 1.59 0.7 0.49 0.33 0.27 0.2
1976 0.16 0.22 0.16 0.19 3.14 1.97 2.78 1.91 1.11 1.4 0.53 0.31
1977 0.22 0.18 0.15 0.21 0.35 0.93 1.97 1.38 0.8 1.84 0.67 0.33
1978 0.24 0.19 0.15 0.21 2.84 3.21 1.81 2.79 1.56 1.05 0.79 0.38
1979 0.27 0.33 0.24 0.28 0.53 2.9 3.97 2.79 1.82 0.69 0.35 0.26
1980 0.2 0.17 0.15 0.28 0.77 0.6 2.65 2.61 1.37 0.81 0.36 0.26
1981 0.21 0.17 0.41 0.54 1.06 1.61 2.55 1.46 1.35 1.36 0.76 0.39
1982 0.28 0.22 0.19 0.17 0.7 1.47 2.5 3.03 1.82 0.68 0.54 0.32
1983 0.24 0.19 0.16 0.23 1.39 1.01 2.08 2.16 1.53 0.92 0.69 0.35
1984 0.26 0.2 0.17 0.15 0.4 1.47 1.43 2.07 1.02 0.59 0.32 0.23
1985 0.18 0.15 0.16 0.26 0.65 1.36 1.41 3.04 1.53 0.59 0.68 0.34
1986 0.24 0.19 0.16 0.61 1.49 2.63 2.66 2.02 2 0.85 0.39 0.28
1987 0.22 0.18 0.15 0.13 2.07 1.25 1.23 2.09 1.18 1.16 0.6 0.33
1988 0.24 0.19 0.16 0.14 0.98 1.71 2.74 2.14 1.11 0.6 0.32 0.24
1989 0.22 0.17 0.14 0.12 0.4 3.3 2.29 1.54 0.61 0.36 0.25 0.18
1990 0.14 0.19 0.97 0.62 0.88 2.2 3.66 1.56 1.15 0.6 0.38 0.27
1991 0.21 0.17 0.39 0.27 0.39 1.71 1.61 2.29 1.02 0.4 0.31 0.33
1992 0.24 0.24 0.18 0.14 1.43 2.69 2.05 0.68 0.79 0.35 0.24 0.23
1993 0.22 0.32 0.22 0.21 0.35 2.11 2.88 1.63 1.75 0.62 0.32 0.23
1994 0.17 0.14 0.14 0.12 1.53 1.72 1.96 1.44 0.9 0.84 0.4 0.48
1995 0.3 0.22 0.17 0.14 0.37 2.66 2.84 2.62 1.26 0.47 0.29 0.22
1996 0.17 0.14 0.41 0.27 0.62 2.15 2.51 2.21 1.01 0.62 0.35 0.25
1997 0.2 0.16 0.31 0.78 0.43 2.23 2.26 2.29 1.15 0.96 0.41 0.29
1998 0.22 0.18 0.18 0.34 0.64 2.8 3.67 2.16 0.97 0.4 0.28 0.21
1999 0.17 0.14 0.12 0.17 0.35 0.53 2.23 3.61 1.55 0.78 0.4 0.27
2000 0.2 0.15 0.12 0.1 0.25 1.25 1.69 1.12 0.84 1.09 0.41 0.28
2001 0.2 0.2 0.23 0.25 0.81 1.15 3.37 2.32 0.81 0.75 0.43 0.29
Mean 0.216 0.184 0.207 0.252 1.042 2.015 2.658 2.275 1.267 0.771 0.435 0.287
108
Head Loss Calculation for Giap Trung Hydropower
Assumptions
gross H = 68.0 m
Rated Q = 0.6 m3/s
L horizontal = 40.0 m
Material = Steal
d = 0.45 m
l = 78.9 m
A = 0.159 m^2
k = 1.5 mm
k/d = 3.333 mm/mm
ξ [local] = 0.027 -
K valve+Kbend+Kentrence = 1.2
Q exceed. v h [local] h [friction] h [total]
l/s % m/s m m m
0.01 100% 0.06 0.001 0.000 0.001
0.03 90% 0.19 0.008 0.002 0.010
0.07 80% 0.44 0.045 0.012 0.057
0.12 70% 0.75 0.133 0.035 0.168
0.20 60% 1.26 0.369 0.097 0.466
0.31 50% 1.95 0.887 0.233 1.120
0.58 40% 3.65 3.107 0.814 3.921
1.01 30% 6.35 9.420 2.469 11.889
1.43 20% 9.00 18.884 4.950 23.834
2.10 10% 13.21 40.725 10.674 51.399
2.60 5% 16.36 62.427 16.362 78.789
109
Cost Estimation for Giap Trung Hydropower
Technical Parameters Qd = 600 l/s
Pel = 244 kW
No. Item / Specification Unit Quantity Rate Total
Summary rounded figuresA Civil Works
1,813,508,000B Electro-mechanical Equipment
2,025,200,000C Transmission Lines
5,039,200,000D Land Acquisition
15,000,000E Project Planning, Engineering Design, Site Supervision
and Administration 395,000,000G Contingencies
718,547,000 Total Project Cost (VND) 10,006,455,000 Total Project Cost (USD) 649,770 Unit Project Cost (USD/kW) 2,663 Unit hydropower Cost (USD/kW) 1,322
A Civil Works Section 1: Preliminary and General
1.1 Mobilisation / Demobilisation
Allow for mobilisation of all personnel, plant and equipment to the project site and the initial establishment on the project site, including associated preliminary costs.
Allow for demobilisation of all personnel, plant, equipment and materials, etc. from the project site on completion, including clean-up of site and restoration of contractor's establishment areas.
- - lump sum 30,000,000
1.2 Maintain Construction Establishment
Allow to maintain construction establishment for the whole project duration, including storage sheds for materials and plant, site office, accommodation for personnel as well as setting out all the work. Month 12.0 10,000,000 120,000,000
Note: site supervision, and all head office associated charges to be included in all-in labour rates and the unit rate mark-up.
1.3 Insurance
Allow for insurance premiums (other than workers' compensation insurance), security deposits / bond and retention moneys - - lump sum 100,000,000
Note: workers' compensation to be included in all-in labour rates
Total Section 1 (carried forward to Summary Part A) 250,000,000 Section 2: Intake Works
2.1 Site clearance at intake m2 100.0 4,500 450,000
110
2.2 Temporary coffer dam as required for construction of intake works (incl. pumping if required and removal of dam on completion)
- - lump sum 15,000,000
2.3 Excavation in rock and boulders to form intake works including preparation of excavated surface for fill or concrete and backfill (measurement: solid volume) m3 70.0 90,000 6,300,000
2.4 Loading, transporting and disposal of surplus material from
intake excavation (measurement: excavated material) m3 91.0 8,000 728,000
2.5 Supply, place, compact and cure high grade concrete in slabs, piers and walls of intake structure m3 25.0 1,000,000 25,000,000
2.6 Supply, fix and remove formwork to slabs, piers and walls of
intake structure (all surfaces: planar, inclined and sloping) Allow for triangular ledge at all exposed edges m2 120.0 120,000 14,400,000
2.7 Supply and fix reinforcing bars in intake structure kg 3000.0 9,000 27,000,000
2.8 Supply, place, compact and cure cyclopean concrete in weir body m3 35.0 700,000 24,500,000
2.9 Supply, place, compact and cure high grade concrete in weir m3 17.0 1,000,000 17,000,000
2.10 Supply, fix and remove formwork to weir (all surfaces: planar,
inclined and sloping) Allow for triangular ledge at all exposed edges m2 80.0 120,000 9,600,000
2.11 Supply and fix reinforcing bars in weir kg 2040.0 9,000 18,360,000
2.12 Stone masonry for intake structures (mortar 1:4) m3 45.0 750,000 33,750,000
2.13 Rendering / pointing stone masonry structures (mortar 1:5) m2 100.0 23,000 2,300,000
2.14 Supply and install sluice gate, 1.2 x 2.0 m, t = 10 mm, incl. corrosion protection kg 400.0 17,000 6,800,000
2.15 Supply and install sliding gate at intake canal, 1.2 x 1.55 m, t
= 8 mm, incl. corrosion protection kg 230.0 17,000 3,910,000 Total Section 2 (carried forward to Summary Part A) 205,098,000 Section 3: Sand trap [L=30m, b=2m)
3.1 Site clearance in sand trap area m2 120.0 4,500 540,000
3.2 Excavation in all materials (excl. rock and boulders) to form sand trap structure including backfill (measurement: solid volume) m3 20.0 30,000 600,000
3.3 Excavation in rock and boulders to form sand trap structure
including backfill (measurement: solid volume) m3 20.0 90,000 1,800,000
3.4 Loading, transporting and disposal of surplus material from sand trap excavation (measurement: excavated material) m3 48.0 7,500 360,000
111
3.5 Stone masonry for sand trap (mortar 1:4) m3 200.0 600,000 120,000,000
3.6 Rendering / pointing stone masonry structures (mortar 1:5) m2 180.0 23,000 4,140,000
3.7 Supply, place, compact and cure concrete grade K225 in
operating platforms and piers for gate installation m3 3.0 1,000,000 3,000,000
3.8 Supply, fix and remove formwork to operating platforms and piers (all surfaces: planar, inclined and sloping)
Allow for triangular ledge at all exposed edges m2 20.0 120,000 2,400,000
3.9 Supply and fix reinforcing bars in intake structure kg 250.0 9,000 2,250,000
3.10 Supply and install sluice gate at sand trap, 0.9 x 0.9 m, t=8mm, incl. corrosion protection kg 90.0 17,000 1,530,000
3.11 Supply and install slide gate at headrace pipe taking off from
sand trap, 0.7 x 0.6 m, t=8mm, incl. corrosion protection kg 90.0 17,000 1,530,000
3.12 Metal work for trash racks, steel strips 4 x 60 mm, 1.8 x 2.0 m (surface treatment: 2 coats zinc rich primer; 3 coats tar epoxy resin for finishing) kg 300.0 17,000 5,100,000
Total Section 3: (carried forward to Summary Part A) 143,250,000 Section 4: Headrace (L~=7100 m)
4.1 Site clearance along headrace route m2 1100.0 5,000 5,500,000
4.2 Excavation in all materials (excl. rock and boulders) for headrace canal (measurement: solid volume), incl. backfill m3 1600.0 30,000 48,000,000
4.4 Excavation in rock and boulders for headrace canal
(measurement: solid volume), incl. backfill m3 55.0 90,000 4,950,000
4.5 Loading, transporting and disposal of surplus material from headrace excavation (measurement: excavated material) m3 1986.0 7,000 13,902,000
4.6 Stone masonry for headrace canal, incl. spillways (mortar 1:4)
m3 1207.0 600,000 724,200,000
4.7 Pointing stone masonry structures (mortar 1:5) m2 6035.0 7,000 42,245,000
4.8 Supply, place, compact and cure concrete for drainage crossings etc. m3 7.0 1,000,000 7,000,000
4.9 Supply, fix and remove formwork
Allow for triangular ledge at all exposed edges m2 23.3 120,000 2,797,200
4.10 Supply and fix reinforcing bars kg 560.0 9,000 5,040,000 Total Section 4 (carried forward to Summary Part A) 853,634,200 Section 5: Forebay
112
5.1 Site clearance in pond area m2 50.0 4,500 225,000
5.2 Excavation in all materials (incl. rock and boulders), using heavy equipment to form head pond and fore bay structure (measurement: solid volume) m3 35.0 60,000 2,100,000
5.3 Loading, transporting and disposal of surplus material from
sand trap and fore bay excavation (measurement: excavated material) m3 42.0 7,000 294,000
5.4 Stone masonry for lining and embankment (mortar 1:4) m3 25.0 600,000 15,000,000
5.5 Rendering floor and top of stone masonry lining in storage
pond, thickness 15 mm (mortar 1:2) m2 20.0 15,000 300,000
5.6 Supply, place, compact and cure concrete grade K125 in operating platforms and piers for rack installation m3 2.0 1,000,000 2,000,000
5.7 Supply, fix and remove formwork to operating platforms and
piers (all surfaces: planar, inclined and sloping) Allow for triangular ledge at all exposed edges m2 5.3 120,000 640,800
5.8 Supply and fix reinforcing bars in intake structure kg 200.0 9,000 1,800,000
5.9 Metal work for trash rack (surface treatment: 2 coats zinc rich primer; 3 coats tar epoxy resin for finishing) kg 800.0 17,556 14,044,800
5.10 Supply and install rungs to fore bay and sand trap walls, hot-
dip galvanised no. 5.0 77,000 385,000 Total Section 5: (carried forward to Summary Part A) 36,789,600 Section 6: Spillway (length approx. 40m)
6.10 Site clearance in spillway area m2 80.0 4,500 360,000
6.2 Excavation in all materials (incl. rock and boulders) to form spillway channel including backfill (measurement: solid volume) m3 100.0 15,000 1,500,000
6.3 Disposal of surplus material from spillway (measurement:
excavated material) m3 80.0 7,000 560,000
6.4 Stone masonry for spillway channel (mortar 1:3) m3 75.0 600,000 45,000,000
6.5 Rendering / pointing stone masonry structures, thickness 15 mm m2 250.0 15,000 3,750,000
6.7 Supply and install sliding gate for waste way (end of headrace
/ beginning of spillway collection channel); width 0.40 m; height of gate leaf 1.30 m; frame height 2.20 m; incl. Corrosion protection
kg 70.0 17,000 1,190,000 Total Section 6: (carried forward to Summary Part A) 52,360,000 Section 7: Penstock
113
7.1 Site clearance along penstock route m2 100.0 5,000 500,000
7.2 Excavation in all materials (incl. rock and boulders) to form a
trench for the penstock pipe and the associated anchor blocks.
m3 50.0 30,000 1,500,000
7.3 Disposal of surplus material from penstock excavation (measurement: excavated material) m3 60.0 15,000 900,000
7.4 Supply and install rolled welded steel pipes internal diameter
450 mm, wall thickness 4.0 mm, welded on site, mass = 85 kg/m m 74.0 800,000 59,200,000
7.5 Flanges
welded on pipe ends of dia. 450 mm with conical reduction to suit valve DN 500, PN 10 no. 2.0 300,000 600,000
7.6 Puddle flanges welded onto pipes of item 7.4, at fore bay and
anchor blocks, dia pipe 570 mm; OD 670 mm no. 5.0 120,000 600,000
7.7 Mitre steel bends (for on-site welding) dia. 450 mm, approx. 30°, t = 4 mm no. 1.0 1,000,000 1,000,000
7.8 Socket for by-pass, welded onto flanged pipe of item 7.5; 2" (DN 50), threaded (female) to suit galvanised steel by-pass pipes no. 1.0 150,000 150,000
7.9 Blank flange dia. 450 mm, PN 10, with two tapings BSP 1"
(for pressure testing) no. 2.0 650,000 1,300,000
7.10 Expansion joint dia.450 mm, PN 6 no. 1.0 3,000,000 3,000,000
7.11 Straub (or Viking Johnson) Coupling for steel pipes dia. 450 mm to provide a dismantling joint for valves no. 1.0 3,100,000 3,100,000
7.12 Supply and install breather pipe at fore bay, steel pipe DN 100,
t = 3.6 mm, 7.00 m long with 90° bend, welded to penstock on site no. 1.0 1,000,000 1,000,000
7.13 Supply and install a butterfly valve DN 500, PN 10 at fore bay
and at the powerhouse, with hand wheel and reduction gear
no. 1.0 30,000,000 30,000,000
7.14 Supply, place, compact and cure medium grade concrete in penstock anchor blocks m3 18.0 1,000,000 18,000,000
7.15 Supply, fix and remove formwork to anchor blocks, allow for
triangular ledge at exposed edges. m2 36.0 120,000 4,320,000
7.16 Reinforcing bars in anchor and thrust blocks kg 1080.0 9,000 9,720,000
7.17 Stone masonry for saddles, supports and slope protection including stairs using river stones or cleaned stones from excavation (mortar: 1 PC : 4 sand) m3 35.0 600,000 21,000,000
114
7.18 Stone masonry for drainage channel along penstock route (mortar 1:3) m3 20.0 650,000 13,000,000
7.19 Rendering / pointing stone masonry structures (stairs, drainage
channel) m2 120.0 23,000 2,760,000
7.20 Galvanised steelwork for penstock holding-down straps / bolts kg 30.0 20,000 600,000
Total Section 7: (carried forward to Summary Part A) 172,250,000 Section 8: Powerhouse and tailrace
8.1 Site clearance around powerhouse and tailrace area m2 100.0 4,500 450,000
8.2 Excavation in all materials (incl. rock and boulders) to form powerhouse foundation and tailrace structure including backfill and disposal of surplus material m3 35.0 60,000 2,100,000
8.3 Supply and install subsoil drainage works consisting of
perforated pipes dia. 100 mm, drainage aggregate (0 - 30 mm, approx. 0.1 m3/m), geofabrics min 180 g/m2 to wrap aggregate, and all pipe fittings such as bends and tees.
m 30.0 150,000 4,500,000
8.4 Stone masonry for tailrace structure (mortar 1:3) m3 50.0 650,000 32,500,000
8.5 Rendering of tailrace structure m2 100.0 15,000 1,500,000
8.6 Stone masonry for powerhouse footing (mortar 1:4) m3 6.0 600,000 3,600,000
8.7 Blinding and filling concrete, 1 PC : 8 aggregate m3 4.0 450,000 1,800,000
8.8 Supply, place, compact and cure high grade concrete in powerhouse floor above the tail race and parapet and ring beam (anchor block included in Section 6 above) m3 4.0 1,000,000 4,000,000
8.9 Supply, fix and remove formwork to powerhouse sub-
structure, allow for triangular ledge at exposed edges. m2 5.2 120,000 624,000
8.10 Reinforcing bars in powerhouse structure (deformed bars) kg 400.0 9,000 3,600,000
8.11 Brick wall in powerhouse superstructure (mortar 1:3), max. Height 2.70 m m2 60.0 90,000 5,400,000
8.12 Rendering / plastering of brick wall in powerhouse m2 400.0 15,000 6,000,000
8.13 Framed, ledged and braced sliding door (steel): w = 2 x 0.90
m, h = 2.50 m no. 1.0 4,600,000 4,600,000
8.14 Louver windows with timber frames b = 0.60, h = 1.00 m no. 3.0 350,000 1,050,000
8.15 Roof truss made from single angle bars, double pitch, span 6 m, truss spacing 2.80 m; incl. Corrosion protection kg 261.0 10,000 2,610,000
8.16 Purloins and bracings from angle bars kg 320.0 10,000 3,200,000
115
8.17 Corrugated Zincalum m2 37.0 70,000 2,590,000
8.18 Stone masonry structures for transformer platform, hard stand, tailrace (mortar: 1 PC to 4 sand) m3 3.5 600,000 2,100,000
8.19 Rendering of stone masonry of transformer platform, hard
stand, etc. m2 6.0 7,000 42,000
8.20 Supply, place, compact and cure secondary high grade concrete in plinth of turbine-generator unit, incl. formwork and rebar m3 2.9 1,000,000 2,900,000
8.21 Supply and drive copper earthling rods (heavy duty, dia. 19
mm, 2.4 m long) into powerhouse footings, incl. connection to rebar of powerhouse no. 4.0 230,000 920,000
8.22 Supply universal beam on tripod-type supports as rails for the
chain hoist (including corrosion protection) kg 135.0 10,000 1,350,000
8.23 Supply hand chain hoist, capacity 25 kN, with trolley, brand: "CM Cyclone, low head-room" or similar no. 1.0 6,000,000 6,000,000
Total Section 8 (carried forward to Summary Part A) 93,436,000 Section 9: Day work
9.1 3-tonne truck incl. operator day 1.0 1,400,000 1,400,000
9.2 Hydraulic excavator, track mounted, incl. operator day 1.0 1,800,000 1,800,000
9.3 Concrete vibrator, needle diameter 50 mm, incl. drive unit day 1.0 140,000 140,000
9.4 Concrete mixer, include drive unit day 1.0 450,000 450,000
9.5 Dewatering / sump pump; capacity 4 m3/h at 5 m head, incl. discharge hose day 1.0 350,000 350,000
9.6 Compaction equipment, incl. operator
a) hand-operated vibrating plate day 1.0 250,000 250,000 b) hand-operated mechanical rammer day 1.0 200,000 200,000
9.7 Electric welding plant incl. generator and welder, capacity 150 Amp. day 1.0 300,000 300,000
9.8 Unskilled labourer day 20.0 40,000 800,000
9.9 Semi-skilled labourer, day 10.0 60,000 600,000
9.10 Tradesman, (welder, bricklayer, concreter, carpenter,
fitter/machinist, sheet metal worker) day 5.0 80,000 400,000 Total Section 10 (carried forward to Summary Part A) 6,690,000 Summary Part A: Civil Works
1 Preliminary and General 250,000,000
116
2 River Intake Works 205,098,0003 Sand trap 143,250,0004 Headrace 853,634,2005 Storage Pond / Fore bay 36,789,6006 Spillway 52,360,0007 Penstock 172,250,0008 Powerhouse and Tailrace 93,436,0009 Day work 6,690,000 Total Part A: Civil Works 1,813,507,800
B Electro-mechanical Equipment
1.1 Elecro-mechanical equipment including: kW 244.0 8,300,000 2,025,200,000 - Transportation - Erection, Test, Commissioning and Training Total Part B: Electro-mechanical Equipment 2,025,200,000 (carried forward to Summary Page 1)
C Transmission and Distribution Lines Section 1: Transmission, MV, 35 kV
1.1 Transmission lines from Power house to EVN's transformer km 7.5 150,000,000 1,125,000,0001.2 Transmission line form 35 kV lines to hamlets km 14.2 150,000,000 2,130,000,000
Total Section 1 (carried forward to Summary Part C) 3,255,000,000 Section 2: Transmission, LV, 0.4 kV
2.1 Backbone line km 13.2 80,000,000 1,056,000,000 Total Section 2 (carried forward to Summary Part C) 1,056,000,000 Section 3: Transformer
3.1 Transformer 320 kVA, 35 kV/440 V, outdoor type set 1.0 140,000,000 140,000,0003.2 Transformer 25 kVA, 35 kV/440 V, outdoor type set 4.0 60,000,000 240,000,000
Total Section 3 (carried forward to Summary Part C) 380,000,000 Section 4: Distribution LV
4.1 Cable AAAC 3 x 15 mm2 km 20.5 5,000,000 102,500,0002.0 Household Connectors set 546.0 450,000 245,700,000
Total Section 4 (carried forward to Summary Part C) 348,200,000 Summary Part C: Transmission and Distribution Lines
1 Transmission 35 kV 3,255,000,0002 Transmission LV 1,056,000,0003 Distribution LV 348,200,0004 Transformer 380,000,000
117
Total Part C: Transmission and Distribution Lines 5,039,200,000
D Land Acquisition
1 Land lease certification (excluding yearly premium payments)m2 15,000,000
2 Administrative costs for land acquisition - - - Total Part D: 15,000,000 (carried forward to Summary Page 1)
E Project Support Costs
1 awareness rising - lump sum 25,000,000
2 community mobilisation - lump sum 100,000,000
3 Company formation - lump sum 0
4 feasibility study and engineering design - lump sum 120,000,000
5 project management and supervision - lump sum 150,000,000 Total Part E: Project Planning, Engineering Design and
Supervision VND 395,000,000 (carried forward to Summary Page 1)
F Contingency
1 for Part A: Civil Works: 10 % 181,350,800
2 for Part B: Electro-mechanical Equipment: 5% 101,260,000
3 for Parts C, D and E: all 8 % 435,936,000 Total Part F: Contingencies VND 718,546,800 (carried forward to Summary Page 1)
118
APPENDIX 4
OPTIMAZATION OF THE HYDROPWER SCHEME
119
Economic Avoided cost of EVN's power system
Dry season Wet season
US cent/kWh VND/kWh US cent/kWh VND/kWh
Energy 4.73 710 2.81 422
Generation Capacity 0.6 90 0.6 90
Network capacity 1.4 210 1.4 210
Total capacity 2 300 2 300
Energy plus Capacity 6.73 1010 4.81 722
Power consumption features and economic tariff for commune
Dry season Wet season
Electricity consumption 75% 25%
Peak load 65% 50%
Off peak load 35% 50%
Seasonal tariff (VND/kWh) 905 572
Avarage tariff (VND7kWh) 821.8
120
Input data for economic cost calculation
Giap Trung commune Number of households 546 Household Peak load 62.9 kW Annual electricity demand 163428 kWh Growth rate - First 3 years 2.50% - From year 4th 1.50% Losses in the commune grid 5% Discount rate 10% Analysed period 20 year Unit cost 35 KV MV lines 150 VND/km LV backbone lines 80 VND/km LV lines to households 5 VND/km 35 kV/0.4kV 320 kVA transformer 140 mil VND/set 35 kV/0.4kV 110 kVA transformer 100 mil VND/set 35 kV/0.4kV 25 kVA transformer 60 mil VND/set Connection fee 0.45 mil VND/HH Electricity tariff for household 1000 VND/kWh Electricity at National grid 606 VND/kWh Diesel genset cost 6.5 mil VND/kW Fuel consumption 0.45 l/kWh Fuel cost 5500 VND/l O&M cost for hydropower T/D lines 3.0% O&M cost for T/D lines 1.5% O&M cost for diesel generator 6.0% Technical option data
121
Option 1: Grid connected mini hydropower Investment cost MV lines to the commune, 14.2 km 2130.0 mil VND LV backbone lines, 13.2 km 1056.0 mil VND LV lines to households, 20.5 km 102.5 mil VND 35 kV/0.4kV 25 kVA transformer, 4 set 240.0 mil VND Connection fee, 546 households 245.7 mil VND Sub total investment cost 3774.2 mil VND Option 2: Off grid micro hydropower Investment cost for the micro hydropower, 82 kW 3140.0 mil VND MV lines form power house to the commune, 15.7 km 2355.0 mil VND LV backbone lines,13.2 km 1056.0 mil VND LV lines to households, 20.5 km 102.5 mil VND 35 kV/0.4kV 25 kVA transformer, 4 set 240.0 mil VND 35 kV/0.4kV 110 kVA transformer, 1 set 100.0 mil VND Connection fee, 546 households 245.7 mil VND Total investment cost 7239.2 mil VND Option 3: National Grid Connection MV lines, 14.2 + 6.8 = 21.0 km 3150 mil VND LV backbone lines, 13.2 km 1056 mil VND LV lines to households, 20.5 km 102.5 mil VND 35 kV/0.4kV 25 kVA transformer, 3 set 180 mil VND 35 kV/0.4kV 110 kVA transformer, 1 set 100.0 mil VND Connection fee, 546 households 245.7 mil VND Total investment cost 4834.2 mil VND Option 4: Diesel Genset Diesel Generators, 80 kW 520.0 mil VND LV backbone lines, 13.2 km 1056.0 mil VND LV lines to households, 20.5 km 102.5 mil VND Connection fee, 546 households 245.7 mil VND Total investment cost 1924.2 mil VND
122
Option 1: Grid connected hydropower
NPV 6,201.1 Mil. VND
Electricity cost 3,980 VND/kWh
Household cost 11.4 mil VND/HH
Year Investment cost O&M cost Electricity
demand Cost for
electricity Total mil. VND mil. VND 103 kWh mil. VND mil. VND
1 4108.2641 4108.32 61.6 167.5 211.1 272.73 61.6 171.7 216.3 278.04 61.6 176.0 221.8 283.45 61.6 178.6 225.1 286.76 61.6 181.3 228.5 290.17 61.6 184.0 231.9 293.58 61.6 186.8 235.4 297.09 61.6 189.6 238.9 300.5
10 61.6 192.4 242.5 304.111 61.6 195.3 246.1 307.712 61.6 198.3 249.8 311.413 61.6 201.2 253.5 315.214 61.6 204.2 257.4 319.015 61.6 207.3 261.2 322.816 61.6 210.4 265.1 326.817 61.6 213.6 269.1 330.718 61.6 216.8 273.1 334.819 61.6 220.0 277.2 338.920 61.6 223.3 281.4 343.021 61.6 226.7 285.6 347.222 61.6 230.1 289.9 351.523 61.6 233.5 294.3 355.924 61.6 237.0 298.7 360.325 61.6 240.6 303.1 364.8
123
Option 2: Off grid hydropower
NPV 7,513.8 Mil. VND
Electricity cost 4,823 VND/kWh
Household cost 13.8 mil VND/HH
Year Investment cost O&M cost Electricity
demand Cost for
electricity Total mil. VND mil. VND 103 kWh mil. VND mil. VND
1 6873.394 6873.42 144.7 167.5 144.73 144.7 171.7 144.74 144.7 176.0 144.75 144.7 178.6 144.76 144.7 181.3 144.77 144.7 184.0 144.78 144.7 186.8 144.79 144.7 189.6 144.7
10 144.7 192.4 144.711 144.7 195.3 144.712 144.7 198.3 144.713 144.7 201.2 144.714 144.7 204.2 144.715 144.7 207.3 144.716 144.7 210.4 144.717 144.7 213.6 144.718 144.7 216.8 144.719 144.7 220.0 144.720 144.7 223.3 144.721 616.3 144.7 226.7 761.022 144.7 230.1 144.723 144.7 233.5 144.724 144.7 237.0 144.725 144.7 240.6 144.7
124
Option 3: Connection to national grid
NPV 6,563.1 Mil. VND
Electricity cost 4,213 VND/kWh
Household cost 12.0 mil VND/HH
Investment cost O&M cost Electricity
demand Cost for
electricity Total mil. VND mil. VND 103 kWh mil. VND mil. VND
5058.936 5058.9 75.9 167.5 144.5 220.4 75.9 171.7 148.2 224.0 75.9 176.0 151.9 227.7 75.9 178.6 154.1 230.0 75.9 181.3 156.4 232.3 75.9 184.0 158.8 234.7 75.9 186.8 161.2 237.1 75.9 189.6 163.6 239.5 75.9 192.4 166.0 241.9 75.9 195.3 168.5 244.4 75.9 198.3 171.1 246.9 75.9 201.2 173.6 249.5 75.9 204.2 176.2 252.1 75.9 207.3 178.9 254.8 75.9 210.4 181.6 257.4 75.9 213.6 184.3 260.2 75.9 216.8 187.0 262.9 75.9 220.0 189.9 265.7 75.9 223.3 192.7 268.6 75.9 226.7 195.6 271.5 75.9 230.1 198.5 274.4 75.9 233.5 201.5 277.4 75.9 237.0 204.5 280.4 75.9 240.6 207.6 283.5
125
Option 4: Diesel Generators
NPV 7,109.4 Mil. VND
Electricity cost 4,563 VND/kWh
Household cost 13.0 mil VND/HH
Investment cost O&M cost Electricity
demand Fuel cost Total mil. VND mil. VND 103 kWh mil. VND mil. VND
1924.2 1924.2 115.5 167.5 435.3 550.8 115.5 171.7 446.2 561.7 115.5 176.0 457.4 572.8 115.5 178.6 464.2 579.7 115.5 181.3 471.2 586.6 115.5 184.0 478.3 593.7 115.5 186.8 485.4 600.9 115.5 189.6 492.7 608.2 115.5 192.4 500.1 615.6 115.5 195.3 507.6 623.1 115.5 198.3 515.2 630.7 115.5 201.2 522.9 638.4 115.5 204.2 530.8 646.2
1539.4 115.5 207.3 538.8 2193.6 115.5 210.4 546.8 662.3 115.5 213.6 555.0 670.5 115.5 216.8 563.4 678.8 115.5 220.0 571.8 687.3 115.5 223.3 580.4 695.8 115.5 226.7 589.1 704.5 115.5 230.1 597.9 713.4 115.5 233.5 606.9 722.4 115.5 237.0 616.0 731.5 115.5 240.6 625.2 740.7
126
Input data for economic benefit of investment
Giap Trung commune Number of households 546 Household Peak load 62.9 kW Annual electricity demand 163428 kWh Growth rate - First 3 years 2.5% - From year 4th 1.5% Losses in the commune grid - In commune grid 5.0% - In MV lines to national grid 1.0% General data Discount rate 10% Water fee 2% Analyzed period 20 year Economic price Electricity for household 4,213 VND/kWh Electricity for National grid (average) 606 VND/kWh - Wet season 422 VND/kWh - Dry season 710 VND/kWh O&M cost for hydropower 3.0% O&M cost for hydropower and T/D lines 1.5% Technical option data Option 1: Grid connected mini hydropower Investment cost for the micro hydropower 10006.5 mil VND - Hydropower plant 4409.5 mil VND - T&D transmission lines 5597.0 mil VND Annual output 1452354 kWh - Wet season 522755 kWh - Dry season 929599 kWh Option 2: Off grid micro hydropower Investment cost for the micro hydropower 6873.4 mil VND - Hydropower plant 2774.2 mil VND - T&D transmission lines 4099.2 mil VND Annual output 674862 mil VND
127
Option 1: Grid connected hydropower Net Present Value 1,592.7 mil VND Internal rate of return before tax 12.2% Electricity cost before tax 936.49 VND/kWh
Year Investment cost O&M Total cost Energy output Supply to Commune
Economic benefit
Feeding into National grid
Economic benefit Total revenue Cash flow
mil VND mil VND mil VND 103 kWh 103 kWh mil VND 103 kWh mil VND mil VND mil VND 1 10006.5 10006.5 -10006.5 2 216.2 216.2 1452 168 706 1264 766 1472 1255.7 3 216.2 216.2 1452 172 723 1259 764 1487 1270.7 4 216.2 216.2 1452 176 741 1255 761 1502 1286.1 5 216.2 216.2 1452 179 753 1252 759 1512 1295.5 6 216.2 216.2 1452 181 764 1249 758 1521 1305.1 7 216.2 216.2 1452 184 775 1247 756 1531 1314.9 8 216.2 216.2 1452 187 787 1244 754 1541 1324.8 9 216.2 216.2 1452 190 799 1241 752 1551 1334.8
10 216.2 216.2 1452 192 811 1238 751 1561 1345.0 11 216.2 216.2 1452 195 823 1235 749 1572 1355.3 12 216.2 216.2 1452 198 835 1232 747 1582 1365.8 13 216.2 216.2 1452 201 848 1229 745 1593 1376.5 14 216.2 216.2 1452 204 860 1226 743 1604 1387.3 15 216.2 216.2 1452 207 873 1222 741 1615 1398.3 16 216.2 216.2 1452 210 886 1219 739 1626 1409.4 17 216.2 216.2 1452 214 900 1216 737 1637 1420.7 18 216.2 216.2 1452 217 913 1212 735 1648 1432.2 19 216.2 216.2 1452 220 927 1209 733 1660 1443.8 20 216.2 216.2 1452 223 941 1206 731 1672 1455.7 21 1822.68 216.2 2038.9 1452 227 955 1202 729 1684 -355.0 22 216.2 216.2 1452 230 969 1199 727 1696 1479.8 23 216.2 216.2 1452 234 984 1195 725 1708 1492.2 24 216.2 216.2 1452 237 999 1191 722 1721 1504.8 25 216.2 216.2 1452 241 1014 1188 720 1734 1517.5
128
Option 2: Off grid hydropower Net Present Value (950.8) mil VND Internal rate of return before tax 8.0% Electricity cost before tax 4,823 VND/kWh
Year Investment cost O&M Total cost Annual output Supply to Commune
Feeding into National grid Total revenue Cash flow
mil VND mil VND mil VND 103 kWh 103 kWh 103 kWh mil VND mil VND 1 6873.4 6873.4 -6873.4 2 144.7 144.7 658 168 706 561.0 3 144.7 144.7 658 172 723 578.6 4 144.7 144.7 658 176 741 596.7 5 144.7 144.7 658 179 753 607.8 6 144.7 144.7 658 181 764 619.1 7 144.7 144.7 658 184 775 630.6 8 144.7 144.7 658 187 787 642.2 9 144.7 144.7 658 190 799 654.0
10 144.7 144.7 658 192 811 666.0 11 144.7 144.7 658 195 823 678.2 12 144.7 144.7 658 198 835 690.5 13 144.7 144.7 658 201 848 703.0 14 144.7 144.7 658 204 860 715.7 15 144.7 144.7 658 207 873 728.6 16 144.7 144.7 658 210 886 741.7 17 144.7 144.7 658 214 900 755.0 18 144.7 144.7 658 217 913 768.5 19 144.7 144.7 658 220 927 782.2 20 144.7 144.7 658 223 941 796.1 21 616.3 144.7 761.0 658 227 955 194.0 22 144.7 144.7 658 230 969 824.6 23 144.7 144.7 658 234 984 839.1 24 144.7 144.7 658 237 999 853.9 25 144.7 144.7 658 241 1014 868.9
129
APPENDIX 5
ECONOMIC AND FINANCIAL ANALYSIS
130
Ability and willing ness to pay for service
Total yearly cost of alternative energy to electricity 270.8 Mil VND Electricity need to meet the service 163428 kWh/year Willingness to pay 1657.2 VND/kWh General data Number of household 546 household Pico-hydro Penetration rate 74.2% Life span of Pico 30 months Cost for purchasing Owning Sharing
Price Household Cost Price Household Cost (VND) (HH) (VND) (VND) (HH) (VND)
250000 1 250000 100000 1 100000300000 4 1200000 280000 1 280000330000 1 330000 300000 2 600000350000 2 700000 380000 4 1520000360000 1 360000 500000 1 500000380000 1 380000 600000 1 600000400000 2 800000 700000 2 1400000
Average cost (VND) 387143 360000 Cost for maintenance Owning Sharing
Price Household Cost Price Household Cost (VND) (HH) (VND) (VND) (HH) (VND)
3000 2 6000 5000 2 100005000 4 20000 10000 3 30000
10000 5 50000 13000 1 1300018000 3 54000 18000 1 18000
20000 1 20000 25000 1 25000 40000 1 40000Average cost (VND) 9286 15600
131
Monthly average cost for one Pico (
VND) 24895Yearly average cost for whole commune 121.0 Kerosene Penetration rate 97.0% Kerosene cost 5000 VND/litre Monthly consumption Consumption Household Total cons. (litre) (HH) (litre) 0.2 1 0.2 0.5 3 1.5 0.8 1 0.8 1.0 15 15.0 1.5 2 3.0 2.0 6 12.0 3.0 3 9.0 4.0 1 4.0Average consumption (litre/household) 1.4 Yearly cost for whole commune (mil VND) 45.1 Dry cell battery Penetration rate 78.7% Proportion using for radio 50.0% Dry cell cost 2500 VND/pair Monthly consumption Consumption Household Total cons. (pair) (HH) (pair) 2.0 5 10.0 4.0 14 56.0 6.0 6 36.0 12.0 1 12.0Average using (pair/household) 4.4Yearly cost for whole commune (mil VND) 28.3 Diesel fuel Fuel cost 5500 VND/litre Yearly fuel consumption For rice husking 1848 Litre
132
For wood processing 12045 Liter Sum 13893 Liter Yearly fuel cost for the whole commune (mil VND) 76.4
133
Economic analysis for Giap Trung hydropower (Base case)
Economic indicators Net Present Value NPV 3,070.6 mil VND Internal rate of return EIRR 15.2% Electricity cost Pc 850.8 VND/kWh
Year Investment cost O&M Total cost Energy sold Supply to Commune
Economic benefit
Feeding into National grid
Economic benefit Total benefit Cash flow
mil VND mil VND mil VND 103 kWh 103 kWh mil VND 103 kWh mil VND mil VND mil VND 1 9005.8 9005.8 -9005.8 2 214.6 214.6 1452 168 706 1264 917 1623 1408.4 3 214.6 214.6 1452 172 723 1259 915 1638 1423.4 4 214.6 214.6 1452 176 741 1255 912 1653 1438.8 5 214.6 214.6 1452 179 753 1252 910 1663 1448.3 6 214.6 214.6 1452 181 764 1249 909 1672 1457.9 7 214.6 214.6 1452 184 775 1247 907 1682 1467.6 8 214.6 214.6 1452 187 787 1244 905 1692 1477.5 9 214.6 214.6 1452 190 799 1241 903 1702 1487.5
10 214.6 214.6 1452 192 811 1238 902 1712 1497.7 11 214.6 214.6 1452 195 823 1235 900 1723 1508.1 12 214.6 214.6 1452 198 835 1232 898 1733 1518.6 13 214.6 214.6 1452 201 848 1229 896 1744 1529.2 14 214.6 214.6 1452 204 860 1226 894 1755 1540.0 15 214.6 214.6 1452 207 873 1222 892 1766 1551.0 16 214.6 214.6 1452 210 886 1219 890 1777 1562.1 17 214.6 214.6 1452 214 900 1216 888 1788 1573.5 18 214.6 214.6 1452 217 913 1212 886 1800 1584.9 19 214.6 214.6 1452 220 927 1209 884 1811 1596.6 20 214.6 214.6 1452 223 941 1206 882 1823 1608.4 21 214.6 214.6 1452 227 955 1202 880 1835 1620.4 22 214.6 214.6 1452 230 969 1199 878 1847 1632.6 23 214.6 214.6 1452 234 984 1195 876 1860 1645.0 24 214.6 214.6 1452 237 999 1191 874 1872 1657.5 25 214.6 214.6 1452 241 1014 1188 871 1885 1670.2
134
Economic analysis for Giap Trung hydropower (Investment cost increases 10%)
Economic indicators Net Present Value NPV 2,103.9 mil VND Internal rate of return EIRR 13.3% Electricity cost Pc 934.5 VND/kWh
Year Investment cost O&M Total cost Energy sold Supply to Commune
Economic benefit
Feeding into National grid
Economic benefit Total benefit Cash flow
mil VND mil VND mil VND 103 kWh 103 kWh mil VND 103 kWh mil VND mil VND mil VND 1 9906.4 9906.4 -9906.4 2 234.1 234.1 1452 168 706 1264 917 1623 1389.0 3 234.1 234.1 1452 172 723 1259 915 1638 1404.0 4 234.1 234.1 1452 176 741 1255 912 1653 1419.3 5 234.1 234.1 1452 179 753 1252 910 1663 1428.8 6 234.1 234.1 1452 181 764 1249 909 1672 1438.4 7 234.1 234.1 1452 184 775 1247 907 1682 1448.1 8 234.1 234.1 1452 187 787 1244 905 1692 1458.0 9 234.1 234.1 1452 190 799 1241 903 1702 1468.1
10 234.1 234.1 1452 192 811 1238 902 1712 1478.3 11 234.1 234.1 1452 195 823 1235 900 1723 1488.6 12 234.1 234.1 1452 198 835 1232 898 1733 1499.1 13 234.1 234.1 1452 201 848 1229 896 1744 1509.8 14 234.1 234.1 1452 204 860 1226 894 1755 1520.6 15 234.1 234.1 1452 207 873 1222 892 1766 1531.5 16 234.1 234.1 1452 210 886 1219 890 1777 1542.7 17 234.1 234.1 1452 214 900 1216 888 1788 1554.0 18 234.1 234.1 1452 217 913 1212 886 1800 1565.5 19 234.1 234.1 1452 220 927 1209 884 1811 1577.1 20 234.1 234.1 1452 223 941 1206 882 1823 1588.9 21 234.1 234.1 1452 227 955 1202 880 1835 1600.9 22 234.1 234.1 1452 230 969 1199 878 1847 1613.1 23 234.1 234.1 1452 234 984 1195 876 1860 1625.5 24 234.1 234.1 1452 237 999 1191 874 1872 1638.0 25 234.1 234.1 1452 241 1014 1188 871 1885 1650.8
135
Economic analysis for Giap Trung hydropower (Output decreases 10%)
Economic indicators Net Present Value NPV 2,407.6 mil VND Internal rate of return EIRR 14.1% Electricity cost Pc 945.9 VND/kWh
Year Investment cost O&M Total cost Energy sold Supply to Commune
Economic benefit
Feeding into National grid
Economic benefit Total benefit Cash flow
mil VND mil VND mil VND 103 kWh 103 kWh mil VND 103 kWh mil VND mil VND mil VND 1 9005.8 9005.8 -9005.8 2 214.6 214.6 1307 168 706 1120 830 1536 1321.2 3 214.6 214.6 1307 172 723 1116 828 1551 1336.2 4 214.6 214.6 1307 176 741 1111 825 1566 1351.6 5 214.6 214.6 1307 179 753 1108 823 1576 1361.1 6 214.6 214.6 1307 181 764 1106 821 1585 1370.7 7 214.6 214.6 1307 184 775 1103 820 1595 1380.4 8 214.6 214.6 1307 187 787 1100 818 1605 1390.3 9 214.6 214.6 1307 190 799 1097 816 1615 1400.4
10 214.6 214.6 1307 192 811 1094 814 1625 1410.5 11 214.6 214.6 1307 195 823 1091 813 1635 1420.9 12 214.6 214.6 1307 198 835 1088 811 1646 1431.4 13 214.6 214.6 1307 201 848 1085 809 1657 1442.0 14 214.6 214.6 1307 204 860 1082 807 1667 1452.8 15 214.6 214.6 1307 207 873 1079 805 1678 1463.8 16 214.6 214.6 1307 210 886 1075 803 1690 1475.0 17 214.6 214.6 1307 214 900 1072 801 1701 1486.3 18 214.6 214.6 1307 217 913 1069 799 1712 1497.7 19 214.6 214.6 1307 220 927 1065 797 1724 1509.4 20 214.6 214.6 1307 223 941 1062 795 1736 1521.2 21 214.6 214.6 1307 227 955 1058 793 1748 1533.2 22 214.6 214.6 1307 230 969 1055 791 1760 1545.4 23 214.6 214.6 1307 234 984 1051 789 1772 1557.8 24 214.6 214.6 1307 237 999 1048 786 1785 1570.3 25 214.6 214.6 1307 241 1014 1044 784 1798 1583.1
136
Economic analysis for Giap Trung hydropower (Commune demand decreases 10%)
Economic indicators Net Present Value NPV 2,559.5 mil VND Internal rate of return EIRR 14.4% Electricity cost Pc 850.4 VND/kWh
Year Investment cost O&M Total cost Energy sold Supply to Commune
Economic benefit
Feeding into National grid
Economic benefit Total benefit Cash flow
mil VND mil VND mil VND 103 kWh 103 kWh mil VND 103 kWh mil VND mil VND mil VND 1 9005.8 9005.8 -9005.8 2 214.6 214.6 1452 151 635 1281 928 1563 1348.4 3 214.6 214.6 1452 155 651 1277 926 1577 1361.9 4 214.6 214.6 1452 158 667 1273 923 1590 1375.8 5 214.6 214.6 1452 161 677 1271 922 1599 1384.3 6 214.6 214.6 1452 163 687 1268 920 1608 1392.9 7 214.6 214.6 1452 166 698 1266 919 1616 1401.7 8 214.6 214.6 1452 168 708 1263 917 1625 1410.6 9 214.6 214.6 1452 171 719 1260 915 1634 1419.6
10 214.6 214.6 1452 173 730 1258 914 1643 1428.8 11 214.6 214.6 1452 176 741 1255 912 1653 1438.1 12 214.6 214.6 1452 178 752 1252 910 1662 1447.5 13 214.6 214.6 1452 181 763 1250 909 1672 1457.1 14 214.6 214.6 1452 184 774 1247 907 1681 1466.9 15 214.6 214.6 1452 187 786 1244 905 1691 1476.7 16 214.6 214.6 1452 189 798 1241 904 1701 1486.8 17 214.6 214.6 1452 192 810 1238 902 1712 1496.9 18 214.6 214.6 1452 195 822 1235 900 1722 1507.3 19 214.6 214.6 1452 198 834 1232 898 1732 1517.8 20 214.6 214.6 1452 201 847 1229 896 1743 1528.4 21 214.6 214.6 1452 204 859 1226 894 1754 1539.2 22 214.6 214.6 1452 207 872 1223 892 1765 1550.2 23 214.6 214.6 1452 210 885 1219 890 1776 1561.3 24 214.6 214.6 1452 213 899 1216 888 1787 1572.6 25 214.6 214.6 1452 217 912 1213 886 1799 1584.0
137
Financial analysis for Giap Trung hydropower (Base case)
Indicator on Equity Net Present Value NPV 306.7 mil. VND Internal Rate of Return IRR 13.8% Payback Period PBP 10.0 Year Unit Cost Pc 617.6 VND/kWh
Investment cost Running cost Revenue Cash
Total - Foreign loan - Local loan Water Profit Electric Electric Income Income Input flow
Year Inves. Annual IDC Annual Interest Annual IDC Annual Interest Equity Grant Depre. O&M fee Tax sold to sold to from from VAT Total On
Cost Inves. payment payment Inves. payment payment commune Grid commune grid return Equity
mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND 103 kWh 103 kWh mil.VND mil.VND mil.VND mil.VND mil.VND 0 10006 1769 53 0 0 2359 106 0 0 1769 5898 0 0 -1769 1 0 182 109 0 247 222 0 591 236 9 0 168 1264 201 736 500 1437 431 2 0 182 98 0 247 200 0 591 236 9 0 172 1259 206 733 0 939 -33 3 0 182 87 0 247 178 0 591 236 9 0 176 1255 211 731 0 942 2 4 0 182 77 0 247 155 0 591 236 9 0 179 1252 214 729 0 943 37 5 0 182 66 0 247 133 0 591 236 9 0 181 1249 218 727 0 945 72 6 0 182 55 0 247 111 0 591 236 9 0 184 1247 221 726 0 946 106 7 0 182 44 0 247 89 0 591 236 9 0 187 1244 224 724 0 948 141 8 0 182 33 0 247 67 0 591 236 9 1 190 1241 228 722 0 950 175 9 0 182 22 0 247 44 0 591 236 10 4 192 1238 231 721 0 951 207 10 0 182 11 0 247 22 0 591 236 10 6 195 1235 234 719 0 953 239 11 0 0 0 0 0 0 0 591 236 10 9 198 1232 238 717 0 955 700 12 0 0 0 0 0 0 0 591 236 10 18 201 1229 241 715 0 957 693 13 0 0 0 0 0 0 0 591 236 10 18 204 1226 245 713 0 959 695 14 0 0 0 0 0 0 0 591 236 10 18 207 1222 249 712 0 960 696 15 0 0 0 0 0 0 0 591 236 10 19 210 1219 253 710 0 962 698 16 0 0 0 0 0 0 0 591 236 10 19 214 1216 256 708 0 964 699 17 0 0 0 0 0 0 0 591 236 10 19 217 1212 260 706 0 966 701 18 0 0 0 0 0 0 0 591 236 10 20 220 1209 264 704 0 968 702 19 0 0 0 0 0 0 0 591 236 10 20 223 1206 268 702 0 970 704 20 0 0 0 0 0 0 0 591 236 10 20 227 1202 272 700 0 972 706 21 1823 0 0 0 0 0 0 1823 122 236 10 91 230 1199 276 698 0 974 -1186 22 0 0 0 0 0 0 0 122 236 10 91 234 1195 280 696 91 1067 730 23 0 0 0 0 0 0 0 122 236 10 92 237 1191 284 694 0 978 640 24 0 0 0 0 0 0 0 122 236 10 92 241 1188 289 691 0 980 642 25 0 0 0 0 0 0 0 122 236 10 92 244 1184 293 689 0 982 644
138
Financial analysis for Giap Trung hydropower (Tariff to national grid increases 10%)
Indicator on Equity Net Present Value NPV 781.2 mil. VND Internal Rate of Return IRR 16.7% Payback Period PBP 8.0 Year Unit Cost Pc 618.1 VND/kWh
Investment cost Running cost Revenue Cash
Total - Foreign loan - Local loan Water Profit Electric Electric Income Income Input flow
Year Inves. Annual IDC Annual Interest Annual IDC Annual Interest Equity Grant Depre. O&M fee Tax sold to sold to from from VAT Total On
Cost Inves. payment payment Inves. payment payment commune Grid commune grid return Equity
mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND 103 kWh 103 kWh mil.VND mil.VND mil.VND mil.VND mil.VND 0 10006 1769 53 0 0 2359 106 0 0 1769 5898 0 0 -1769 1 0 182 109 0 247 222 0 591 236 10 0 168 1264 201 809 500 1511 504 2 0 182 98 0 247 200 0 591 236 10 0 172 1259 206 806 0 1012 39 3 0 182 87 0 247 178 0 591 236 10 0 176 1255 211 804 0 1015 75 4 0 182 77 0 247 155 0 591 236 10 0 179 1252 214 802 0 1016 109 5 0 182 66 0 247 133 0 591 236 10 0 181 1249 218 800 0 1018 144 6 0 182 55 0 247 111 0 591 236 10 1 184 1247 221 798 0 1019 177 7 0 182 44 0 247 89 0 591 236 10 4 187 1244 224 796 0 1021 209 8 0 182 33 0 247 67 0 591 236 10 6 190 1241 228 795 0 1022 241 9 0 182 22 0 247 44 0 591 236 10 9 192 1238 231 793 0 1024 273
10 0 182 11 0 247 22 0 591 236 10 12 195 1235 234 791 0 1025 305 11 0 0 0 0 0 0 0 591 236 10 14 198 1232 238 789 0 1027 766 12 0 0 0 0 0 0 0 591 236 10 29 201 1229 241 787 0 1028 753 13 0 0 0 0 0 0 0 591 236 10 29 204 1226 245 785 0 1030 755 14 0 0 0 0 0 0 0 591 236 10 29 207 1222 249 783 0 1031 756 15 0 0 0 0 0 0 0 591 236 10 29 210 1219 253 781 0 1033 757 16 0 0 0 0 0 0 0 591 236 10 30 214 1216 256 779 0 1035 759 17 0 0 0 0 0 0 0 591 236 10 30 217 1212 260 776 0 1037 760 18 0 0 0 0 0 0 0 591 236 10 30 220 1209 264 774 0 1038 762 19 0 0 0 0 0 0 0 591 236 10 30 223 1206 268 772 0 1040 763 20 0 0 0 0 0 0 0 591 236 10 31 227 1202 272 770 0 1042 765 21 1823 0 0 0 0 0 0 1823 122 236 10 101 230 1199 276 768 0 1044 -1127 22 0 0 0 0 0 0 0 122 236 10 102 234 1195 280 765 91 1137 788 23 0 0 0 0 0 0 0 122 236 10 102 237 1191 284 763 0 1047 699 24 0 0 0 0 0 0 0 122 236 10 102 241 1188 289 761 0 1049 700 25 0 0 0 0 0 0 0 122 236 11 102 244 1184 293 758 0 1051 702
139
Financial analysis for Giap Trung hydropower (Commune demand increases 10%)
Indicator on Equity Net Present Value NPV 380.4 mil. VND Internal Rate of Return IRR 14.3% Payback Period PBP 10.0 Year Unit Cost Pc 617.6 VND/kWh
Investment cost Running cost Revenue Cash
Total - Foreign loan - Local loan Water Profit Electric Electric Income Income Input flow
Year Inves. Annual IDC Annual Interest Annual IDC Annual Interest Equity Grant Depre. O&M fee Tax sold to sold to from from VAT Total On
Cost Inves. payment payment Inves. payment payment commune Grid commune grid return Equity
mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND 103 kWh 103 kWh mil.VND mil.VND mil.VND mil.VND mil.VND 0 10006 1769 53 0 0 2359 106 0 0 1769 5898 0 0 -1769 1 0 182 109 0 247 222 0 591 236 9 0 184 1246 221 726 500 1447 441 2 0 182 98 0 247 200 0 591 236 9 0 189 1241 227 723 0 949 -23 3 0 182 87 0 247 178 0 591 236 10 0 194 1237 232 720 0 952 13 4 0 182 77 0 247 155 0 591 236 10 0 196 1234 236 718 0 954 47 5 0 182 66 0 247 133 0 591 236 10 0 199 1231 239 716 0 956 82 6 0 182 55 0 247 111 0 591 236 10 0 202 1227 243 715 0 957 117 7 0 182 44 0 247 89 0 591 236 10 0 205 1224 247 713 0 959 152 8 0 182 33 0 247 67 0 591 236 10 2 209 1221 250 711 0 961 185 9 0 182 22 0 247 44 0 591 236 10 4 212 1218 254 709 0 963 218 10 0 182 11 0 247 22 0 591 236 10 7 215 1214 258 707 0 965 250 11 0 0 0 0 0 0 0 591 236 10 10 218 1211 262 705 0 967 711 12 0 0 0 0 0 0 0 591 236 10 20 221 1208 266 703 0 969 703 13 0 0 0 0 0 0 0 591 236 10 20 225 1204 270 701 0 971 705 14 0 0 0 0 0 0 0 591 236 10 20 228 1201 274 699 0 973 706 15 0 0 0 0 0 0 0 591 236 10 21 231 1197 278 697 0 975 708 16 0 0 0 0 0 0 0 591 236 10 21 235 1194 282 695 0 977 710 17 0 0 0 0 0 0 0 591 236 10 21 238 1190 286 693 0 979 712 18 0 0 0 0 0 0 0 591 236 10 22 242 1186 290 691 0 981 713 19 0 0 0 0 0 0 0 591 236 10 22 246 1182 295 688 0 983 715 20 0 0 0 0 0 0 0 591 236 10 22 249 1179 299 686 0 985 717 21 1823 0 0 0 0 0 0 1823 122 236 10 93 253 1175 304 684 0 988 -1174 22 0 0 0 0 0 0 0 122 236 10 93 257 1171 308 682 91 1081 742 23 0 0 0 0 0 0 0 122 236 10 94 261 1167 313 679 0 992 652 24 0 0 0 0 0 0 0 122 236 10 94 265 1163 318 677 0 994 654 25 0 0 0 0 0 0 0 122 236 10 94 269 1159 322 674 0 997 656
140
Financial analysis for Giap Trung hydropower (Foreign loan accounts for 70%)
Indicator on Equity Net Present Value NPV 562.4 mil. VND Internal Rate of Return IRR 15.6% Payback Period PBP 9.0 Year Unit Cost Pc 591.6 VND/kWh
Investment cost Running cost Revenue Cash
Total - Foreign loan - Local loan Water Profit Electric Electric Income Income Input flow
Year Inves. Annual IDC Annual Interest Annual IDC Annual Interest Equity Grant Depre. O&M fee Tax sold to sold to from from VAT Total On
Cost Inves. payment payment Inves. payment payment commune Grid commune grid return Equity
mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND 103 kWh 103 kWh mil.VND mil.VND mil.VND mil.VND mil.VND 0 10006 4129 124 0 0 0 0 0 0 1769 5898 0 0 -1769 1 0 425 255 0 0 0 0 570 236 9 0 168 1264 201 736 500 1437 511 2 0 425 230 0 0 0 0 570 236 9 0 172 1259 206 733 0 939 39 3 0 425 204 0 0 0 0 570 236 9 0 176 1255 211 731 0 942 67 4 0 425 179 0 0 0 0 570 236 9 0 179 1252 214 729 0 943 94 5 0 425 153 0 0 0 0 570 236 9 0 181 1249 218 727 0 945 121 6 0 425 128 0 0 0 0 570 236 9 0 184 1247 221 726 0 946 148 7 0 425 102 0 0 0 0 570 236 9 2 187 1244 224 724 0 948 173 8 0 425 77 0 0 0 0 570 236 9 4 190 1241 228 722 0 950 198 9 0 425 51 0 0 0 0 570 236 10 6 192 1238 231 721 0 951 223 10 0 425 26 0 0 0 0 570 236 10 8 195 1235 234 719 0 953 248 11 0 0 0 0 0 0 0 570 236 10 10 198 1232 238 717 0 955 699 12 0 0 0 0 0 0 0 570 236 10 21 201 1229 241 715 0 957 690 13 0 0 0 0 0 0 0 570 236 10 21 204 1226 245 713 0 959 691 14 0 0 0 0 0 0 0 570 236 10 22 207 1222 249 712 0 960 693 15 0 0 0 0 0 0 0 570 236 10 22 210 1219 253 710 0 962 694 16 0 0 0 0 0 0 0 570 236 10 22 214 1216 256 708 0 964 696 17 0 0 0 0 0 0 0 570 236 10 22 217 1212 260 706 0 966 698 18 0 0 0 0 0 0 0 570 236 10 23 220 1209 264 704 0 968 699 19 0 0 0 0 0 0 0 570 236 10 23 223 1206 268 702 0 970 701 20 0 0 0 0 0 0 0 570 236 10 23 227 1202 272 700 0 972 703 21 1823 0 0 0 0 0 0 1823 122 236 10 91 230 1199 276 698 0 974 -1186 22 0 0 0 0 0 0 0 122 236 10 91 234 1195 280 696 91 1067 730 23 0 0 0 0 0 0 0 122 236 10 92 237 1191 284 694 0 978 640 24 0 0 0 0 0 0 0 122 236 10 92 241 1188 289 691 0 980 642 25 0 0 0 0 0 0 0 122 236 10 92 244 1184 293 689 0 982 644
141
Financial analysis for Giap Trung hydropower (Interest of local loan reduces to 7%)
Indicator on Equity Net Present Value NPV 478.2 mil. VND Internal Rate of Return IRR 15.0% Payback Period PBP 10.0 Year Unit Cost Pc 600.2 VND/kWh
Investment cost Running cost Revenue Cash
Total - Foreign loan - Local loan Water Profit Electric Electric Income Income Input flow
Year Inves. Annual IDC Annual Interest Annual IDC Annual Interest Equity Grant Depre. O&M fee Tax sold to sold to from from VAT Total On
Cost Inves. payment payment Inves. payment payment commune Grid commune grid return Equity
mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND 103 kWh 103 kWh mil.VND mil.VND mil.VND mil.VND mil.VND 0 10006 1769 53 0 0 2359 83 0 0 1769 5898 0 0 -1769 1 0 182 109 0 244 171 0 577 236 9 0 168 1264 201 736 500 1437 485 2 0 182 98 0 244 154 0 577 236 9 0 172 1259 206 733 0 939 15 3 0 182 87 0 244 137 0 577 236 9 0 176 1255 211 731 0 942 45 4 0 182 77 0 244 120 0 577 236 9 0 179 1252 214 729 0 943 75 5 0 182 66 0 244 103 0 577 236 9 0 181 1249 218 727 0 945 105 6 0 182 55 0 244 85 0 577 236 9 0 184 1247 221 726 0 946 134 7 0 182 44 0 244 68 0 577 236 9 1 187 1244 224 724 0 948 163 8 0 182 33 0 244 51 0 577 236 9 3 190 1241 228 722 0 950 190 9 0 182 22 0 244 34 0 577 236 10 5 192 1238 231 721 0 951 218 10 0 182 11 0 244 17 0 577 236 10 8 195 1235 234 719 0 953 245 11 0 0 0 0 0 0 0 577 236 10 10 198 1232 238 717 0 955 699 12 0 0 0 0 0 0 0 577 236 10 20 201 1229 241 715 0 957 691 13 0 0 0 0 0 0 0 577 236 10 20 204 1226 245 713 0 959 692 14 0 0 0 0 0 0 0 577 236 10 21 207 1222 249 712 0 960 694 15 0 0 0 0 0 0 0 577 236 10 21 210 1219 253 710 0 962 695 16 0 0 0 0 0 0 0 577 236 10 21 214 1216 256 708 0 964 697 17 0 0 0 0 0 0 0 577 236 10 21 217 1212 260 706 0 966 699 18 0 0 0 0 0 0 0 577 236 10 22 220 1209 264 704 0 968 700 19 0 0 0 0 0 0 0 577 236 10 22 223 1206 268 702 0 970 702 20 0 0 0 0 0 0 0 577 236 10 22 227 1202 272 700 0 972 704 21 1823 0 0 0 0 0 0 1823 122 236 10 91 230 1199 276 698 0 974 -1186 22 0 0 0 0 0 0 0 122 236 10 91 234 1195 280 696 91 1067 730 23 0 0 0 0 0 0 0 122 236 10 92 237 1191 284 694 0 978 640 24 0 0 0 0 0 0 0 122 236 10 92 241 1188 289 691 0 980 642 25 0 0 0 0 0 0 0 122 236 10 92 244 1184 293 689 0 982 644
142
Financial analysis for Giap Trung hydropower (Investment cost increases 10%)
Indicator on Equity Net Present Value NPV (263.9) mil. VND Internal Rate of Return IRR 10.6% Payback Period PBP 11.0 Year Unit Cost Pc 675.9 VND/kWh
Investment cost Running cost Revenue Cash
Total - Foreign loan - Local loan Water Profit Electric Electric Income Income Input flow
Year Inves. Annual IDC Annual Interest Annual IDC Annual Interest Equity Grant Depre. O&M fee Tax sold to sold to from from VAT Total On
Cost Inves. payment payment Inves. payment payment commune Grid commune grid return Equity
mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND 103 kWh 103 kWh mil.VND mil.VND mil.VND mil.VND mil.VND 0 11007 1946 58 0 0 2595 117 0 0 1946 6488 0 0 -1946 1 0 200 120 0 271 244 0 651 258 9 0 168 1264 201 736 550 1487 384 2 0 200 108 0 271 220 0 651 258 9 0 172 1259 206 733 0 939 -128 3 0 200 96 0 271 195 0 651 258 9 0 176 1255 211 731 0 942 -89 4 0 200 84 0 271 171 0 651 258 9 0 179 1252 214 729 0 943 -51 5 0 200 72 0 271 146 0 651 258 9 0 181 1249 218 727 0 945 -13 6 0 200 60 0 271 122 0 651 258 9 0 184 1247 221 726 0 946 25 7 0 200 48 0 271 98 0 651 258 9 0 187 1244 224 724 0 948 63 8 0 200 36 0 271 73 0 651 258 9 0 190 1241 228 722 0 950 101 9 0 200 24 0 271 49 0 651 258 10 0 192 1238 231 721 0 951 140 10 0 200 12 0 271 24 0 651 258 10 0 195 1235 234 719 0 953 178 11 0 0 0 0 0 0 0 651 258 10 3 198 1232 238 717 0 955 685 12 0 0 0 0 0 0 0 651 258 10 6 201 1229 241 715 0 957 683 13 0 0 0 0 0 0 0 651 258 10 6 204 1226 245 713 0 959 685 14 0 0 0 0 0 0 0 651 258 10 6 207 1222 249 712 0 960 687 15 0 0 0 0 0 0 0 651 258 10 7 210 1219 253 710 0 962 688 16 0 0 0 0 0 0 0 651 258 10 7 214 1216 256 708 0 964 690 17 0 0 0 0 0 0 0 651 258 10 7 217 1212 260 706 0 966 691 18 0 0 0 0 0 0 0 651 258 10 7 220 1209 264 704 0 968 693 19 0 0 0 0 0 0 0 651 258 10 8 223 1206 268 702 0 970 695 20 0 0 0 0 0 0 0 651 258 10 8 227 1202 272 700 0 972 696 21 1823 0 0 0 0 0 0 1823 122 258 10 88 230 1199 276 698 0 974 -1204 22 0 0 0 0 0 0 0 122 258 10 88 234 1195 280 696 91 1067 711 23 0 0 0 0 0 0 0 122 258 10 88 237 1191 284 694 0 978 622 24 0 0 0 0 0 0 0 122 258 10 89 241 1188 289 691 0 980 624 25 0 0 0 0 0 0 0 122 258 10 89 244 1184 293 689 0 982 626
143
Financial analysis for Giap Trung hydropower (Output decreases 10%)
Indicator on Equity Net Present Value NPV (247.6) mil. VND Internal Rate of Return IRR 10.6% Payback Period PBP 11.0 Year Unit Cost Pc 685.5 VND/kWh
Investment cost Running cost Revenue Cash
Total - Foreign loan - Local loan Water Profit Electric Electric Income Income Input flow
Year Inves. Annual IDC Annual Interest Annual IDC Annual Interest Equity Grant Depre. O&M fee Tax sold to sold to from from VAT Total On
Cost Inves. payment payment Inves. payment payment commune Grid commune grid return Equity
mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND 103 kWh 103 kWh mil.VND mil.VND mil.VND mil.VND mil.VND 0 10006 1769 53 0 0 2359 106 0 0 1769 5898 0 0 -1769 1 0 182 109 0 247 222 0 591 236 9 0 168 1120 201 652 500 1353 348 2 0 182 98 0 247 200 0 591 236 9 0 172 1116 206 649 0 855 -116 3 0 182 87 0 247 178 0 591 236 9 0 176 1111 211 647 0 858 -81 4 0 182 77 0 247 155 0 591 236 9 0 179 1108 214 645 0 860 -46 5 0 182 66 0 247 133 0 591 236 9 0 181 1106 218 644 0 861 -11 6 0 182 55 0 247 111 0 591 236 9 0 184 1103 221 642 0 863 24 7 0 182 44 0 247 89 0 591 236 9 0 187 1100 224 640 0 864 58 8 0 182 33 0 247 67 0 591 236 9 0 190 1097 228 639 0 866 93 9 0 182 22 0 247 44 0 591 236 9 0 192 1094 231 637 0 868 128 10 0 182 11 0 247 22 0 591 236 9 0 195 1091 234 635 0 870 163 11 0 0 0 0 0 0 0 591 236 9 3 198 1088 238 633 0 871 624 12 0 0 0 0 0 0 0 591 236 9 5 201 1085 241 632 0 873 623 13 0 0 0 0 0 0 0 591 236 9 6 204 1082 245 630 0 875 624 14 0 0 0 0 0 0 0 591 236 9 6 207 1079 249 628 0 877 626 15 0 0 0 0 0 0 0 591 236 9 6 210 1075 253 626 0 878 627 16 0 0 0 0 0 0 0 591 236 9 7 214 1072 256 624 0 880 629 17 0 0 0 0 0 0 0 591 236 9 7 217 1069 260 622 0 882 630 18 0 0 0 0 0 0 0 591 236 9 7 220 1065 264 620 0 884 632 19 0 0 0 0 0 0 0 591 236 9 7 223 1062 268 618 0 886 634 20 0 0 0 0 0 0 0 591 236 9 8 227 1058 272 616 0 888 635 21 1823 0 0 0 0 0 0 1823 122 236 9 79 230 1055 276 614 0 890 -1256 22 0 0 0 0 0 0 0 122 236 9 79 234 1051 280 612 91 983 659 23 0 0 0 0 0 0 0 122 236 9 79 237 1048 284 610 0 894 570 24 0 0 0 0 0 0 0 122 236 9 79 241 1044 289 608 0 896 572 25 0 0 0 0 0 0 0 122 236 9 80 244 1040 293 606 0 899 574
144
Financial analysis for Giap Trung hydropower (Commune demand decreases 10%)
Indicator on Equity Net Present Value NPV 233.0 mil. VND Internal Rate of Return IRR 13.4% Payback Period PBP 10.0 Year Unit Cost Pc 617.5 VND/kWh
Investment cost Running cost Revenue Cash
Total - Foreign loan - Local loan Water Profit Electric Electric Income Income Input flow
Year Inves. Annual IDC Annual Interest Annual IDC Annual Interest Equity Grant Depre. O&M fee Tax sold to sold to from from VAT Total On
Cost Inves. payment payment Inves. payment payment commune Grid commune grid return Equity
mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND 103 kWh 103 kWh mil.VND mil.VND mil.VND mil.VND mil.VND 0 10006 1769 53 0 0 2359 106 0 0 1769 5898 0 0 -1769 1 0 182 109 0 247 222 0 591 236 9 0 151 1281 181 746 500 1427 421 2 0 182 98 0 247 200 0 591 236 9 0 155 1277 185 744 0 929 -44 3 0 182 87 0 247 178 0 591 236 9 0 158 1273 190 741 0 931 -8 4 0 182 77 0 247 155 0 591 236 9 0 161 1271 193 740 0 933 26 5 0 182 66 0 247 133 0 591 236 9 0 163 1268 196 738 0 934 61 6 0 182 55 0 247 111 0 591 236 9 0 166 1266 199 737 0 936 96 7 0 182 44 0 247 89 0 591 236 9 0 168 1263 202 735 0 937 130 8 0 182 33 0 247 67 0 591 236 9 0 171 1260 205 734 0 939 165 9 0 182 22 0 247 44 0 591 236 9 3 173 1258 208 732 0 940 197 10 0 182 11 0 247 22 0 591 236 9 5 176 1255 211 731 0 942 229 11 0 0 0 0 0 0 0 591 236 9 8 178 1252 214 729 0 943 690 12 0 0 0 0 0 0 0 591 236 9 16 181 1250 217 727 0 945 683 13 0 0 0 0 0 0 0 591 236 9 16 184 1247 221 726 0 946 684 14 0 0 0 0 0 0 0 591 236 9 17 187 1244 224 724 0 948 686 15 0 0 0 0 0 0 0 591 236 9 17 189 1241 227 722 0 950 687 16 0 0 0 0 0 0 0 591 236 10 17 192 1238 231 721 0 951 688 17 0 0 0 0 0 0 0 591 236 10 17 195 1235 234 719 0 953 690 18 0 0 0 0 0 0 0 591 236 10 18 198 1232 238 717 0 955 691 19 0 0 0 0 0 0 0 591 236 10 18 201 1229 241 715 0 957 693 20 0 0 0 0 0 0 0 591 236 10 18 204 1226 245 714 0 958 694 21 1823 0 0 0 0 0 0 1823 122 236 10 89 207 1223 248 712 0 960 -1197 22 0 0 0 0 0 0 0 122 236 10 89 210 1219 252 710 91 1053 718 23 0 0 0 0 0 0 0 122 236 10 89 213 1216 256 708 0 964 629 24 0 0 0 0 0 0 0 122 236 10 90 217 1213 260 706 0 966 630 25 0 0 0 0 0 0 0 122 236 10 90 220 1209 264 704 0 968 632
145
Financial analysis for Giap Trung hydropower (Local accounts for 70%)
Indicator on Equity Net Present Value NPV 113.6 mil. VND Internal Rate of Return IRR 12.6% Payback Period PBP 11.0 Year Unit Cost Pc 637.0 VND/kWh
Investment cost Running cost Revenue Cash
Total - Foreign loan - Local loan Water Profit Electric Electric Income Income Input flow
Year Inves. Annual IDC Annual Interest Annual IDC Annual Interest Equity Grant Depre. O&M fee Tax sold to sold to from from VAT Total On
Cost Inves. payment payment Inves. payment payment commune Grid commune grid return Equity
mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND mil.VND 103 kWh 103 kWh mil.VND mil.VND mil.VND mil.VND mil.VND 0 10006 0 0 0 0 4129 186 0 0 1769 5898 0 0 -1769 1 0 0 0 0 431 388 0 607 236 9 0 168 1264 201 736 500 1437 372 2 0 0 0 0 431 349 0 607 236 9 0 172 1259 206 733 0 939 -87 3 0 0 0 0 431 311 0 607 236 9 0 176 1255 211 731 0 942 -46 4 0 0 0 0 431 272 0 607 236 9 0 179 1252 214 729 0 943 -6 5 0 0 0 0 431 233 0 607 236 9 0 181 1249 218 727 0 945 35 6 0 0 0 0 431 194 0 607 236 9 0 184 1247 221 726 0 946 75 7 0 0 0 0 431 155 0 607 236 9 0 187 1244 224 724 0 948 116 8 0 0 0 0 431 116 0 607 236 9 0 190 1241 228 722 0 950 156 9 0 0 0 0 431 78 0 607 236 10 2 192 1238 231 721 0 951 195 10 0 0 0 0 431 39 0 607 236 10 5 195 1235 234 719 0 953 233 11 0 0 0 0 0 0 0 607 236 10 8 198 1232 238 717 0 955 702 12 0 0 0 0 0 0 0 607 236 10 16 201 1229 241 715 0 957 695 13 0 0 0 0 0 0 0 607 236 10 16 204 1226 245 713 0 959 697 14 0 0 0 0 0 0 0 607 236 10 16 207 1222 249 712 0 960 698 15 0 0 0 0 0 0 0 607 236 10 16 210 1219 253 710 0 962 700 16 0 0 0 0 0 0 0 607 236 10 17 214 1216 256 708 0 964 702 17 0 0 0 0 0 0 0 607 236 10 17 217 1212 260 706 0 966 703 18 0 0 0 0 0 0 0 607 236 10 17 220 1209 264 704 0 968 705 19 0 0 0 0 0 0 0 607 236 10 18 223 1206 268 702 0 970 706 20 0 0 0 0 0 0 0 607 236 10 18 227 1202 272 700 0 972 708 21 1823 0 0 0 0 0 0 1823 122 236 10 91 230 1199 276 698 0 974 -1186 22 0 0 0 0 0 0 0 122 236 10 91 234 1195 280 696 91 1067 730 23 0 0 0 0 0 0 0 122 236 10 92 237 1191 284 694 0 978 640 24 0 0 0 0 0 0 0 122 236 10 92 241 1188 289 691 0 980 642 25 0 0 0 0 0 0 0 122 236 10 92 244 1184 293 689 0 982 644
146
APPENDIX 6
PHOTOGRAPHS
147
Houses in Giap Trung commune. Source: Oliver, Entec, 2002
Nam Nung stream. Source: Oliver, Entec, 2002
148
Road to Giap Trung commune and Track to power weir site. Source: Oliver, Entec, 2002
Children at school. Source: Oliver, Entec, 2002
149
Declaration
I hereby certify that this paper/dissertation was independently written by me. No
material was used other than that referred to. Sources directly quoted and ideas used,
including figures, tables, sketches, drawings and photos, have been correctly denoted.
Those not otherwise indicated belong to the author.
Flensburg, March 20th, 2003
Signature