A Basic Design Guideline for Mechanical Engineering Systems Could Be Categorised Into Five (5)...
-
Upload
sam-wing-hong -
Category
Documents
-
view
81 -
download
10
description
Transcript of A Basic Design Guideline for Mechanical Engineering Systems Could Be Categorised Into Five (5)...
1. SANITARY AND SEWERAGE PIPE MANHOLE SERVICES
1.1.All design guideline for Sanitary and Sewerage Pipe Manhole Services are based on
Guide to Sewerage Systems - Malaysian Water Association (MWA)/(BS5572:1994)
1.2.Make sure all proposed design calculations and drawings documentation to be prepared
earlier and need to be endorsed & sign by the Clients before doing any final Building
Submissions to the authorities. (e.g. Majlis Perbandaran Selayang, Majlis Perbandaran
Kelang, Majlis Perbandaran Shah Alam, Dewan Bandaraya Kuala Lumpur and etc. Those
approval processes would take around three (3) to four (4) months from the date of
submission.
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
2. HOT & COLD WATER PLUMBING SERVICES AND SUCTION &
ELEVATED ROOF WATER TANK & PUMPING SYSTEM
2.1. All proposed design guidelines are based on Guide to Water Supply System – JKR/MWA
2.2. Make sure all proposed design calculations and drawings for Hot & Water Plumbing
and Suction/Elevated Roof Water Tank and Pumping System need to be prepared for
Tender for Construction purposes and JBA/Syabas and District Council Authorities
submission and approval.
2.3. The Size of Elevated Storage/Domestic Water Tank is based on the number of
population per sq.ft. (100 sq.ft/ 1 person) or Specified Required Gallons of Water
Demand per sq.m(2.2 Ig/ 1 sq.m) – this case would be direct tapping from the Main
Bulk Water Meter to the Elevated Storage/Domestic Water Tank. Hence, under Penang
Water Authorities (PBA) the total Water Demand would be around 5.5 Igals/ 1 sq.m.
2.4. In any special case if there is a very low pressure from the Main Bulk Water Meter to
the Elevated Water Tank, it is required to have One Suction Tank that would be *1/3 of
Storage/day from the total water demand and balance 2/3 of Storage/day is for the
Elevated Roof/Storage Tank. It is noted that all final selection of Water Tank Size is
depends upon on the incoming size of the pipe from the Water Reticulation (e.g. Size
of Ductile Iron Pipe = 65 mm, need to consider the free board of 10” from the surface
of sitting ball valve to the inner surface of the tank height and the balance bottom
height of 3” where from the height of the water outlets to the inner surface of the
bottom water tank.
2.5. A Suction Pump (Booster – Multistage Vertical Type) need to be analysed and designed
for 6 to 8 hours Operation/day in a proper way by considering all water supply from
the Suction Tank to be controlled by On/Off Procedures (Pressure Regulating Control
Valves) where could be read off by the Motorised Valve at Roof Storage Tanks. The
effective capacity (KW) of the Suction Pump would be considered by the following
criteria’s:
2.6. Design flow rates (Q – Igpm) = Total Water Demand / 8 X 60 min.
Total Pump Head (ft.) = Highest Static Head + Pipe Friction Head Loss
2.7. (Pipe friction head loss = s.factor, 20% X Pipe friction factor [Equivalent Pipe Length +
Straight Pipe Length]
2.8. Min. Pump Cap. = 1.2 X Pump B.H.P X 0.746; i.e. Pump B.H.P = TPH X Q / 3300 X
Pump effieciency (60% to 65%)
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
2.9. The location of the Suction Tank would be at the Ground or Lower Ground Floor
depends upon S.O Architect’s requirements.
2.10. Material of Suction Tank shall be FRP – Fibre Reinforced Plastics or R.C –
Reinforced Concrete.
2.11. A Booster Pump for Roof Tanks calculations could be determined by considering
the number and type of fittings to be used and its individual loading unit’s factor. So,
by totaling up the number of loading unit’s factor then only the required Design Flow
Rates (Igmin. – Imperial Gallon/min.) could be determined by referring to CP310:1965
Graph – Fig.1 (Water Supply Rules – JKR)
2.12. Total Pump Head need to be considered by estimating the Total Pump Head
(TPH) would be considered same like determining the Suction Pump.
2.13. A Break Tank for Cold Water Plumbing Services only needed as per SYABAS
requirement if the High Rise Apartment/Condominium level height above 75 m.
2.14. Below table is a sample plant room & risers that for High Rise
Apartment/Condominium that need to be clarified with S.O’s Architects;
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
Sample Plant Room for Cold water:
Roof tank room 10m x 10m x 4.6m (H) Centre roof area
Roof pump room 4m x 2m x 3m (H) Shall be attached to roof tank
room
Suction tank room 10m x 5m x 3.5m (H) Within apartment footprint
Suction pump room 4m x 3m x 3.5m (H) Shall be attached to suction tank
room
Cold water riser 1.2m x 0.75m Required near staircase 1, 2 & 3
Cold Water Break Tank (if Building height > 75m)
(TANK TYPE : FRP)
a) Tank Sizing 4m(W) x 4m(L) x 2m(H) For the building height above
75m. Within 1 no. of
apartment unit for Block A &
B. At Level 17th. Sharing
with the apartment unit of
Wet Riser break tank.
b) Tank & Pump Room 4m(W) x 7m(L) x 2m(H)
Swimming Pool Requirement
a) Swimming Pool
Balancing Tank
Room
6(W) x 5(L) x 5(H) Within apartment footprint
(TANK TYPE : RC)
Swimming Pool Balancing
Tank Pump Room
5(W) x 5(L) x 5(H) Shall be attached to swimming
pool balancing tank room
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
3. AIR – CONDITIONING & MECHANICAL VENTILATION SERVICES
3.1. All proposed design guidelines are based on HVAC and Air – Conditioning System –
ASHRAE/MASHRAE or SMACNA
3.2. Make sure all proposed design calculations and drawings for Air - Conditioning and
Mechanical Ventilation System need to be prepared for Tender for Construction
purposes.
3.3. The selection of Chiller Unit is firstly to Determine the tentative heat loads for Chiller
Condensing unit by doing the estimation on the Average between maximum and
minimum of Grand Total Cooling Load/effective area, Sq.Ft. as can be referred to Table
1 – Design and Cooling Load Checks
3.4. (e.g. GTC – Hospital = 80 Btuh/Sq.Ft. Factories = 80 Btuh/Sq.Ft., Offices = 75
Btuh/Sq.Ft., Shopping Complexes = 60 Btuh/Sq.Ft. Houses, Condominiums &
Apartments = 65 Btuh/Sq.ft. and etc.).
3.5. Then only the Chiller Cooling Load in ‘Btuh’ Unit need to convert into Ton of
Refrigerant - T.R (1 T.R = 12,000 Btuh) and not to forget by adding up the Safety
factor of 10 to 15 percent.
3.6. Smoke Control System for the Air Handling Unit for all types of buildings should
consider the Suction Air and Return Air. A basic rule of thumbs as referred from below
formula;
CFM (Suction Air) = RSH (Room Sensible Heat)/1.08 X 15 and
CFM (Return Air) = 0.8 GTC
3.7. Cooling Tower Unit need to be determined by adding up 25% (i.e. multiply by factor of
1.25) from the total Chiller Cooling Unit. (T.R unit)
3.8. The Size of Make Up Water Tank need to be determined by considering below formula;
Total Size of Cooling Tower (CT-T.R) X 3.0 U.S Gallons X 8 hours of pump
operations.
(convert to Ig – Imperial Gallons, multiply by factor of 0.833)
3.9. Sub total capacity of Chilled Water Flow Rates - for individual AHU Units (m³/h) = (GTC,
KW)/1.16 X (7ºC - different of temp. on the refrigerating effects)
3.10. Total Capacity of Chilled Water Flow Rates (m³/h) = 7% of Sub – total capacity of
Chilled Water Flow Rates
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
3.11. Total Condenser Water Flow Rates (m³/h), as at 30ºC-32ºC = 25% of Total Chilled
Water Flow Rates(m³/h), as at 24ºC-26ºC
3.12. Chilled/Condensing Water Pump Capacity = Total Flow Rates,igpm
(Condenser/Chiller) X total pump head (ft)/3300 X Pump effieciency; considering 1 unit
each on standby and 2 units each on duty (total overall = 6 units of Condenser/Chilled
Water Pumps)
3.13. Chilled/Condenser Water Pipes could be determined same like the Cold Water
Pipe Calculations but the only difference is to take care any heat/cold losses from
those piping works by considering the fire rated pipe insulations.
3.14. Condenser Water flow rates for Water Cool Package Unit (l/min) = (GTC + Input)
KW / (7ºC - different of temp. on the refrigerating effects) X 0.07
3.15. Fan Coil Unit Power Consumption; for Air Cooled Package = 1.5KW/ton and Water
Cooled Package = 0.9KW/ton
3.16. Exhaust/Fresh Air Fan for Gen-set and Electrical Switch room; the Air – Change/hr
(ACH) = 15, Toilet = 10, Kitchen= 20, Basement = 6, Restaurant = 15 to 20 (depends
on the heat loads of the restaurant), Car-park = 12, Lift Motor Room = 12, Auditorium
= 0.14 cmm/seat, Canteen = 0.28 cmm/seat and the Air Flow Rates can be calculated,
CFM = Room Volume (m³) X ACH / 60
3.17. Total Pressure Losses for AHU Ducting Lines; Pressure Duct Losses = ( ? ft. X
0.1”wg/100ft) + fan losses = 0.2”wg + Grille Losses = 0.1” wg
3.18. AHU Fan Power Rated; Air Flow Rates (m³/s) X Total Pressure Losses (mm
wg)/102 X motor efficiency (65%)
3.19. The Air – Cooled Supply Velocity from the AHU – Air Handling Unit could be
determined by using the Ductulator (e.g. TRANE, YORK DUNHAM BUSH)
3.20. Air Fan Capacity for Kitchen Area (m³/hr) = Kitchen Room Size (m³) X 25 ACH / 1
hr.
3.21. Kitchen Hood Size = W (m) X L (m) X 1.02 (h)
3.22. Suction Air Fan at the Kitchen Hood (CFM) = (1.4 X 0.4m/s X 2(W+L) X 1.02, by
converting to CFM) X Grille losses, 0.5”wg
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4. FIRE PROTECTION SERVICES & FIRE ALARM SYSTEM
All proposed design calculations and drawings for Fire Protection Services & Fire Alarm
System need to follow a design guidelines that based on the book title; Guide To Fire
Protection in Malaysia – 2nd.edition, March 2006 (Active Submission, by refer to Chapter
5 to 13 – Portable Fire Extinguisher, External Fire Hydrant System, Hose Reel System,
Dry Riser System, Wet Riser System, Downcomer System, Automatic Sprinkler System,
Automatic CO2 Extinguishing System, and Automatic Fire Detection & alarm System)
Pressurisation System in Building, Smoke Control System Using Natural Displacement
or Powered Extracted Ventilation, Fire Lift, and Emergency Power System would be put
under separate submission due to the building requirements (by refer to Chapter 14 to
17)
All Passive Submission and Performance Base would be under Architectural and C&S
Scope of Works Only. (Chapter 4 and 18 only)
Make sure all proposed design calculations and drawings for Active Fire Protection
Services need to be prepared for Tender for Construction purposes and BOMBA
submission and approval.
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.1. Portable Fire Extinguisher –
It could be categorised into different types of Media and Application/Classes by following its
Colour Coding;
Water – Suit for *Class A fires (in red colour code)
Foam – Suit for Class A & B fires (in cream colour code)
Dry Chemical Powder – Suit for Class A, B, C and E fires (in blue colour code)
Carbon Dioxide – Suit for Class B & E fires (in black colour code)
Halon – Suit for Military, Aviation or Special Application (in golden yellow colour
code)
Wet Chemical System – new requirement by BOMBA that need to be installed at all
Kitchen Areas. – suit under Class F
Selection of the P.F.E – Potable Fire Extinguisher; e.g., at the floor area of 1600m²:
0.065 X 1600 = 104A
104A = 13A X 8 Units of PFE Cylinders X 4 Kg; or
108A = 27A X 4 Units of PFE Cylinders X 6 Kg
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.2. External Fire Hydrant System –
4.2.1. Design Standard
– MS1489 Part 1 (Hydrant System, Hose Reels and Foam Inlets)
– MS1395 Part 1 (Pillar Hydrant)
4.2.2. Design Method of Fire Hydrant System:
4.2.2.1. Design Method could be categorized into two types of external fire
hydrant systems;
– Direct from main intake to all the pillars
– Pressurized by Fire Pumps
4.2.2.2. Pillar Hydrant Location is < 30m from the breeching inlet at the
building
4.2.2.3. Hydrant Pillar System location ≥ 6m from the building if it is
a High Rise Building.
4.2.2.4. Hydrant Pillar Spacing ≤ 90m in between and each location has a
min. 6m (width) that could withstand 26 tons.
4.2.2.5. Each Hydrant Pillar should be provided with 30m of 65mm dia.
Canvas Hose, Coupling and Nozzles that to be placed in the special
cabinets nearby.
4.2.2.6. In any special case for Pressurized Installation (used Pumps) each
Hydrant Pillars (twin outlets) need to have a Water Supply at the
minimum flow rates of 1000 lit./min (1m³/h) and at Working Pressure
of 4 Bar (58 Psi/9m head/30ft. head).
4.2.2.7. Each outlets from the Hydrant Pillars – 500 lit/min (0.5 m³/h) and at
min. Working Pressure of 2 Bar (29 Psi/4.5m head/15ft. head)
4.2.2.8. Pressure Regulating type of outlet valve need to be introduced if
ever the outlet pressure from the fire mains boost to 7 Bar (101.5
Psi/16m head/53ft. head)
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.2.2.9. Pipe Material of the Hydrant Systems could be categorized into two
(2) types that approved by BOMBA;
– Cement Lined Steel Pipe
– ABS (anti-corrosion pipe)
4.2.2.10.Hydrant Pump Specifications;
– One (1) Unit Standby – 3 m³/min (3000 lit./min) – Electrical/Diesel
Engine driven,
– One (1) Unit On Duty - 3 m³/min (3000 lit./min) – Electrical driven
and
– One (1) unit of Jockey Pump – To maintain system pressure and
as a Start–Up for On Duty/Standby Pumps and usually an
electrical motor driven with a capacity of around 120 lit./min
(0.12 m³/min)
4.2.2.11.The Flow rates for both Standby/On Duty Hydrant Pumps could be
increased depends upon the number of Pillar Hydrants to be
installed
– because the limitation for the flow rates of 3000 lit/min each
pumps are only limited to 3 n.o.s of Pillars hydrant only; i.e. 1
n.o.s of Pillar Hydrant = 1000 lit. /min and as example if 6 n.o.s
of Pillars Hydrant = 6000 lit. /min and so forth.
4.2.2.12.The Hydrant Pump-Set should be protected from weather (i.e. effect
by flooding season)
4.2.2.13.The Fire Water Storage Tank should be sized for a minimum
effective capacity of 135, 000 lit. /min (Approximately: 35,000 to
36,000 Imp. Gallons) that would consider the Upper Level height
(free board) and bottom level height (600mm/0.6m)
4.2.2.14.Before doing any testing on the Hydrant Pumps all procedures below
need to be followed;
– Starting the duty pump-set at 80% of the system pressure;
– Starting the standby pump – set at 60% of the system pressure;
and
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
– Starting and Stopping the jockey pump – set at 90% and 110% of
the system pressure.
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.3. Hose Reel System –
4.3.1. Design Standard
– M.S.1489 Part 1: Hydrant System, Hose Reels and Foam Inlets;
– M.S.1447 - Hose Reels with semi – rigid hose;
– M.S.1488: Semi – rigid hoses for first aid fixed installations.
4.3.2. Design Method of Hose Reel System;
4.3.2.1. It should be complied with M.S.1447 and stated detailed under the
10th.Schedule (refer to UBBL)
4.3.2.2. The location for each hose reel are usually to be placed where could
cover 30 meters of hose coverage between the hose reels stack.
4.3.2.3. Each hose reel outlet to discharge a minimum of 30 lit/min (1.8
m³/min) of water within 6 meters of all parts of the space protected.
4.3.2.4. The rubber hoses should comply to M.S 1488 (min: 30 m in length)
4.3.2.5. Size of Hose Reel Pipe is 50mm (nom. dia.) and the material is
Galvanised Steel – Medium Grade Class B for above ground but for
Underground G.I Pipe -Heavy Grade Class C & to be feed to
individual hose pipe size ≥ 25mm dia.
4.3.2.6. The pipe shall be painted with primer and finished with red paint or
may be identified with red bands.
4.3.2.7. Hose Reel Pumps – 1 (One) unit on Duty and 1 (One) unit on Standby
4.3.2.8. Pump Flow Rates – 120 lit/min@ operating pressure at 2 to 3 bars (4
Hose Reels could be activated at one time)
4.3.2.9. The Standby Hose Reel Pump – Set should be supplied with power
from the emergency generator or diesel engine driven (fuel supply
should be adequate for min. 1 hour of operation)
4.3.2.10.Starting and Stopping the Duty pump-set need to be set at 80% and
100% of System pressure respectively;
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.3.2.11.Starting and Stopping the Standby pump – set need to be set at 60%
to 100% of system pressure respectively.
4.3.2.12.Diesel pump – set should be capable of automatic starting but
should only be stopped manually.
4.3.2.13.If the total hose reel < 4 Units than no need to use emergency
power; i.e Electrical Generator or Diesel Engine Driven.
4.3.2.14.All hose reels system shall not be tapped off from Automatic
Sprinkler System
4.3.2.15.Min. Floor Size Area of Hose Reel Stacks : 1200mm - Length X
800mm - Depth (mm²)
4.3.2.16.Minimum Effective Capacity of Fire Water Storage Tank should be
sized based 2275 litres (500 Ig) for the first hose reel and 1137.5
liters (250 Ig) for every additional hose reel. The maximum effective
capacity is approximately 9100 litres (2001 Ig).
4.3.2.17.The Material used for the Fire Tank is either made from Pressed
Steel (hot dipped galvanised and coated internally with Bituminous
paints for corrosion protection), FRP – Fiberglass Reinforced Plastics
or R.C Concrete.
4.3.2.18.This Hose Reel Tank need to be refilled with 50mm Supply pipe and
at the min. flow rates of 150lit/min (33 Igpm)
4.3.2.19.Pump Rooms would be located at the Ground Floor or Roof Floor
Level and the min. Fire Protection Plant Room Size as following
below table;
Plant Room for Hose Reel Tank
Hose Reel Tank
Room
(TANK TYPE : RC)
3(W) x 2(L) x 5(H) Within apartment footprint and could be
shared with Wet Riser Tank Room if
Required.
If the location of hose reel tank at roof
top than it is advisable to combine with
a Roof Storage Water Tank (i.e Shopping
Complexes like Carrefour, Tesco or
Giant)
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
Ventilation slots should be provided with
insect screen to prevent entry of vermin
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.4. Dry Riser System –
4.4.1. Design Standard
– M.S.1489 Part 1: Hydrant System, Hose Reels and Foam Inlets;
– M.S.1210 Part 2: Landing Valves for Dry Risers;
– M.S 1210 Part 3: Inlet Breeching Inlet for Risers Inlet
– M.S 1210 Part 4: Boxes for Landing Valves for Dry Risers
4.4.2. Design Method of Dry Riser System;
4.4.2.1. It should be complied with UBBL 1984, the by Laws 230 and 232
4.4.2.2. Dry Risers are a form of internal hydrant and are only required for
buildings where the topmost floor is higher than 18.3 meters and
less than 30.5 meters.
4.4.2.3. Dry Risers are basically dry and all depends upon the Fire Engine to
pump water into the system by considering the Breeching Inlet to be
located about 30 meters from the External Hydrant System.
4.4.2.4. Landing Valves are provided on each floor and should comply with
M.S 1210: Part 2.
4.4.2.5. Those Landing Valves would be located within the fire access
lobbies, protected staircases or other protected lobbies at not more
than 0.75 meters from the floor level.
4.4.2.6. To protect the landing valves, boxes may be provided and these
should comply with M.S.1210 Part 4.
4.4.2.7. Fire Hose Reel Pipings > 38mm dia., 30 meters in length, complete
with 65mm dia. Quick Coupling and nozzle should be provided at
each landing valve.
4.4.2.8. Breeching Inlet would be installed at the bottom of the riser and
should comply with M.S. 1210: Part 3. The breeching inlet is
enclosed within a box, the enclosure should comply with M.S.1210
Part 5 and labeled ‘Dry Riser Inlet’ and a typical drain should be
provided at the bottom of the riser to drain the system after used.
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.4.2.9. 2 – Way Breeching Inlet should be provided for a 100mm dia. Of dry
riser pipes but 4 – Way Breeching Inlets : 200mm dia. Of Dry Riser
Pipes and should be located 18 meters from the fire appliance
access road. (the distance of fire fighters truck to be placed)
4.4.2.10.The riser pipe diameter size – 150mm usually located within the fire
access lobby or staircase if the highest outlet is more than 22.875m
above the breeching inlet. Otherwise the riser pipe diameter size –
100mm.
4.4.2.11.The material of the Riser Pipe shall be Galvanised Iron to B.S. 1387
(heavy gauge) or Class C, tested to 21 Bars (305 Psi)
4.4.2.12.All feeding Pipe-works that runs horizontally need to be sloped to
enable proper draining after used and also an Air Release Valve
should be installed at the top of the riser to relief air trapped in the
system.
4.4.2.13.The riser pipe should be electrically earthed or connected to the
building earth to achieve equipotential.
4.4.2.14.The riser to be hydraulically tested to a pressure of 14 Bars for 2
hours that to be measured at the Breeching inlet and not forget to
check all leakage at the joints and landing valves connections.
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.5. Wet Riser System –
4.5.1. Design Standard
– M.S.1489 Part 1: Hydrant System, Hose Reels and Foam Inlets;
– M.S.1210 Part 2: Landing Valves for Dry Risers;
– M.S 1210 Part 3: Inlet Breeching Inlet for Risers Inlet
– M.S 1210 Part 4: Boxes for Landing Valves for Dry Risers
4.5.2. Design Method of Wet Riser System;
4.5.2.1. It should be complied with UBBL 1984, the by Laws 231, 232 and
248
4.5.2.2. Wet Risers are a form of internal hydrant and are always charged
with water. The topmost floor is higher than 30.5 meters and less
than 70.15 meters for each stage of Wet Risers. If > than 70.15
meters, so a Break Tank is required.
4.5.2.3. Wet Riser System comprises duty fire pump with standby pump
discharging into a 150mm diameter riser pipe with landing valves at
each floor and to which canvas hose with nozzles can be connected
to direct the water jet at the fire.
4.5.2.4. The function of a Jockey Pump is to maintain system pressure.
4.5.2.5. Landing valves that usually being installed at each floor should
comply with M.S. 1210: Part 1 and located within fire fighting access
lobbies, protected staircases or other protected lobbies.
4.5.2.6. The height of the landing valves should be < 0.75 m from the floor
level and for the safety purposes this landing can be protected by
providing boxes and need to comply with M.S 1210: Part 4
4.5.2.7. Recommended pressure for each landing valve should be in between
4 to 7 bars (58 to 102 Psi)
4.5.2.8. Landing Valve could be categorised into two types : -
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
– Pressure reducing type with relief outlet – require a wet riser
return pipe
– Pressure reducing type without relief outlet
4.5.2.9. Size of the Fire Hose Canvas type ≥ 38mm and the required length
is 30m. complete with 65mm dia. Of quick coupling and jet and
spray nozzle should be provided in a hose cradle beside each
landing valve.
4.5.2.10.Breeching Inlet for the Wet Riser System is normally same with the
Dry Riser System where the firemen could usually pump the water
from the water source (External Fire Hydrant Pillar – located < 30m
from the breeching inlet) into the Wet Riser Storage Tank to make –
up for water used.
4.5.2.11.These breeching inlets need to be located < 18m from the fire
appliance access road.
4.5.2.12.The Breeching inlet should be a 4 – Way type complying with M.S
1210: Part 3 and enclosed within a box that also complies with M.S
1210: Part 5. These box enclosures need to be labelled as ‘Wet Riser
Inlet’ and to provide a drain at the bottom of the riser to drain the
system after use.
4.5.2.13.Wet Riser Main Pipeline usually located within the Smoke Lobby or
protected areas and such that all spaces are to be within 45m
coverage from a Landing Valve and more than one riser is required
for each floor.
4.5.2.14.Distance between the risers should not exceed 60m and also where
between the lowest and topmost landing valve in any upper stage
risers.
4.5.2.15.The Size of the Pipe Riser should be 150mm dia. (Galvanised Iron to
B.S. 1387 – Heavy Gauge or Class C)
4.5.2.16.The Size of Relief Pipe shall be at min. of 100mm dia. (Galvanised
Iron to B.S. 1387 – Medium Gauge or Class B, where discharging
back to the Wet Riser Tank whenever possible and all air relief need
to be installed at the top of the riser to relief any air trapped in the
system).
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.5.2.17.The Wet Risers pipe should be coated with primer and finished with
red gloss paint or any special condition those wet riser pipes can be
colour coded with red bands of 100mm width but only at the elbows
& tees need to be fully painted in red.
4.5.2.18.All Wet Riser Pipe should be electrically earthed to achieve
equipotential with the building.
4.5.2.19.There two sets of Wet Riser Pumps – One (1) unit is on duty and One
(1) unit on standby and both pump capacity are usually sized to
deliver 1500 l/min at a running pressure in between 4 to 7 Bars that
would cater for three (3) landing valves at one time of operation
during building in fire.
4.5.2.20.All Standby Wet Riser Pump-set should be supplied with power from
the emergency generator set or otherwise by using a Diesel Engine
Driven.
4.5.2.21.All Fuel Supply should be adequate for minimum 2 hours of
continuous mode of operations.
4.5.2.22.Batteries for the Diesel Engine driven type of Standby Pump should
maintenance – free type.
4.5.2.23.All electrical cabling to Supply Power the Wet Riser Pumps should be
of MICC or Fire Rated Cable Type.
4.5.2.24.All Wet Riser Pump – Sets should be protected away from fire and
flooded areas.
4.5.2.25.A Sump Pump need to be considered for any special case of that
Wet Riser Pump – Sets to be located at the basement below the
external drainage levels. This Wet Riser Pump – Sets room also need
to be naturally or mechanical ventilated with a necessary signage
and to provide a CO2 – Portable Type of Fire Extinguisher for any
case of fire.
4.5.2.26.Effective Capacity of the Wet Riser Tank need to be sized up to
minimum capacity of 45,500 liters (10,009 Imp. Gallon) c/w
automatic refill rate of 455 lit/min (100.1 Igpm).
4.5.2.27.The Intermediate Break Tank for upper stages of the Wet Riser
should be sized up to a minimum effective capacity of 11,375 liters
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
(2503 Imp. Gallon) c/w automatic refill rate of 1365 lit/min (300.3
Igpm).
4.5.2.28.Wet Riser Tank Materials are usually from a Pressed Steel, Fibre
Reinforced Polyester (FRP) and Reinforced Concrete (R.C)
4.5.2.29.Pressed Steel – Wet Riser Tank should be Hot Dipped Galvanised and
Coated Internally with Bituminous paint for corrosion protection.
4.5.2.30.Both Pressed Steel and FRP – Wet Riser Tank need to be
compartmented unless they are Reinforced Concrete (R.C) and all
compartmented wet riser tanks need to provide with a separate Ball
Float Valves, Overflow Pipes, Drain Pipes and Water Level Indicator.
4.5.2.31.All Wet Riser Tank need to be painted red or else a red band of
minimum 200mm should be painted to indicate that this is a fire
tank.
4.5.2.32.All Wet Riser Tank could located on the Ground Floor, 1st.Lower
Ground Floor or 2nd.Lower Ground Floor level.
4.5.2.33.Wet Riser Tanks are usually separated from the Domestic Water
Storage/Suction Tanks but however could be combined with Hose
Reel Tank and need to be compartmented.
4.5.2.34.Pump Starter Panel should be complete with indicator lights as
shown at the appendix – a.
4.5.2.35.All types of ventilation slots should be provided with insect screen to
prevent entry of vermin (small insects; i.e. ants, spiders and etc.)
4.5.2.36.Power Supply cables to the panel should be of mineral insulated
copper cable (MICC) or fire rated type of cables within areas with low
risk.
4.5.2.37.The Fire Pump Starter panel should be placed within the same room
as the fire pumps it controls.
4.5.2.38.Wet Riser Pumps need to be automatically started upon actuation of
the pressure switches but should only be stopped manually. Usually
three pressure switches are provided with the following suggested
pressure settings:
starting the duty pump – set : 80% of the system pressure
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
starting the standby pump – set: 60% of the system pressure
starting and stopping the jockey pump – set at 90% and 110% of
the system pressure respectively.
4.5.2.39.Testing requirements for the Wet Riser System are the following;
Static Pressure Test – to clear up the debris from the inside of
Those main wet risers and hydraulically the pressure to be tested
up to 14 Bars or 150% the WorkingPressure, whichever is the
higher for 2 hours, measured at the lowest landing valve and a
check is carried out for leakage at all joints and landing valve
connections.
Flow Test – A three way of landing valve should be provided on
the roof or topmost floor for testing purposes where the main
motif is to measure the water flow rates
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.6. Downcomer System –
4.6.1. Design Standard
– M.S.1489 Part 1: Hydrant System, Hose Reels and Foam Inlets;
– M.S.1210 Part 2: Landing Valves for Dry Risers;
– M.S 1210 Part 3: Inlet Breeching Inlet for Risers Inlet
– M.S 1210 Part 4: Boxes for Landing Valves for Dry Risers
4.6.2. Design Method of Downcomer System;
4.6.2.1. It should be complied with UBBL 1984, relating to Downcomer
systems is the 10th.Schedule and relevant standards for Downcomer
systems as above mentioned.
4.6.2.2. Downcomers are a form of internal hydrant and are only required for
buildings where the topmost floor is not higher than 60 meters
above the fire appliance access level and should be adopted for low
cost flats only.
4.6.2.3. Downcomer system comprises a high level water storage tank
discharging into a 150mm dia. Riser pipe with landing valves at each
floor and to which canvas hose with nozzles can be connected to
direct the water jet at the fire.
4.6.2.4. No pumps are provided and therefore the system pressure is limited
to the static pressure head only.
4.6.2.5. Landing Valves are provided on each floor and should comply with
M.S 1210: Part 2.
4.6.2.6. Those Landing Valves would be located within the fire access
lobbies, protected staircases or other protected lobbies at not more
than 0.75 meters from the floor level.
4.6.2.7. A Semi – rigid 40mm diameter hose and nozzles should be provided
at every landing valve on each floor.
4.6.2.8. In addition, two sets of fire hose of the canvas type of not less than
38mm diameter, 30 metres in length complete with 65mm dia. quick
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
coupling and jet and spray nozzle should be provided at the
caretakers unit or property management office.
4.6.2.9. Fire Hose Reel Pipings > 38mm dia., 30 meters in length, complete
with 65mm dia. Quick Coupling and nozzle should be provided at
each landing valve.
4.6.2.10.A 4 - Way type of Breeching Inlet would be installed at the bottom of
the riser and should comply with M.S. 1210: Part 3. The breeching
inlet is enclosed within a box, the enclosure should comply with
M.S.1210 Part 5 and labeled ‘Downcomer Inlet’ and a typical drain
should be provided at the bottom of the riser to drain the system
after used.
4.6.2.11.This Breeching inlet should be located at no more than 18 metres
from the fire appliance access and not more than 30 metres from
the nearest external hydrant.
4.6.2.12.A Check Valve need to be installed between the topmost landing
valve and the tank to prevent any backflow of water from the
Downcomer into the tank.
4.6.2.13.The Downcomer mains are usually located within smoke free lobby
or protected areas and that all spaces are to be within 45 metres
coverage from a landing valve.
4.6.2.14.If more than 60 metres, so then need to have more than one riser is
required for each floor.
4.6.2.15.The Riser Pipe size should be 150mm and the material of the Riser
Pipe shall be Galvanised Iron to B.S. 1387 (heavy gauge) or Class C,
tested to 21 Bars (305 Psi)
4.6.2.16.All feeding Pipe-works that runs horizontally need to be sloped to
enable proper draining after used and also an Air Release Valve
should be installed at the top of the riser to relief air trapped in the
system.
4.6.2.17.All Downcomer pipes should be coated with primer and finished with
red gloss paint or otherwise can be colour coded with red bands of
100mm width and the elbows and tees painted red.
4.6.2.18.The riser pipe should be electrically earthed or connected to the
building earth to achieve equipotential.
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.6.2.19.The riser to be hydraulically tested to a pressure of 14 Bars for 2
hours that to be measured at the Breeching inlet and not forget to
check all leakage at the joints and landing valves connections.
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.7. Automatic Sprinkler System –
4.7.1. Design Standard
– BS EN 12845: 2003 – Automatic Sprinkler Systems – Design, Installation
and Maintenance.
– NFPA 13
Both above standards need to be followed unless the specific aspect is not
covered in the selected standard.
4.7.2. Design Method of Automatic Sprinkler System;
4.7.2.1. It should be complied with UBBL 1984, the by Laws 226 and 228
4.7.2.2. An Automatic Sprinkler System is designed for having a response to
detect, control and extinguishes a fire, and warned the occupants of
the occurrence of fire.
4.7.2.3. Basic mechanical installations for the Automatic Sprinkler System
are such as like Fire Pumps, Water Storage Tanks, Control Valve
Sets, Sprinkler Heads, Flow Switches, Pressure Switches, Pipe –
works and valves. This system operates automatically without
human intervention.
4.7.2.4. The Sprinkler Head usually has a liquid filled glass bulb that breaks
due to heat of the fire and releases water that sprays over the fire.
4.7.2.5. There are various types of Sprinkler Systems are as follows;
Wet Pipe installation – ready filled up with water and discharge
once the sprinkler bulb breaks
Dry Pipe installation – always filled up with air under pressure
and air is released once the sprinkler bulb breaks then only the
water fills the pipe and is discharged at the sprinkler head.
Pre–action installation – normally charged with air unde pressure
and a valve is opened to fill the system with water when fire is
detected by smoke or heat detectors and also when the sprinkler
bulb breaks.
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
Deluge Installation – the sprinkler head has no bulb and water is
discharged simultaneously from all heads when fire is detected
and the deluge valve is open
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.8. Occupancy Hazards Groups:
4.8.1. Light Hazards : Non–Industrial occupancies with low quantity and
combustibility contents, e.g. apartments, schools and hospitals.
4.8.2. Ordinary Hazards : Commercial and Industrial occupancies in which By
handling and storing ordinary combustible materials and group under the
followings;
4.8.2.1. OH Group I for offices, restaurants and hotels,
4.8.2.2. OH Group II for laundries, bakeries and tobacco factory,
4.8.2.3. OH Group III for car parks, departmental stores, large retail shops
and cinemas, clothing and paint factories and
4.8.2.4. OH Group IIIS for match factories, film and television studios.
Note:
- for high rise buildings with multiple type of occupancies, the hazard class
recommended is OH Group III
4.8.3. High Hazards : Commercial and Industrial occupancies in which By handling
and storing the abnormal fire loads covering process hazards, high piled
storage hazards, oil and flammable liquid hazards and group under the
followings;
– Process Risk, e.g. clothing, rubber, wood wool and paint factories High
Piled Storage risk could be categorised into four (4) categories;
Category I – Carpets and textile exceeding 4 meters in height,
Category II – furniture factory piled above 3 meters,
Category III – rubber, wax coated paper piled > 2m and
Category IV – for foam, plastics piled > 1.2m.
4.8.4. Sprinkler Pump Requirements;
4.8.4.1. Normal Standard
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
One (1) unit on Duty, One (1) unit on Standby and One (1) of
Jockey Pump to maintain the system pressure.
4.8.4.2. The nominal pressure and flow requirements under all types of
hazards are as the followings;
Light Hazard
15 meters: flow - 0.3 m³/min and at operating pressure of 1.5
bars
30 meters: flow - 0.34 m³/min and at operating pressure of
1.8 bars
45 meters: flow - 0.375 m³/min and at operating pressure of
2.3 bars
Ordinary Hazard Group I
15 meters: flow – 0.9 m³/min and at operating pressure of 1.2
bars
30 meters: flow – 1.15 m³/min and at operating pressure of
1.9 bars
45 meters: flow – 1.36 m³/min and at operating pressure of
2.7 bars
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
Ordinary Hazard Group II
15 meters: flow – 1.75 m³/min and at operating pressure of
1.4 bars
30 meters: flow – 2.05 m³/min and at operating pressure of
2.0 bars
45 meters: flow – 2.35 m³/min and at operating pressure of
2.6 bars
Ordinary Hazard Group III
15 meters: flow – 2.25 m³/min and at operating pressure of
1.4 bars
30 meters: flow – 2.70 m³/min and at operating pressure of
2.0 bars
45 meters: flow – 3.10 m³/min and at operating pressure of
2.5 bars
Ordinary Hazard Group IIIS
15 meters: flow – 2.65 m³/min and at operating pressure of
1.9 bars
30 meters: flow – 3.05 m³/min and at operating pressure of
2.4 bars
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.8.5. Notes for Mech. Engr.’s –
4.8.5.1. for Building exceeds 45m than the multiple stage of sprinkler
installations should be implemented. This would be able to serve the
full height of the building with each stage not exceeding 45 meters.
4.8.5.2. A standby Sprinkler Pump – Set should be supplied with power from
the emergency generator or else need to use a diesel engine driven.
All Diesel Oil Supply could withstand 4 hours – Ordinary Hazards and
6 hours for High Hazard applications.
4.8.5.3. All Electrical Cabling to supply the power to the Sprinkler Pumps
should be a fire rated cable type or MICC. Batteries for the diesel
engine also need to be a maintenance – free type
4.8.5.4. All Sprinkler Pumps that protecting the high rise buildings need to
consider the static pressure between the pump and the lowest
sprinkler head by adding up to the above pump pressure
requirement.
4.8.5.5. All Sprinkler Pumps should be under positive head as far as possible,
protected from fire and flooded areas. Sump Pump could
be considered if this Sprinkler Pump to be located at the Basement
below the the external drainage levels. As usual this Pump Room
that located at the basement need to be naturally / mechanical
ventilated c/w a necessary signage and must also provide a CO2 –
Portable Extinguisher.
4.8.5.6. All Sprinkler Pump Starter Panels and Controls should
be Compartmented for each duty, standby and jockey pumps c/w
indicator lights as shown in the figure 11.2 (as per the attachments
at apprendix – A).
4.8.5.7. As normal practice all Fire Fighting Pump room need to provide with
an insect screen to prevent entry of vermin (e.g. insects, flies,
cockroach and etc.) and the location of Pump Starter Panel should
be placed at the same room as the fire pumps it controls.
4.8.5.8. Usually three pressure switches are provided with the following
Suggested pressure settings:
starting the duty pump – set : 80% of the system pressure
starting the standby pump – set: 60% of the system pressure
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
starting and stopping the jockey pump – set at 90% and 110% of
the system pressure respectively.
4.8.5.9. Electrical interlocks should be provided so that the sprinkler pumps
at each installation would not operate in parallel simultaneously and
a buzzer should be sounded and the isolator should be in the off or
manual position.
4.8.5.10.All Sprinkler Pump – Sets should be able to start automatically and
stop manually.
4.8.5.11.Sprinkler Fire Tanks –
4.8.5.11.1. Light Hazard
15 meters: flow - 9 m³ (1980 Imp. Gallon)
30 meters: flow - 10 m³ (2200 Imp. Gallon)
45 meters: flow - 11 m³ (2420 Imp. Gallon)
4.8.5.11.2. Ordinary Hazard Group I
15 meters: flow - 55 m³ (12,100 Imp. Gallon)
30 meters: flow - 70 m³ (15,400 Imp. Gallon)
45 meters: flow - 80 m³ (17,600 Imp. Gallon)
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html
4.8.5.11.3. Ordinary Hazard Group II
15 meters: flow - 105 m³ (23,100 Imp. Gallon)
30 meters: flow - 125 m³ (27,500 Imp. Gallon)
45 meters: flow - 140 m³ (30,800 Imp. Gallon)
4.8.5.11.4. Ordinary Hazard Group III
15 meters: flow - 135 m³ (29,700 Imp. Gallon)
30 meters: flow - 160 m³ (35,200 Imp. Gallon)
45 meters: flow - 185 m³ (40,700 Imp. Gallon)
4.8.5.11.5. Ordinary Hazard Group IIIS
15 meters: flow - 160 m³ (35,200 Imp. Gallon)
30 meters: flow - 185m³ (40,700 Imp. Gallon)
4.8.5.11.6. High Hazard
Storage Capacity shall be dependent on the design
density of discharge in mm/min
4.8.5.12.It is noted for all Mechanical Engineer’s to read and understand all
other standard & procedures that required from the latest Fire
Protection Services (Second Edition – 2006) at Chapter 11, 12, 13,
14, 15 till Chapter 20.
4.8.5.13.Design reference from last and current projects.
Adopted from http://leonim.blogspot.com/2011/02/basic-design-guideline-for-mechanical.html