9130 BSC Evolution Commissioning

46
Alcatel-Lucent GSM 9130 BSC Evolution Commissioning BSC & TC Document Commissioning Manual Release B10 3BK 17430 3121 RJZZA Ed.07

Transcript of 9130 BSC Evolution Commissioning

Page 1: 9130 BSC Evolution Commissioning

Alcatel-Lucent GSM

9130 BSC Evolution

Commissioning

BSC & TC Document

Commissioning Manual

Release B10

3BK 17430 3121 RJZZA Ed.07

Page 2: 9130 BSC Evolution Commissioning

Status RELEASED

Short title mxbsccom

All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel-Lucent.

BLANK PAGE BREAK

2 / 46 3BK 17430 3121 RJZZA Ed.07

Page 3: 9130 BSC Evolution Commissioning

Contents

Contents

Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

1.1.1 Hardware Description - Rack Configurations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.2 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.1.3 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.1.4 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.1.5 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141.2.2 Site-Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151.4 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

1.4.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161.4.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161.4.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

2 9130 BSC Evolution Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192.1 Before Going on Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202.2 Before You Start (On Arrival at the Site) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

2.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

2.3 Complete BSC Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212.3.1 Install Boards in ATCA Shelf . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212.3.2 Check Boards Position in LIU Shelf . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252.3.3 Check the ATCA-LIU Ethernet Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272.3.4 Check the JSXLIU Shelf Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 292.3.5 Connect PCM Cables to JSXLIU Shelf . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30

2.4 Hardware Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.4.1 Check the Equipment Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.4.2 Check the JAXPC Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.4.3 Check the JAXPC Address for Board Variant Before 3BK 27226 AACA . . . . . . 312.4.4 Check the JAXPC Address from Board Variant 3BK 27226 AACA On . . . . . . . 332.4.5 Check the JBXFAN Switch Position . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34

2.5 Powering Up the BSC Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 352.5.1 Check the Customer Power Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 352.5.2 Check Polarity of DC Cables on BSC Side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 352.5.3 Powering Up the BSC Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 372.5.4 Check Power Line Redundancy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38

2.6 Check BIOS Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 402.7 Software Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.8 Check the Firmware Version . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.9 Commissioning Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41

2.9.1 Option: LMT Installation (O1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.9.2 Connect the LMT to the BSC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 422.9.3 Option: Connect O&M cables from MFS to BSC (O2) . . . . . . . . . . . . . . . . . . . . . . 432.9.4 Perform the Rack Inventory . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44

2.10 Connect the OMC-R . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 442.11 Option: Check the Connection with the CBC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45

2.11.1 Open a Telnet Session . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 452.11.2 Ping the CBC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46

2.12 End of Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46

3BK 17430 3121 RJZZA Ed.07 3 / 46

Page 4: 9130 BSC Evolution Commissioning

Contents

4 / 46 3BK 17430 3121 RJZZA Ed.07

Page 5: 9130 BSC Evolution Commissioning

Preface

Preface

Purpose This document describes the configuration and verification procedures to becarried out when commissioning the 9130 BSC Evolution in release B10.

In this document JBXTP stands for all TPGSM functional variants JBXTP andJBXTP3. Procedures specific to any variant should be mentioned explicitly.

What’s New In Edition 07Description improvement in Check Power Redundancy for ATCA Shelves(Section 2.5.4.1).

In Edition 06Description improvement in the following sections:

Hardware Description - Rack Configurations (Section 1.1.1)

Site-Specific Information (Section 1.2.2)

Check the JAXPC Address (Section 2.4.2)

Check the JBXFAN Switch Position (Section 2.4.5)

Check BIOS Settings (Section 2.6)

Connect the OMC-R (Section 2.10).

Section Check the Extraction Handles was removed.

In Edition 05Description improvement in:

Site-Specific Information (Section 1.2.2)

Install Boards in ATCA Shelf (Section 2.3.1).

In Edition 04Update with the new equipment naming.

In Edition 03Update of system title.

3BK 17430 3121 RJZZA Ed.07 5 / 46

Page 6: 9130 BSC Evolution Commissioning

Preface

In Edition 02Section Check the Extraction Handles was added.

In Edition 01First release of the document.

Audience This document is addressing to the following:

Site administrators

Supervisors

Project managers

Field service technicians

Occasional users

Assumed Knowledge The personnel involved must be familiar with:

Commissioning tools

Personal Computers using the Windows 2000/XP environment

Digital’s UNIX operating system environment.

6 / 46 3BK 17430 3121 RJZZA Ed.07

Page 7: 9130 BSC Evolution Commissioning

1 Overview

1 Overview

This Overview gives information needed by project managers and foremen, forpresentation to the customer and for site planning.

3BK 17430 3121 RJZZA Ed.07 7 / 46

Page 8: 9130 BSC Evolution Commissioning

1 Overview

1.1 Presentation

1.1.1 Hardware Description - Rack Configurations

The following figure shows the rack layout for an 9130 BSC Evolution in 1000TRX configuration.

123456789012345678912345678901234567891234567890123456789

−48 / 60 VDC

4A

−48 / 60 VDC

4A

XPEM XLIU XMUXXLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEMXMUX

LIUShelf 1

Free Space(ATCA Shelf 4)

ATCAShelf 3

JSXPDU

JBX

SS

W

JBX

SS

W

JBX

OM

CP

JBX

OM

CP

JBX

CC

P

JBX

CC

P

JBX

TP

JBX

TP

JBX

CC

P

JBX

CC

P

Free space(LIU Shelf 2)

Air inlet

Not

Use

d

Not

Use

d

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

JBX

CC

P

JBX

CC

P

Figure 1: Example of 9130 BSC Evolution Rack Layout - Front View

8 / 46 3BK 17430 3121 RJZZA Ed.07

Page 9: 9130 BSC Evolution Commissioning

1 Overview

The following figure shows the rack layout for an 9130 BSC Evolution 1000TRX configuration /9130 MFS Evolution 9 JBXGPU configuration in case ofrack shared configuration.

1234567890123456789123456789012345678912345678901234567891234567890123456789

CLOSED / OPEN

H/S OOS

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

−48 / 60 VDC

4A

−48 / 60 VDC

4A

XPEM XLIU XMUXXLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEMXMUX

LIUShelf 1

ATCAShelf 3

ATCAShelf 4

JSXPDU

JBX

SS

W

JBX

SS

W

JBX

OM

CP

JBX

OM

CP

JBX

GP

U

LIUShelf 2

Air inlet

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

JBX

GP

U

JBX

GP

U

JBX

GP

U

JBX

GP

U

JBX

GP

U

JBX

GP

U

JBX

GP

U

JBX

GP

U

JBX

GP

U

−48 / 60 VDC

4A

−48 / 60 VDC

4A

XPEM XLIU XMUXXLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEMXMUX

1234567890123456789123456789012345678912345678901234567891234567890123456789

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

Air inlet

JBX

TP

JBX

TP

JBX

CC

P

JBX

SS

W

JBX

SS

W

JBX

OM

CP

JBX

OM

CP

JBX

CC

P

JBX

CC

P

JBX

CC

P

Not

Use

d

Not

Use

d

JBX

CC

P

JBX

CC

P

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

Figure 2: Example of 9130 BSC Evolution Rack Layout - Front View

3BK 17430 3121 RJZZA Ed.07 9 / 46

Page 10: 9130 BSC Evolution Commissioning

1 Overview

The following figure shows the rack layout in case of rack shared by two 9130BSC Evolution 1000 TRX configuration.

−48 / 60 VDC

4A

−48 / 60 VDC

4A

XPEM XLIU XMUXXLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEMXMUX

LIUShelf 1

ATCAShelf 3

ATCAShelf 4

JSXPDU

LIUShelf 2

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

−48 / 60 VDC

4A

−48 / 60 VDC

4A

XPEM XLIU XMUXXLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEMXMUX

1234567890123456789123456789012345678912345678901234567891234567890123456789

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

Air inlet

JBX

TP

JBX

TP

JBX

CC

P

JBX

SS

W

JBX

SS

W

JBX

OM

CP

JBX

OM

CP

JBX

CC

P

JBX

CC

P

JBX

CC

P

Not

Use

d

Not

Use

d

JBX

CC

P

JBX

CC

P

1234567890123456789123456789012345678912345678901234567891234567890123456789

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

Air inlet

JBX

TP

JBX

TP

JBX

CC

P

JBX

SS

W

JBX

SS

W

JBX

OM

CP

JBX

OM

CP

JBX

CC

P

JBX

CC

P

JBX

CC

P

Not

Use

d

Not

Use

d

JBX

CC

P

JBX

CC

P

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

Figure 3: Example of Two 9130 BSC Evolution Rack Layout - Front View

10 / 46 3BK 17430 3121 RJZZA Ed.07

Page 11: 9130 BSC Evolution Commissioning

1 Overview

The following figure shows the back rack layout for an 9130 BSC Evolutionin any configuration.

JAX

SS

W

JAX

SS

W

−(P

OW

ER

)

+(R

ET

UR

N)

−(P

OW

ER

)

+(R

ET

UR

N)

OOS

OK

ACT

H/S

OOS

OK

ACT

H/S

1234567890123456789123456789012345678912345678901234567891234567890123456789

Air outlet

GND

JBXPS JAX

SM

M

JAX

PC

JAX

PC

JBXPS JAX

SM

M

JAXPC JAXPC

JAX

SS

W

JAX

SS

W

−(P

OW

ER

)

+(R

ET

UR

N)

−(P

OW

ER

)

+(R

ET

UR

N)

−(P

OW

ER

)

+(R

ET

UR

N)

−(P

OW

ER

)

+(R

ET

UR

N)

OOS

OK

ACT

H/S

OOS

OK

ACT

H/S

1234567890123456789123456789012345678912345678901234567891234567890123456789

Air outlet

GND

JBXPS JAX

SM

M

JAX

PC

JAX

PC

JBXPS JBXPS JBXPS JAX

SM

M

Open

Closed

OOS

OK

Ha

nd

le

H/S

Alarm/Reset

Telc

o A

larm

s &

Rela

ys

JAXPC

Open

Closed

OOS

OK

Ha

nd

le

H/S

Alarm/Reset

Telc

o A

larm

s &

Rela

ys

JAXPC

For shelf variant before 3BK 27291 ABxx From shelf variant 3BK 27291 ABxx on

Figure 4: Example of 9130 BSC Evolution Rack Layout - Rear View

3BK 17430 3121 RJZZA Ed.07 11 / 46

Page 12: 9130 BSC Evolution Commissioning

1 Overview

1.1.2 Cases

None.

1.1.3 Options

The following options apply:

O1: Install LMT

O2: Connect O&M cables from MFS to BSC, in rack shared configuration

1.1.4 Restrictions

None.

12 / 46 3BK 17430 3121 RJZZA Ed.07

Page 13: 9130 BSC Evolution Commissioning

1 Overview

1.1.5 Grouped Task Sequence

The following figure shows the task sequence for the 9130 BSC Evolutioncommissioning.

Before going site

Before you start

Boards installation

Hardware check

Set LIU shelf address

Power up rack

Check firmware version

Commisioning test

Connect the OMC−R

Check connection to CBC

End commissioning

3BK 17430 3121 RJZZA Ed.07 13 / 46

Page 14: 9130 BSC Evolution Commissioning

1 Overview

1.2 Preparation

1.2.1 Prerequisites

The following prerequisites apply:

The site must conform to the "Safety rules" (see B10 BSS MethodsHandbook).

The site must conform to SPP- 59, Specification for Site Preparation

9130-BSC

The OMC-R must be operational and ready for connection to the BSC.

The router must be configured and ready for connection (if applicable).

1.2.2 Site-Specific Information

Network information:

BSC Id and name

External Host name, external IP address and netmask for each OMCP

station

OMCP1 is ’START_OAM_IP_ADDRESS’

OMCP2 is ’START_OAM_IP_ADDRESS’ + 1

IP address of the alias host name for active station ("station_BSC")The IP address of 9130 BSC Evolution is ’START_OAM_IP_ADDRESS’ + 2

IP address for the default gateway for external network used for connectionBSC - OMC

If necessary, IP address for the external router for subnet B and subnet C

IP address for the CBC

User name and password for external router between BSC and CBC

Ports in external router where to connect the Ethernet cables

Routing configuration between OMC-R and BSC

Local network sockets position to plug in the OMCP Servers network

cables (if applicable)

Position of cables connection on the CISCO router to plug in the OMCPServers network cables (if applicable).

BSC configuration:

Number of CCP boards

JBXTP board variant

LIU shelf configuration.

14 / 46 3BK 17430 3121 RJZZA Ed.07

Page 15: 9130 BSC Evolution Commissioning

1 Overview

1.3 SchedulingThe following table gives the duration for each task.

Task Duration (min)

Preliminary checks

Preparation before leaving for the site 15

Before starting (on arrival at the site) 10

Boards installation 20

Hardware check 10

Set LIU shelf address 5

Powering up the BSC rack

Check the power panel 5

Check the polarity on the BSC side 10

Powering up the BSC rack 5

Check power line redundancy 10

Check firmware version 30

Commissioning tests

Option: LMT installation 20

Connecting LMT to the BSC 2

Software installation 65

Perform rack inventory 15

Connecting the OMC-R 10

Option: Check the connection with the CBC 5

End of commissioning 10

Total 4h10

Table 1: Scheduling

3BK 17430 3121 RJZZA Ed.07 15 / 46

Page 16: 9130 BSC Evolution Commissioning

1 Overview

1.4 Resources

1.4.1 Tools

1.4.1.1 Hardware ToolsThe following table is used to check, at base, the availability of the necessarytools.

See Tools Catalogue for Field Activity for checking the content.

Kit name Reference Calibration

Basic kit OUT 001 NO

Test cables and plugs (BSC) OUT 013 NO

Utility PC (IMT) DES 002 NO

Digital multimeter DES 001 NO

1.4.1.2 Software ToolsThe following table is used to check, at base, the availability and the versionof the necessary software.

Refer to the corresponding document for checking the SW version.

Name Version checking

Windows 2000/XP -

Netscape Communicator 4.78 -

1.4.1.3 FormsNone.

1.4.2 Supplies

None.

16 / 46 3BK 17430 3121 RJZZA Ed.07

Page 17: 9130 BSC Evolution Commissioning

1 Overview

1.4.3 Applicable Documents

The following list is used to check, at base, the availability of the necessarydocuments.

Catalogue of Technical and Logistic Information (ITL), 3DF 00462 0004AAAGA

Catalogue of Instruction Operation (IO), 3DF 00300 0004 UAZZA

BSS Methods Handbook, 3BK 21268 AAAA PCZZA

CI 08 - Site Equipment Inventory, 3BK 17257 0001 RJZZA

Tools Catalogue for Field Activity, 3BK 20458 0001 RJZZA

SPP-59, Specification for Site Preparation 9130 MFS Evolution/BSC

Evolution, 8BL 00704 0076 DRZZA

BSS site premises inspections, post handover, 8BL 00704 0016 DRBRA

Site Premises Inspection Form (CEL), 8BL 00704 0015 DRBRA

9130 BSC Evolution Software Installation, 3BK 17430 3126 RJZZA

9130 BSC Evolution Firmware Upgrade, 3BK 17422 3106 RJZZA.

3BK 17430 3121 RJZZA Ed.07 17 / 46

Page 18: 9130 BSC Evolution Commissioning

1 Overview

18 / 46 3BK 17430 3121 RJZZA Ed.07

Page 19: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

This section describes the tasks to be performed during 9130 BSC Evolutioncommissioning.

3BK 17430 3121 RJZZA Ed.07 19 / 46

Page 20: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.1 Before Going on SiteBefore going on site you must check the following:

All Prerequisites (Section 1.2.1) are fulfilled

The customer has been informed of the

Date and time

Site name and address

Purpose of the operation.

Personnel are available and ready for operation (refer to Scheduling(Section 1.3)

Site-Specific Information (Section 1.2.2) is available

Tools (Section 1.4.1) are available and ready for operation

Software Tools (Section 1.4.1.2) are available and ready for operation

Applicable Documents (Section 1.4.3) are available.

2.2 Before You Start (On Arrival at the Site)

2.2.1 Checks

Before you start, perform the following operations:

Check that all Prerequisites (Section 1.2.1) are fulfilled

Check applicable notifications and operating instructions (refer to the

Applicable Notifications List and Applicable Operation Instructions List)

Check the availability of all necessary tools and supplies.

Refer to BSS site premises inspections, post handover and complete the

Site Premises Inspection Form (CEL).

Check that the safety precautions have been taken in accordance with the

safety instructions described in the B10 BSS Methods Handbook.

Check which Cases (Section 1.1.2) or Options (Section 1.1.3) apply

Complete the header field of the CCL. The CCL is completed as eachinstruction is carried out.

2.2.2 Required Knowledge

You must be familiar with the following:

The safety rules and precautions given in the B10 BSS Methods Handbook.

How to document faults and anomalies as described in the B10 BSS

Methods Handbook.

20 / 46 3BK 17430 3121 RJZZA Ed.07

Page 21: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.3 Complete BSC Configuration

2.3.1 Install Boards in ATCA Shelf

To install the boards:

1. Check the configuration requested by the customer. Refer to Site-SpecificInformation (Section 1.2.2) for details.

Note: For JBXCCP boards shelf filling is done from center to shelf sides.

When inserting the JBXTP boards make sure that both boards are of the sametype and corresponding to the request.

The following table gives the JBXCCP and JBXTP boards allocationin ATCA shelf.

Physical slotsBoards Configuration(No. of TRX)

1 2 3 4 5 6 7 8 9 10 11 12 13 14

200 - - - - x - - - - x - - - -

400 - - - - x - - - - x x - - -

600 - - - x x - - - - x x - - -

800 - - - x x - - - - x x x - -

JBXCCP

1000 - - x x x - - - - x x x - -

JBXTP All x x - - - - - - - - - - - -

Table 2: JBXCCP and JBXTP Position in ATCA Shelf

3BK 17430 3121 RJZZA Ed.07 21 / 46

Page 22: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

The ATCA configuration is described in the following figure:

1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123456789012

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

CLOSED / OPEN H/S OOS

JBX

SS

W

JBX

SS

W

JBX

OM

CP

JBX

OM

CP

JBX

CC

P

JBX

CC

P

JBX

TP

JBX

TP

JBX

CC

P

JBX

CC

P

CLOSED / OPEN H/S OOS

Air inlet

Physicalslot

1 2 3 4 5 6 7 8 9 10 11 1312 14

Not

Use

d

Not

Use

d

JBX

CC

P

JBX

CC

P

Figure 5: ATCA Shelf Boards

2. Put on an ESD wrist strap and connect it to the shelf by attaching the frontor rear ESD jack.

3. Ensure that the lower and upper handles are in the outward position.

4. Insert the board into the shelf by placing the top and bottom edges of theboard in the card guides of the shelf.

Ensure that the guiding module of shelf and board are aligned properly.Press the lower and upper parts of the handle together.

Figure 6: Insert the Board

22 / 46 3BK 17430 3121 RJZZA Ed.07

Page 23: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

5. Slide the board into the shelf until you feel resistance.

6. Simultaneously move the top and bottom handles to the inward position tolock the board to the shelf.

Figure 7: Board in ATCA Shelf, Secured with Handles to the Inward Position

3BK 17430 3121 RJZZA Ed.07 23 / 46

Page 24: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

7. Install one by one all the boards for the requested configuration. Duringboards insertion:

Holes on back side of the board must be in line with guiding pins on

the back plane

Figure 8: Holes in Line with Guiding Pins

EMI stripes must not be damaged when inserting the boards

Figure 9: EMI Stripes

8. Tighten the front plate screws to secure the board to the shelf.

9. Insert a filler (JBXFILL) in each unused slot.

10. Tighten the front plate screws to secure the filler to the shelf.

24 / 46 3BK 17430 3121 RJZZA Ed.07

Page 25: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.3.2 Check Boards Position in LIU Shelf

Check the configuration requested by the customer. Refer to Site-SpecificInformation (Section 1.2.2) for details.

In case of 200 and 400 TRX configurations check that there are boards onslots 19 and 20 (for slot numbering, see Figure 2), otherwise you must replacethe JBXDUM fillers from slots 19 and 20 with the JBXLIU boards from slots 8and 9, using the procedure below.

The following table shows the boards correspondence in case of replacingJBXLIU with JBXDUM:

JBXLIU JBXDUM

8 19Slot No. in LIUShelf

9 20

Table 3: Boards Correspondence

To move the boards from slots 8 and 9 to slots 19 and 20, in LIU shelf:

1. Put on an ESD wrist strap and connect it to the shelf by attaching thefront or rear ESD jack

2. Unfasten the top and the bottom screws of the JBXDUM fillers.

3. Remove the JBXDUM fillers.

4. Unfasten the top and the bottom screws of the JBXLIU boards.

The bottom screw is located under the handle.

5. Using the board handle, remove the JBXLIU boards.

6. Using the board handle, insert the JBXLIU boards to the correspondingslots, until you feel resistance (for boards correspondence see Table 3).

7. Fasten the top and the bottom screws of the JBXLIU boards.

8. Insert the JBXDUM fillers in the empty slots.

9. Fasten the top and the bottom screws of the JBXDUM fillers.

The following figures show the LIU shelf for different 9130 BSC Evolution200 and 400 TRX configurations.

−48 / 60 VDC

4A

−48 / 60 VDC

4A

JBXPEM JBXLIU JBXMUXJBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXPEMJBXMUXJBXDUM JBXDUM JBXDUM JBXDUM JBXDUM JBXDUM JBXDUMJBXDUM

Figure 10: LIU Shelf for BSC with 200 and 400 TRX Configuration

3BK 17430 3121 RJZZA Ed.07 25 / 46

Page 26: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

The following figures show the LIU shelf for different 9130 BSC Evolution600/800/1000 TRX configuration.

−48 / 60 VDC

4A

−48 / 60 VDC

4A

JBXPEM JBXLIU JBXMUXJBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXPEMJBXMUX

Figure 11: LIU Shelf for BSC with 600 TRX Configuration

26 / 46 3BK 17430 3121 RJZZA Ed.07

Page 27: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.3.3 Check the ATCA-LIU Ethernet Cables

Shelves used for 9130 BSC Evolution configurations are:

ATCA shelf 3 with LIU shelf 1

ATCA shelf 4 and LIU shelf 2.

Therefore the inter-shelves Ethernet cables are always connected between:

ATCA shelf 3 and LIU shelf 1

ATCA shelf 4 and LIU shelf 2.

To connect ATCA-LIU Ethernet cables:

1. Connect the first JLCAT6 Ethernet cable (1AB 22983 0005) on ATCA shelf3/4, JAXSSW1, Ethernet port 2. See Figure 12.

ETH8

OOS

OK

ACT

HS

ETH1

ETH2

ETH3

ETH4

ETH5

ETH6

ETH7

ETH8

OOS

OK

ACT

HS

ETH1

ETH3

ETH4

ETH5

ETH6

ETH7

ATCA Shelf 3Rear side

JAXSSW2 JAXSSW1

JBXMUXJBXLIU JBXMUXJBXLIU JBXLIU JBXLIUJBXDUM

TestTest

GbEGbE

JLCAT6 Ethernet cables1AB 22983 0005

LIU Shelf 1Front side

ETH2

Figure 12: JLCAT6 Cable Connection

3BK 17430 3121 RJZZA Ed.07 27 / 46

Page 28: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2. Run the cable under the JSXLIU shelf 1

ATCA Shelf 4

LIU Shelf 1

ATCA Shelf 3

Free Space(LIU Shelf 2)

FRONT REAR

123456789012345678123456789012345678

Figure 13: JLCAT6 Cable Routing

3. Connect the first JLCAT6 Ethernet cable (1AB 22983 0005) to the GbE porton JBXMUX1 (slot 10) in JSXLIU shelf 1/2. See Figure 12.

4. Connect the second JLCAT6 Ethernet cable (1AB 22983 0005) on ATCAshelf 3/4, JAXSSW2, Ethernet port 2. See Figure 12.

5. Run the cable under the JSXLIU shelf 1. See Figure 13.

6. Connect the second JLCAT6 Ethernet cable (1AB 22983 0005) to the GbEport on JBXMUX2 (slot 12) in JSXLIU shelf 1/2. See Figure 12.

To connect the OMC-R Ethernet cables:

1. Identify the OMC-R Ethernet cables

2. Connect the first OMC-R Ethernet cable to the ATCA shelf 3/4 JAXSSW1,Ethernet port 3

3. Label the cables near the connectors.

28 / 46 3BK 17430 3121 RJZZA Ed.07

Page 29: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.3.4 Check the JSXLIU Shelf Address

To check the JSXLIU shelf address:

1. Remove the dummy panel from the slot 11 in JSXLIU shelf

2. On the slot 11 check that the shelf address is set as follows:

”1”, jumper from position 1 is removed (see Figure 14 a), if theconcerning BSC is installed in the lower ATCA Shelf

”2”, jumper from position 2 is removed (see Figure 14 b), if the

concerning BSC is installed in the upper ATCA Shelf

PE

M A

LIU

1

MU

X A

LIU

2

LIU

3

LIU

4

LIU

5

LIU

6

LIU

7

LIU

8

MU

X B

LIU

9

PE

M B

LIU

10

LIU

11

LIU

12

LIU

13

LIU

14

LIU

15

LIU

16

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

12345678

12345678

a) b)

Figure 14: Slot 11 Back Panel Jumper Numbering

3. If the positions of the jumpers are not as described, it must be corrected.

4. Fix the dummy panel on slot 11 and fix it with the screws.

3BK 17430 3121 RJZZA Ed.07 29 / 46

Page 30: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.3.5 Connect PCM Cables to JSXLIU Shelf

To connect the PCM cables to the JSXLIU shelf:

1. Connect the cables to the JBXLIU boards

2. Check that there is a good connection of the cables

3. Close the front door to check if the cables are not stressed by it

4. Open the front door and arrange the cables if necessary

5. Attach the cables to the rack

6. Label the cables near the connectors.

30 / 46 3BK 17430 3121 RJZZA Ed.07

Page 31: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.4 Hardware Checks

2.4.1 Check the Equipment Configuration

The hardware check is done to see if the equipment configuration correspondsto the customer’s order.

Check the presence and position of the boards according to the requestedconfiguration.

Refer to the Site-Specific Information and Hardware Description - RackConfigurations sections.

2.4.2 Check the JAXPC Address

Depending on the board variant apply the appropriate case:

Check the JAXPC Address for Board Variant Before 3BK 27226 AACA

(Section 2.4.3)

Check the JAXPC Address from Board Variant 3BK 27226 AACA On

(Section 2.4.4).

2.4.3 Check the JAXPC Address for Board Variant Before 3BK 27226AACA

To check the JAXPC address:

1. Put on an ESD wrist strap and connect it to the shelf by attaching the frontor rear ESD jack.

2. Unfasten the screws fixing the JAXPC card to the ATCA shelf.

3. Carefully remove the JAXPC card from the slot.

4. Check if S2 switch is set to “0” and S1 switch is set to “3” for shelf 3 and to”4” for shelf 4 . If different setting is present correct it as follows.

3BK 17430 3121 RJZZA Ed.07 31 / 46

Page 32: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

S2

S1

Figure 15: Rotary Switches on JAXPC Card Before Variant 3BK 27226 AACA

5. On the JAXPC board set the S2 switch to ”0”.

6. On the JAXPC board set the S1 switch to ”3” for shelf 3 and to ”4” for shelf 4.See Figure 2 for shelf numbering.

7. Carefully insert the JAXPC card in the slot.

8. Tighten the screws fixing the JAXPC card to the ATCA shelf.

9. Place the JAXPC board handle switch to Closed position.

32 / 46 3BK 17430 3121 RJZZA Ed.07

Page 33: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.4.4 Check the JAXPC Address from Board Variant 3BK 27226 AACA On

To check the JAXPC address:

1. Check if SGA MS switch is set to “0” and SGA LS switch is set to “3” for shelf3 and to ”4” for shelf 4 . If different setting is present correct it as follows.

LS

MS

Figure 16: Rotary Switches on JAXPC Card from Variant 3BK 27226 AACA On

2. On the JAXPC board set the SGA MS switch to ”0”.

3. On the JAXPC board set the SGA LS switch to ”3” for shelf 3 and to ”4”for shelf 4. See Figure 2 for shelf numbering.

4. Perform the same operation for both JAXPC cards in a shelf and for bothshelves if equipped.

3BK 17430 3121 RJZZA Ed.07 33 / 46

Page 34: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.4.5 Check the JBXFAN Switch Position

This check must be done only in case of JBXFAN variants before 3BK 27352AACA.

To check the JBXFAN switch position:

1. Unfasten the screws fixing the JBXFAN cover plate.

Figure 17: JBXFAN Cover Fixing Screws

2. Remove the JBXFAN cover plate.

Figure 18: Remove JBXFAN Cover

3. Check if JBXFAN switch is set to Closed position otherwise set it to Closeposition.

4. Perform the check for all four JBXFAN units and for all equipped ATCAshelves.

5. Fit back the JBXFAN cover and fasten the fixing screws.

34 / 46 3BK 17430 3121 RJZZA Ed.07

Page 35: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.5 Powering Up the BSC Rack

Two people are needed for performing this task.

2.5.1 Check the Customer Power Panel

To check the rating of the fuses:

1. On the customer power panel, check for the existence of two DC powersupply distribution circuits. Each distribution circuit is provided with aDC circuit breaker (fuse holder).

(See Site-Specific Information (Section 1.2.2) )

2. On the power panel, disconnect the two -48V power supply lines by usingthe fuse holders for the rack.

3. Check that the fuse ratings are in accordance with the SPP document(See SPP-59).

2.5.2 Check Polarity of DC Cables on BSC Side

To check the connection of the power cables between the site power panel andthe power interface on the BSC side:

1. At the customer power panel, make sure the two power lines for the BSCare disconnected (breakers OFF) (See Site-Specific Information (Section1.2.2) ).

2. At the 9130 BSC Evolution, check that the A1 to A5 and B1 to B5 switches,located at the front of the PDU, are OFF. If not, switch them OFF.

I

O

I

O

I

O

I

O

I

O

I

O

I

O

I

O

I

O

I

O

B1 B2 B3 B4 B5A2 A3 A4 A5A1

Shelf 4 Shelf 2 Shelf 3 Shelf 1 Shelf 4 Shelf 2 Shelf 3 Shelf 1

Figure 19: PDU on top of 9130 BSC Evolution (JSXPDU)

3BK 17430 3121 RJZZA Ed.07 35 / 46

Page 36: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

3. At the top of the BSC rack, remove the PDU cover.

35 mm 2 from power station

16 mm 2 to ATCA shelf

Cover (made of two independent parts for branch A and B)

VBAT

BATR

GND

Cables must be fixed on this plane

VBAT

Breaker

VBAT

Figure 20: Connections for One Single Breaker

4. Check the power line connections for both lines A and B:

Blue cables in the BATA and BATB position

Black cables in the BATR position

Yellow-green cable in GND position

5. Check that nothing can cause a short circuit between the BATA, BATB andBATR connectors.

Line cable from power station (branch A)35 mm2 diameter 14 mm

Racking braket Battery return connection plate (BATR)

Earthing(GND)

75A 75A 75A10A 10A

Line cable from power station (Branch B) 35 mm2 diameter 14 mm

BATB

BATR

75A 75A 75A10A 10A

BATR

BATA

Figure 21: Connections from Power Station to PDU

6. On the site power panel, connect the power supply line, using fuse holder Afirst.

Circuit A is connected.

36 / 46 3BK 17430 3121 RJZZA Ed.07

Page 37: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

7. Test the A circuit.

Check with the multimeter the presence of -48V and the polarity betweenBATA and BATR.

8. On the site power panel, disconnect the power supply line, using fuseholder A.

9. Repeat the previous operations for circuit B. Check the presence of -48Vand the polarity between BATA/B and BATR on each circuit, then leavethe circuits disconnected.

10. Replace the PDU cover plate.

2.5.3 Powering Up the BSC Rack

In the following steps power up only the shelves used by the installedconfiguration.

To power up the BSC rack:

1. On the JSXPDU, check that the corresponding switches, Ax and Bx are inthe OFF position (see Figure 19) where:

x is 1 for ATCA Shelf 4

x is 2 for JSXLIU Shelf 2

x is 3 for ATCA Shelf 3

x is 4 for JSXLIU Shelf 1.

2. Check that switches on JBXPS modules are switched OFF, otherwiseset them OFF.

3. On the site power panel, connect the DC power supply lines (circuitsA and B).

DC Lines A and B are connected.

Power Up JSXLIU1 Shelf 4. Switch ON (engage) the switches A4 and B4. Power LED on JBXPEMs inJSXLIU shelf switches ON.

Power Up ATCA3 Shelf 5. Switch ON (engage) the breakers A3 and B3.

6. Check on each JBXPS front panel that Rev. Power LED is OFF. If Rev.Power LED is ON switch OFF the breakers A3 and B3 and check powerpolarity on JBXPS terminals.

7. Switch ON the breaker on all JBXPS modules. The OK green LED oneach JBXPS switches ON.

Power Up JSXLIU2 Shelf 8. If JSXLIU2 shelf is used, switch ON (engage) the switches A2 and B2.Power LED on JBXPEMs in JSXLIU shelf switches ON.

Power Up ATCA4 Shelf 9. If ATCA4 shelf is used, switch ON (engage) the switches A1 and B1.

10. Check on each JBXPS front panel that Rev. Power LED is OFF. If Rev.Power LED is ON switch OFF the breakers A1 and B1 and check powerpolarity on JBXPS terminals.

11. Switch ON the breaker on all JBXPS modules. The OK green LED oneach JBXPS switches ON.

3BK 17430 3121 RJZZA Ed.07 37 / 46

Page 38: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.5.4 Check Power Line Redundancy

2.5.4.1 Check Power Redundancy for ATCA ShelvesTo check the power lines redundancy for ATCA shelves:

1. Connect an Ethernet cable between the PC and the ETH port of the activeshelf manager.

The active shelf manager is the one with the ACT LED switched ON.

2. Open a telnet session on the active shelf manager:telnet 172.168.y.x

where:

x is 8 if the active JAXSMM is JAXSMM1

x is 9 if the active JAXSMM is JAXSMM2

y is 3 for ATCA shelf 3

y is 4 fot ATCA shelf 4.

3. Enter the user name and password:

Username:root

Password:root

4. Check that the four fan trays are correctly detected. Enter the followingcommand:

hpifan

An example of the output of the command is given below.resource:{RACK,0}{ADVANCEDTCA_CHASSIS,3}{COOLING_UNIT,0}{COOLING_UNIT,0}fan: num 1, id Fanmin 0max 100default 35current 35resource:{RACK,0}{ADVANCEDTCA_CHASSIS,3}{FAN_TRAY_SLOT,4}{COOLING_UNIT,7}fan: num 1, id Fanmin 15max 100default 100state ignoredresource:{RACK,0}{ADVANCEDTCA_CHASSIS,3}{FAN_TRAY_SLOT,3}{COOLING_UNIT,6}fan: num 1, id Fanmin 15max 100default 100state ignored

38 / 46 3BK 17430 3121 RJZZA Ed.07

Page 39: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

resource:{RACK,0}{ADVANCEDTCA_CHASSIS,3}{FAN_TRAY_SLOT,1}{COOLING_UNIT,4}fan: num 1, id Fanmin 15max 100default 100state ignoredresource:{RACK,0}{ADVANCEDTCA_CHASSIS,3}{FAN_TRAY_SLOT,2}{COOLING_UNIT,5}fan: num 1, id Fanmin 15max 100default 100state ignored

5. Check that the four fan trays are running (RPM not equal to zero). Enterthe command:

hpisensor | grep "RPM"

An example of the output of the command is given below.RDR[131073]: Sensor Fan RPM = 1840.00 rpmRDR[131073]: Sensor Fan RPM = 1800.00 rpmRDR[131073]: Sensor Fan RPM = 1840.00 rpmRDR[131073]: Sensor Fan RPM = 1800.00 rpm

6. On the power distribution unit (JSXPDU), switch OFF the -48 V DC powersupply lines A3 (if ATCA shelf 3 is used) or A1 (if ATCA shelf 4 is used)using the corresponding fuse holders.

7. Check that the ATCA shelves remain powered up and the boards are notaffected.

For all boards check the LEDs status.

8. For the fan trays repeat steps 4 and 5, then check that:

The four fan trays are still detected

RPM must be different from zero.

9. Switch ON the -48 V DC power supply lines A3 (if ATCA shelf 3 is used) orA1 (if ATCA shelf 4 is used).

No boards are affected and lines A3 and A1 are connected.

10. On the power distribution unit (JSXPDU), switch OFF the -48 V DC powersupply lines B3 (if ATCA shelf 3 is used) or B1 (if ATCA shelf 4 is used)using the corresponding fuse holders.

11. Check that the ATCA shelves remain powered up and the boards are notaffected.

For all boards check the LEDs status.

12. For the fan trays repeat steps 4 and 5, then check that:

The four fan trays are still detected

RPM must be different from zero.

3BK 17430 3121 RJZZA Ed.07 39 / 46

Page 40: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

13. Switch ON the -48 V DC power supply lines B3 (if ATCA shelf 3 is used) andB1 (if ATCA shelf 4 is equipped)

No boards are affected and lines B3 and B1 are connected.

14. Close the connection on the shelf manager and remove the cable.

2.5.4.2 Check Power Redundancy for LIU ShelfTo check the power line redundancy for JSXLIU shelf:

1. On the power distribution unit (JSXPDU), disconnect the -48 V DC powersupply line A4 (if JSXLIU shelf 1 is used) or A2 (if JSXLIU 2 is used).

2. Check that the boards in JSXLIU shelf remain powered up and are notaffected (The LED on both JBXPEM front plate boards is orange).

3. Reconnect the -48 V DC power line A4 (if JSXLIU shelf 1 is used) or A2 (ifJSXLIU 2 is used).

No boards are affected and line A4 or A2 are connected.

4. On the power distribution unit (JSXPDU), disconnect the -48 V DC powersupply line B4 (if JSXLIU shelf 1 is used) or B2 (if JSXLIU 2 is used).

5. Check that the boards in JSXLIU shelf remain powered up and are notaffected (The LED on both JBXPEM front plate boards is orange).

6. Reconnect the -48 V DC power line B4 (if JSXLIU shelf 1 is used) or B2 (ifJSXLIU 2 is used).

No boards are affected and line B4 or B2 are connected.

2.6 Check BIOS Settings

Perform the following steps for both OMCP1 and OMCP2 boards.

To check System Date & Time and Boot Sequence on the OMCPs:

1. Connect the Ethernet cable from the Local PC to the JAXSSW1 port ETH 8 incorresponding ATCA shelf see Connect the LMT to the BSC (Section 2.9.2).

2. Using Internet Protocol (TCP/IP) Properties window, set the Local PC IPaddress.

The IP address for Local PC is 172.17.0.251

The subnetmask is 255.255.0.0

3. Open a DOS console window. Connect to the OMCP board throughSHMC as follows:

For Windows XP:telnet 172.17.y.8 <port number>

Port number is 4503 for OMCP1Port number is 4504 for OMCP2y is 3 for the lower ATCA Shelfy is 4 for the upper ATCA Shelf

40 / 46 3BK 17430 3121 RJZZA Ed.07

Page 41: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

For Windows 2000:telnetset term vt100open 172.17.y.8 <port number>

Port number is 4503 for OMCP1Port number is 4504 for OMCP2y is 3 for the lower ATCA Shelfy is 4 for the upper ATCA Shelf

4. Type the username:root

and the password:alcatel

5. Reboot the OMCP board:reboot

Note: For hardware reset of board variants before 3BK 27236 AACA use the resetbutton from JBXOMCP board.

For board variants from 3BK 27236 AACA on, the reset button is no moreavailable.

6. With the OMCP terminal window connection through SHMC selected, press[ ESC ] + [ 2 ] or press [ F2 ] several times from the installation PC keyboardduring the OMCP booting sequence.

7. Check ’System Time’ and ’System Date’ from Main menu are the currentones, otherwise you must correct it.

8. Check boot sequence from Boot menu are the correct ones, otherwiseyou must modify it.

The correct order must be Hard Drive -> ETH1 -> ETH2 -> CD-ROM Drive-> Removable Devices.

9. Press [ F10 ] and then press [ Enter ] to save the changes you made andexit the BIOS.

2.7 Software InstallationTo install the 9130 BSC Evolution software, refer to the 9130 BSC EvolutionSoftware Installation document (3BK 17430 3126 RJZZA).

After finishing the software installation perform the commissioning tests.

2.8 Check the Firmware VersionFor checking the Firmware Version please refer to 9130 BSC EvolutionFirmware Upgrade.

2.9 Commissioning Tests

2.9.1 Option: LMT Installation (O1)

If you have not already installed the LMT, refer to the 9130 BSC EvolutionTerminal User Guide for how to install and configure the LMT.

3BK 17430 3121 RJZZA Ed.07 41 / 46

Page 42: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.9.2 Connect the LMT to the BSC

The LMT cable (with RJ45 connector) must be available at ATCA shelf rearside (shelf 3 or 4).

1. Connect the LMT to the JAXSSW1 (position 7 on used ATCA shelf rearside), port ETH8.

See Tools (Section 1.4.1)

ETH8

OOS

OK

ACT

HS

ETH1

ETH2

ETH3

ETH4

ETH5

ETH6

ETH7

Figure 22: JAXSSW at the ATCA Rear Side

2. Check on the front panel that the LED corresponding to the connection portis lit (for the port Eth8 the corresponding LED is situated on row 8 column C).

BASE

12345678

INTERFACE

A B C

Figure 23: Part of JBXSSW Front Plate

42 / 46 3BK 17430 3121 RJZZA Ed.07

Page 43: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.9.3 Option: Connect O&M cables from MFS to BSC (O2)

In case of rack shared configuration, O&M link can be transported from MFSto OMC-R via BSC.

On ATCA rear side, connect the O&M Ethernet cables as follows:

1. Connect the first JLCAT6 cable (1AB229830001) from ATCA Shelf 4JAXSSW1 port ETH3 to ATCA Shelf 3 JAXSSW1 port ETH3.

2. Connect the second JLCAT6 cable (1AB229830001) from ATCA Shelf 4JAXSSW2 port ETH3 to ATCA Shelf 3 JAXSSW2 port ETH3.

ETH8

OOS

OK

ACT

HS

ETH1

ETH2

ETH3

ETH4

ETH5

ETH6

ETH7

ETH8

OOS

OK

ACT

HS

ETH1

ETH2

ETH4

ETH5

ETH6

ETH7

ETH8

OOS

OK

ACT

HS

ETH1

ETH2

ETH3

ETH4

ETH5

ETH6

ETH7

ETH8

OOS

OK

ACT

HS

ETH2

ETH4

ETH5

ETH6

ETH7

1234567890123456789012345678901234567890123456789012345678901234567890123456789012345678901234567890

ATCA Shelf 3Rear side

ATCA Shelf 4Rear side

JLCAT6 Ethernet cables 1AB 22983 0001

JAXSSW2 JAXSSW1

JAXSSW2 JAXSSW1

ETH1

ETH3

ETH3

Figure 24: ATCA Shelf 3,4 rear side

3BK 17430 3121 RJZZA Ed.07 43 / 46

Page 44: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.9.4 Perform the Rack Inventory

To check the firmware status and the hardware technical level of the hardwareby performing a rack inventory:

1. Check the hardware technical level of modules and boards by performingthe rack inventory.

To perform the 9130 BSC Evolution rack inventory, refer to the CI 08 - SiteEquipment Inventory document (3BK 17257 0001 RJZZA).

2. Check that there are no errors reported by the Inventar software regardingthe technical level of modules and boards.

2.10 Connect the OMC-R1. Ask the OMC-R operator to check the network connection to the 9130 BSC

Evolution. Open for example SSH connection for all external IP addressesas following:

OMCP1 is ’START_OAM_IP_ADDRESS’

OMCP2 is ’START_OAM_IP_ADDRESS’ + 1

Active OMCP is ’START_OAM_IP_ADDRESS’ + 2.

See Site-Specific Information (Section 1.2.2).

2. Wait for OMC-R confirmation that the connection is OK.

Check the Equipment

Status

3. Wait for the telecom boards to finish their initialization

Check the equipment status.

44 / 46 3BK 17430 3121 RJZZA Ed.07

Page 45: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.11 Option: Check the Connection with the CBC

2.11.1 Open a Telnet Session

To open a Telnet session:

1. In Windows 2000/XP, select:

Start ⇒ Run

2. In Open window enter:telnet

3. Click on [ Ok ]

A telnet window opens.

4. Connect to the station as follows:

Under Windows 2000, the connection is done as follows:set term vt100open 172.17.y.x

Under Windows XP, the connection is done as follows:open 172.17.y.x

where:

x is 3 for OMCP1

x is 4 for OMCP2

y is 3 for Shelf 3

y is 4 for Shelf 4

5. Click on [ Enter ]

6. In the Telnet window enter the login name and password.

7. Connect to the router used for connection with CBC servertelnet <IP address of the gateway for LSN>

By default IP address of the gateway for LSN1 is172.17.y.10, for LSN2 is 172.18.y.10user:password:

where:

y is 3 for Shelf 3

y is 4 for Shelf 4

8. Press [ Enter ] to start.

3BK 17430 3121 RJZZA Ed.07 45 / 46

Page 46: 9130 BSC Evolution Commissioning

2 9130 BSC Evolution Commissioning

2.11.2 Ping the CBC

To ping the CBC:

1. Enter the following command to check the connection between the BSCand the CBC:

ping <IP address of the CBC>

If answers from the CBC are received, the connection between the BSCand the CBC server is established.

2. Exit from the router:quit

3. Exit from BSC Control Stationexit

2.12 End of Commissioning1. Leave the 9130 BSC Evolution powered up

2. Close the doors of the rack

3. Check the CCL

4. Leave the site tidy:

Remove all packaging and unused equipment.

Clean the site.

5. Close the site and hand the keys to the key holder

6. Return the completed forms and the inventory files relating to the operationto base.

46 / 46 3BK 17430 3121 RJZZA Ed.07