9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy...

download 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

of 62

Transcript of 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy...

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    1/62

    Presentation on Regulatory Aspects of Standard of

    Performance of DISCOM andIncreasing Energy Efficiency by

    Energy Audit & Renewable Energy

    ProjectBy

    POWER TECH CONSULTANTS1-A/6, Swati Villa Surya ViharLink Road, Cuttack-753012

    Phone:9437155337, 06712328844Email: [email protected]

    www.pwrtch.com

    mailto:[email protected]:[email protected]
  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    2/62

    GUARANTEED STANDARDS OFPERFORMANCE OF DISCOM

    Restoration of Power Supply

    Within 4 (Four) hours of receipt of complaint, the Licensee shallinform, on enquiry by the consumer, the likely time by which thepower supply be restored.

    Normal Fuse-off

    The Licensee shall restore power supply in the case of normalfuse-off calls (replacing Horn Gap (HG) fuses or Low Tension (LT)fuses at the distribution transformer or at the consumer premises)within 6 hours of receiving the complaint in towns and cities andwithin 24 hours of receiving the complaint in rural areas.

    Orissa Electricity Regulatory Commission (Licensees Standards of

    Performance) Regulations, 2004 is applicable to all Distribution Licenseesand all Trading Licensees engaged in supply of electricity to the people ofOrissa.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    3/62

    Line Breakdowns

    In case of line breakdowns, the licensee shall ensure restoration ofpower supply within 12 hours of occurrence of breakdown in townsand cities and within 24 hours of occurrence of breakdown in ruralareas. However, in case of major breakdowns due to heavy rain,lightning, whirlwind requiring replacement of conductor, structures

    the licensee shall ensure restoration of power supply within 24 hrs ofoccurrence of breakdown in towns and cities and within 48 hrs ofoccurrence of breakdown in rural areas.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    4/62

    Distribution Transformer failure:

    The Licensee shall restore supply in the case of distributiontransformer failures by replacement of transformer within 24 hours ofreceiving the complaint in towns and cities and within 48 hours ofreceiving the complaint in rural areas.

    Period of scheduled outages:

    Interruption in power supply due to scheduled outages shall benotified by the licensee at least 24 hours in advance and shall notexceed 12 hours in a day. In each such event, the licensee shall

    endeavour to ensure that the supply is restored by 6:00 PM duringSummer and 5 PM during winter.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    5/62

    Information on Standards of Performance

    1. The Licensee shall furnish to the Commission, in monthly

    reports and a consolidated annual report for each financial year,the following information as to the Guaranteed Standards ofPerformance:

    The levels of performance achieved by the Licensee

    The number of cases in which compensation were payable andthe aggregate amount of the compensation paid

    The number of claims made by the consumer against theLicensee for failure to meet the Guaranteed Standards ofPerformance and the action taken by the Licensee

    The measures taken by the licensee to improve performance inthe areas covered by Guaranteed Standards and Licenseesassessment of the targets to be imposed for the ensuing year.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    6/62

    Registration of Complaint

    The licensee shall maintain a register for recording the complaintsreceived personally or phone or any other means available. Everycomplaint so received shall be recorded as Section no., name of thecomplainant, details of complaint, date and time of complaint. Thecomplaint Sl. No. shall be intimated to the complainant on the spot.

    The record in the Register should be available for inspection anytime by any person on demand. The aim of maintaining this registeris to provide adequate service to the consumer and the requiredinformation to the Commission.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    7/62

    Quality of Power Supply

    Voltage Variations

    The Licensee shall maintain the voltages at the point ofcommencement of supply to a consumer within the limitsstipulated hereunder, with reference to declared voltage:

    In the case of Low/Medium Voltage, +6% and -6% In the case of High Voltage, +6% and -9%;

    In the case of Extra High Voltage, +10% and -12.5%.

    On receipt of a voltage variation complaint, the licensee shallverify and take further action to

    Improve the voltage variations within 15 days of original

    complaint if no expansion/enhancement of network isinvolved; Resolve the complaint within 120 days, in case of upto 11KV

    and 180 days in case of upto 33KV. If it is beyond its control (i.e. due to transmission system) the

    Licensee should intimate the consumer of such reason within

    7 days.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    8/62

    Harmonics

    (i) The Licensee shall maintain the limits of harmonics as perthe stages specified hereunder:

    Stage-1: The cumulative Total Voltage Harmonic Distortion(THDv) at the Point of Commencement of Supply

    for each consumer connected at 132KV and above shallbe limited to 3%Stage-2: The cumulative Total Voltage Harmonic Distortion

    (THDv) at the Point of Commencement of Supply foreach consumer connected at 33KV shall be limited to8%

    Stage-3: The cumulative Total Voltage Harmonic Distortion(THDv) at the Point of Commencement of Supply foreach consumer connected at 11KV shall be limited to8%

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    9/62

    Complaints about meters

    (i) The licensee shall inspect and check the correctness of the meterwithin 7 working days of receiving the complaint. If the meter is not

    working including that it is stuck up, running slow, fast or creepingbeyond the limits, the Licensee shall replace the meter within 30 daysof receiving the original complaint if the meter belongs to theLicensee.

    (ii) The Licensee shall replace burnt out meters within 30 working days

    of removal of the meter after receiving the complaint if theburning of meter is not due to causes attributable to the consumerlike tampering, defect in consumers installation, meter getting wet,connecting unauthorized additional load by consumer etc.

    (iii) If the meter is burnt due to reasons attributable to the consumer, heLicensee shall serve a notice to the consumer for recovery of cost ofthe meter within 7 days of detection, and shall replace the meterwithin 15 days of receiving the payment from the consumer and afternecessary corrective action is taken to avoid future damage to the

    meter.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    10/62

    Applications for New connections/Additional Load

    i) For 230V/400V supplies:

    The licensee shall deal with consumer's application for new connectionas follows:

    (a) Within three days of receipt of application, the licensee shall send 3(three) clear days notice to the applicant for the purpose ofinspection of premises and fixation of point of entry of supplymains and the position of mains, cutouts or circuit breakersand meters.

    (b) Estimate charges for providing connection and security depositrequired shall be intimated within one week after the point of entryof supply mains and the position of mains, cutouts or circuitbreakers and meter has been settled.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    11/62

    ii) For H.T. supply up to 33KV and EHT supply:

    The licensee shall deal with of consumer's application for new connectionas follows:

    (a) If supply is requested to be given at H.T., the licensee shall respondwhether connection is feasible or not within 21 working days of application.

    If feasible, licensee shall intimate voltage at which supply will be given andpoint of commencement of supply. The licensee shall intimate theconsumer seeking the new connection, estimated charges and timerequired for providing the new connection within 60 (sixty) working days ofnotifying feasibility of supply.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    12/62

    (b) If supply is requested to be given at EHT, the licensee shallobtain the final reply regarding feasibility from the Transmissionlicensee and communicate the same to the applicant within 30working days of receipt of original application. The licenseeshall intimate the consumer seeking the new connection,estimated charges and time required for providing the newconnection within 60 (sixty) working days of notifying feasibilityof supply.

    (c) Connection shall be provided within the estimated time, asintimated, after deposit of Estimated charges, submission ofTest Report by consumers, inspection by Supplier'sEngineer/Electrical Inspector and Agreement, if required. The

    licensee shall, however, not be held responsible for delay, if any,for providing connection, if the same is on account of statutoryclearances, Rights of way, acquisition of land over whichlicensee has no reasonable control.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    13/62

    Where Power supply Requires Extensionof Distribution Mains

    Type of service connection

    requested

    Period from date of payment of

    required security, within which

    supply of electricity should beprovided

    Low Tension (LT) supply (30) days

    11KV supply (60) days

    33KV supply (90) days

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    14/62

    The licensee shall give effect to transfer of ownership, change ofcategory and conversion of the existing services from Low Tensionto High Tension and vice-versa within the following time limits

    (a) Title transfer of ownership - within 15 days of receipt ofapplication, with necessary documents and necessary fee, if any

    (b) Change of category

    Within 30 days from the single phase to Low Tension and vice-versa.

    Within 60 days from the Low Tension to 11KV and vice-versa. Within 90 days from the Low Tension to 33KV and vice- versa.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    15/62

    (i) The Licensee shall acknowledge the consumers complaintimmediately, if received in person and within 2 days, ifreceived by post. The licensee shall resolve the complaintregarding electricity bills within 30 days of its receipt.

    (ii) In case the complaint is genuine and revision of bill alreadyissued becomes necessary, the due date for payment of billshall be reckoned from the date of receipt of revised bill forthe purpose of disconnection of supply or for levy ofadditional charges for belated payment.

    Complaints about consumers bills

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    16/62

    Service area Compensation payable to affected consumer Manner of payment

    Normal Fuse-off

    Urban Areas Rs. 100 in each case of default Automatic

    Other Areas

    Line Breakdowns

    Urban Areas Rs. 100 to each affected consumer To be Claimed

    Other Areas

    Distribution Transformer failure

    Urban Areas Rs. 200 to each affected consumer To be Claimed

    Other Areas

    Period of scheduled outages

    Maximum duration in a single stretch Rs. 200 to each affected consumer To be Claimed

    Restoration of supply

    Voltage Variations

    No expansion/enhancement of network is involved Rs. 200 in each case of default Automatic

    Up-gradation of distribution system is required Rs. 500 in each case of default

    Harmonics

    EHT connections To be decided by the Commission at appropriate time.

    HT connections

    Meter Complaints

    Inspect and check correctness Rs. 100 in each case of default To be Claimed

    Replace slow, creeping or stuck up meters Rs. 100 in each case of default Automatic

    Replace burnt meters if cause not attributable to

    consumer

    Rs. 200 in each case of default Automatic

    Replace burnt meters in all other casesApplication for new connection/additional load Connection feasible from existing network

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    17/62

    Service area Compensation payable to affected consumer Manner of payment

    Network expansion/enhancement required for providing connection

    Release of supply Low Tension (including agriculture) Rs. 100 for each day of default To be Claimed

    Release of supply High Tension 11KV supply Rs. 500 for each day of default To be Claimed

    Release of supply High Tension 33KV supply Rs. 500 for each day of default Automatic

    Release of supply Extra High Tension services

    Erection of Substation required for release of supply Rs. 1000 for each day of default Automatic

    Transfer of ownership and conversion of service

    Title transfer of ownership Rs. 100 for each day of default Automatic

    Change of category

    Conversion from LT 1-ph to LT 3-ph Rs. 100 for each day of default Automatic

    Conversion from LT to HT and vice-versa Rs. 200 for each day of default Automatic

    Resolution of complaints on consumer's bills

    Resolution of complaint. Rs. 50 for each day of default Automatic

    Reconnection of supply following disconnection

    Urban Areas Rs. 100 for each case of default

    Other Areas Automatic

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    18/62

    ENERGY AUDIT

    Under the Act Energy Audit means the verification,monitoring and analysis of use of Energy including submission

    of technical report containing recommendations for improving

    Energy Efficiency with cost benefit analysis & action plan to

    reduce energy consumption .

    TYPE OF ENERGY AUDIT

    1. Preliminary Energy Audit2. Targeted Energy Audit

    3. Detailed Energy Audit

    4. Investment Grade Energy Audit (IGEA)

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    19/62

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    20/62

    AREAS OF ENERGY AUDIT

    Demand Side Management

    Power Factor Improvement

    Reactive Compensation

    Harmonics study

    Transformer & Motor Loading Survey Lighting Energy Audit & Lux Survey

    Audit of Main Plant Equipment like HVAC, Air

    Compressor, Boiler, DG set

    ENCON Option listing with cost benefit analysis Energy Management System

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    21/62

    BENEFITS OF AN INDUSTRIAL ENERGY AUDIT

    Energy Savings (Minimum 15% to 20%) Avoiding power factor penalties & environmental

    compliance costs.

    Quality improvements

    Productivity improvements

    Reduced Maintenance

    Fewer Breakdowns

    Better safety & Protection

    A process for repeatable improvements.

    PROCESS VS. EQUIPMENT

    Equipment efficiency improvement : Max 5%

    Process efficiency improvement : 15% to 30%

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    22/62

    In Ordnance Factory, Badmal there are 4 nos. of oil fired Boilers of

    capacity 10 TPH, located at Boiler house -1 &2. In each boiler

    house one boiler is operated for steam generation.

    Per day consumption of water for steam generation is 23064

    liters for boiler-1 & 23604 Liters for boiler-3. Water is fed from DMplant at ambient temperature 35 C.

    For pre heating the feed water of the boiler from the ambient

    temperature to 85 C, Solar water heating system is proposed to

    be installed which will increase the temperature of water up to 85C, so as to supply this feed water to the boiler.

    This Solar water heating system can be installed after the storage

    water tank. The heated water can be fed to boiler through Boiler

    Feed Pump (BFP). Total 480 Nos. of panels will be required for

    heating of water @240 Nos. of panels for each boiler house.

    OPTIMIZATION OF FO BY USE OF SOLAR WATER HEATING SYSTEM

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    23/62

    Solar Flat Plate Collector Array (Proposed)

    Circulation pumps-2

    nos. 1W + 1S (Proposed)

    Soft water

    tank 2 x 12000

    Liter Capacity(Existing)

    Hot Water

    Storage Tank24000 Ltr.Capacity

    (Proposed)

    Deareator15000 Ltr.capacity(Existing)

    BFPTo Boiler

    80 - 85 Deg C

    Water Flow Meter

    Gate Valve

    NRV

    Pump

    (Proposed)

    Pump (existing)

    SCHEMATIC DIAGRAM OF SOLAR WATER HEATING

    SYSTEM

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    24/62

    1 Ambient temp. in C 352 Proposed Temp. rise of water in C 853 Temp. to be increased in C 504 Water Consumption in Ltr./Hr. 1922

    5 Assuming operational Hours in Hr. 126 Water consumption in Ltr./Day 230647 Heat gain per day in Kcal 11532008 GCV of Furnace Oil in Kcal/kg 100009 Density of Furnace Oil 0.9337

    10 Equivalent amount of Furnace Oil to be saved inLtr./Annum 37052.59

    11 Annual cost Saving for FO in lacs 10.00412 Investment in lacs 28.6013 Simple pay back period 2.86

    CONSERVATION OF FURNACE OIL BY INSTALLATION

    SOLAR WATER HEATER

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    25/62

    In Ordnance Factory, Badmal each compressor control had to be manually set

    with its own, independent control pressure band, matching with the plantsproduction. As the plant requirement is dynamic, the air demand varies. As the

    air demand increases and additional compressors were brought on line, the

    plant pressure fluctuated widely and the pressure band between the

    compressors became progressively wider.

    Further during lunch hour and during the closing hour, the requirement of

    compressed air is significantly low, however the operator has to run the

    compressor as he has little idea about the production requirement.

    By installing PLC based central control system, CENTAC energy Master (CEM)

    from Ingersoll and (or equivalent from other manufacturers), all compressors

    will be utilized their optimum capability and thus reducing the operating period

    of the compressors. The sequencers also performance time sharing functionsand automatically levels running hours among multiple compressors.

    PLC control system utilizes a common highly accurate pressure transducer and

    controller. The system operates all compressors in a common pressure control

    span; the advantage is a very small pressure control range and energy saving.

    The pressure control band can be lowered to 6.4 6.6 kg/cm2 range from theexisting range of 6.0 to 6.9 kg/cm2.

    OPTIMIZATION OF COMPRESSED AIR BY USE OF CENTAC

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    26/62

    Total compressor load KW 540

    Estimated power saving % 20

    Power Saving KW 72

    Time of operation in a day Hour 10

    Assuming no. of working days in a year No. of days. 300

    Annual energy saved KWh 216000

    Annual financial saving Rs. 6,26,400.00

    Investment required Rs. 12,00,000.00

    Simple payback period In year 2 Years

    COST BENEFIT ANALYSIS BY USE OF CENTAC IN COMPRESSOR

    SYSTEMS

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    27/62

    DEMAND SIDE MANAGEMENT

    The contract Demand of the National Library Building for

    the consumer no- 1074001003 is at 900 KW. The average maximum demand of the building is at

    463.68 at 0.75 PF.

    Thus the contract demand / connected load are kept at a

    very high value. The rate of demand charge is Rs.220 per KVA.

    The average present monthly demand charge of National

    Library Building is Rs.134760.19 Per Month.

    Because of higher contract demand, the building has topay higher demand charges to the CESC.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    28/62

    COST BENEFIT ANALYSIS FOR REDUCTION OF CONTRACT

    DEMAND

    Cost Benefit Analysis for Reduction of Contract Demand

    Particulars Unit Value

    Present Contract Demand KW 900

    Present Monthly EnergyConsumption

    KWh 1,56,370.20

    Present Monthly EnergyCharge

    Rs. Per Month 7,16,082.95

    Present Monthly Energy Bill Rs. Per Month 7,92,009.73

    Present Monthly DemandCharge

    Rs. Per Month 1,98,000.00

    Future Contract Demand KVA 650.00

    Future Demand Charge Rs. Per Month 1,43,000.00

    Future Monthly EnergyConsumption

    KWh 3,66,271.03

    Monthly Saving in DemandCharge

    Rs. Per Month 55,000.00

    Annual Saving in DemandCharge

    Rs. Per Annum 6,60,000.00

    Investment Required Rs. NILPayback Period Year Immediate

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    29/62

    REDUCTION OF LIGHTING LOAD

    The Fluorescent tube lights in use presently in India are of

    the T12 (40W) and T8 (36W).

    T12 implies that the tube diameter is 12/8 (33.8mm), T8

    implies diameter of 8/8 (26mm) and T5 implies diameter

    of 5/8 (16mm).

    This means the T5 lamp is slimmer than the 36W slim tubelight. The advantage of the T5 lamps is due to its small

    diameter, luminary efficiency can be improved by about

    5%. The luminous flux of T5 is 3200 lm compare to 2450

    lm for T8 lamps. In National Library all the T12 and T8 FTLs are replaced by

    T5 lamps.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    30/62

    COST BENEFIT ANALYSIS FOR T12 FTL RETROFIT WITH

    T5 FITTINGS

    Particulars Unit Value

    Present T12 FTLs No. 1875

    No. of T5 type Fittingsrequired

    No. 1875

    Present KW KW 103.125To be KW KW 56.25

    Saving in KW KW 46.875

    Run hour /day HR 18

    Annual Energy Saving KWH 253125

    Annual Energy BillSaving

    Lacs Rs. 11.77

    Investment(@Rs.500/-per fitting)

    Lacs Rs. 9.38

    Simple PB Period Years 0.80

    For (T12) FTL Fixtures

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    31/62

    COST BENEFIT ANALYSIS FOR T8 FTL RETROFIT WITH T5

    FITTINGS

    Particulars Unit Value

    Present T8 FTLs No. 5199

    No. of T5 type Fittings required No. 5199

    Present KW KW 270.348

    To be KW KW 155.97

    Saving in KW KW 114.378

    Run hour /day HR 18

    Annual Energy Saving KWH 617641.2

    Annual Energy Bill Saving Lacs 28.72

    Investment(@Rs.500/- per fitting) Lacs 26.00

    Simple PB Period Years 0.91

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    32/62

    REACTIVE LOAD MANAGEMENT

    National Library, Kolkata has installed AUTO ON typecapacitor banks of 814 KVAR capacities in LT buses in order toimprove the PF to about 0.99 at present load condition. TheAuto ON type banks can take care of varying nature of loads in

    Office & Non-Office hours by suitably switching on requiredcapacitor capacity to get the desired PF.

    It is estimated that about annually saved amounting in EnergyBill to about Rs. 9.51 Lacs which can be saved per annum.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    33/62

    COST BENEFIT ANALYSIS FOR INSTALLATION OF

    CAPACITOR BANK

    DETAILS UNIT VALUELoad KW 1100.00

    Average Annualised PF 0.75

    To be PF 0.99

    Capacitor Required KVAR 814.00

    Run Hour / Day HR/Day 18.00

    Present monthly average energy bill Lacs 14.45

    Monthly Energy Bill Saved because of PFimprovement Lacs 0.43Annual Saving in Energy Bill

    Lacs

    5.20

    Annual PF Penalty and overdrawl penalty paidby the Consumer

    Lacs 4.31Total Annual savings Lacs 9.51

    Investment Lacs 8.14

    Simple PB Period

    Years

    0.86

    ENCON BY USE OF LED LIGHTING SYSTEMS

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    34/62

    In HPCL, Mumbai Refinery, it was proposed to replace the existing250W HPSV light fittings with 120 W Light Emitting Diode (LED)

    street lights. and accordingly a demonstrative study with the newly

    proposed LED fitting was carried out.

    Make : SANARTI

    Power Rating : 120 Watt

    Supply Voltage : 170-270 V AC

    Electrical Connection : Lead wire 1m long

    Dispersion angle : 60 degree

    Environment Protection : IP65

    ENCON BY USE OF LED LIGHTING SYSTEMS

    LUX & POWER MEASUREMENT WITH

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    35/62

    Locati

    onRemark Volt Amp PF KW

    THD

    (V)

    THD

    (I)

    B3,

    AVE-B

    250W HPSV

    lamp was

    ON

    227.8 1.30.73

    40.21 2.1% 16.5%

    Location Lux at

    Ground

    level

    Lux at 1

    elevation

    from

    ground

    level

    Lux at 2

    elevation

    from

    ground

    level

    Lux at 3

    elevation

    from

    ground

    level

    Lux at 4

    elevation

    from

    ground

    level

    Lux at 5

    elevation

    from

    ground

    level

    J 22 25 26 27 28 30

    K 36 37 42 45 50 55L 31 31 34 37 41 43

    M 9 9 9 10 11 11

    N 8 9 9 9 9 9

    O 8 9 9 9 9 9

    A 2 4 4 4 4 4

    D 3 4 4 4 4 4

    G 2 2 2 3 3 3

    LUX & POWER MEASUREMENT WITH

    EXISTING 250 W HPSV LAMP

    LUX MEASUREMENT WITH NEW 120 W LED

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    36/62

    Locat

    ion

    Lux

    atGroun

    d

    level

    Lux at

    1

    elevatio

    n from

    ground

    level

    Lux at

    2

    elevatio

    n from

    ground

    level

    Lux at

    3

    elevatio

    n from

    ground

    level

    Lux at

    4

    elevati

    on

    from

    ground

    level

    Lux at

    5

    elevati

    on

    from

    ground

    levelJ 43 48 52 55 59 65

    K 45 48 54 56 58 62

    L 33 35 36 37 38 40

    M 8 9 9 10 11 13

    N 8 8 9 11 11 11O 7 7 7 8 9 10

    A 1 1 1 1 1 1

    D 1 1 1 1 1 1

    G 1 1 1 1 1 1

    LUX MEASUREMENT WITH NEW 120 W LED

    STREET LIGHTS

    POWER MEASUREMENT WITH NEW 120 W LED

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    37/62

    Voltage (Max) Volt 218.5

    Voltage (Min) Volt 216.9

    Voltage (Avg.) Volt 217.2

    Supply Frequency HZ 49.3

    Current Amp 0.5

    Power Factor 0.907 (lagging)

    Power Consumption Watt 110.2

    THD-V % 2.8%

    THD-I % 12.8%

    POWER MEASUREMENT WITH NEW 120 W LED

    STREET LIGHTS

    COST BENEFIT ANALYSIS OF REPLACEMENT OF 250 W

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    38/62

    Total Quantity of 250 W HPSV Street Light No. 430

    No. of 120 W LED Fittings required

    No.

    430

    Power Consumption in HPMV fittings Watt 210

    Present KW KW 90

    Measured Power Consumption in LED fittings Watt 110

    To be KW after installation of LED fittings KW 47

    Saving in KW KW 43Run hour /day HR 12

    Annual Energy Saving KWH 187963

    Average Energy Tariff Rs./ KWH 5.61

    Annual Energy Bill Saving Lacs Rs. 10.54

    Cost of the each LED Fittings Rs. 19000.0Installation Cost per lamp Rs. 1000.0

    Total cost of replacement with one LED fittings Rs. 20000.0

    Total investment for replacement with 430 nos. of LED

    street LightRs. Lacs 86.0

    Simple PB Period Years 8.16

    COST BENEFIT ANALYSIS OF REPLACEMENT OF 250 W

    HPSV STREET LIGHT WITH 120 W LED STREET LIGHT

    VARIOUS OTHER INDUSTRIAL CASE STUDIES

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    39/62

    Replacement of Cooling Tower solid cell fan blade with Epoxy Coated Hollow

    Energy Efficient Fan Blade at Rinfra-SPS

    The CW system is open re-circulating type with an induced draft cooling tower.Circulating water pumps discharge is led to the condenser. Outlet is returned to

    the cooling tower for cooling.

    There are total ten numbers cooling tower cells which are fitted with individual

    fans. During design, fans were made up of GRP solid fan blades.

    During ENCON activity and vendor discussion it was revealed that, energyconservation opportunity is available and all cell fan blades are replaced with

    Epoxy Coated Hollow Energy Efficient Fan Blade.

    These cell fan blades are with reduced weight and designed for same air flow

    with higher efficiency.Total investment : INR. 20, 00,533 /-

    Annual Energy Savings: 1129602 KWH

    Annual energy cost savings : INR. 25, 41,605/-

    Power saving of 128.95 kW is achieved.

    VARIOUS OTHER INDUSTRIAL CASE STUDIES

    VARIOUS OTHER INDUSTRIAL CASE STUDIES

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    40/62

    Modifying Cooling Tower makeup system from Motor driven pumping to

    Gravity system at Rinfra-SPS

    For maintaining cooling tower basin level, Clarified water from the

    clarified water reservoir is pumped by Cooling Tower make-up pumps and

    fed to the cooling tower basin to maintain normal level in Cooling Tower

    basin For maintaining cooling tower basin level, two Cooling Tower

    makeup motors of 30 kW are installed, at a time only one pump is inservice.

    As an energy conservation measure, system study is done for modifying

    existing system to gravity system & system is taken in service from Feb 15,

    2010.

    Total investment : Rs. 2,44,444 /-

    Annual Energy Saving: 199728 KWH

    Annual energy cost savings : Rs. 4, 49,388/-

    Power saved is 22.8 kW.

    VARIOUS OTHER INDUSTRIAL CASE STUDIES

    VARIOUS OTHER INDUSTRIAL CASE STUDIES

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    41/62

    Wind Ventilators

    At Rinfra-SPS at different locations depending on the

    heat load, motor operated ventilation systems are

    installed. For adopting renewable energy

    technologies, Rinfra - SPS has evaluated several

    methodologies. After evaluating site requirement, it

    was decided to change motor driven ventilation

    system with wind driven ventilators.

    Wind ventilators operating working principle is on

    thermo-siphon.

    Total investment : Rs. 3,20,645 /-Annual Energy Savings: 224431 KWH

    Annual energy cost savings : Rs. 5, 04,970/-

    Power saving of 4.27 KW per fan.

    VARIOUS OTHER INDUSTRIAL CASE STUDIES

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    42/62

    VARIOUS OTHER INDUSTRIAL CASE STUDIES

    Arresting Steam Leakages in Main Steam Lines

    It have been noticed that leakage are not considered as aproblem till the steam required pressure for continuous

    operation of plant is maintained by the process. Through

    Leakages are considered as very minor loss, but a good

    amount of energy can be saved by arresting leakages whichdoesnt require huge investment. It has been estimated that

    a 3mm diameter hole on a pipeline carrying 7kg/cm2 steam

    would waste 32.65 KL of fuel oil per year.

    In Thermal Power Station leakage sealing improves the boiler

    efficiency.

    Annual Energy Saving: 5155500 KWH

    Investment Required: Nil

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    43/62

    VARIOUS OTHER INDUSTRIAL CASE STUDIESInstallation of Automatic Temperature Controller in CT Fan

    In cooling towers the temperature of cold water depends onthe factors namely heat load, ambient, relative humidity andambient air velocity. It was observed that the operations of the

    cooling tower is not controlled based on the ambient climatic

    conditions vis--vis temperature differential. As a result CT fans

    were operating continuously without taking into account of the

    inlet & outlet temperature variations. If outlet cooling

    temperature is lower than the desired value, then natural

    cooling is sufficient.

    Annual Cost Saving: Rs. 3196800.00

    Investment Required: Rs. 4000000

    Payback Period: 15 months

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    44/62

    VARIOUS OTHER INDUSTRIAL CASE STUDIES

    Application of Glass Filled Polymer Coating in CW PumpsCorrocoat fluiguide coating which is the glass flake filled polyester based

    resin is applied to the impeller of cooling water pumps. The advantage of

    impeller coating is as follows.

    It improves efficiency & save energy

    It reduces surface roughness The coating is hydrophobic in nature

    Annual Cost Saving: Rs. 15466500.00

    Investment Required: Rs. 30000000.00

    Payback Period: 23 months

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    45/62

    VARIOUS OTHER INDUSTRIAL CASE STUDIES

    Cleaning Of Condenser Tubes Using Bullet Shots

    The performance of condensers depends on efficiency of its tubes, based oncleanliness factor practice of its heat transfer surface, water flow and prevention of

    air leakage.

    The in efficient condenser leads to poor vacuum creation for the condensate. In a

    thermal power station it is found full vacuum is not developing in unit 1 and 2 due

    to the fact that they were installed in 1983 and due to aging factor condenser tubesare no longer capable of transferring the heat properly. Through discussion with

    the plant managers it is understood that DM make up water consumption in unit 3

    to 7 is on average 10 M/hr with full generation of 210 MW in each unit where as in

    unit 1 and 2 the DM water consumption is about 15 m/hr with 110MW generation

    in each unit. So they have done condenser cleaning by using Bullet shots so thatthe efficiency of the tubes have increased and unit #1 & 2 have consumed less

    make up water than before.

    Total Financial Saving: Rs. 51072000.00

    Investment Required: Rs. 30000000.00

    Payback Period: 07 months

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    46/62

    VARIOUS OTHER INDUSTRIAL CASE STUDIES

    Energy saving by installation of VFD at HT/LT motors

    In order to reduce the auxiliary consumption of units one no.

    of medium voltage VFD at CEP-5A and 3 nos. of low voltage

    VFD at seal air fan has been installed in a thermal power

    station. The commissioning and trial operation of VFD has

    been completed during January 2011.

    Annual Energy Saving : 170712 KWH

    Annual Financial Saving : Rs. 6145632.00

    Investment Required: Rs. 10180000.00

    Payback Period: 20 months

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    47/62

    Energy Monitoring MethodologyA well defined Energy Management Organization Structure

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    48/62

    GRIDCOs Power Handling Capacity = 2000 MW

    CGPs Power Generation Capacity = 2000 MW Total Average Power Use = 4000 MW

    Estimated Saving Potentials @ 10%= 400 MW

    Energy Efficiency can avoid the present power deficit scenario and

    load regulation can be avoided Energy Audit should be mandatory for all HT consumers having

    contract demand above 110 KVA

    Submission of Annual Energy Audit report and Specific Energy

    Consumption report should be submitted to SDA

    Joint verification of Financial Audit Report and Energy Audit

    Report of all HT consumers will discourage power theft and AT&C

    losses of DISCOM will be reduced.

    Both State Govt. and OERC have a major role to play to bring

    energy efficiency practices in Odisha.

    ENERGY EFFICENCY IN ODISHA

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    49/62

    REC Mechanism Conceptual Framework

    RE Generation

    Sale at

    preferential tariff Obligated Entities

    Sale in REC

    Framework

    ElectricityComponent

    Host Distribution

    Utility at a pricenot more than

    average pool price

    Third Party sale atmutually agreed

    prices

    A CPP based onRenewable Energy

    Sources

    Sale through

    Power Exchange

    RenewableComponent (REC)

    Sale throughPower Exchange

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    50/62

    REC REGULATIONSSALIENT FEATURESEligible Source

    All sources recognised by MNRE under Renewable Energy CategoryTwo Categories of Certificates one for Solar and other for Non-Solar

    Eligible Entities defined in RegulationsGrid Connected RE Power Projects having NO PPA at preferential tariff and received

    accreditation certificate from State Agency

    Shall sell electricity at Pooled cost of Power Purchase to distribution utility or at

    mutually agreed price to any other licensee

    Obligated EntitiesAs defined by SERC, distribution utility, OA User, Captive Consumer

    States to amend existing RPO Regulations

    REC Issuing AuthorityNational Load Despatch Centre to issue REC to Generator based on the EnergyInjection Report prepared by SLDC

    Sale/Purchase of RECTransaction of REC shall take place at Power Exchanges

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    51/62

    RPO & COMPLIANCE REGULATION

    OERC has published Renewable Purchase Obligation

    (RPO) & Compliance Regulation. This is in line with CERC,NLDC, FOR scheme of RPO and has the mandate ofMNRE.

    As per the Regulation GIRDCO and an Industry with coal

    based CGP>5MW have to purchase Solar RenewableEnergy Certificate @ 0.1 %, Non solar REC @1.2% and Co-Generation REC @3.7% totaling 5% of their totalconsumption for FY 2011-12.

    This % will keep on increasing progressively from 5% totune of 7% in FY 2015-16

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    52/62

    RPO TARGET

    Year-wise

    target

    Minimum quantum of purchase in percentage

    (in terms of energy consumption in the State in KWH)

    Renewable Co-generation Total

    Solar Non-solar

    2011-12 0.10 1.20 3.70 5.0

    2012-13 0.15 1.40 3.95 5.5

    2013-14 0.20 1.60 4.20 6.0

    2014-15 0.25 1.80 4.45 6.5

    2015-16 0.30 2.00 4.70 7.0

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    53/62

    REC SCHEME & CALCULATION

    Particulars Units For FY 2011-12 For FY 2012-13 For FY 2013-14 For FY 2014-15 For FY 2015-16

    Assume CGP Capacity MW 250 250 250 250 250

    Total MW Consumed by Industry from

    CGP MW 150 150 150 150 150

    The Total Energy Consumed by

    Industry from CGP KWh 1,314,000,000 1,314,000,000 1,314,000,000 1,314,000,000 1,314,000,000

    Solar RPO Obligation as per OERC

    Regulation % 0.10% 0.15% 0.20% 0.25% 0.30%

    Solar REC required to be purchased by

    CGP KWh 1,314,000 1,971,000 2,628,000 3,285,000 3,942,000

    Annual Cash Outgo due to

    procurement of Solar REC from theExchange @ Rs.12.00 per KWh Rs. 15,768,000 23,652,000 31,536,000 39,420,000 47,304,000

    The Capacity of SPV Plant Required MW 0.789473684 1.184210526 1.578947368 1.973684211 2.368421053

    Non-Solar RPO Obligation as per

    OERC Regulation % 4.90% 5.35% 5.80% 6.25% 6.70%

    Non-solar REC required to be

    purchased by CGP KWh 64,386,000 70,299,000 76,212,000 82,125,000 88,038,000

    Annual Cash Outgo due toprocurement of Non-Solar REC in the

    Exchange @1.50 per KWh Rs. 96,579,000 105,448,500 114,318,000 123,187,500 132,057,000

    The Capacity of Non solar Power

    Plant Required MW 9.1875 10.03125 10.875 11.71875 12.5625

    Total Value of REC i.e. Annual Cash

    Outgo of the Industry without any

    Input Energy due to statutory

    requirement of procurement of REC Rs. 112,347,000 129,100,500 145,854,000 162,607,500 179,361,000

    REC Trading

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    54/62

    Electricity to Grid Electricity from Grid

    ENERGY

    A/c

    Application to issue REC

    Issuance

    of REC

    Confirmation of EA

    RedemptionOf REC

    RPOComplianceReporting

    ComplianceMonitoring

    RE- GeneratorAccreditation

    REC Trading through Power Exchange

    State Agency State Agency

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    55/62

    HOW TO FULFIL RPO

    Purchase REC both solar and Non solar => We will

    facilitate REC purchase on behalf of CGP. PTC shall carryout bidding through our net work in Exchange Platform onbehalf of CGP and Transaction shall be cleared throughCGP accounts.

    Purchase Non solar REC and establish SPV PowerPlant=> We will provide technical consultancy forpreparation of TEFR, DPR and shall accredit and registerthe project REC scheme and Trade the solar REC in PX.

    Establish both solar and Non Solar Power Project. => Wewill provide technical consultancy for preparation of TEFR,DPR and shall accredit and register the project REC

    scheme and Trade the solar & Non Solar REC in PX.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    56/62

    CBA OF SPV POWER PLANT

    Units Generation Unit Value

    Installed Capacity MW 2

    Net Generation MU 3.3288Land Requirement Acres 10

    Project Cost Crores Rs. 26

    Tariff Components (Fixed Charge) Unit Value

    O&M Expenses Rs. Lakh 18

    Depreciation

    Rs. Lakh

    182Interest on Term Loan Rs. Lakh 227.5

    Interest on Working Capital Rs. Lakh 14.015925

    Total Fixed Cost Rs. Lakh 441.51593

    Per Unit Tariff Components Unit Value

    PU O&M Expenses Rs./kWh 0.5407354PU Depreciation Rs./kWh 5.4674357

    PU Interest on Term Loan Rs./kWh 6.8342946

    PU Interest on Working Capital Rs./kWh 0.4210504

    PU Tariff Components Rs./kWh 13.263516

    Levellised Tariff for a period of 20 years Rs./kWh 8.9460944Minimum Value of REC in Exchange Rs./kWh 12.00

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    57/62

    CBA OF BIOMASS POWER PLANT

    Installed Capacity MW 10

    Gross Generation MU 70.08

    Net Generation MU 63.07

    Tariff Components (Fixed Charge) UnitO&M Expenses Rs. Lakh 226.35

    Depreciation Rs. Lakh 400.86

    Interest on Term Loan Rs. Lakh 515.39

    Interest on Working Capital Rs. Lakh 103.87

    Return on Equity Rs. Lakh 0.00

    Per Unit Tariff Components Unit

    PU O&M Expenses Rs./kWh 0.36PU Depreciation Rs./kWh 0.64

    PU Interest on Term Loan Rs./kWh 0.82

    PU Interest on Working Capital Rs./kWh 0.16

    PU Fixed Cost Rs./kWh 1.98

    PU Biomass Cost Rs./kWh 1.37

    PU Coal Cost Rs./kWh 0.49

    PU LDO Cost Rs./kWh 0.08PU Water Cost Rs./kWh 0.00

    PU Variable Cost Rs./kWh 1.94

    PU Total Cost of Generation Rs./kWh 3.92

    Energy Component CostRs./kWh

    4.00

    REC Component CostRs./kWh

    1.50

    Total Revenue Generation Rs./kWh 5.50

    ABOUT POWER TECH CONSULTANTS

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    58/62

    ABOUT POWER TECH CONSULTANTS

    Power Tech Consultants is a consulting house in thefields of power, energy, project management.

    Power Tech Consultants undertakes Investment Grade Energy Audit (IGEA) Third party audit Consultancy on regulatory, power trading issues

    PAT Audit

    Power Tech Consultants provides Project Management consultancy Preparation of DPR/ TEFR of Power Projects

    We have adequate no. of experienced consultants,certified Energy Auditor and Certified Energy Managerduly certified by Bureau of Energy Efficiency, Ministry ofPower, Govt. of India.

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    59/62

    State Designated Agency (SDA), Orissa

    Chhattisgarh State Renewable Energy Development

    Agency (CREDA)

    Energy Efficiency Services Limited (EESL), Ministry of

    Power, Govt. of India

    Ministry of New & Renewable Energy, Govt. of India,

    Orissa Electricity Regulatory Commission (OERC)

    POWER TECH CONSULTANTS EMPANELLED WITH

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    60/62

    Ordnance Factory Badmal Limited (OFBL)

    Madhya Pradesh Urja Vikas Nigam Limited (MPUVNL)

    Federation of Indian Chambers of Commerce &Industry (FICCI)

    National Productivity Council, Govt. of India (NPC)

    Orissa Small Industries Corporation Ltd (OSIC)

    POWER TECH CONSULTANTS EMPANELLED WITH

    POWER TECH CONSULTANTS CLIENTS

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    61/62

    POWER TECH CONSULTANTS CLIENTS

  • 8/2/2019 9 Regulatory Aspects of Standard of Performance of DISCOM and Increasing Energy Efficiency by Energy Audit & Renewable Energy Project

    62/62