5351txt

download 5351txt

of 10

Transcript of 5351txt

  • 7/30/2019 5351txt

    1/10

    5351REP2011 20th

    Dec 2011

    GEOTECHNICAL SITE INVESTIGATION

    FOR THE PROPOSED VILLA OF

    MR SAEED ATIK SAEED AL HUMAIRI

    & MUZA MATAR KHALIFA

    PLOT NO-61, SECTOR: SE-42

    KHAILFA CITY (A)

    ABU DHABI

    Consultant:

    Al H iwar Engineer ing Consul tants

    Abu Dhabi -UAE

  • 7/30/2019 5351txt

    2/10

    Preface

    This report is directed towards the evaluation of the

    Geotechnical situation of the proposed site. Our

    evaluations are based upon findings of field investigations

    and lab testing.

    Site investigations are carried out on 17th Dec 2011 upon

    the request of our client Messers.MR SAEED ATIK SAEED AL HUMAIRI& MUZA MATAR KHALIFA..

    Data of engineering interest, which are gathered during our

    course of investigation, are completely considered in

    developing our recommendations.

    Eng. Fayez Shadid

  • 7/30/2019 5351txt

    3/10

    Abstract

    During the period from 17th Dec 2011 to 18th Dec 2011,

    three boreholes were drilled to a depth of 25 meters each.

    Drilling revealed the presence of cohesionless soil

    underlain by bedrock. Water table is met from (1.5-1.7)

    meter below the present ground level (0.00) assumed

    center of the asphalt pavement level. Water level may besubjected to tidal and seasonal variations or by induced arti f icial

    effects.)

    According to information supplied by our client and in the

    light of our findings, deep foundation system is proposed.

    End bearing bored piles are suggested to support the

    projected Villa and to be erected at depth of 11.5 meters

    below the present ground level (0.00) assumed center of

    the asphalt pavement level. With allowable pile bearingcapacity of 1.21*10 KN & pile diameter of 500mm.

    Total sulfate contents are considerably high in soils along

    pile perimeter. Therefore, Salt resistant Portland cement is

    recommended in pile construction.

  • 7/30/2019 5351txt

    4/10

    Contents Page

    * Preface ii

    * Abstract iii

    * Contents iv

    1. Introduction 1

    2. Scope of investigation 1

    3. Borehole Drilling 1

    4. In situ Testing 2

    5. General Geology 2

    6. Subsurface Materials 3

    7. Laboratory Tests 3

    8. Type and Depth of Foundation 4

    9. Pile Bearing Capacity 4

    10. Settlement 4

    11. Findings 5

    12. Recommendations 5

    13. Precautionary Measures 6

    AppendicesBorehole log sheetsTest result tables

    Grain size distribution curves

    Calculation sheets

    Borehole correlation cross section

    Borehole location map

    Legend to boring logs

    Key to subsurface material tests

    Abbreviations & Notations

  • 7/30/2019 5351txt

    5/10

    1

    1. Introduction

    Purpose of the investigations conducted at the request of our client is

    to determine the values of the geotechnical parameters needed for the

    design of a safe and economic foundation for his projected villa.

    We commenced work on the 17

    th

    Dec 2011. Work was completed onthe 18th Dec 2011. Our trained drillers and technicians under the

    supervision of our qualified engineers carried out Works. The

    projected villa is proposed to be constructed at Plot No 61. Sector SE-

    42, Khalifa City A- Abu Dhabi.

    2. Scope of Investigation

    Investigations were performed in situ and in the laboratory. These are

    consisting of:

    Borehole drillings and sampling at various levels of theboreholes carried out according to BS 5930, section 4,

    18 & 19.

    Survey of geotechnical features. Standard penetration tests were performed according to

    BS 1377 test 19 and BS 5930, section 4 (21.2).

    Unconfined compression tests were done according toBS 1377 test 20.

    Grain size analysis was conducted according to BS1377 test 7.

    Chemical Analysis was conducted according to BS1377 test 8.

    Bulk densities were determined according to BS 812part 2.

    3. Borehole Drilling

    Drilling operations include three boreholes were drilled at the site at

    the locations shown on the enclosed location map. They were

    numbered BH1 through BH3 inclusive. Drilling depths are 25 meterseach below the present ground level (0.00) assumed center of the

    asphalt pavement level.. Drilling equipment used was Boyles rotary

    drilling rig utilizing water flush method. Drilling in overburden is

    performed by the means of non-coring bits and casing of HX size.

  • 7/30/2019 5351txt

    6/10

    2

    Continuous coring utilizing T-86 size double tube core barrels carries

    out drilling in bedrock.

    Tube samplers obtained disturbed samples. Samples were packed in

    plastic bags labeled and brought to the laboratory.

    Extracted core samples are also labeled and placed in wooden boxesand delivered to the laboratory.

    Lithologic descriptions of subsurface sediments are presented in the

    attached borehole log sheets:

    Borehole 1-3 Sheets 1&2

    4. In Situ Testing

    Standard penetration tests using the standard penetration test (SPT)

    equipment were carried out. Penetration tests were advanced by the

    use of the split spoon sampler, due to the nature of the encountered

    formation. The SPT apparatus is in accordance with British Standard

    1377 test 19 (5.4.2.4), and utilizing automatically dropping weight of

    65.0 kg. With free fall distance of 760 mm.

    SPT results are shown at the attached borehole log sheets, and

    tabulated in the attached table 1.

    5 . General Geology

    United Arab Emirates lie within the Arabian platform that is

    characterized by thick sediments continued from the early Cambrianto recent age. Structural developments of The Arabian Platform had

    influenced the sedimentary pattern in the UAE. Sedimentation

    conditions had been changed considerably after the tectonic events

    (Hersenien Movement) that formed mountains at the end of the

    carboniferous epoch. Sedimentary rocks were altered from detrital

    deposits to calcareous deposits that had been deposited in shallow

    marine water and continued to Holocene age. Sandy sediments mainly

    cover UAE.

  • 7/30/2019 5351txt

    7/10

    3

    The exposed rocks are limited to certain areas at Alain, Jabal

    Dhannah, Das, Delma, Arzanah, Zirkoh, Jabal Alqamar Aljanubi,

    Jabal Alqamar Alshamali, Khor fakan Alfujairah and Ras Alkhaimah.

    Sandy sediments form chains of hills and dunes separated by flat

    gravely areas. Evaporate flats (Sabkha) are widely spread at coastalplains. In general most of rocks in UAE are sedimentary rocks except

    some exposed igneous rock intrusions and metamorphic rocks at Jabal

    Hafeet and at north east of the northern emirates. Our site in particular

    lies within an area of calcareous sand of marine origin, calcareous

    rocks with coastal gravel, platform gravel, detritus, terrestrial silty

    clayey sand and evaporates, underlain by intercalated layers of

    anhydrite, shale, marl and calcareous rocks which may be related to

    the early Miocene or younger. Fossil rich calcareous rocks deposited

    in shallow marine water underlie the most predominant superficial

    sediments. These fossiliferous calcarenites may be related to

    Oligocene age.

    6. Subsurface Materials

    Borehole drilling revealed that subsurface strata are mainly composed

    of Sandstone & MudStone and Gypsum, overlain by an overburden of

    recent marine deposits consists of loose to dense silty sand. Ground

    water level is encountered at depth from (1.5-1.7) meter below thepresent ground level (0.00) assumed center of the asphalt pavement

    level The attached correlated cross section reflects the subsurfacedeposition pattern of the site.

    7. Laboratory Tests

    Laboratory tests were restricted to mechanical, physical and chemical

    properties of sub soil useful in safe foundation design.

    Tests carried out in our laboratory are:

    Unconfined compression tests were carried out on coresamples extracted from bedrock to determine their

    compressive strength, which is necessary to certain, theallowable bearing capacity of the subsurface strata.

    Results of the above mentioned tests are tabulated in the

    attached table 3.

  • 7/30/2019 5351txt

    8/10

    4

    Chemical Analysis of subsurface soil and ground water inorder to determine the pH-Value, Sulfate and Chloride

    contents. This is helpful in choosing the type of cement

    suitable for concrete mix design to protect foundations

    from unfavorable chemical reactions. Analysis results arepresented in table 2, attached to this report.

    Core sample bulk densities are determined and fixed intable 3 of the unconfined compression test results.

    Grain size analysis results are presented in curves attachedto this report.

    8. Type & Depth of Foundation

    Due to the considerably heavy load of the proposed structure, the

    most adequate bearing strata is at depth of 11.5 meters below the

    present ground level (0.00) assumed center of the asphalt pavement

    level. Therefore pile foundations are the most suitable.

    9. Pile Load Capacity

    Calculations of bored piles bearing loads are presented in the attached

    calculation sheets. Formulas used in calculations assume that pile

    load capacity is derived from both point resistance and from the bond

    between concrete and rock along surface perimeter of the socket in

    addition to skin friction of the cohesionless soil along the pile shaftsurface. Final pressure on rock is determined from the analysis of the

    core samples extracted from the foundation bearing strata. Allowable

    bearing pressure as a function of pile diameter for rock strata with

    favorable characteristics is calculated in the calculation sheets

    attached to this report.

    10. Settlement

    Settlement analysis of piles setting on rock is difficult and frequently

    unreliable because of discontinuities inherent in bedrockstratification.

    In general settlements in sound rocks are minimal and many times it

    is negligible due to their high elasticity modules. An attempt to

    calculate maximum total immediate settlement is presented in the

    attached calculation sheet 3. Calculations based upon the assumption

    that the bearing strata are behaving as an elastic body.

  • 7/30/2019 5351txt

    9/10

    5

    11. Findings

    Drilling proved that water table is encountered from (1.5-1.7)meter below the present ground level (0.00) assumedcenter of the asphalt pavement level.

    Overburden deposits are composed of cohesionless soilwith thickness of (10.5) meters.Cohesionless soil deposits are not adequate to bear theproposed load.

    Bedrock strata that exist at 11.5 meter deep below thepresent ground level (0.00) assumed center of the asphalt

    pavement level. form an adequate bearing foundation.

    Chemical tests proved that site materials are within class2 of the British Building Research Establishment

    12. Recommendations

    The followings are recommended in the light of our findings:

    Piles are of cast in place board piles.Piles are to be erected at depth of 11.5 meters below thepresent ground level (0.00) assumed center of the asphalt

    pavement level

    Pile socket length in bedrock is 1.0 meter.The boundary wall foundation & the connected one story

    buildings (Guard & Electric rooms) are to be erected as stripshallow foundation at depth of 1.0 m below the present ground

    level (0.00) assumed center of the asphalt pavement level with

    allowable bearing capacity of not more than 0.5 kg/cm

    Or simply attached to adjacent piles

    Values of the allowable safe pile load in KN versus pilediameter in meters are shown in tables and curves at the

    attached calculation sheets.

    Sulfate resisting Portland cement (SRPC) should be usedin pile concrete.

    Pile load tests should be carried out to ensure the above-mentioned parameters.

  • 7/30/2019 5351txt

    10/10

    6

    13. General Precautionary Measures

    The following precautionary measures should be considered duringbored pile construction.

    Inspection of the bottom of each pile shaft to eliminate thepresence of debris between the bottom of the concrete

    shaft and rock surface.

    Borehole bottom should be properly cleaned to preventoccurrence of large settlement during bearing capacity

    mobilization, due to the compression of the remain mud in

    the bottom of the socket.

    Controlling ground water flow during pile shaft boring toavoid loss of ground and potential long term undermining

    of floor areas.

    Ready mix concrete discharge pipe should not be pulledout of the concrete during placing, so that some of the

    concrete flows through water. These form a layer or a

    pocket of sand and gravel and a concentration of cement

    or laitance at cut-off level.

    The temporary liner should not be withdrawn too fastcausing soil to intrude in the concrete section (necking).

    The temporary liner should not be allowed to becomestuck and to be withdrawn after partial set of concrete has

    taken place, causing cracking of the shaft.