5351txt
-
Upload
yousif-mohammed-yousif -
Category
Documents
-
view
222 -
download
0
Transcript of 5351txt
-
7/30/2019 5351txt
1/10
5351REP2011 20th
Dec 2011
GEOTECHNICAL SITE INVESTIGATION
FOR THE PROPOSED VILLA OF
MR SAEED ATIK SAEED AL HUMAIRI
& MUZA MATAR KHALIFA
PLOT NO-61, SECTOR: SE-42
KHAILFA CITY (A)
ABU DHABI
Consultant:
Al H iwar Engineer ing Consul tants
Abu Dhabi -UAE
-
7/30/2019 5351txt
2/10
Preface
This report is directed towards the evaluation of the
Geotechnical situation of the proposed site. Our
evaluations are based upon findings of field investigations
and lab testing.
Site investigations are carried out on 17th Dec 2011 upon
the request of our client Messers.MR SAEED ATIK SAEED AL HUMAIRI& MUZA MATAR KHALIFA..
Data of engineering interest, which are gathered during our
course of investigation, are completely considered in
developing our recommendations.
Eng. Fayez Shadid
-
7/30/2019 5351txt
3/10
Abstract
During the period from 17th Dec 2011 to 18th Dec 2011,
three boreholes were drilled to a depth of 25 meters each.
Drilling revealed the presence of cohesionless soil
underlain by bedrock. Water table is met from (1.5-1.7)
meter below the present ground level (0.00) assumed
center of the asphalt pavement level. Water level may besubjected to tidal and seasonal variations or by induced arti f icial
effects.)
According to information supplied by our client and in the
light of our findings, deep foundation system is proposed.
End bearing bored piles are suggested to support the
projected Villa and to be erected at depth of 11.5 meters
below the present ground level (0.00) assumed center of
the asphalt pavement level. With allowable pile bearingcapacity of 1.21*10 KN & pile diameter of 500mm.
Total sulfate contents are considerably high in soils along
pile perimeter. Therefore, Salt resistant Portland cement is
recommended in pile construction.
-
7/30/2019 5351txt
4/10
Contents Page
* Preface ii
* Abstract iii
* Contents iv
1. Introduction 1
2. Scope of investigation 1
3. Borehole Drilling 1
4. In situ Testing 2
5. General Geology 2
6. Subsurface Materials 3
7. Laboratory Tests 3
8. Type and Depth of Foundation 4
9. Pile Bearing Capacity 4
10. Settlement 4
11. Findings 5
12. Recommendations 5
13. Precautionary Measures 6
AppendicesBorehole log sheetsTest result tables
Grain size distribution curves
Calculation sheets
Borehole correlation cross section
Borehole location map
Legend to boring logs
Key to subsurface material tests
Abbreviations & Notations
-
7/30/2019 5351txt
5/10
1
1. Introduction
Purpose of the investigations conducted at the request of our client is
to determine the values of the geotechnical parameters needed for the
design of a safe and economic foundation for his projected villa.
We commenced work on the 17
th
Dec 2011. Work was completed onthe 18th Dec 2011. Our trained drillers and technicians under the
supervision of our qualified engineers carried out Works. The
projected villa is proposed to be constructed at Plot No 61. Sector SE-
42, Khalifa City A- Abu Dhabi.
2. Scope of Investigation
Investigations were performed in situ and in the laboratory. These are
consisting of:
Borehole drillings and sampling at various levels of theboreholes carried out according to BS 5930, section 4,
18 & 19.
Survey of geotechnical features. Standard penetration tests were performed according to
BS 1377 test 19 and BS 5930, section 4 (21.2).
Unconfined compression tests were done according toBS 1377 test 20.
Grain size analysis was conducted according to BS1377 test 7.
Chemical Analysis was conducted according to BS1377 test 8.
Bulk densities were determined according to BS 812part 2.
3. Borehole Drilling
Drilling operations include three boreholes were drilled at the site at
the locations shown on the enclosed location map. They were
numbered BH1 through BH3 inclusive. Drilling depths are 25 meterseach below the present ground level (0.00) assumed center of the
asphalt pavement level.. Drilling equipment used was Boyles rotary
drilling rig utilizing water flush method. Drilling in overburden is
performed by the means of non-coring bits and casing of HX size.
-
7/30/2019 5351txt
6/10
2
Continuous coring utilizing T-86 size double tube core barrels carries
out drilling in bedrock.
Tube samplers obtained disturbed samples. Samples were packed in
plastic bags labeled and brought to the laboratory.
Extracted core samples are also labeled and placed in wooden boxesand delivered to the laboratory.
Lithologic descriptions of subsurface sediments are presented in the
attached borehole log sheets:
Borehole 1-3 Sheets 1&2
4. In Situ Testing
Standard penetration tests using the standard penetration test (SPT)
equipment were carried out. Penetration tests were advanced by the
use of the split spoon sampler, due to the nature of the encountered
formation. The SPT apparatus is in accordance with British Standard
1377 test 19 (5.4.2.4), and utilizing automatically dropping weight of
65.0 kg. With free fall distance of 760 mm.
SPT results are shown at the attached borehole log sheets, and
tabulated in the attached table 1.
5 . General Geology
United Arab Emirates lie within the Arabian platform that is
characterized by thick sediments continued from the early Cambrianto recent age. Structural developments of The Arabian Platform had
influenced the sedimentary pattern in the UAE. Sedimentation
conditions had been changed considerably after the tectonic events
(Hersenien Movement) that formed mountains at the end of the
carboniferous epoch. Sedimentary rocks were altered from detrital
deposits to calcareous deposits that had been deposited in shallow
marine water and continued to Holocene age. Sandy sediments mainly
cover UAE.
-
7/30/2019 5351txt
7/10
3
The exposed rocks are limited to certain areas at Alain, Jabal
Dhannah, Das, Delma, Arzanah, Zirkoh, Jabal Alqamar Aljanubi,
Jabal Alqamar Alshamali, Khor fakan Alfujairah and Ras Alkhaimah.
Sandy sediments form chains of hills and dunes separated by flat
gravely areas. Evaporate flats (Sabkha) are widely spread at coastalplains. In general most of rocks in UAE are sedimentary rocks except
some exposed igneous rock intrusions and metamorphic rocks at Jabal
Hafeet and at north east of the northern emirates. Our site in particular
lies within an area of calcareous sand of marine origin, calcareous
rocks with coastal gravel, platform gravel, detritus, terrestrial silty
clayey sand and evaporates, underlain by intercalated layers of
anhydrite, shale, marl and calcareous rocks which may be related to
the early Miocene or younger. Fossil rich calcareous rocks deposited
in shallow marine water underlie the most predominant superficial
sediments. These fossiliferous calcarenites may be related to
Oligocene age.
6. Subsurface Materials
Borehole drilling revealed that subsurface strata are mainly composed
of Sandstone & MudStone and Gypsum, overlain by an overburden of
recent marine deposits consists of loose to dense silty sand. Ground
water level is encountered at depth from (1.5-1.7) meter below thepresent ground level (0.00) assumed center of the asphalt pavement
level The attached correlated cross section reflects the subsurfacedeposition pattern of the site.
7. Laboratory Tests
Laboratory tests were restricted to mechanical, physical and chemical
properties of sub soil useful in safe foundation design.
Tests carried out in our laboratory are:
Unconfined compression tests were carried out on coresamples extracted from bedrock to determine their
compressive strength, which is necessary to certain, theallowable bearing capacity of the subsurface strata.
Results of the above mentioned tests are tabulated in the
attached table 3.
-
7/30/2019 5351txt
8/10
4
Chemical Analysis of subsurface soil and ground water inorder to determine the pH-Value, Sulfate and Chloride
contents. This is helpful in choosing the type of cement
suitable for concrete mix design to protect foundations
from unfavorable chemical reactions. Analysis results arepresented in table 2, attached to this report.
Core sample bulk densities are determined and fixed intable 3 of the unconfined compression test results.
Grain size analysis results are presented in curves attachedto this report.
8. Type & Depth of Foundation
Due to the considerably heavy load of the proposed structure, the
most adequate bearing strata is at depth of 11.5 meters below the
present ground level (0.00) assumed center of the asphalt pavement
level. Therefore pile foundations are the most suitable.
9. Pile Load Capacity
Calculations of bored piles bearing loads are presented in the attached
calculation sheets. Formulas used in calculations assume that pile
load capacity is derived from both point resistance and from the bond
between concrete and rock along surface perimeter of the socket in
addition to skin friction of the cohesionless soil along the pile shaftsurface. Final pressure on rock is determined from the analysis of the
core samples extracted from the foundation bearing strata. Allowable
bearing pressure as a function of pile diameter for rock strata with
favorable characteristics is calculated in the calculation sheets
attached to this report.
10. Settlement
Settlement analysis of piles setting on rock is difficult and frequently
unreliable because of discontinuities inherent in bedrockstratification.
In general settlements in sound rocks are minimal and many times it
is negligible due to their high elasticity modules. An attempt to
calculate maximum total immediate settlement is presented in the
attached calculation sheet 3. Calculations based upon the assumption
that the bearing strata are behaving as an elastic body.
-
7/30/2019 5351txt
9/10
5
11. Findings
Drilling proved that water table is encountered from (1.5-1.7)meter below the present ground level (0.00) assumedcenter of the asphalt pavement level.
Overburden deposits are composed of cohesionless soilwith thickness of (10.5) meters.Cohesionless soil deposits are not adequate to bear theproposed load.
Bedrock strata that exist at 11.5 meter deep below thepresent ground level (0.00) assumed center of the asphalt
pavement level. form an adequate bearing foundation.
Chemical tests proved that site materials are within class2 of the British Building Research Establishment
12. Recommendations
The followings are recommended in the light of our findings:
Piles are of cast in place board piles.Piles are to be erected at depth of 11.5 meters below thepresent ground level (0.00) assumed center of the asphalt
pavement level
Pile socket length in bedrock is 1.0 meter.The boundary wall foundation & the connected one story
buildings (Guard & Electric rooms) are to be erected as stripshallow foundation at depth of 1.0 m below the present ground
level (0.00) assumed center of the asphalt pavement level with
allowable bearing capacity of not more than 0.5 kg/cm
Or simply attached to adjacent piles
Values of the allowable safe pile load in KN versus pilediameter in meters are shown in tables and curves at the
attached calculation sheets.
Sulfate resisting Portland cement (SRPC) should be usedin pile concrete.
Pile load tests should be carried out to ensure the above-mentioned parameters.
-
7/30/2019 5351txt
10/10
6
13. General Precautionary Measures
The following precautionary measures should be considered duringbored pile construction.
Inspection of the bottom of each pile shaft to eliminate thepresence of debris between the bottom of the concrete
shaft and rock surface.
Borehole bottom should be properly cleaned to preventoccurrence of large settlement during bearing capacity
mobilization, due to the compression of the remain mud in
the bottom of the socket.
Controlling ground water flow during pile shaft boring toavoid loss of ground and potential long term undermining
of floor areas.
Ready mix concrete discharge pipe should not be pulledout of the concrete during placing, so that some of the
concrete flows through water. These form a layer or a
pocket of sand and gravel and a concentration of cement
or laitance at cut-off level.
The temporary liner should not be withdrawn too fastcausing soil to intrude in the concrete section (necking).
The temporary liner should not be allowed to becomestuck and to be withdrawn after partial set of concrete has
taken place, causing cracking of the shaft.