4.2 Risk Register

2
Status Active Impacted Managed Open Proposed Rejected Risk ID Impact Scale 1~4 Likelihood Scale 1~4 Risk Level IxL Next action due date Risk Owner Status Last updated RIBEX01 4 4 16 NAHEEL / ALG Active 24Aug14 RIBEX02 4 4 16 NAKHEEL/PIC Managed 18Feb14 RIBEX03 4 4 16 ALG Impacted 31Aug14 RIBEX04 4 4 16 ALG Impacted 24Aug14 RIBEX05 4 4 16 ALG / PIC / CON Managed 31Aug14 RIBEX06 4 4 16 NAKHEEL/ALG Managed 31Jan14 RIBEX07 4 4 16 ALG / PIC / CON Impacted 31Aug14 RIBEX08 3 4 12 ALG Managed 31Jul14 RIBEX08 4 4 16 ALG Managed 31Aug14 RIBEX09 4 4 16 NAKHEEL/ALG Managed 31Aug14 Impact Scale : 1Low 2. Medium 3. High 4. Very High Likeelihood Scale : 1Low 2. Medium 3. High 4. Very High Risk Level : 04 Low 58 Medium 912 High 1316 Very High LEGENDS Risk Definition Possible out Comes / Situation Revised Building Permit has been issued on 09Aug14. Still release of Building Permit for C2 is awaited Application for COC1 was submitted on 02Feb14 and was inspected and approved on 18Feb14 Design NOCs (DEWA, Du / Etisalat, RTA, Nakheel, Tarkhess, EHS….etc) Delay in Release of IFC Drawings Delay in Release of As Built Drawings of Existing Mall and Services Items to be removed by Mall Management Relocation of Existing MEP Services Delay in Release of Payment # 2 RISK REGISTER Mitigation Ibn Battuta Shopping Mall Expansion Expansion A, B & C IFC Drawings has been issued with Major change in Dimension NOCs for RTA and CCTV is still Awaited. Civil IFC: IFC has been issued on 24Aug14 MEP IFC: ALG has provided MEP IFC drawings for Exp A & Exp B only All IFC drawings ZoneC2 is awaited ALG Provided as built drawings for exisiting services however there is descripency between drawings and actual condition at site 30Apr15 Date Date Early resolution of MEP issues, preperation of Shop Drawings and Approvals will reduce the delay Timely release of Payment will help in ordering Long lead Items and hence reduce the Delays. Since this issue has delayed the project. Therefore, Revised Working Program has been prepared and submitted for Client Review Revised Working Program has been prepared and submitted for Client Review same as RIBEX01 RTA NOC is still awaited. Need to resolved this issue for completion of ZoneC Revised Working Program has been prepared and submitted for Client Review CON / PIC has prepared and submitted shop drawings for relocation. Mall Management has to remove their items also has to provide specific location for storage of items removed by PIC Job No : 131 Monthly Report No. 16 Issuance of Building Permits Issuance of COC1 Will impact the start of Piling works. 1) Chilled Water Pipe: PIC submitted proposal for relocation of Chilled Water Pipes and Valve Chambers. 2) HV Cable in C1: PIC has submitted proposal for rerouting of HV Cable. 3) Water Supply Pipeline Water supply line inside the mall is not sufficient for expansion project/ new water tank. Delay in release of payment can impact the procurement schedule and timely completion of construction works. Change in Dimension of ZoneC Delay in Release of Payment # 3 Delay in release of payment can impact the procurement schedule and timely completion of construction works. Timely release of Payment will help in ordering Long lead Items and hence reduce the Delays.

description

Risk Register

Transcript of 4.2 Risk Register

  • Status

    Active

    Impacted

    Managed

    Open

    Proposed

    Rejected

    RiskID ImpactScale1~4LikelihoodScale1~4

    RiskLevelIxL

    Nextactionduedate RiskOwner Status Lastupdated

    RIBEX01 4 4 16 NAHEEL/ALG Active 24Aug14

    RIBEX02 4 4 16 NAKHEEL/PIC Managed 18Feb14

    RIBEX03 4 4 16 ALG Impacted 31Aug14

    RIBEX04 4 4 16 ALG Impacted 24Aug14

    RIBEX05 4 4 16 ALG/PIC/CON Managed 31Aug14

    RIBEX06 4 4 16 NAKHEEL/ALG Managed 31Jan14

    RIBEX07 4 4 16 ALG/PIC/CON Impacted 31Aug14

    RIBEX08 3 4 12 ALG Managed 31Jul14

    RIBEX08 4 4 16 ALG Managed 31Aug14

    RIBEX09 4 4 16 NAKHEEL/ALG Managed 31Aug14

    ImpactScale:1Low2.Medium3.High4.VeryHigh

    LikeelihoodScale:1Low2.Medium3.High4.VeryHigh

    RiskLevel:04Low58Medium912High1316VeryHigh

    L

    E

    G

    E

    N

    D

    S

    RiskDefinition PossibleoutComes/Situation

    RevisedBuildingPermithasbeenissuedon09Aug14.StillreleaseofBuildingPermitforC2isawaited

    ApplicationforCOC1wassubmittedon02Feb14andwasinspectedandapprovedon18Feb14

    DesignNOCs(DEWA,Du/Etisalat,RTA,Nakheel,Tarkhess,EHS.etc)

    DelayinReleaseofIFCDrawings

    DelayinReleaseofAsBuiltDrawingsofExistingMallandServices

    ItemstoberemovedbyMallManagement

    RelocationofExistingMEPServices

    DelayinReleaseofPayment#2

    RISKREGISTER

    Mitigation

    IbnBattutaShoppingMallExpansionExpansionA,B&C

    IFCDrawingshasbeenissuedwithMajorchangeinDimension

    NOCsforRTAandCCTVisstillAwaited.

    CivilIFC:IFChasbeenissuedon24Aug14MEPIFC:ALGhasprovidedMEPIFCdrawingsforExpA&ExpBonly

    AllIFCdrawingsZoneC2isawaited

    ALGProvidedasbuiltdrawingsforexisitingserviceshoweverthereisdescripencybetweendrawingsandactualconditionatsite

    30Apr15DateDate

    EarlyresolutionofMEPissues,preperationofShopDrawingsandApprovalswillreducethedelay

    TimelyreleaseofPaymentwillhelpinorderingLongleadItemsandhencereducetheDelays.

    Sincethisissuehasdelayedtheproject.Therefore,RevisedWorkingProgramhasbeenpreparedandsubmittedforClientReview

    RevisedWorkingProgramhasbeenpreparedandsubmittedforClientReview

    sameasRIBEX01

    RTANOCisstillawaited.NeedtoresolvedthisissueforcompletionofZoneC

    RevisedWorkingProgramhasbeenpreparedandsubmittedforClientReview

    CON/PIChaspreparedandsubmittedshopdrawingsforrelocation.

    MallManagementhastoremovetheiritemsalsohastoprovidespecificlocationforstorageofitemsremovedbyPIC

    JobNo:131 MonthlyReportNo.16

    IssuanceofBuildingPermits

    IssuanceofCOC1

    WillimpactthestartofPilingworks.

    1)ChilledWaterPipe:PICsubmittedproposalforrelocationofChilledWaterPipesandValveChambers.

    2)HVCableinC1:PIChassubmittedproposalforreroutingofHVCable.

    3)WaterSupplyPipelineWatersupplylineinsidethemallisnotsufficientforexpansionproject/newwatertank.

    Delayinreleaseofpaymentcanimpacttheprocurementscheduleandtimelycompletionofconstructionworks.

    ChangeinDimensionofZoneC

    DelayinReleaseofPayment#3 Delayinreleaseofpaymentcanimpacttheprocurementscheduleandtimelycompletionofconstructionworks.TimelyreleaseofPaymentwillhelpinorderingLongleadItemsandhencereducetheDelays.

  • RIBEX10 4 4 16 ALG Managed 31Aug14

    RIBEX11 4 4 16 ALG/PIC Impacted 30Sep14

    RIBEX12 3 4 12 NAKHEEL/ALG Active 30Sep14

    RIBEX13 3 3 9 NAKHEEL/ALG Active 30Sep14

    RIBEX14 ExtensionofTime(EOT)Claim(Rev02) 3 4 12 NAKHEEL/ALG Active 30Sep14

    RIBEX15 4 3 12 ALG/PIC Managed

    RIBEX16 4 3 12 ALG/PIC Managed

    RIBEX17 4 3 12 ALG/PIC Managed

    RIBEX18 3 3 9 ALG/PIC Managed

    RIBEX19 3 3 9 ALG/PIC Managed

    RIBEX20 3 3 9 ALG/PIC Open

    RIBEX21 3 3 9 ALG/PIC Active

    RIBEX22 3 3 9 ALG/PIC/CON Managed

    RIBEX23 3 3 9 ALG/PIC Active

    RIBEX24 3 3 9 ALG/PIC Active

    RIBEX25 3 3 9 ALG/PIC Active

    RIBEX26 4 4 16 ALG/PIC Active

    RIBEX27 3 3 9 ALG/PIC Proposed

    RIBEX28 3 3 9 PIC/CON Proposed

    RIBEX29 3 3 9 PIC/CON Proposed

    RIBEX30 3 3 9 PIC/CON Proposed

    RIBEX31 3 4 12 PIC/CON Active

    30Sep14

    RIBEX32 3 4 12 PIC/CON Proposed

    Earlydecisionarerequiredtoavoilddelay

    Completion/InspectionofSubstationA

    PIChassubmittedEOTclaims.AwaitingforApproval

    LateconstructioncanleadtodelayinstartofExpC

    SuplierforElevatorsandEscalatorshasbeenfinalizedbyALG.

    LateDecisioncanleadtodelayinprocurementandhencecompletionofproject

    Earlyapprovalisrequiredsopracticalschedulecouldbefollowed.

    NeedtostartconstructionofWaterTankimmediately

    Earlydecisionarerequiredtoavoilddelay

    SincerelocationofExisitingHVcableisrequiredtoproceedforworkthereoreearlyresolutionoftheissueisrequiredtoavoidfurtherdelayinExpC

    SwitchoverfromOldSubstationstoNewSubstation

    Completion/InspectionofSubstationB

    Completion/InspectionofLVRoomC

    LayingofHVCableandinstallationofTransformer

    ApprovalofBaselineProgram

    ConstructionofWaterTank&PumpRoom

    ProvisionalSumElevators&Escalators

    ProvisionalSumLightFittings

    DEWAapprovedDrawingsforSubstationA

    ApprovalofSupplierandMaterialofFAHU

    ApprovalofSubcontractorandMaterialforAluminumWorks

    ApprovalofSupplier/SubconandMaterialsforFireFightingWorks

    ApprovalofSupplier/SubconandMaterialsforFireAlarmSystem

    ApprovalofSupplierandMaterialforLPGWorks

    MaterialforFlooring

    DEWAapprovedDrawingsforSubstationB

    DEWAapprovedDrawingsforLVRoomC

    ApprovalofSubContractors&DesignofPileWorks

    ApprovalofSubContractors&DesignofPrecastSlabsA&B

    PrecastBeamsandSlabforExpC

    ApprovalofSubContractors&DesignofSteeelstructure

    Lateapprovalwillleadtoambiguousdatesforactivities. ALG&NakheelhastoreviewClaimsatearliestsoPICwouldbeablereviseBaselineprogramasperapproval