400kV Circuit Breaker_O&M

109
OPERATION & MAINTENANCE MANUAL FOR 400kV CIRCUIT BREAKER JINDAL INDIA THERMAL POWER LIMITED (2 x 600MW THERMAL POWER PROJECT) DOC. No. - SIEM-JITPL.5404A-EL-3-2112 400kV Circuit Breaker Date 23.06.2011 Page 1 of 109 Project JINDAL INDIA THERMAL POWER LIMITED (2 x 600 MW THERMAL POWER PROJECT) O&M Consultant TATA CONSULTING ENGINEERS OPERATION & MAINTENANCE MANUAL FOR 400kV CIRCUIT BREAKER Owner JINDAL INDIA THERMAL POWER LIMITED Project 2 x 600 MW THERMAL POWER PROJECT Consultant TATA CONSULTING ENGINEERS Document Type O & M Manual (Information Only) Document Number Document Name 400kV Circuit Breaker - Manual SIEM-JITPL.5404A-EL-3-2112 Siemens Limited, Aurangabad. Copyright© Siemens Ltd 2007. The reproduction, transmission or use of this document or its contents is not permitted without express written au- thority. Offenders will be liable for damages. All rights, including rights created by patent grant or registration of a utility model or design, are reserved.

Transcript of 400kV Circuit Breaker_O&M

Page 1: 400kV Circuit Breaker_O&M

OPERATION & MAINTENANCE MANUAL FOR

400kV CIRCUIT BREAKER JINDAL INDIA THERMAL POWER LIMITED (2 x 600MW THERMAL POWER PROJECT)

DOC. No. - SIEM-JITPL.5404A-EL-3-2112 400kV Circuit Breaker Date 23.06.2011 Page 1 of 109 Project JINDAL INDIA THERMAL POWER LIMITED

(2 x 600 MW THERMAL POWER PROJECT) O&M Consultant TATA CONSULTING ENGINEERS

OPERATION & MAINTENANCE MANUAL FOR 400kV CIRCUIT BREAKER

Owner JINDAL INDIA THERMAL POWER LIMITED

Project

2 x 600 MW THERMAL POWER PROJECT

Consultant TATA CONSULTING ENGINEERS

Document Type

O & M Manual (Information Only) Document Number

Document Name

400kV Circuit Breaker - Manual SIEM-JITPL.5404A-EL-3-2112

Siemens Limited, Aurangabad.

Copyright© Siemens Ltd 2007. The reproduction, transmission or use of this document or its contents is not permitted without express written au-thority. Offenders will be liable for damages. All rights, including rights created by patent grant or registration of a utility model or design, are reserved.

Page 2: 400kV Circuit Breaker_O&M

1

s

Operating Instructions Circuit-Breaker 3AP2 Fl

for rated voltage 420 kV

1003006a

Siemens Ltd. © Siemens Ltd 2007

Page 3: 400kV Circuit Breaker_O&M

2

The Siemens Ltd, Power Transmission and Distribution Group, High Voltage Division has introduced and appiies a quality system in accordance with EN ISO 9001. If you require further copies of the operating instructions, please order them from the appropriate Siemens office, indicating the title and order number: Published by: Siemens Ltd. Power Transmission and Distribution High Voltage E-76. Waluj MIDC Aurangabad 431136 Tel.: +91 240-2554008 Fax: +91 240-2554701 Subject to change. All rights, including rights of translation, reproduction by printing, copying or similar methods, even of parts are reserved. Offenders will be liable for damages.

Page 4: 400kV Circuit Breaker_O&M

3

1 Contents

1 Contents 2 General 72.1 Introduction 72.1.1 Arrangement of the Operating Instructions 7

2.1.2 Communication by Means of the Operating Instructions 7

2.2 Safety Instructions 8

3 Description 11

3.1 Technical Data 113.1.1 Standards, Regulations 113.1.2 Operating Temperatures 113.1.3 Insulation Rating 123.1.4 Electrical Data 123.1.5 Operating Times 133.1.6 Arc Quenching Medium SF6 143.1.7 Auxiliary Switch 143.1.8 Anti-Condensation Heaters 153.1.9 Reference Contact IK-3 153.1.10 Further Technical Data 153.2 Circuit-Breaker 163.3 Pole Column 183.4 Interrupter Unit 203.5 Arc Quenching 223.6 Spring Drive Mechanism of the Circuit- Breaker 24

3.6.1 Charging the Closing Spring 243.6.2 Closing 243.6.3 Opening 253.6.4 Operating Sequence 253.7 Function of the Spring Drive Mechanism 263.7.1 Charging the Closing Spring 263.7.2 Closing 293.7.3 Tripping 343.8 Control 353.8.1 Spring Winding Mechanism 363.8.2 Gas Monitoring 363.8.3 Lockouts 393.8.4 Motor Control 393.8.5 Anti-Condensation Heaters 393.8.6 Signals 393.8.7 Free Auxiliary Switch Contacts 403.8.8 Operating Cycle Counter 403.9 Reference Contact IK-3 413.9.1 Introduction 41

Page 5: 400kV Circuit Breaker_O&M

4

1 Contents

4 Installation 434.1 Safety Rules for Installation 43

4.2 Delivery and Storage 464.2.1 Packing 464.2.2 Checking on Arrival 464.2.3 Storage 464.3 Cleaning Liquids, Lubricants and Corrosion Protection Agents 48

4.3.1 Cleaning Liquids 484.3.2 Lubricants and Corrosion Protection Agents 49

4.4 General Instructions for Installation 504.5 Installation of the Circuit-Breaker 514.5.1 Requirements for Assembly 514.5.2 Assembly on Supporting Pillars at the Place of Installation 51

4.5.3 Assembly Overview 524.5.4 Disassembling the Insulator Column Kit 524.5.5 Assembly of the Control Cubicle 554.5.6 Assembly of the Operating Mechanism Cubicles 56

4.5.7 Assembling the Insulator Column 574.5.8 Erecting the Double-Break Assembly 624.5.9 Lifting Plate 684.5.10 Coupling the Operating Mechanism 694.5.11 Connecting the Gas Pipes 704.6 Earthing and Connecting the Leads 724.6.1 Earthing 724.6.2 Work on High-Voltage Terminals 72

4.6.3 Connecting the Leads 73

4.7 Filling the Circuit-Breaker with Gas 744.7.1 Evacuating 744.7.2 Filling the Breaker from the Gas Cylinder 744.7.3 Leakage Test after Installation 764.8 Carrying Out Test Operations 774.9 Checks before Commissioning 794.9.1 Anti-Condensation Heaters 794.9.2 Test of Wiring between Substation and Circuit-Breaker 79

4.9.3 Commissioning Report 79

5 Operation 81

5.1 Instructions for Operation 815.1.1 Closing and Opening 815.1.2 SF6 Pressure 815.1.3 General Lockout 82

Page 6: 400kV Circuit Breaker_O&M

5

1211

1 Contents 5.1.4 Mechanical Reclosing Lockout 825.1.5 Max. Permissible Number of Interruptions 82

5.1.6 Recommended Procedure in the Event of Irregularities on the Circuit-Breaker 3AP2 Fl

85

5.2 Disposing of High-Voltage Switching Devices and Systems 87

6 Maintenance 896.1 Inspection and Maintenance - General 896.1.1 Maintenance Services (Schedule) 896.1.2 Assignment of Personnel 906.1.3 Maintenance Kits 906.1.4 Initial Date for Inspection and Maintenance Service 90

6.1.5 Disturbances 916.1.6 Points to be Noted 916.2 Safety Rules for Inspection and Maintenance Service - General 92

6.3 Maintenance Schedule 966.4 Work to be Carried Out in Accordance with the Maintenance Schedule 98

6.4.1 General Inspection 986.4.2 Drawing Off the SF6 Gas 986.4.3 Check of Contact System 996.4.4 Evacuating and Filling the Circuit-Breaker with Gas 100

6.4.5 Check Gas Pressure Gauge 1036.4.6 Testing the Density Monitor 1036.4.7 Check for Leaks on Operational Circuit- Breaker 104

6.4.8 Checks at Drive Mechanism 1056.4.9 Terminal Strip 1076.4.10 Anti-Condensation Heaters 1076.4.11 Function Checks 1076.4.12 Check of Motor Control 1086.4.13 Measuring the SF6 Gas Humidity Content 1086.4.14 Measuring the SF6 Air Content 1086.4.15 Anti-Corrosion Protection 1096.4.16 Special Occurrences 109 Commissioning Report for the Circuit-Breaker 3AP 111

Function Diagram of Spring Drive Mechanism 119

1 Contents

Page 7: 400kV Circuit Breaker_O&M

6

2 General

2 General

2.1 Introduction

These operating instructions apply to high-voltage circuit-breakers with the serial numbers given on the title page. They are intended to familiarize operating personnel with the design and functioning of the circuit-breaker. They also supply details of operation and provide information on installation and maintenance.

All values of pressure given are gauge values unless absolute pressure is expressly stated.

It is advisable for the operating personnel to familiarize themselves as early as possible with the instructions, and with the aid of other documents supplied to gather any relevant further information on the circuit-breaker and its features.

Note

The operating instructions contain information on proper operation and maintenance of the circuit-breaker, together with certain supplementary warning notices. They are intended to point out impermissible actions and to show the potential danger associated with operation of the circuit-breaker.

Should further information be desired or should particular problems arise which are not covered sufficiently in the operating instructions, the matter should be referred to the local Siemens sales office.

2.1.1 Arrangement of the Operating Instructions These operating instructions are divided into chapters 1- Contents, 2- General, 3- Description, 4- Installation, 5- Operation and 6- Maintenance.

2.1.2 Communication by Means of the Operating Instructions In verbal or written communication, as well as when ordering any spare parts required, please use the des-ignations and part numbers used in the operating instructions, giving details of the order number of the operating instructions 927 00966 174 A, the page number and specifying the number of the illustration (Fig.). In this way, misunderstandings can be prevented.

Page 8: 400kV Circuit Breaker_O&M

7

2 General

2.2 Safety Instructions

During operation, certain parts of the circuit-breaker are live and hazardous voltages therefore present. Certain parts are also under gas pressure (SF6).

In its pure state, sulphur hexafluoride (SF6) is a colourless, odourless, tasteless, non-toxic and non-flammable gas, inactive like nitrogen. SF6 is safe if there is adequate oxygen present in inhaled air. SF6 constitutes no danger to the ecosystem.

Personnel must be thoroughly familiar with all warnings and procedures for installation, operation, maintenance and repair contained in these operating instructions.

WARNING Non-observance of warnings can result in death, severe personal injury and substantial property and environmental damage.

The user of the circuit-breaker must ensure that the installation, maintenance and relevant operating direc-tives to the appropriate activity, local safety regulations and information on what to do in the event of an acci-dent are available or displayed, e.g. on a notice board so that they can be referred to at any time. Additionally to the safety rules valid in the country in question a few precautionary measures and points to be noted are listed below: - The accessory items required for installation, operation and maintenance of the circuit-breaker and for

reasons of safety (protecting clothes, devices for manual operation, warning signs, hand lamps, fire extinguishers etc.) must be stored neatly at a certain point and be checked regularly for completeness and proper functioning. This also includes the complete operating instructions.

- The specified maintenance intervals and the instructions for repair and replacement must be adhered to. - Detailed warning references describing the secure execution of dangerous work are included in the

particular sections of the operating instructions. They are highlighted by frames, bold lettering and/or other means.

WARNING in the sense of these operating instructions means that death, severe personal injury or substantial property and environmental damage may occur if appropriate safety measures are not taken.

Attention in the sense of these operating instructions means that light personal injury or property/environmental damage may occur if appropriate safety measures are not taken.

Note Note in the sense of these operating instructions means information to simplify and improve the handling of the circuit-breaker. They are based on the experiences of Siemens staff.

Page 9: 400kV Circuit Breaker_O&M

8

3 Description 3 Description

3.1 Technical Data

The 3AP2 Fl circuit-breaker is of the self-compression type and uses SF6-gas for insulation and arc-quench-ing purposes. It is of triple-pole outdoor design.

The circuit-breaker is equipped with one operating mechanism per pole and therefore suitable for single and triple pole auto reclosing.

3.1.1 Standards, Regulations

The circuit-breaker, together with the equipment and special tools supplied, is in conformity with the statutory laws, rules and standards applying at the time of delivery.

- The specifications in IEC Publications 62271-100.

- The specifications in lEC-Publications 60694.

3.1.2 Operating Temperatures

The circuit-breakers are designed for operation in an ambient temperature range from -25°C to 45°C.

Page 10: 400kV Circuit Breaker_O&M

9

3 Description 3.1.3 Insulation Rating

Rated voltage 420 kV

Rated short-duration power-frequency withstand voltage

to earth 520 kV

across the open circuit-breaker 610 kV

between phases 520 kV

Rated lightning impulse withstand voltage

to earth 1425 kV

across the open circuit-breaker 1425 kV

between phases 1425 kV

Impulse against power frequency voltage

1425 kV +240 kV

Rated switching impulse withstand voltage

to earth 1050 kV

across the open circuit-breaker 1050 kV

between phases 1575 kV

Impulse against power frequency voltage

900 kV + 345 kV

Flashover distance in air to earth 3180 mm

across the open circuit-breaker 3200 mm

between phases see dimension drawing

Minimum creepage distance over the insulators' surfaces

to earth 10050 mm

across the open circuit-breaker 10500 mm

Table 1 Insulation rating 3.1.4 Electrical Data

Rated voltage 420 kV

Rated frequency 50 Hz

Rated normal current 3150 A

Rated short-circuit breaking current 50 kA

Rated line-charging breaking current (1.4 p.u.)

600 A

Rated cable-charging breaking current (1.4 p.u.)

400 A

Transient recovery voltage under terminal fault conditions

ace. to IEC

Rated short-circuit making current 135kA

Rated short-circuit duration 3s

Rated operating sequence O-0,3s-CO-3min-CO

Table 2 Electrical data

Page 11: 400kV Circuit Breaker_O&M

10

3 Description 3.1.5 Operating Times

Minimum command duration (Closing com-mand)

80 ms

Minimum command duration (Opening command)

80 ms

Closing time 65 ms + 6 ms Opening time 23 ms + 3 ms Rated break time <40 ms Close-open-time 60 ms + 10 ms Dead time 300 ms Table 3 Operating times

Page 12: 400kV Circuit Breaker_O&M

3 Description 3.1.6 Arc Quenching Medium SF6

a SF6-filling gauge pressure (nominal density line) b Signal Loss of SF6c General lockout SF6e Liquefaction curve Fig. 1 SF6-filling and operating values of density

monitor (gauge pressure)

Filling weight (complete circuit-breaker) 44.6 kg Volume (complete circuit-breaker) 966 dm3 SF6 nominal filling gauge pressure at +20°C 6.0 bar

Monitoring of the SF6

Signal Loss ofSF6 at 20°C

General lockout SF6 at 20°C

5.2 bar 5.0 bar

Filter material (complete circuit-breaker) 7.5 kg Table 4 Arc quenching medium SF6

3.1.7. Auxiliary Switch

Rated voltage 250 VDC 220 VDC 125VDC 110VDC 60VDC 48VDC

Rated normal current 10A 10A 10A 10A 10A 10A Switching capacity Resistive load 2.5 A 2.5 A 4A 5A 9A 10A Resistive-inductive load (time constant x = 20 ms)

1,2 A 2A 2.5 A 4A 7A 9A

Table 5 Auxiliary switch

Auxiliary switch contact class 1

11

Page 13: 400kV Circuit Breaker_O&M

12

3 Description

3.1.8 Anti-Condensation Heaters Control cubicle 90 W

Operating mechanism 210 W Table 6 Anti-condensation heaters

The anti-condensation heaters must always be switched on. 3.1.9 Reference Contact IK-3

Principle Fixed Hall sensor and moving magnet

Hall sensor HE-6103

Magnet HE-6104

Supply voltage 24VDC

Operating tempera-ture

-40°C ... +85°C

Output 4...20 mA, CLOSE: >18 mA, OPEN: <6 mA

Resolution <0,2 ms

Transmission Current loop, max. 500 m Table 7 Technical Data IK-3 3.1.10 Further Technical Data

Note Technical Data for

- Trip voltage - Control voltage - Heater voltage - Pressure monitoring for SF6 - Charging motor of the spring drive mecha-

nism are indicated in the circuit diagram.

Note Technical Data for - Circuit-breaker weights - the permitted cable pull F are indicated in the dimension drawing.

Page 14: 400kV Circuit Breaker_O&M

3 Description

3.2 Circuit-Breaker

The pole columns of the circuit-breaker are each mounted on a base 11, to the side of each of which an operating mechanism cubicle 15.1 is fitted.

The insulator columns are assembled from several multished insulators and each of them supports an double break interrupter assembly consisting of two interrupter units 22 with grading capacitors 23 connected in parallel and a bell-crank mechanism 21.

Control cabinet 12 is also located at pole B.

15.112

21

11 Base 12 Control cubicle 15.1 Operating mechanism cubicle 16 Post insulator 21 Bell-crank mechanism 22 Interrupter unit Fig. 2 Design of the circuit-breaker 3AP2 Fl

1003000a

13

Page 15: 400kV Circuit Breaker_O&M

14

3 Description

The two interrupter units provide a double-break feature per pole, the grading capacitors ensuring uniform voltage distribution.

The double break assembly and the insulator column are filled with SF6 for arc-quenching and insulating purposes.

The density of the SF6 gas for each circuit-breaker pole is monitored by a density monitor and the gas pressure indicated by a manometer.

The energy required for switching is stored in one closing spring and one opening spring. The closing and opening springs are located in the operating mechanism unit.

Control cabinet 12, which is attached to circuit-breaker pole B, contains the equipment for controlling and mon-itoring the circuit-breaker and the terminal blocks required for the electrical connection. SF6 gas is monitored single-poled in the operating mechanism cabinet.

There are cables for electrical coupling of the control with the three operating mechanism.

Page 16: 400kV Circuit Breaker_O&M

3 Description

3.3 Pole Column

The circuit-breaker's three pole columns are of identical design. Fig. 3 shows a cross-section of a pole column. The double break assembly unit is mounted on post insulators which provide insulation against earth.

22.22 15.16.3

15.11

15.9 15

15.8.315 Corner gear 15.11 Filter cowl 15.16.3 Filter bag 15.8.3 Shaft 15.9 Lever 16 Post insulator 16.9 Operating rod 18.27.1 Driving rod 21 Bell-crank mechanism 22 Interrupter unit 22.1 Jacket 22.22 High-voltage terminal Fig. 3 Sectional view of pole column

15

Page 17: 400kV Circuit Breaker_O&M

16

3 Description

The switching operation is transmitted to the interrupter units 22 (high-voltage potential) by the spring drive mechanism (ground potential) via an operating mechanism rod 18.27.1, the shaft 15.8.3, the operating rod 16.9 and the bell-crenk mechanism 21.

The filter cowls 15.11 contains the filter material 15.16.3 which collects SF6 decompositon products and moisture residue.

22

23.223.1

1001360a 22 Interrupter unit 23 Grading capacitor 23.1 Inner bracket 23.2 Outer bracket Fig. 4 Arrangement of grading capacitor

Page 18: 400kV Circuit Breaker_O&M

3 Description

3.4 Interrupter Unit

Fig. 5 shows a sectional view of an interrupter unit. The breaker contacts are accommodated in the gas-tight porcelain jacket 22.1.

15.11 Filter cowl 16.9 Operating rod 21.1 Gear unit housing 22.1 Jacket 22.11 Tube contact 22.11.1 Nozzle 22.11.17 Piston 22.11.18 Valve plate 22.11.19 Valve group 22.11.2 Auxiliary nozzle 22.17.1 Pull rod 22.17.2 Coupling rod 22.22 High-voltage terminal 22.23 Inner socket 22.29 Sealing ring 22.3 Contact laminations 22.31 Contact carrier 22.32 Base 22.35 Cover 22.4 Tandem gear 22.41 Heat cylinder 22.45 Electrode 22.5 Guide rail 22.52 Pin 22.9 Pin Fig. 5 Interrupter unit

The main circuit of an interrupter unit consists of the high-voltage terminal 22.22, the socket 22.32, the contact carrier 22.31, the contact laminations 22.3 arranged in rings in the contact carrier, the heat cylinder 22.41, the inner socket 22.23 and the gearbox 21.1.

The contact laminations 22.3 support themselves centrically from the contact carrier 22.31 inwards to the heating cylinder 22.41. The internal stress of the contact laminations 22.3 generates the necessary contact pressure from the contact carrier 22.31 onto the heating cylinder 22.41.

17

Page 19: 400kV Circuit Breaker_O&M

18

3 Description

Parallel to the main circuit is the arcing circuit, which is made up of the movable pin 22.9 in the contact carrier 22.31 and the moving tube contact 22.11 situated in the heating cylinder 22.41.

The pin 22.9 and the tube contact 22.11 are made of materials which produce only minimal contact erosion.

The tube contact 22.11, the piston 22.11.17 and the heat cylinder 22.41 are mechanically interconnected and coupled with the pull rod 22.17.1. They form the moving part of the interrupter unit.

A guide rail 22.5 is mounted at the nozzle 22.11.1. This engages with the control lever 22.46 via the pin 22.52. As a result, the control lever is subjected to rotary movement, causing linear movement of the pin against the direction of movement of the nozzle. The electrode 22.45 is connected to the nozzle via the gears using two connecting rods and provides the pin with dielectric shielding.

The rear side of the piston 22.11.17 is equipped with a valve plate 22.11.18 which together with the valve group 22.11.19 makes up the compression unit for arc quenching.

The breaking process in the interrupter unit is described in a schematic diagram in the section 3.5 Arc Quenching.

Page 20: 400kV Circuit Breaker_O&M

3 Description

3.5 Arc Quenching

In an opening operation, the main contact that exists between the contact laminations 22.3 and the heat cylinder 22.41 is opened (Fig. 6, position b). The arcing contact, consisting of the pin 22.9 and the tube contact 22.11 remains closed, with the result that the current commutates onto the arcing contact.

22.11.19 KV 22.11.18 22.41 22.11 22.5 22.52

19

a)

22.11.17 HV 22.11.2 22.3 22.11.1 22.9 22.51 22.46 22.56

b)

C)

d) a) CLOSED position b) Opening: main contact in OPEN position c) Opening: arcing contact in OPEN position d) OPEN position HV Heating volume KV Compression volume 22.11 Tube contact 22.11.1 Nozzle 22.11.17 Piston 22.11.18 Valve plate 22.11.19 Valve group 22.11.2 Auxiliary nozzle 22.3 Contact lamination 22.41 Heat cylinder 22.46 Cam lever 22.5 Guide rail 22.51 Coupler 22.52 Pin 22.56 Lever 22.9 Pin (moving) Fig. 6 Schematics of opening operation

Page 21: 400kV Circuit Breaker_O&M

20

3 Description

The pin (moving) 22.9 is moved against the direction of movement of the tube contact 22.11 by the connected components of heating cylinder 22.41, nozzle 22.11.1, connecting rod 22.51, pin 22.52, control lever 22.46 (circuit-breaker opening movement).

The moved electrode 22.45 is also pushed in the direction of the heating cylinder 22.41.

During the continued course of the opening operation, the arcing contact opens, creating an arc (Fig. 6c). At the same time, the heat cylinder 22.41 moves to the left and compresses the quenching gas between piston 22.11.17 and valve group 22.11.19. This causes the quenching gas to be forced in the direction opposite to the movement of the moving contact components through the non-return valve, consisting of piston 22.11.17 and valve plate 22.11.18, into the heat cylinder and through the gap between the tube contact 22.11 and the arc quenching nozzle, thus quenching the arc.

With large short-circuit currents the quenching gas surrounding pin 22.9 in the arcing chamber is heated by the arc's energy and driven into the heat cylinder 22.41 at high pressure. When the current passes through zero, the gas flows back from the heat cylinder into the nozzle and quenches the arc. When this happens, the valve plate 22.11.18 in the heat cylinder 22.41 prevents the high pressure from entering the compression chamber between piston 22.11.17 and the valve group 22.11.19.

Page 22: 400kV Circuit Breaker_O&M

21

3 Description

3.6 Spring Drive Mechanism of the Circuit-Breaker

This section contains a general presentation of the spring drive mechanism; see the 3D illustration on the foldout page at the end of these operating instructions. Its function is described in section 3.7 Function of the Spring Drive Mechanism.

3.6.1 Charging the Closing Spring

Circuit-breaker in OPEN position

The closing spring 18.4 (see 3D illustration at the end of these operating instructions) is charged by the charging gears 18.2 using the motor 18.1 byway of the charging shaft 18.14 and connecting rod 18.10. At the end of the charging operation, the charging shaft is separated from the gears by the free-wheel 18.3 and secured with the CLOSE latch 18.17. The closing spring 18.4 is now charged for the closing operation and the circuit-breaker is therefore ready for closing.

3.6.2 Closing

The closing latch 18.17 is released by actuation of the trip coil 18.16. The energy of the discharging closing spring 18.4 is transmitted via the cam plate 18.6 to the lever 18.7 and the operating shaft 18.22 connected to it. In the process, the opening spring 18.11 is charged by means of the rotation of the operating shaft 18.22, the operating lever 18.24 and the connecting rod 18.27. The movement of the connecting rod 18.27 along the operating mechanism rod 15.9.1, the torque shaft 15.8 and the operating rod 16.9 is transmitted to the centre interrupter unit 22. At the same time, the contacts of the interrupter units 22 are closed.

On completion of the closing operation, the residual kinetic energy is absorbed by closing damper 18.41. Cam 18.19 and roller 18.41.1 prevent backward swinging of charging shaft 18.14.

Lever 18.7 is simultaneously engaged with OPEN latch 18.9. The pole is now in a CLOSED position and can thus be switched off.

The closing spring 18.4 is then completely recharged in less than 15 s. A mechanical lockout prevents switching back on of the operating mechanism before the opening operation.

Page 23: 400kV Circuit Breaker_O&M

22

3 Description

3.6.3 Opening

Actuating tripping coil 18.8 releases OPEN latch 18.9. The contacts of interrupter unit 22 are separated by opening spring 18.11 via connecting rod 18.27, operating lever 18.24, operating mechanism rod 18.27.1, lever 15.9, torque shaft 15.8.3 and operating rod 16.9. The kinetic energy at the end of the opening cycle will thereby be absorbed by opening damper 18.15. Opening damper 18.15 simultaneously serves as an end stop for the opening cycle.

3.6.4 Operating Sequence

In the closed position of the circuit-breaker, the opening and closing spring are in charged state. This means the circuit-breaker is in a position to perform O-C-0 switching sequences.

Page 24: 400kV Circuit Breaker_O&M

23

3 Description

3.7 Function of the Spring Drive Mechanism

The function of the spring drive mechanism is described below in conjunction with the major modular assemblies.

It is advisable first to read the section 3.6 Spring Drive Mechanism of the Circuit-Breaker.

3.7.1 Charging the Closing Spring

Starting position: the circuit-breaker is in the OPEN position. The closing and opening spring are relaxed, i.e. a switching operation is not possible.

The cam disc 18.6 and the connecting rod 18.10 are near the lower dead centre point. The guide lever 18.7 and operating lever 18.24 are rigidly connected and are in the OPEN position (Fig. 7).

To charge the closing spring, the charging shaft 18.14 is rotated by means of the charging motor 18.1 and gears 18.2. The free-wheel 18.3 engages in the cam of the charging shaft 18.14 (Fig. 8) and rotates it as far as the upper dead centre point.

The charging shaft 18.14 is then turned as far as the closing latch 18.17 more quickly by the effect of the partly relaxed closing spring 18.4 than by the freewheel, i.e. the form-fit between the free-wheel of the charging gear and the charging shaft is cancelled and the charging shaft outpaces the charging gear. Before the cam plate 18.6 is stopped in the position 10° beyond the upper dead centre by means of the roller 18.23 and the closing latch 18.17 (Fig. 9), the cam 18.19 fixed to the mechanism housing disengages the free-wheel 18.3 from the charging shaft 18.14 (Fig. 10). Charging shaft 18.14 and gear 18.2 are thereby separated. The motor is shut down automatically and runs down with the gearing.

The closing spring is charged and the operating mechanism ready for the closing process.

Page 25: 400kV Circuit Breaker_O&M

24

3 Description

18.10 Connecting rod (for closing spring) 18.11 Opening spring 18.14 Charging shaft 18.15 Damper for opening 18.16 Release CLOSE 18.17 Closing latch 18.17.1 Support lever 18.19 Cam 18.22 Operating shaft 18.23 Roller 18.24 Operating lever 18.27 Connecting rod (for opening spring) 18.27.1 Driving rod 18.31 Mechanical closing interlock 18.4 Closing spring 18.4.1 Spring washer 18.41 Damper for closing 18.41.1 Roller 18.6 Cam disc 18.7 Lever 18.7.1 Roller 18.8 Release OPEN 18.9 Opening latch 18.9.1 Supporting latch 18.9.2 Support lever 22 Interrupter unit

Fig. 7 Function diagram of closing and opening latching:

OPEN position, closing and opening spring relaxed

Page 26: 400kV Circuit Breaker_O&M

25

3 Description

18.20

18.14

18.2 18.1

18.3

1000661a 18.1 Motor 18.14 Charging shaft 18.2 Charging gear 18.20 Cam 18.3 Free-wheel Fig. 8 Function of the free-wheel: Charging of the closing

spring

18.4

1000810a 18.14 Charging shaft 18.17 Closing latch 18.23 Roller 18.31 Mechanical closing interlock 18.4 Closing spring 18.6 Cam disc Fig. 9 Function diagram of closing and opening latching:

OPEN position, closing spring charged

Page 27: 400kV Circuit Breaker_O&M

3 Description

26

18.14 Charging shaft 18.2 Charging gear 18.20 Cam 18.3 Free-wheel Fig. 10 Function of the free-wheel: Uncoupling the charging

gear

3.7.2 Closing

Actuating CLOSE tripping coil 18.16 releases cam disk 18.6 via CLOSE latch 18.17 and supporting lever 18.17.1 (Fig. 11).

18.16

18.17.1

18.23 18.17

18.6

1000813a 18.16 Release CLOSE 18.17 Closing latch 18.17.1 Support lever 18.23 Roller 18.6 Cam disc Fig. 11 Function diagram of closing and opening latching:

Disenagement of the closing latch

Page 28: 400kV Circuit Breaker_O&M

3 Description

The effect of the closing spring turns the charging shaft 18.14 (Fig. 12). The roller 18.7.1 of the lever 18.7 moves along the cam 18.6 and transmits the movement to the operating shaft 18.22. The movement is then transmitted by the lever 18.24 (fixed to the operating shaft 18.22) and the operating mechanism rod 18.27.1 to the interrupter unit 22. The contacts of the interrupter unit 22 are closed.

18.11 Opening spring 18.14 Charging shaft 18.22 Operating shaft 18.24 Operating lever 18.27 Connecting rod (for opening spring) 18.27.1 Driving rod 18.6 Cam disc 18.7 Lever 18.7.1 Roller 18.9 Opening latch 18.9.1 Supporting latch 22 Interrupter unit Fig. 12 Function diagram of closing and opening latching:

Closing

27

Page 29: 400kV Circuit Breaker_O&M

28

3 Description

At the same time the opening spring 18.11 is charged by way of the operating lever 18.24 and the connecting rod 18.27. The opening latch 18.9 moves along the roller of the latch lever 18.9.1 (Fig. 12). At the end of the curve, the lever 18.7 overtravels, with the result that the opening latch 18.9 can drop behind the roller of the latch lever 18.9.1 (Fig. 13). 18.19 Cam 18.41 Damper for closing 18.41.1 Roller 18.6 Cam disc 18.7 Lever 18.7.1 Roller 18.9 Opening latch 18.9.1 Supporting latch Fig. 13 Function diagram of closing and opening latching:

Overtravel of the lever

Page 30: 400kV Circuit Breaker_O&M

3 Description

On completion of the closing cycle, cam 18.19 will run on roller 18.141.1 and transfer its residual kinetic energy to damper for closing 18.41 (Fig. 13). Following this, roller 18.41.1 will jump behind cam 18.19 to prevent backward swinging of charging shaft 18.14 (Fig. 15).

After leaving the cam disc 18.6, the lever 18.7 turns back a little towards OPEN, until the opening latch 18.9 is resting on the roller of the supporting latch 18.9.1 (Fig. 14). The circuit-breaker is now latched in the CLOSED position.

18.19 Cam 18.41.1 Roller 18.6 Cam disc 18.7 Lever 18.9 Opening latch 18.9.1 Supporting latch Fig. 14 Function diagram of closing and opening latching:

Latching in the closed position

29

Page 31: 400kV Circuit Breaker_O&M

30

3 Description 18.14 Charging shaft 18.15 Damper for opening 18.17 Closing latch 18.17.1 Support lever 18.31 Mechanical closing interlock 18.4 Closing spring Fig. 15 Function diagram of closing and opening latching:

Latching of the charged closing spring

As the closing process takes place, the charging motor is switched on. The charging of the closing spring is repeated according to paragraph 3.7.1 Charging the Closing Spring.

Subsequently the charging shaft must be latched to top dead centre with the charged closing spring (Fig. 15). Mechanical closing lock-out 18.31 prevents unintentional starting of the operating mechanism before the opening cycle by blocking supporting lever 18.17.1 (see Fig. 15).

The closing and opening springs are charged and the circuit-breaker is consequently ready for an O-C-0 switching sequence.

Page 32: 400kV Circuit Breaker_O&M

3 Description

3.7.3 Tripping

Actuating OPEN trip coil 18.8 releases OPEN latch 18.9 via supporting latch 18.9.1 and supporting lever 18.9.2. Operating lever 18.24 and lever 18.7 are withdrawn by opening spring 18.11 over connecting rod 18.27 to the OPEN position (Fig. 16). The contacts of interrupter unit 22 are simultaneously shifted to the OPEN position over operating mechanism rod 18.27.1.

At the end of the opening movement the kinetic energy is absorbed by the damper (for opening) 18.15. The damper serves also as end stop.

18.11 Opening spring 18.15 Damper for opening 18.24 Operating lever 18.27 Connecting rod (for opening spring) 18.27.1 Driving rod 18.7 Lever 18.8 Release OPEN 18.9 Opening latch 18.9.1 Supporting latch 18.9.2 Support lever 22 Interrupter unit Fig. 16 Function diagram of closing and opening latching: Disengagement of the opening latch

31

Page 33: 400kV Circuit Breaker_O&M

32

3 Description

3.8 Control

The control system includes all secondary technical components necessary for the operation of the circuit-breaker, which are for the main part located inside the control cubicle and the housing of the operating mech-anism.

The documentation for the circuit-breaker includes the circuit diagram of the control system.

This diagram contains the following documents: - Location diagram - Schematic diagram - Extended equipment diagram with technical data and list of equipment - Terminal diagram - Connector diagram Fig. 17 shows the inside of the control cubicle.

R..

1001369a K... Contactors, time relays P... Operating cycle counter R... Heating (preventing condensation formation) S4 Confirmation X1 Terminal blocks 12.1.1 Equipment mounting plate 18 Climate-proof, ventilated and heated outdoor cubicle,

degree of protection IP 55 Fig. 17 Inside of the control cubicle.

Page 34: 400kV Circuit Breaker_O&M

3 Description

Note

The operator is responsible for the fuse protection for the auxiliary circuits, unless otherwise agreed with the manufacturer.

3.8.1 Spring Winding Mechanism

The spring winding mechanism consists of the motor and the charging gear. The spring state indicators (symbols) are on the spring cups and will be shown by intelligible symbols. See chapter 3.6 Spring Drive Mechanism of the Circuit-Breaker.

a) Spring is charged b) Spring is not charged 18.1 Motor 18.11 Opening spring 18.16 Release CLOSE 18.20 Motor limit switch 18.4 Closing spring 18.8 Release OPEN Fig. 18 Spring drive mechanism

3.8.2 Gas Monitoring

Each pole column is a closed gas compartment (Fig. 19) and is gas-monitored individually. The gas compartment of a pole column to be monitored contains a non-return valve, a density monitor B4 and pressure gauge, the filling connection W1, the test connection W2 and piping for connecting the components.

33

Page 35: 400kV Circuit Breaker_O&M

3 Description B4 SF6 density monitor MA Pressure gauge W1 Filling flange W2 Test connection Fig. 19 Diagram of SF6 monitoring in a pole column

The density of the SF6 arc quenching material in the gas compartment is monitored by a density monitor B4 (Fig. 21). The SF6 filling and response values for the density monitor can be found in section 3.1.6 Arc Quenching Medium SF6.

The connection W1 (Fig. 20) for filling the pole column with SF6 gas is in the relevant operating mechanism unit next to the pressure gauge. The test connection W2 is located in the base (at the side of the operating mechanism cubicle) (Fig. 21).

34

1001304a

W1 Filling flange Fig. 20 Filling flange W1

Page 36: 400kV Circuit Breaker_O&M

3 Description

B4

1001305a

B4 Density monitor W2 Test connection Fig. 21 Test connection W2 (view with cover of the contact position indicator removed)

3.8.2.1 Function of the Density Monitor

The density monitor compares the density of the SF6 gas in the compartment to be monitored with the density of reference gas enclosed inside the monitor. Both gases are exposed to the same ambient temperature. The density comparison is replaced by a pressure comparison in both systems (gas compartment - reference compartment).

The density monitor responds to a change in pressure as a result of a leak between circuit-breaker gas compartment and atmosphere. Pressure changes as a result of temperature changes are not taken into account.

The density monitor is set at the works to the limit density required. Resetting is neither necessary nor possible.

35

Page 37: 400kV Circuit Breaker_O&M

3 Description

5.00 Bellows 5.10 Microswitch 5.20 Housing 5.30 Circuit-breaker gas compartment 5.40 Reference gas compartment Fig. 22 Schematic diagram of the density monitor (under

working pressure)

3.8.3 Lockouts

The individual functions are explained in the order of their appearance in the circuit diagram.

A General lockout SF6 prevents any switching of the circuit-breaker if the SF6 pressure is too low.

The closing lockout prevents the circuit-breaker from being switched on while the closing spring is being charged.

The anti-pumping device of the circuit-breaker pole ensures that it is not repeatedly opened and closed in the event of simultaneous CLOSE and OPEN commands.

The swich S4 is for acknowledgement of enforced triple-pole operation.

3.8.4 Motor Control

The motor charges the closing spring and is controlled by a limit switch.

3.8.5 Anti-Condensation Heaters

To protect sensitive components in the operating mechanism cubicles and in the control cubicle from condensed water during rapid temperature changes, the units are always fitted with heating resistors. As condensation can occur at any ambient temperature, these resistors must always be in continuous operation.

3.8.6 Signals

Signals are information on the condition of the circuit-breaker.

36

Page 38: 400kV Circuit Breaker_O&M

37

3 Description

3.8.7 Free Auxiliary Switch Contacts

Additional free auxiliary switch contacts at the terminal fixture X1 are available for customer's purposes.

3.8.8 Operating Cycle Counter

The circuit-breaker is equipped with one counter per pole (Fig. 17). It counts the number of switching operations performed.

Page 39: 400kV Circuit Breaker_O&M

3 Description

3.9 Reference Contact IK-3

3.9.1 Introduction

Attention The warnings in the operating instructions for high-voltage circuit-breakers must be observed! Work may only be performed at the reference contact in the OPEN position with the closing and opening springs relaxed.

Discharge the closing and opening springs:

- Disconnect motor power supply,

- Open circuit-breaker (from closed position),

- Close the circuit-breaker,

- Re-open the circuit-breaker.

The reference contact is connected mechanically to the interrupter unit of a high-voltage circuit-breaker and serves for indirect determination of the switching time/ inherent switching time.

The reference contact is tripped by the operating mechanism of the circuit-breaker.

The difference in time between switching the interrupter unit and the output signal of the reference contact is recorded in the test document.

There is no direct mechanical connection with the circuit-breaker's contact system.

FA Operating mechanism RK Reference contact UE Interrupter unit Fig. 23 Function diagram of the IK-3

The IK-3 is a non-contact contact system consisting of a Hall Effect sensor with actuating magnets. The Hall sensor is the fixed part and the magnet the moving part of the contact system.

38

Page 40: 400kV Circuit Breaker_O&M

3 Description

A Edge to be evaluated at CLOSE B Edge to be evaluated at OPEN Fig. 24 Output signal of the IK-3

The IK-3 is designed as a two-wire system in which the output signal is transmitted by a current loop.

3

1 Sensor electronics 2 Sensor HE-6103 3 Magnet HE-6104 4 Fastening plate Fig. 25 Reference contact

The reference contact is set at the factory.

The air gap between the sensor and the magnet must be 2 ... 4 mm.

39

Page 41: 400kV Circuit Breaker_O&M

40

4 Installation 4 Installation

4.1 Safety Rules for Installation

WARNING Danger to installation personnel can result from

- hazardous voltage

- SF6-gas

- falling and/or toppling parts and/or moving parts.

Non-observance of warnings can result in death, severe personal injury and substantial property and environmental damage.

In order to avoid accidents, fire and impermissible burdens on the environment and in order to assure the functional reliability of the switchgear, the user must ensure that:

- a responsible person, if necessary authorized to supervise, is put in charge of performance of commissioning,

- only qualified and instructed personnel are assigned,

- the regulations and instructions for work safety (e.g. in the use of equipment), together with instructions on action to be taken in the event of accidents and fire, are available at all times and if necessary displayed in the place of work,

- the tools, equipment and apparatus required for work safety and the personal protective equipment required for certain tasks are available,

- only those materials, lubricants and auxiliary equipment approved by the manufacturer are used.

Page 42: 400kV Circuit Breaker_O&M

4 Installation

The safety regulations in these operating instructions are minimum requirements. They do not affect statutory laws, standards, specifications or internal regulations of the company concerned with the work. They do not claim to cover all eventualities and must be expressed concretely by the responsible persons at the latest before work actually starts. In addition to company internal rules and the specific work conditions, the product descriptions and instructions for use of tools, devices, apparatus, materials, lubricants and auxiliary equipment must be taken into account.

The following safety regulations provide an overview of the dangers existing and their sources, and describe the possible consequences if the rules specified are not complied with. They are expressed more exactly in the operating instructions.

WARNING Hazardous voltage - Electric shock and burning as a result of arcing are possible if live parts are approached.

If high voltage is present in the vicinity at the place-where work is to be done, a responsible person from the power supply utility must, before work starts:

- Switch off and isolate

- Prevent unintentional switch-on

- Test that equipment is dead

- Ground and short-circuit the equipment

- Cover or fence off nearby live parts

It must be confirmed that these safety measures have been taken.

WARNING The pole columns are under pressure (see section 3.1.6 Arc Quenching Medium SF6) - Damage to the porcelain parts can result in severe personal injury.

- Do not allow any tools or hoisting gear to knock against the porcelain parts.

- Do not lean any ladders against the pole columns; use step ladders.

41

Page 43: 400kV Circuit Breaker_O&M

42

4 Installation

WARNING SF6 is heavier than air. In closed areas it may displace the air - Danger of suffocation!

Use a service unit for all work with SF6 gas. Extract the SF6 filling; do not let it escape into the air.

WARNING

Improperly performed installation and maintenance can result in danger and malfunctions.

In the context of installation and commissioning, the commissioning report must be filled out.

Page 44: 400kV Circuit Breaker_O&M

4 Installation

4.2 Delivery and Storage

Attention Avoid damaging the porcelain bodies.

4.2.1 Packing

The circuit-breaker is supplied as pretested modular assembly.

If transported by land, the components are delivered in crates. If transported by container (by sea), some are supplied on pallets and some in crates.

All components and parts required for commissioning and operation are included in the shipment in a separate package.

The parts comprised in the transport unit are indicated in the checklist provided with every circuit-breaker.

SF6 gas is supplied in cylinders.

The electrical circuit-breaker control is wired to the terminal strip in the control cubicle.

4.2.2 Checking on Arrival

When a shipment arrives it should be checked immediately against the dispatch notes and check list. If it shows signs of damage determine the extent of the damage and its probable cause without delay. Should the damage have been caused in transport, call in a representative of the forwarding agent in order to record the facts. This is an essential requirement if a claim for damages is to be submitted.

4.2.3 Storage

If a circuit-breaker is not to be assembled immediately after delivery, the crates can be stored outdoors.

For better ventilation and as a protection against ground dampness, the crates should then be placed on wooden planks and covered with tarpaulins.

Note

In case of storing the circuit-breaker longer then 3 months the anti-condensation heater in the control cubicle and on the operating mechanism cubicles must be switched on.

43

Page 45: 400kV Circuit Breaker_O&M

44

4 Installation

After one year's storage, the external surfaces treated with Tectyl 506 should be given a thick second coating.

Before storing the accessory items, check their plastic wrapping for signs of damage. If the plastic foil has sus-tained damage, unpack the parts and store them in a dry, ventilated room.

Page 46: 400kV Circuit Breaker_O&M

4 Installation

4.3 Cleaning Liquids, Lubricants and Corrosion Protection Agents

4.3.1 Cleaning Liquids

For cleaning and degreasing metal parts and sealing rings use any of the following (not included in the scope of supply).

Attention Improper handling can result in personal injury, fire and environmental damage.

In the interest of safety, follow instructions for use of cleaning liquids carefully.

Outer surfaces/minor dirt

Cleaning liquids Warm water solution with a mild household cleaning liquid

Instructions Wipe off with a damp lint-free paper or cloth. Avoid drips. Do not let solution get into openings and gaps.

Outer surfaces, parts/greasy surfaces, surfaces coated with anticorrosion agent (Tectyl 506), sealing rings

Cleaning liquids Cold-application cleaning agent, hydrocarbon-basis (free from halogenated hydrocarbons) flash point >55°C, e.g. Shellsol D60 (Shell), Es-sovarsol 60 (Esso), Aral 4005 (Aral), Haku 1025/920 (Kluthe)

Instructions Wipe off with a damp lint-free paper or cloth. Avoid drips. Wipe clean with a dry, lint-free paper or cloth. Immerse small parts if necessary. Do not immerse sealing rings in agent.

Safety instructions Fire hazard! No smoking! Read product de-scriptions and follow relevant safety instruc-tions.

Insulating parts in SF6-compartments

Cleaning liquids Ethyl alcohol, isopropyl alcohol, Haku 3294 (Kluthe)

Instructions Wipe off with a damp lint-free paper or cloth. Avoid drips.

Safety instructions Flammable! No smoking! Explosion protection necessary! Read product descriptions and follow relevant safety instructions.

45

Page 47: 400kV Circuit Breaker_O&M

46

4 Installation

4.3.2 Lubricants and Corrosion Protection Agents

The following lubricants and corrosion protecting agents are required for installation and maintenance of the circuit-breakers:

Kliiber grease Centoplex 24 DL

for all lubricating points and non-hot-galvanized screws, unless another brand of lubricant is specified.

Isoflex Topas L32

for radial sealing rings and rolling contact bearings of the SF6 shaft seal on the corner gear and on the operating mechanism.

Shell Vaseline 8420

for sealing rings and terminal faces for high-voltage cables.

WD40 or Trost Multifunction Fluid

for flange faces inside the sealing rings, including the slots.

Tectyl 506

for flange faces outside the sealing rings and for clamping sleeves.

Molykote Longterm 2 plus

for the threads of all hot-galvanized screws.

Page 48: 400kV Circuit Breaker_O&M

4 Installation

4.4 General Instructions for Installation

For assembling the circuit-breaker use only the bolts supplied. Spare bolts are included in the accessories pack, in case any are lost during assembly work.

WARNING If unsuitable bolts are used, they can malfunction and cause severe personal injury.

If the number of bolts supplied for the pressure vessels is insufficient, spare bolts must be ordered from the factory only.

Grease the threads of all hot-galvanized bolts with Molykote Longterm 2 plus.

Attention

Unchecked tightening can result in damage to or loosening of bolt joints.

Use torque wrench for assembly. Tightening torque see Table 11.

Bolts are of 8.8 grade or higher.

i.e. Minimum tensile strength 800 N/mm2 Minimum yield strength ReH = 640 N/mm2

Screwed joint Tightening torque M6 8 + 1 Nm M8 20 + 2 Nm M10 40 + 4 Nm M12 70 + 7 Nm M16 170 + 20 Nm M20 340 + 30 Nm M24 600 + 60Nm

Table 11 Tightening torques required for screw joints

Screw on all union nuts with a tightening torque of 40 ± 4 Nm.

Differing torques are indicated in the text.

Any locking washers and gaskets loosened or exposed during assembly must be replaced.

47

Page 49: 400kV Circuit Breaker_O&M

48

4 Installation

4.5 Installation of the Circuit-Breaker

WARNING The control leads must not be connected to the terminal block of the operating mechanism until the circuit-breaker has been erected complete with the pole columns.

4.5.1 Requirements for Assembly

You will require the following equipment and tools for next work steps in the assembly of the circuit-breaker:

- A crane with suitable suspension tackle

- Evacuating equipment P= 20 mbar

- SF6 filling device W423

- SF6-leak detector

- A conventional standard toolbox.

4.5.2 Assembly on Supporting Pillars at the Place of Installation

The circuit-breaker must be assembled at the point of installation. The following sequence of steps must thereby be observed.

WARNING Failure to observe the specified screw lengths for assembly of the circuit-breaker can lead to severe damage or even destruction of the circuit-breaker.

Page 50: 400kV Circuit Breaker_O&M

4 Installation

4.5.3 Assembly Overview

Fig. 26 Assembly overview

Note

Discard all screws and nuts marked red!

4.5.4 Disassembling the Insulator Column Kit

Loosen the M16 nuts at the fixing point between the bracket 1.3 and the wooden beams 1.6.

Lift the three insulator columns in the kit with the crane and put them down onto the brackets 1.3 on a solid base but do not disconnect the suspension tackle fom the insulator column kit.

49

Page 51: 400kV Circuit Breaker_O&M

4 Installation

VD Packaging cap for insulator column 1.3 Bracket 1.4 Connecting plate 1.5 Lifting eye plate 1.6 Wooden beam 1.8 Lifting eye-bolt Fig. 27 Insulator column kit

Disassemble the insulator column kit as shown in Fig. 27 starting at the bottom and put the individual columns down on a solid base. Put the insulator columns down on the connecting plates or a wooden base (rest on the metal flange, not on the porcelain parts).

Fig. 28 Separating the insulator columns

4.5.4.1 Fixing the Reinforcing Sheets

To fit the reinforcing sheets 1 and 2 in the breaker base, replace the four M 16x80 screws shown in Fig. 29 and the three M16x55 screws on all three pole columns with the seven M16x10 screws supplied in the accessory pack.

Note

When replacing the screws to fit the reinforcing sheets 1 and 2, make sure that the screws are individually loosened, replaced and tightened again.

50

Page 52: 400kV Circuit Breaker_O&M

4 Installation

BM 16x55 BM 16x55

BM 16x55

B The M16x55 screw is not replaced. Fig. 29 Screw distribution for insulator column assembly.

The screws are then tightened to 170 Nm.

51

Page 53: 400kV Circuit Breaker_O&M

52

4 Installation

4.5.5 Assembly of the Control Cubicle

12 Control cubicle 15.1 Operating mechanism Fig. 30 Control cubicle/operating mechanism transport unit

Insert the crane hook into the lifting eye-bolts of the control cubicle and undo screw joints to the other components of the transport unit.

Move control cubicle with a crane and bolt in front to the centre pillar (pole B) (4 bolts M 16x60, 4 nuts, 8 washers from the accessories pack).

The length of the bolts from the accessories pack is suitable for a pillar wall thickness of up to 35 mm (Fig. 31).

Page 54: 400kV Circuit Breaker_O&M

4 Installation

53

11.13 Pillar 12 Control cubicle Fig. 31 Assemble control cubicle at pillar

4.5.6 Assembly of the Operating Mechanism Cubicles

The doors of the operating mechanism cubicles are labelled LA, LB and LC. The operating mechanism cubicles are assembled on the pillars for poles A, B and C according to this labelling.

This allocation of operating mechanism to poles must be strictly observed because of the coded pole connecting cables.

To assemble the drive cabinet, insert the crane hooks into the lifting eye-bolts of the drive cabinet and undo the screwed connections to the other components of the transport unit.

Place the operating mechanism cabinet with base 11 onto flange plate F of the corresponding pillar and secure with screws (4 screws M 16x80, 4 nuts, 8 washers from the accessory pack).

The length of the bolts from the accessories pack is suitable for a pillar wall thickness of up to 45 mm (Fig. 32).

4

4 Installation

Page 55: 400kV Circuit Breaker_O&M

54

F Pillar Flange Plate 11 Breaker base Fig. 32 Operating mechanism cabinet with base mounted on

pillar

4.5.7 Assembling the Insulator Column

The circuit-breaker poles are labelled LA, LB and LC on the double interrupter heads, the insulator columns and the lower part of the circuit-breaker. Make sure the double interrupter heads and insulator columns are assigned correctly to the circuit-breaker poles and check the last four digits in the serial number on the lower part of the circuit-breaker when you install the circuit-breaker.

The insulator columns consisting of corner gears, insulators and operating rods are fully assembled at the factory. The top openings on the insulator columns are sealed with a packaging cap for protection and to prevent contamination during transport (Fig. 33).

Page 56: 400kV Circuit Breaker_O&M

4 Installation

VD Packaging cap 1.8 Lifting eye-bolt

Fig. 33 Packaging cap for insulator column

Attention The time between removing the transport cover and evacuation of the circuit-breaker pole must not exceed one hour.

Attention During assembly work, the open insulator column should be protected against atmospheric influences using suitable covers.

Remove the bolt 10.9 (Fig. 49) from the corner gear 15 and the lever 15.9 and keep them ready for linking the operating rod.

Remove the transport fastenings (cable ties) for the operating rod 18.27.1 (Fig. 49).

Installing the insulator columns

The insulator columns for the circuit-breaker are identical. Use the pole labels on the corner gear to assign the poles.

55

Page 57: 400kV Circuit Breaker_O&M

56

4 Installation

H Wood 1.4 Connecting plate 1.5 Lower lifting eye plate 15 Comer gear 15.9.01 Lever 1.8 Upper lifting eye plate Fig. 34 Installing insulator columns (diagram shows the top

insulator column in the kit)

Loosen and remove the 2 lifting eye plates 1.5.

Before you raise the insulator column place a wooden base under the corner gear. This will prevent damage when turning. Now lift the insulator column carefully by the 2 angled lifting eye bolts 1.8.

Make sure that the crane hook and the insulator column head are always vertical to prevent the insulating columns slipping when lifted.

The connecting plate 1.4 can then be loosened and removed.

You can remove the lower connecting plate once the insulator column has been lifted far enough.

Now insert the insulator column carefully into the carrier opening.

Fig. 37 Breaker pole mounted

Page 58: 400kV Circuit Breaker_O&M

Then align the insulator column so that pegging out with the bolt 10.9 (Fig. 49) is possible.

Now tighten the four M 16x65 screws to a torque of 170 Nm.

Tighten the four M8x40 screws and nuts with a torque of20Nm.

16.7

15.16.3

1002226a Fl Humidity indicator N Groove for teflon strip 16.6.1 VD Packaging cap 1 Transport protection device 15.16.3 Desiccant agent 16 Post insulator 16.7 Sealing ring 16.9 Operating rod 1.8 Lifting eye-bolt 2 Cable fastener Fig. 38 Packaging cap for insulator column

57

Page 59: 400kV Circuit Breaker_O&M

4 Installation

4.5.8 Erecting the Double-Break Assembly

The coupling bolt 10.9 on the corner gear should be removed and laid out ready for later use.

Remove the 90° offset jack rings 1.8 and laid out ready for the next insulator column.

Attention During assembly work, the open insulator column should be protected against atmospheric influences using suitable covers.

Remove the packaging cover from the insulator column and read the moisture indicator on the inside of the cover immediately.

Handling the humidity indicator

The effectiveness of the drying agent can be determined using the humidity indicator.

In its initial state (dry) the indicator display is blue. If the relative humidity increases, the indicator display changes from blue to pink.

When taking the reading, check which semicircle is the most pink or is already lighter than the area around all the semicircles. (Fig. 39). The relative humidity in % is above this figure, but still below the next higher figure.

Note

The humidity value reading may not exceed 40 %. If the humidity value is above this, inform the nearest Siemens representative!

58

Page 60: 400kV Circuit Breaker_O&M

4 Installation

Fig. 39 Humidity indicator

The old desiccant agent is removed and disposed of. Treatment of the sealing flanges and the guide

The sealing faces of the flanges and the guide must be treated carefully since even minor damage may lead to leaking joints.

59

A Grease with corrosion protection agent WD 40 or Trost

multifunction oil B Grease with Tectyl 506 C Grease sealing rings with Vaseline 8420 Fig. 40 Treatment of the sealing flanges and the guide

The flange for the insulator column should also be cleaned and treated with Tectyl.

Take two new O-rings from the accessory kit, clean with lint-free cloth, lubricate with Vaseline and lay out ready for use.

Page 61: 400kV Circuit Breaker_O&M

4 Installation

Move the lever to CLOSED position (the drive rod moves upwards) and lock it to the base using the rubber retaining ring supplied so that ir remains in CLOSED position.

Position a lubricated O-ring on the upper flange of the post insulator column. Remove the transport protection 1, which is used only during transport (Fig. 38) from the guide tube 16.6. The prepared sliding ring 16.6.1 from the accessory pack is positioned around the groove with one hand. At the same time, the guide 16.6 can be pushed over the slide ring with the other hand (see Fig. 46).

Note

When inserting the guide, ensure that the longer section of the guide is at the bottom.

By turning it slightly in all directions, ensure that the lower O-ring is positioned centrically in the groove.

16.3

16.9.1

1002573a 16.3 Post insulator 16.6 Centering guide 16.6.1 Teflon strip 16.7 Sealing ring 16.9 Operating rod 16.9.1 Yoke head

Fig. 41 Teflon strip

Insert the upper O-ring in the upper groove on the guide.

Install spacer

Insert three spacers W350 in the post insulator flange so that the slit in the threaded bolt is pointing to the flange and fasten M16 nuts (Fig. 46).

60

Page 62: 400kV Circuit Breaker_O&M

61

4 Installation W350 Spacer 16.6 Centering guide 16.7 Sealing ring 16.9.1 Yoke head Fig. 42 Install spacer

Lift double interrupter head to eye level with crane on the lifting plates (Fig. 47).

1 Lifting plate Fig. 43 Lifting plate arrangement

Attention The double interupter head must be suspended horizontally for assembly.

Page 63: 400kV Circuit Breaker_O&M

4 Installation

Remove the transport cover 21.9.9 (Fig. 45) from the double interrupter head and take out the desiccant bags. Prepare the sealing flanges as described above.

Remove the cable binder used as transport protection. Bring the interrupter unit into OPEN position by pulling the two coupling levers jerkily as far as they will go. The coupling bolt 21.7.3 supplied can be used for this purpose.

The double interrupter head is placed on the spacer in such a way that the grading capacitors are situated on the side of the operating mechanism cabinet.

The holes in the fork head of the drive rod and in the two coupling levers should be aligned, to enable the coupling bolt to be inserted. To do this, the two coupling levers are held in a V-shape with one hand, while the coupling bolt is inserted into the aligned holes with the other hand after positioning the drive rod.

Protect coupling bolt 21.7.3 with PE fuse 21.11.

1002230a

VD Packaging cap 15.16.3 Desiccant agent 1.8 Lifting eye-bolt 21.9.9 Packaging cap for double interrupter head Fig. 44 Packaging cap for double interrupter head and insulator column

62

Page 64: 400kV Circuit Breaker_O&M

4 Installation

W350 Spacer 16.6 Centering guide 16.7 Sealing ring 21.11 SL-Safety clip 21.7 Coupling lever 21.7.3 Coupling bolt Fig. 45 Erecting the double-break assembly

63

Page 65: 400kV Circuit Breaker_O&M

4 Installation

W350 Spacer 16.3 Post insulator 16.6 Centering guide 16.6.1 Teflon strip 16.7 Sealing ring 16.9 Operating rod 16.9.1 Yoke head 21.1 Housing 21.7 Coupling lever 21.7.3 Bolt Fig. 46 Centering guide and coupters fitted

Attention Hold the double-break assembly by means of the crane; do not lift it!

Remove the three spacers. To do this, unscrew the nuts and unscrew the threaded bolt downwards out of the hexagonal socket. Remove the hexagonal socket to the side.

Before the double interrupter head is lowered, release the reversing lever 15.9 from its locked position -remove the rubber retaining ring and bolt 10.9.

Carefully lower the double interrupter head onto the insulator and screw it onto the insulator column to 170 Nm with 8 screws M 16x75.

4.5.9 Lifting Plate

The lifting plates used for hoisting the double interrupter head are removed. The screws are re-used.

64

Page 66: 400kV Circuit Breaker_O&M

4 Installation 1 Lifting plate 22 Interrupter unit

Fig. 47 Lifting plate arrangement

4.5.10 Coupling the Operating Mechanism

Using the manual actuator supplied, the lever 15.9 is moved in such a way that it can be connected to the bolt 10.9. The bolt remains in operating position.

W387 Manual operating device W387 15.9 Lever 18.27.1 Driving rod Fig. 48 Manual operating device W387

65

Page 67: 400kV Circuit Breaker_O&M

4 Installation

66

15.9 10.1 10.9 18.27.1

10.1 10.9

1 Marking position 2 Operation position 10.1 Bolt with lock washer 10.9 Bolt 15.9 Lever 18.27.1 Driving rod Fig. 49 Coupling the operating mechanism

Set up the two other poles in the same way replacing the original screws after removal of the lifting eye-bolts.

Next pull the bolt 10.9 out at all three poles (Fig. 49) so that it can be secured in the ring groove with the locking plate 10.1 and two M6 screws.

Bend the locking plate after tightening the two M6 screws.

4.5.11 Connecting the Gas Pipes

During assembly of the tube connections, ensure that the sealing surfaces are clean and the O-ring gasket is in perfect condition.

An gas line must be connected for each pole column.

Page 68: 400kV Circuit Breaker_O&M

67

4 Installation

To connect the gas pipes 51.1 to the flanges 15.40 of the pole columns, remove the union nuts 15.40.1 with sealing cap (Fig. 50) from the flanges 15.40 and make the connections as shown in Fig. 51.

First of all align the gas tube flange 51.1 parallel to the surface of the flange 15.40 on the corner gear and insert a new O-ring 15.40.3 which has been lubricated with Vaseline. Then quickly screw on locking nuts 51.1.1 by hand and tighten with a wrench. Screw on the locking nuts 15.40.4 to a tightening torque of 40 Nm. Vaseline and a new O-ring are to be found in the accessory pack.

Keep the locking screws of the gas pipes and the union nuts with sealing caps of the flanges on the pole columns in a safe place for future transportation and repairs. 15 Corner gear 15.40 Flange 15.40.1 Union nut 15.40.2 Cap plug 15.40.3 O-ring gasket 15.40.4 Valve plunger Fig. 50 Gas connection with non-return valve 15 Corner gear 15.40 Flange 15.40.3 O-ring gasket 51.1 Gas pipe 51.1.1 Union nut

Fig. 51 Mounting the gas pipe

Page 69: 400kV Circuit Breaker_O&M

4 Installation

4.6 Earthing and Connecting the Leads

4.6.1 Earthing

Connect the breaker base to the high-voltage station earth by means of earth terminals provided.

a) Earthing bolts Fig. 52 Earthing bolts in base (viewed from outside/inside)

4.6.2 Work on High-Voltage Terminals

WARNING For safety reasons, work on high-voltage terminals should be carried out before the circuit-breaker is filled with SF6-gas up to nominal pressure.

The connection of the high-voltage conductors is allowed at nominal SF6 pressure provided that the warnings are followed.

WARNING

High gas pressure - Danger of bursting!

The porcelain insulators should not be exposed to any stress (e.g. from vibration, etc.). Great care should be taken to avoid damaging the porcelain body and fins with tools or handling aids.

68

Page 70: 400kV Circuit Breaker_O&M

69

4 Installation

Connecting the high-voltage conductors

Brush the contact surfaces of the high-voltage terminals with a steel wire brush, which has only been used for aluminium, until they are bright and slightly roughened. Wipe the contact surfaces off with lint-free paper or cloth and lightly coat them with acid-free Vaseline, e.g. Shell Vaseline 8420.

Make the connections and tighten the screws. Before commissioning, retighten once again.

In the case of connecting parts made of copper, copper-aluminium spacers must be used.

4.6.3 Connecting the Leads

WARNING

To avoid damaging the circuit-breaker by inadvertent operation, switch on the power to the motor only when the circuit-breaker has been filled with SF6 gas. Pressure must at least be at the level of general lockout SF6, see Table 4.

When the power to the motor is switched on, the closing springs are charged automatically.

Note

Connecting cables must be fitted in dead state.

Page 71: 400kV Circuit Breaker_O&M

70

4 Installation

4.7 Filling the Circuit-Breaker with Gas

4.7.1 Evacuating

WARNING Evacuate the circuit-breaker not later than one hour after removing the transport cover from the double interrupter head.

If serving equipment is not available, you must have a vacuum pump to evacuate the poles before filling with SF6 gas.

Connect the service unit at the filling connection W1 (Fig. 1). Evacuate the circuit-breaker down to a pressure of < 0.02 bar; then switch the service unit for "fill". The required filling pressure and response values are temperature-dependent and must be taken from the diagram, SF6 filling curve and response values of the density monitor, see 3.1.6 Arc Quenching Medium SF6.

4.7.2 Filling the Breaker from the Gas Cylinder

Siemens offers a complete filling device of type W423 for filling the circuit-breaker with SF6 gas from a gas cylinder (Fig. 53).

Attention The circuit-breaker may be filled only by or under the supervision of qualified personnel, and in accordance with the SF6 filling curve (see under 3.1.6 Arc Quenching Medium SF6).

Attention

For filling the breaker with gas only use as good as new SF6-gas which corresponds the demands ace. IEC 60376.

Page 72: 400kV Circuit Breaker_O&M

71

4 Installation

WARNING High gas pressure - Danger of bursting!

Exceeding the permissible filling pressure can cause the pole columns to burst, resulting in severe personal injury and damage to property.

The filling device must include a safety valve (operating pressure 8.0 bar). The safety valve prevents the pressure compartments from being overstressed due to an impermissibly high pressure.

Fig. 53 Gas filling device W423

To pour in gas, connect the hose of the filling device to the filling flange W1 of the pole (Fig. 54 and Fig. 55).

Using the handwheel on the control valve, regulate the gas flow to prevent possible freezing of the cylinder. Monitor the filling process on the precision pressure gauge.

Care must be taken that the filling pressure, which depends on the ambient temperature (see rating plate with information about the filling pressure at 20°C), is correct.

W1 Filling flange Fig. 54 Filling flange W1

4 Installation

Page 73: 400kV Circuit Breaker_O&M

72

W

1 Filling flange 1 Gas cylinder 2 Pressure reducer regulating valve 3 Precision pressure gauge (-1.0 bar up to 9.0 bar) 4 Safety valve Fig. 55 Gas filling device connected

At an ambient temperature other than +20°C, the SF6 filling pressure must be taken from the diagram (Fig. 1).

The filling pressure may be up to 0.30 bar over the nominal pressure curve (temperature-independent).

When filling is completed, unscrew the hose of the filling device and close the filling flange. Screw on the union nut by hand (4 Nm). Ensure that all parts are clean.

4.7.3 Leakage Test after Installation

After successful assembly of the circuit-breaker and filling with SF6 gas, the tube connections should be checked for leakages.

A leak detector must be used. If a leak is detected:

WARNING Release the SF6-pressure before working on the screw connections of the gas chamber.

If a leak is discovered, undo the leaking connection and check the sealing surface for damage or foreign bodies. Then fit a new seal, remake the connection and repeat the leak test.

Page 74: 400kV Circuit Breaker_O&M

73

4 Installation

4.8 Carrying Out Test Operations

When installation work is finished, the circuit-breaker is in the OPEN position. The closing spring of the operating mechanism is not charged. See section 3.7 Function of the Spring Drive Mechanism

When the motor control power supplies are switched on, the charging motors automatically start up and stop again when the closing spring has been charged and latched. The operating mechanism is now ready for a closing operation.

WARNING Blocking of the circuit-breaker is possible.

Before the start of a test run it is essential to check that the bolts 10.9 are inserted in the breaker position 2 and secured (Fig. 56)

A Operation position B Marking position 10.9 Bolt 15.9 Lever Fig. 56 Coupling point on corner gear

WARNING Danger of bursting if porcelain bodies are damaged. Severe personal injury can result.

For safety reasons no persons may remain within 60 m of the circuit-breaker while the first 5 test operations are being carried out.

Page 75: 400kV Circuit Breaker_O&M

4 Installation

WARNING Danger of serious mechanical damage!

Mechanical test operations must only be performed with sufficient SF6 gas filling: Pressure must at least be at the level of general lockout SF6, see Table 4.

When installation work is finished, 5 test switching operations should be carried out per circuit-breaker pole.

With regard to the possibility of the porcelain components having suffered transport damage, these mechanical switching operations must be performed by remote control as safety switching operations.

74

Page 76: 400kV Circuit Breaker_O&M

75

4 Installation

4.9 Checks before Commissioning

Attention The items listed below should be strictly followed during commissioning.

4.9.1 Anti-Condensation Heaters

Check that heating resistors in the three operating mechanism cubicles and in the control cubicle are working, and also the function of any monitoring equipment fitted.

4.9.2 Test of Wiring between Substation and Circuit-Breaker

Check all command and signalling paths.

4.9.3 Commissioning Report

It should be checked that the commissioning report enclosed with the circuit-breaker has been completed in full and signed.

Please return it to the manufacturer at the following address:

Siemens Ltd.

PTD-Division

E-76. Waluj MIDC

Aurangabad 431136

Page 77: 400kV Circuit Breaker_O&M

76

5 Operation 5 Operation

5.1 Instructions for Operation

5.1.1 Closing and Opening

WARNING Danger of serious mechanical damage!

An SF6-minimum gas pressure (SF6-blocking pressure) must be available for test operations (without current and voltage).

WARNING Danger! - High voltage!

A circuit-breaker connected to high voltage may only be operated conforming with the safety regulations of the facility. In this case, the general lockouts of the circuit-breaker may not be bypassed.

Switching operations triggered directly at the tripping coil will bypass both the switchgear interlock and general lockouts of the circuit-breaker.

5.1.2 SF6 Pressure

The pressure of the SF6 gas in the pole columns is monitored by a density monitor and shown on the respective pressure gauge. The response values of the density monitor are shown, see 3.1.6 Arc Quenching Medium SF6.

If the SF6 pressure drops unduly low, a signal Loss of SF6 is initiated. The circuit-breaker must then be topped up as soon as possible with SF6 from a gas cylinder or using the filling device connected to the flange W1 on the gas monitoring unit until nominal pressure is restored. The circuit-breaker must be isolated for this. When filling has been completed, the circuit-breaker can be put back into operations.

WARNING The circuit-breaker must be switched off and earthed for SF6 filling work.

The circuit-breaker can be switched back on when filling is complete and the earthing has been disconnected.

Page 78: 400kV Circuit Breaker_O&M

5 Operation

The filling flange W1 for filling the circuit-breaker with SF6 gas is located inside the drive mechanism housing (connecting thread M26x1.5 or M45x2). The operational gas pressure can be read on the pressure gauge MA (see section 3.8 Control).

WARNING

Release the SF6-pressure before working on the screw connections of the gas chamber.

If the above signal is initiated again after some time, the leak must be located and, if possible, sealed. If the leak cannot be sealed, the nearest Siemens representative should be notified.

5.1.3 General Lockout

If the SF6 pressure in the circuit-breaker drops so low that perfect arc-quenching can no longer be ensured, a general lockout becomes effective and blocks all further operation.

5.1.4 Mechanical Reclosing Lockout

If the circuit-breaker pole is in the CLOSED position, a mechanical reclosing lock-out in the operating mechanism comes into effect. It prevents the operating mechanism from being switched back on.

5.1.5 Max. Permissible Number of Interruptions

The relationship between breaking current I, max. permissible number of interruptions is shown in Fig. 57. If the interruptions take place with higher current, the number of possible interruptions decreases as shown in Fig. 57.

77

Page 79: 400kV Circuit Breaker_O&M

78

5 Operation

I Breaking current in kA k Weighting factor n Max. permissible number of interruptions X During the type tests 10000 mechanical operation cycles were carried out. Fig. 57 Max. permissible number of interruptions as a

function of the breaking current.

The chart (Fig. 57) relates to one pole of a triple-pole circuit-breaker. Three times the number of the permissible single-pole opening operations may thus result in a triple-pole circuit-breaker (e.g. 18 single-pole opening operations with 50 kA).

Weighting factor k simplifies calculation of the max. permissible number of interruptions at different breaking currents.

Page 80: 400kV Circuit Breaker_O&M

5 Operation

m

6000 - Σ (ni • ki) i = 1 kx

nx = 1000037b

ki Weighting factor for breaking current I kx Weighting factor for breaking current lxn. Number of carried out interruptions at breaking current I nx Number of remaining permissible interruptions at breaking current lx. Fig. 58 Formula for calculating the max. number of

permissible interruptions

The maximum number of interruptions still permissible with a given number of operations (with consequent wear) already carried out can be calculated using the above equation.

For example:

The circuit-breaker with a rated short-circuit breaking current of 50 kA has performed 250 interruptions with breaking currents of 3.15 kA, and 2 interruptions 20 kA.

How many interruptions at 40 kA are still permissible?

n40 = = = = 10,7 6000 - (250 + 200)

520

6000 - (n3.15 • k3.15 + n20 • k20)

k40

60 )

520

00 - (250 • 1 + 2 • 100

Fig. 59 Number of remaining permissible interruptions

at breaking current lx.

A total of 10 interruptions at 40 kA are still permissible.

79

Page 81: 400kV Circuit Breaker_O&M

80

5 Operation

5.1.6 Recommended Procedure in the Event of Irregularities on the Circuit-Breaker 3AP2 Fl

Note

The following table is an aid in recognition and assessment of any irregularities occuring in operation of the circuit-breaker.

It also enables specific details to be given if Siemens service Berlin personnel have to be summoned. In such a case, please telephone during business hours

Tel.: +91 240 2565 142

or by fax

+91 240 2554 701

WARNING To avoid any hazard, only qualified personnel may do the work described below.

WARNING Work may only be done on the operating mechanism when the opening and closing spring are relaxed.

WARNING The circuit-breaker must be switched off and earthed for SF6 filling work.

The circuit-breaker can be switched back on when filling is complete and the earthing has been disconnected.

Release the SF6-pressure before working on the screw connections of the gas chamber.

Page 82: 400kV Circuit Breaker_O&M

81

5 Operation

Signal/Lock-out Effect Possible cause(s) Remedial measure(s)

Loss of SF6 Signal only (Leak generally slow) SF6 leak Locate fault and seal leak. Top up SF6 to nominal pressure

General SF6 lock-out No switching possible SF6 leak See Loss of SF6

Reclosing lockout longer than 15s Closing spring not charged, no closing possible

No motor power supply/Motor defective

Provide motor supply/replace motor

Table 12 Disturbances

Page 83: 400kV Circuit Breaker_O&M

82

5 Operation

5.2 Disposing of High-Voltage Switching Devices and Systems

The circuit-breaker 3AP2 Fl is an environmentally compatible product.

In disposal, priority must be given to reuse of the materials. Environmentally acceptable disposal of the device is possible in line with current legislation.

The device can be recycled as mixed scrap, or, if it is dismantled as far as possible, in a more environmentally acceptable way as sorted scrap with a mixed-scrap residual portion.

The following materials have been used to make up the device: Steel, copper, aluminium, PTFE, cast resin or cast-resin-impregnated fabric, glass-fibre-reinforced plastics, rubbers for sealing, ceramics, greases.

Before disposal, it should be ensured that the Shell Aero Fluid hydraulic fluid present in the drive mechanism dampers is drained. This should be done in accordance with current official regulations at the time of disposal.

No oils used in the circuit breaker contain PCB.

In as-supplied-by-Siemens state, the device incorporates no hazardous substances in the sense of the pertinent regulations in Germany. If the device ist to be operated outside Germany, the locally applicable laws and regulations must be followed.

The insulating and quenching media SF6 can be removed by suction using suitable equipment and, after reconditioning, can be made available for reuse.

In the opened gas compartments, there may be solid decomposition products resulting from switching operations. The gaseous products are absorbed by the built-in filters. When switching devices incorporating SF6 as insulating and quenching medium are disposed of (with particular regard to filter material and solid decomposition products), the necessary safety measures must be complied with.

Local customer support offices will be able to answer any questions concerning disposal.

Page 84: 400kV Circuit Breaker_O&M

6 Maintenance 6 Maintenance 6.1 Inspection and Maintenance - General

The circuit-breaker can only function reliably if it is correctly maintained. The purpose of inspection and main-tenance therefore is:

- to determine to what extent certain parts have worn and to assess their state,

- to ensure that parts still in good condition are kept in this state,

- to replace certain parts in good time,

- to ensure corrosion protection.

Inspection and maintenance services are categorized in line with the work involved and designated accordingly.

WARNING Non-observance of warnings can result in death, severe personal injury and substantial property and environmental damage.

6.1.1 Maintenance Services (Schedule)

The inspection and maintenance services scheduled in the Table 13 are each offered separately by Siemens Ltd..

Circuit-breakers which are operated frequently obviously suffer greater wear than circuit-breakers operated only seldom. The following distinction must be made:

- Mechanical wear caused by friction (mechanical operating cycles) and

- Arc erosion due to the switching of load currents or fault currents.

The wear reserve is calculated so that in most cases the various inspection and maintenance services can be performed at fixed intervals. Only if the circuit-breakers are operated particularly frequently might it be necessary to bring forward the corresponding service, because the permissible number of mechanical operations and/or load or fault switching operations have already been exceeded (see section 5.1.5 Max. Permissible Number of Interruptions).

6.1.2 Assignment of Personnel

The inspection and maintenance service may only be carried out by or under the supervision of qualified per-sonnel. This personnel can be assigned by the customer or the next Siemens office.

Tel.: +91 240 2565 142

Fax: +91 240 2554 701

If requested, the customer's personnel can be trained at the manufacturer's works.

The advantage of calling in Siemens personnel is that the work is carried out in accordance with the latest information and experience gained with a large number of circuit-breakers. This is then reflected in the circuit-breaker having a higher reliability standard. Moreover, the fact that they are familiar with the circuit-breaker also enables Siemens personnel to do the job in less time. In this way service interruptions are kept to a minimum.

Assignment of Siemens personnel also means that tools and measuring instruments etc. that are usually not worth buying are provided on a hire basis.

"Maintenance kits" required as part of maintenance, as well as consumables (cleaning liquids, lubricants etc., see section 4.3 Cleaning Liquids, Lubricants and Corrosion Protection Agents) are also supplied.

6.1.3 Maintenance Kits

Maintenance kits contain various spare parts in the appropriate quantities for the particular service.

83

Page 85: 400kV Circuit Breaker_O&M

84

6 Maintenance

Maintenance kits are supplied and charged for by Siemens Ltd. as part of the inspection and maintenance service.

It is not advisable for the customer to hold stocks of maintenance kits, as some parts, e.g. O-ring seals, are subject to aging.

6.1.4 Initial Date for Inspection and Maintenance Service

The starting date for the inspection and maintenance schedule is that at which the filter material is placed in the circuit-breaker, which is then evacuated and filled with gas. This is normally the year of production.

The starting date is only related to the insertion of the filter material, not to the date of energization.

The starting date should be recorded in writing and the number of mechanical operations and fault current operations etc. monitored in order to see whether inspection and maintenance should be carried out as a function of time or of wear.

6.1.5 Disturbances

In the event of a disturbance, please request appropriate Siemens representation of qualified personnel. We ask you to state the type and extent of the disturbance as accurately as possible. Please name any that are showing signs of damage. To simplify identification, state the designations given in the operating instructions (designations and part numbers together with the order number of the operating instructions 927 00966 174 A, page number, number of the illustration) and state the serial number of the circuit-breaker concerned.

6.1.6 Points to be Noted

The locking elements of any screwed joints opened for inspection must be replaced.

The same applies to all seals and gaskets exposed in the process. All open circuit-breaker parts should be covered to prevent the ingress of dirt.

During normal operation no switching dust should result from switching. If dust is found after repeated interruption of high short-circuit currents, proceed as follows:

Any switching dust should be removed immediately when the circuit-breaker is opened and any subassemblies have been removed. When this dust is exposed to air for some time it will absorb moisture and can then only be removed with difficulty.

Gloves should be worn!

Remove the dust with a piece of cloth or use a vacuum cleaner. Do not stir it up unnecessarily. Cloths and switching dust should be disposed of in keeping with environmental regulations.

Page 86: 400kV Circuit Breaker_O&M

6 Maintenance

6.2 Safety Rules for Inspection and Maintenance Service - General

WARNING Danger to maintenance personnel can result from

- hazardous voltage

- operating mechanisms under spring pressure

- gas pressure in the pole columns

- SF6-gas and its decomposition products

- falling and/or toppling parts and/or moving parts.

Non-observance of warnings can result in death, severe personal injury and substantial property and environmental damage.

In order to avoid accidents, fire and impermissible burdens on the environment and in order to assure the functional reliability of the switchgear, the user must ensure that:

- a responsible person, if necessary authorized to supervise, is put in charge of performance of maintenance

- only qualified and instructed personnel are assigned,

- the regulations and instructions for work safety (e.g. in the use of equipment), together with instructions on action to be taken in the event of accidents and fire, are available at all times and if necessary displayed in the place of work,

- the tools, equipment and apparatus required for work safety and the personal protective equipment required for certain tasks are available,

- only those materials, lubricants and auxiliary equipment approved by the manufacturer are used.

The safety regulations in these operating instructions are minimum requirements. They do not affect statutory laws, standards, specifications or internal regulations of the company concerned with the work. They do not claim to cover all eventualities and must be expressed concretely by the responsible persons at the latest before work actually starts. In addition to company internal rules and the specific work conditions, the product descriptions and instructions for use of tools, devices, apparatus, materials, lubricants and auxiliary equipment must be taken into account.

85

Page 87: 400kV Circuit Breaker_O&M

86

6 Maintenance

The following safety regulations provide an overview of the dangers existing and their sources, and describe the possible consequences if the rules specified are not complied with. They are expressed more exactly in the operating instructions.

Hazardous voltage - Electric shock and burning as a result of arcing are possible if live parts are approached.

Before maintenance is to be done, a responsible person from the power supply utility must, before work starts: - Switch off and isolate - Prevent unintentional switch-on - Test that equipment is dead - Ground and short-circuit the equipment - Cover or fence off nearby live parts

It must be confirmed that these safety measures have been taken.

The closing and opening springs may be charged. If the control and motor power supply are not switched off, the closing spring will be automatically recharged after a closing operation. The spring state indicator shows only the position of the closing spring - unintentional switching operations can lead to severe personal injury.

Before beginning maintenance work, relax the opening and closing springs as follows: - Disconnect motor power supply, - open the circuit-breaker, if the circuit-breaker is in the CLOSED position. - close the circuit-breaker and - re-open the circuit-breaker. - disconnect the control voltage.

The pole columns are under pressure (see section 3.1.6 Arc Quenching Medium SF6) - Damage to the porcelain parts can result in severe personal injury. - Before opening interrupter units, ensure pressure relief by means of the facility provided. - After relieving the pressure, gradually and uniformly undo the screw joints. - Do not allow any tools or hoisting gear to knock against the porcelain parts. - Do not lean any ladders against the pole columns;use step ladders.

SF6 is heavier than air and can displace the air required for breathing - Danger of suffocation!

Page 88: 400kV Circuit Breaker_O&M

87

6 Maintenance

- SF6 is odourless, non-toxic and about five times heavier than air. SF6 leads to displacement of oxy gen. SF6 concentrations of more than 19 % vol. call for special protective measures. Such concentrations can occur in opened and unventilated SF6 compartments, in confined spaces on the floor of switchgear installations and in lower-level rooms (e.g. basements, cable ducts).

- Sulphur hexafluoride (SF6) must not be let off to the atmosphere. For maintenance work gas servicing equipment should be used.

Specifications for the use of SF6 gas

- IEC 60376

- IEC 60480

For Germany, the following also applies: Accident prevention sheet (relating to SF6 installations) issued by the statutory industrial accident insurance institution for precision mechanics and electrical engineering.

Under effects of arcs, gaseous decomposition products and switching dust occur. Decomposition products of SF6 are toxic - Coming into physical contact with them or inhaling them can cause irritation to the skin, eyes and mucous membranes. Nausea, dizzines and lung oedema can result.

- These substances vary in toxicity. In combination with moisture, switching dust is caustic and forms a coating that sticks fast.

- Small quantities of gaseous decomposition products already initiate alarm signals, e.g. pungent disagreeable smell similar to rotten eggs (hydrogen sulphide), before there is danger of suffocation.

- If emptied housings are opened after correct pressure relief, there is the possibility of contact with switching dust.

- Do not inhale or swallow switching dust (use dust masks), avoid contact with the eyes (wear gas-tight goggles) and the skin (use special working clothes).

- If switching dust has got onto the skin nevertheless, use plenty of water to rinse it off.

- Handle filters, rags and other material so that the dust extracted does not come off again. Do not open filter bags. Work clothes, filter bags, rags etc. which have come into contact with such dust, dispose of according to local regulations.

- Local environmental protection regulations must always be taken into account when SF6 is disposed of. In special cases regarding SF6 disposal, the nearest Siemens office should be contacted.

- Thoroughly clean face, neck, arms and hands with soap and plenty of water before breaks and at the end of work.

- Do not eat, drink or smoke in rooms containing opened gas compartments with switching dust, and do not keep any foodstuffs in them.

Page 89: 400kV Circuit Breaker_O&M

6 Maintenance

6.3 Maintenance Schedule

The maintenance schedule provides an overview of work to be done in the individual checks/inspections. A detailed description of the work steps is given in section 6.4 Work to be Carried Out in Accordance with the Maintenance Schedule. In both sections, the work steps are referred to by the same numbers.

WARNING Danger to maintenance personnel can result from

- hazardous voltage

- operating mechanisms under spring pressure

- gas pressure in the pole columns

- SF6-gas and its decomposition products

- falling and/or toppling parts and/or moving parts.

The Safety rules listed in section 6.2 should be followed.

Check and maintenance service

Due to time interval Due to wear Remarks

Checks After 12 years after 3000 operating cycles I < Inom

Circuit-breaker must be taken out of service and must be isolated. Gas compartments need not be opened.

Maintenance After 25 years after 6000 operating cycles I < Inom

Circuit-breaker must be taken out of service and must be isolated. Gas compartments are opened.

Check of contact system Permitted conductor pull F Circuit-breaker must be taken out of service and must be isolated. Gas compartments are opened.

Table 13 Maintenance services

88

Page 90: 400kV Circuit Breaker_O&M

89

6 Maintenance

6.3.1 Maintenance Schedule

A B Subsection Maintenance service

X X 6.4.1 General Inspection

X 6.4.2 Drawing Off the SF6 Gas

X 6.4.3 Check of Contact System

X 6.4.3.1 Dimensional Check on the Contact System

X 6.4.3.2 Replace Filter

X 6.4.4 Evacuating and Filling the Circuit-Breaker with Gas

X 6.4.5 Check Gas Pressure Gauge

X X 6.4.6.1 Check Function of Gas Density Monitor

X 6.4.6.2 Check of the Operating Values of the Gas Density Monitor

X 6.4.7 Check for Leaks on Operational Circuit-Breaker

X X 6.4.8 Checks at Drive Mechanism

X 6.4.9 Terminal Strip

X X 6.4.10 Anti-Condensation Heaters

X X 6.4.11.1 Functional Check, Trip Circuits

X X 6.4.11.2.1 Functional Check, Reclosing Lock-Out

X X 6.4.11.2.2 Functional Check SF6 Lockout

X X 6.4.11.3 Functional Check, Anti-Pumping Feature

X X 6.4.11.4 Function Check of Enforced Triple-Pole Operation Feature

X X 6.4.12 Check of Motor Control

X 6.4.13 Measuring the SF6 Gas Humidity Content

X 6.4.14 Measuring the SF6 Air Content

X X 6.4.15 Anti-Corrosion Protection

Table 14 Maintenance Schedule

A = Checks B = Maintenance 6 Maintenance

6.4 Work to be Carried Out in Accordance with the Maintenance Schedule

The measures compiled in the section 6.3 Maintenance Schedule are described in detail below.

6.4.1 General Inspection

The general inspection covers a visual check of the circuit-breaker without it having to be dismantled. The visual check contents the following checks:

- Check the SF6 filling with the circuit-breaker pressure gauge, see 6.4.1.1.

- contamination of insulating parts

- damage to the porcelain body

- Earth terminal

- Number of operating cycles

6.4.1.1 Check the SF6 Filling with the Circuit-Breaker Pressure Gauge

Page 91: 400kV Circuit Breaker_O&M

90

When measuring, the temperature dependence of the pressure as shown in the diagram SF6 filling curve and operating values of density monitor (see 3.1.6 Arc Quenching Medium SF6) should be taken into account.

This means that, if possible, the mean temperature of the SF6 gas in the circuit-breaker should be determined (Measurements should be avoided in times of strong fluctuations of the ambient temperature and immediately after high-current loads).

If the measured value falls below the specified SF6 filling curve, correct the SF6 gas filling (using a gas cylinder or service unit).

Check humidity and the air content of the SF6-gas that may be left in the service unit (see 6.4.13 Measuring the SF6 Gas Humidity Content).

If the measured SF6 pressure lies below the filling curve by not more than 0.30 bar (permissible gas loss), refill with SF6.

If the measured value is more than 0.30 bar below the filling curve specified, a leak test must be carried out and the leak must be repaired. Then the filling must be corrected.

6.4.2 Drawing Off the SF6 Gas

It is recommended to draw off the SF6-gas with a service unit so that it can again be used almost completely for the subsequent filling. The service unit has all the facilities for drawing off and filling the SF6-gas.

The condition of the SF6-gas in the service unit should be checked in advance.

6.4.3 Check of Contact System

The interrupter unit is described in section 3.4 Interrupter Unit.

Note

For the contact system check it is necessary to call in Siemens personal.

6.4.3.1 Dimensional Check on the Contact System

The inspection of the contact system has to be made by a dimensional and a visual check.

The permissible contact erosion will be given by the dimension a.

22.11.17 Piston 22.17.1 Pull rod 22.17.2 Coupling rod 22.23 Base 22.9 Pin Fig. 60 Inspection of contact carrier

Page 92: 400kV Circuit Breaker_O&M

91

6.4.3.2 Replace Filter

It is absolutely necessary to protect the filter material against atmospheric humidity. The material must therefore not be directly exposed to the open air for a longer period than 1 hour. It is supplied in closed tins.

Check the closed tins for damage. Filter material from leaky tins must not be used.

The filter material is accommodated in the filter cowl (see 3.4 Interrupter Unit). Remove cover 15.16.11 with O-seal ring (Fig. 61) (4xM10 screws). Remove the old filter bags from the filter cowls. Lay the new filter bags in the filter cowls. Grease cover 15.16.11 (Fig. 62) with seal ring at the sealing surfaces and reinstall (4xM10 screws).

Page 93: 400kV Circuit Breaker_O&M

6 Maintenance

Note

Dispose of old filter bags 15.16.3 in accordance with local regulations.

Note

Do not fit new filter bags until shortly before evacuation (max. one hour).

A Grease with corrosion protection agent WD 40 or

Trost multifunction oil B Grease with Tectyl 506 1 Grease sealing rings with Vaseline 8420 15 Corner gear 15.16.11 Cover with O-seal ring Fig. 61 Treatment of the sealing flanges

15.11 Filter cowl 15.16.1 Sealing ring 15.16.11 Cover with O-seal ring 15.16.3 Filter bag Fig. 62 Inserting the filter

6.4.4 Evacuating and Filling the Circuit-Breaker with Gas

The circuit-breaker may be filled only by or under the supervision of qualified personnel, and in accordance with the SF6 filling curve (see under 3.1.6 Arc Quenching Medium SF6).

92

Page 94: 400kV Circuit Breaker_O&M

93

6 Maintenance

WARNING A safety valve with a nominal opening pressure of 8.0 bar must be part of the filling device.

The safety valve prevents the pressure compartments from being overstressed due to an impermissibly high pressure.

To fill the breaker with gas, a service unit may be used since this contains all the necessary facilities.

If a service unit is not available, a vacuum pump must then be available for evacuating the circuit-breaker prior to the SF6 being filled in.

The SF6-gas is then taken directly from a gas cylinder via the SF6 filling device W423.

Filling by using a service unit

Connect the service unit at the filling connection W1 (Fig. 63). Evacuate the circuit-breaker down to a pressure of < 0.02 bar; then switch the service unit for "fill". The required filling pressure and response values are temperature-dependent and must be taken from the diagram, SF6 filling curve and response values of the density monitor, see 3.1 Technical Data.

1001304a

W1 Filling flange Fig. 63 Filling flange W1

Filling the breaker from the gas cylinder

Siemens offers a complete filling device of type W423 for filling the circuit-breaker with SF6 gas from a gas cylinder (Fig. 64).

Page 95: 400kV Circuit Breaker_O&M

94

6 Maintenance

W1 Filling flange 1 Gas cylinder 2 Pressure reducer regulating valve 3 Precision pressure gauge (-1.0 bar up to 9.0 bar) 4 Safety valve Fig. 65 Gas filling device connected

To fill, couple the service connection of the filling device with the filling connection W1 (Fig. 63). Slowly open the regulating valve (Fig. 65) at the pressure reducer with the vent valve closed, to avoid any ice formation at the fitting. Monitor the filling process at the precision pressure gauge 3.

Care must be taken that the filling pressure, which depends on the ambient temperature, is correct. For nominal filling pressure see diagram in section 3.1 Technical Data.

At an ambient temperature other than +20°C, the SF6 filling pressure must be taken from the diagram (Fig.1).

Page 96: 400kV Circuit Breaker_O&M

95

6 Maintenance

The filling pressure may be up to 0.30 bar over the nominal pressure curve (temperature-independent).

When filling is completed, unscrew the filling device and close maintenance flange W1 (from Dilo). Tighten the union nut by hand (4 Nm).

6.4.5 Check Gas Pressure Gauge

The difference between the measured values on the test pressure gauge class 0.6 and the operating pressure class 1.0 must not be greater than the sum of the permissible divergence between the two pressure gauges. This means that with a test pressure gauge of class 0.6 having a range from 15.0 bar the divergence from the circuit-breaker pressure gauge of class 1.0 must not be greater than 0.30 bar. A divergence greater than 0.30 bar must be noted at the circuit-breaker pressure gauge (handwritten on adhesive tape).

6.4.6 Testing the Density Monitor

6.4.6.1 Check Function of Gas Density Monitor

Undo sealing cap on test connection W2 (the gas compartment and density monitor are separated by a nonreturn valve) and check whether the density monitor contacts respond.

6.4.6.2 Check of the Operating Values of the Gas Density Monitor

Note

The adjustments of the density monitor for the SF6 signals and the SF6 general lockout cannot be monitored by the filling device W423. For this the filling device W424 is required instead.

For testing the density monitor B4, a connection W2 is provided in the rear wall of the operating mechanism unit 18. (3/4" thread, Fig. 66). The hose of SF6 filling unit W424 can be connected here without any SF6 having to be extracted from the circuit-breaker.

Page 97: 400kV Circuit Breaker_O&M

6 Maintenance

B4

1001305a

B4 Density monitor W2 Test connection Fig. 66 Test connection W2 (view with cover of the contact position indicator removed)

To check the density monitors, remove nut with insert. Gas cannot escape from the breaker with the service connection open. The service connection W2 is now directly connected with the density monitor, so that after connection of the filling device W424 the switching points of the density monitor can be checked by regulation of the SF6 pressure at the pressure reducer (section 3.1.6 Arc Quenching Medium SF6).

6.4.7 Check for Leaks on Operational Circuit-Breaker

The rated pressure of the SF6-gas can be found in the table in the section 3.1.6 Arc Quenching Medium SF6. When the filling of the circuit-breaker is completed, all new connections must be checked for leaks. This can occur with a leak-detector or leak-detecting spray e.g. from Wobst. If neither is available, leaks can also be checked using soap solution.

If a leak is detected:

WARNING Release the SF6-pressure before working on the screw connections of the gas chamber.

If a leak is discovered, undo the leaking connection and check the sealing surface for damage or foreign bodies. Then fit a new seal, remake the connection and repeat the leak test.

96

Page 98: 400kV Circuit Breaker_O&M

97

6 Maintenance

6.4.8 Checks at Drive Mechanism

6.4.8.1 Auxiliary Switch

The bearings of the auxiliary switch are maintenance-free. The coupling gear must be checked for wear and damage (Fig. 67).

18.10

18.22

18.10 Coupling rod for auxiliary switch 18.22 Auxiliary switch Fig. 67 Auxiliary switch

Should leads be disconnected from the auxiliary switch contact, press the spring shackle at the AMP connector to release. With AMP connectors with insulation casing, release is automatic when the sleeves are pulled (Fig. 68). 1 Insulation sleeve 2 Spring shackle 3 Direction of pull Fig. 68 AMP connector

Page 99: 400kV Circuit Breaker_O&M

6 Maintenance

6.4.8.2 Visual Inspection of the Spring Drive Mechanism

Visually inspect dampers for closing and opening for any leaks. Look out for reddish oil traces in the vicinity of the lower damper fastener (Fig. 69).

Note

If you find any reddish oil traces at the specified positions (Fig. 69), inform the Siemens representative responsible and ask for expert assistence.

18.15 Damper for opening 18.41 Damper for closing Fig. 69 Check the dampers

6.4.8.3 Check Trip Coil and Latching Blocks

Check firm connection of the trip plate (cheese head screws M6x40, tightening torque 8±1 Nm) and the latching blocks (cheese head screws M 10x70, tightening torque 40±4 Nm) (Fig. 70).

98

Page 100: 400kV Circuit Breaker_O&M

6 Maintenance

A Cheese-head screw M 10x70 18.16 Release CLOSE 18.21.1 Support lever 18.21.2 Reversing lever 18.21.4 Hex. screw 4x (M6x40) 18.8 Release OPEN Fig. 70 Latching block

6.4.9 Terminal Strip

Check the terminal connections for firm seating and the terminals for damage.

6.4.10 Anti-Condensation Heaters

Check the effectiveness of the anti-condensation heating and the function of the existing monitoring device if applicable.

6.4.11 Function Checks

6.4.11.1 Functional Check, Trip Circuits

Check the tripping action of the circuit-breaker via all the existing tripping paths.

6.4.11.2 Functional Check Lock-Out

6.4.11.2.1 Functional Check, Reclosing Lock-Out

During the process of charging the closing spring, the effectiveness of the reclosing lock-out must be checked by means of an electrical CLOSE command. The tripping coil must not operate.

Perform this check at all poles.

6.4.11.2.2 Functional Check SF6 Lockout

At a level below the operating pressure, check the signal and the effectiveness of the function lockout SF6 lockout by means of electrical CLOSE and OPEN commands in all tripping paths. The circuit-breaker must not operate.

99

Page 101: 400kV Circuit Breaker_O&M

100

6 Maintenance

6.4.11.3 Functional Check, Anti-Pumping Feature

Circuit-breaker in closed position: (closing spring tensioned)

- Give electrical CLOSE command and keep button pressed in (maintained command)

The circuit-breaker must only switch off.

6.4.11.4 Function Check of Enforced Triple-Pole Operation Feature

Close all three poles of the circuit-breaker and open one of them by actuating the operating trip 18.8 (Fig. 70). After the time set on the enforced triple-pole operation relay on the plant side has elapsed, the other two circuit-breaker poles must also be tripped by the enforced triple-pole operation contactor. Carry out this test in a similar manner on the other two circuit-breaker poles.

6.4.12 Check of Motor Control

Check whether after a closing operation the motor is activated by a limit switch, and, whether after the charging process of the closing spring the motor is deactivated via a limit switch.

Perform this check at all poles.

6.4.13 Measuring the SF6 Gas Humidity Content

Before putting the breaker into operation, the humidity of the SF6-gas must be checked. For this a commercially available dew point measuring instrument with °C scale can be used. The maximum permissible dew point temperatures at operating pressure corresponding to the permissible humidity are stated below.

Critical humidity limit -5°C (+23°F) Maximum permissible humidity during commissioning/in operation

-10°C(+14°F)

Table 15 Dew point

If the measured dew point temperature lies above -10°C/+14°F, then the SF6 gas must dried using a service unit.

6.4.14 Measuring the SF6 Air Content

When the breaker has been filled with new gas and following maintenance work, the air content should not be more than 5 % as measured with the SF6 percentage instrument 3-027 from DILO (D-87727 Babenhausen, Federal Republic of Germany). This instrument measures the SF6 volumetric portion (at least 95 %).

Page 102: 400kV Circuit Breaker_O&M

101

6 Maintenance

6.4.15 Anti-Corrosion Protection

Check the paintwork of the circuit-breaker for damage. Defective parts must be derusted, provided with a priming coat and varnished.

6.4.16 Special Occurrences

Check whether, since the last instance of maintenance, any special occurrences, e.g. incorrect opening and closing of the circuit-breaker, loss of SF6-gas etc. have been documented.

Page 103: 400kV Circuit Breaker_O&M

102

SIEMENS Commissioning Report for the Circuit-Breaker 3AP

General

Customer Name of inspector

Substation Signature

Feeder Countersignature

Circuit-breaker type Date

Technical data

Serial number:

SF6 - filling pressure at + 20°C, ace. to rating plate Bar

Rated voltage KV

Rated normal current A

Rated short-circuit breaking current KA

Rated control voltage V

Rated signalling voltage V

Rated voltage (circuit-breaker charging motor) V

Rated current (Charging motor of the circuit-breaker) A

Circuit diagram no./lndex (Circuit-breaker)

Order number of the operating instruction/index

Switching duty

Overhead line Transformer

Generator Cable

Coupling Capacitor

Shunt reactor

Other

Page 104: 400kV Circuit Breaker_O&M

103

Attention

Mechanical test operations must only be performed with sufficient SF6 gas filling: Pressure must at least be at the level of general lockout SF6.

Transport damage

Pole A Pole B Pole C OK

Delivery complete ace. to check list

Visual check for damages (post insulator/bushing and interrupter unit)

Operating mechanism

Control

Transport damage notified

Check SF6 transport filling (only 3AP1)

Installation

OK

In accordance with operating instructions in chapter Installation

If commissioning is not performed immediately the items listed below must be checked:

Pole A Pole B Pole C OK

Electrical circuit for charging motor is interrupted at a suitable point

Anti-condensation heaters connected

Evacuation (.... min, .... mbar) (3AP2, 3AP1 DT)

Date of charging the filters (3AP1 DT)

Protective gas filling (SF6 filling to approx. 0.30 bar) bar

Page 105: 400kV Circuit Breaker_O&M

104

Commissioning

Pole A Pole B Pole C OK

Motor circuit-breaker setting checked (see circuit diagram)

MCBs (if included in scope of supply): tripping current in accordance with circuit diagram > ln [A]

Check of the anti-condensation heaters (all phases) [A]

SF6 -system filled up to rated pressure [bar/°C]

5 CLOSED-OPEN safety switching operations (by remote control, 60 m safety distance)

Attention On three phase A.C. motors, the rotary field direction must be taken into account when connecting the motor voltage.

Function tests ace. to breaker circuit diagrams

OPEN-CLOSE switching operations, lockouts, signals, anti-pumping etc. All details checked against circuit-breaker circuit diagram and system circuit diagram, in particular:

OK

Closing 1

Closing 2

Opening 1

Opening 2

Opening 3

Page 106: 400kV Circuit Breaker_O&M

105

Monitoring SF6

Pole A Pole B Pole C Unit Control

Density monitor serial number -

Loss of SF6 bar/°C

1. General lockout SF6 bar/°C

2. General lockout SF6 bar/°C

bar/°C

bar/°C

bar/°C

Page 107: 400kV Circuit Breaker_O&M

106

Signals (1)

OK

Charging motor: Charging time (< 15 s) s

K9 picked up (motor starting)

Closing spring discharged

1. Auto-reclose lockout Signal Time delay of signal

s

Auto-reclose interlocking I

Auto-reclose interlocking II

2. Auto-reclose lockout Signal Time delay of signal

s

Auto-reclose interlocking 1

Auto-reclose interlocking II

Enforced triple-pole operation feature 1 Signal

Time delay of signal

s

Closing lockout 1

Enforced triple-pole operation feature 2 Signal

Time delay of signal

s

Closing lockout 2

Anti-pumping device 1

Anti-pumping device 2

Circuit-breaker tripping

Indication of circuit-breaker position

Relays, contactors in local control panel (for testing see system circuit diagram)

Operating cycles counter

Page 108: 400kV Circuit Breaker_O&M

107

Signals (2)

OK

Anti-condensation heaters (MCB trip signal F3)

Heating current monitoring functional

Charging motor (MCB trip signal F1)

Limit switch

Damping

Automatic TRIP

Synchronization of the circuit-breaker poles

Motor run time monitoring Signal Time delay of signal

min

Operating hours counter

Socket and lighting

Switch (remote/local control)

The stated functional tests were performed up to the control panel in the circuit-breaker control cabinet/local control cabinet or control room

Page 109: 400kV Circuit Breaker_O&M

108

Final checks

Pole A Pole B Pole C Unit

SF6 leaktightness testing of newly made joints

SF6 humidity (dew point)1)2) °C

SF6 content2) %

Final SF6 filling bar/°C

Date of taking measurements Date

Leads firmly connected to main terminal

Operations counter reading after completion of work

Damage to paintwork repaired and newly fitted screws painted

1) Maximum permissible dew point during commissioning = -10 °C (+14 °F) 2) Measurements not required if gas filled from a new

cylinder

Remarks Remarks

Please complete and return to: Siemens Ltd. PTD H 3 – Circuit Breaker E-76, Waluj MIDC Aurangabad - 431136 India Fax: +91 240 2554 701