4.6.3.2 Explanation and dimension of attachment 4.6.3.2.1 Explanation A complete frame is composed of: 1 front girder (1), 1 rear girder (2), 2 lateral girders (3) and (4), 1 diagonal bracing (5), 2 brackets (6) and (7) equipped with 2 shims (8) and 2 wedges (9) and fitted onto the diagonal bracing (5), 2 brackets (10) and (11), 4 taper keys and various fixing shafts.The front girder (1) has 4 holes in order to allow the fixing of the frame with the building by means of the shafts (13). 4.6.3.2.2 Main dimension of 2m attachment JT262.12 Maintenance Edition 00 – 01/2014 Page 1

description

JKT Tower Crane JT262.12 Assembley Manual

Transcript of 4-3-Assembly(JT262.12)

Page 1: 4-3-Assembly(JT262.12)

4.6.3.2 Explanation and dimension of attachment 4.6.3.2.1 Explanation

A complete frame is composed of:1 front girder (1), 1 rear girder (2), 2 lateral girders (3) and (4), 1 diagonal bracing (5), 2

brackets (6) and (7) equipped with 2 shims (8) and 2 wedges (9) and fitted onto the diagonal bracing (5), 2 brackets (10) and (11), 4 taper keys and various fixing shafts.The front girder (1) has 4 holes in order to allow the fixing of the frame with the building by means of the shafts (13).

4.6.3.2.2 Main dimension of 2m attachment

4.6.4 Installation of 2m attachmentRemove the standard ladder from the mast section which will be equipped with the anchorage

frame. On the ground, place the two lateral girders (1) and (2) onto the front girder (3) (insert shaft (4) only in order to make the spacing of the girders (1) and (2) easier) (Detail A and B- Figure 1).

JT262.12 Maintenance

Edition 00 – 01/2014 Page 1

Page 2: 4-3-Assembly(JT262.12)

Sling and raise the assembly until it reaches the right position on the mast (with the side of the anchoring beam attachment (3) towards the building) (Detail A-Figure 1). In order to make fitting easier, use 2 cords for guiding.

Rest the gussets (5) of the front girder (3) onto the horizontal bracings (6) located in the middle of the mast section (Detail C- Figure 1).

Fold back the lateral girders (1) and (2) and pin−connect the shafts (7) (Detail A and B − Figure 2).

Sling and raise the lateral girder (8), position it and pin−connect it to the rear girders (1) and (2) using the shafts (9) and (10) (Detail C and D − Figure 2).

JT262.12 Maintenance

Edition 00 – 01/2014 Page 2

Page 3: 4-3-Assembly(JT262.12)

Raise and place the bracket (11) equipped with the shim (12), then pin−connect it onto the girders (1) and (2) by means of the shafts (13); fix with split pins (Detail A and B − Figure 3).

Raise and place the bracket (14) equipped with the shim (15), then pin−connect it onto the girders (16) and (17) by means of the shafts (18); fix with split pins (Detail A and B − Figure 3).

Place and pin the diagonal bracing bar (23); pin−connect it onto the brackets (19) and (20) by

JT262.12 Maintenance

Edition 00 – 01/2014 Page 3

Page 4: 4-3-Assembly(JT262.12)

means of the shafts (24) (Detail C − Figure 3).

Check the level of the frame, readjust if required.Place the outer wedges (25) and act on them in order to bring the frame into contact with the

mast uprights (Detail A − Figure 4).Place the inner wedges (26) and drive them in so that the shim (27) comes hard against the

inner side of the mast uprights (28) (Detail A − Figure 4).Having carried out these operations, check that there is no play remaining between the

wedges and the mast uprights.Fit the ladder (29) supplied with the frame instead of the standard ladder, then equip it with its

two back loop parts (30) (Detail B − Figure 4 ).

JT262.12 Maintenance

Edition 00 – 01/2014 Page 4

Page 5: 4-3-Assembly(JT262.12)

4.7 Climbing insde the buliding 4.7.1 General notes

JT262.12 Maintenance

Edition 00 – 01/2014 Page 5

Page 6: 4-3-Assembly(JT262.12)

4.7.1.1 Complete mast section L68D

4.7.1.2 Complete mast section L68C

JT262.12 Maintenance

Edition 00 – 01/2014 Page 6

Page 7: 4-3-Assembly(JT262.12)

4.7.1.3 Complete standard mast section L68B2

4.7.1.3 Equipped climbing collar BA65B

JT262.12 Maintenance

Edition 00 – 01/2014 Page 7

Page 8: 4-3-Assembly(JT262.12)

4.7.2 Climbing insde the building

JT262.12 Maintenance

Edition 00 – 01/2014 Page 8

Page 9: 4-3-Assembly(JT262.12)

4.7.2.3 Composition of the crane tower

JT262.12 Maintenance

Edition 00 – 01/2014 Page 9

Page 10: 4-3-Assembly(JT262.12)

The composition of the crane tower and minimun distance between the climbing collars 12m.Compulsory:The reinforced mast section

must always be located just opposite to the upper climbing collar.This must be compulsory take into account for placing it during the erection of the crane tower(Detail A)

4.7.3 Summary of mast sections for crane tower 2,0m

JT262.12 Maintenance

Edition 00 – 01/2014 Page 10

Page 11: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 11

Page 12: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 12

Page 13: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 13

Page 14: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 14

Page 15: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 15

Page 16: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 16

Page 17: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 17

Page 18: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 18

Page 19: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 19

Page 20: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 20

Page 21: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 21

Page 22: 4-3-Assembly(JT262.12)

JT262.12 Maintenance

Edition 00 – 01/2014 Page 22