![Page 1: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/1.jpg)
395 Express Lanes Project Update Parkfairfax | October 11, 2018
![Page 2: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/2.jpg)
2
Project Overview
395 Express Lanes Project Update
• Project involves: – Expansion and conversion of two High
Occupancy Vehicle (HOV) lanes to three Express Lanes
– Addition of a fourth regular Southbound lane on 395 between Duke Street and Edsall Road
– Improvements in traffic flow at the Eads Street Interchange and carpool access at the Pentagon
– Installation and modification of sound walls – Rehabilitation of bridges over 395
• Extends 8 miles between Edsall Road and the 14th Street Bridge
• Portions of project in Arlington County, City of Alexandria, and Fairfax County
• Some project elements will be located on the Pentagon Reservation
• Project will generate revenue for transit projects such as improved bus services
![Page 3: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/3.jpg)
3
Key Dates
Milestone Date
Full Notice to Proceed July 2017
Draft Noise Abatement Decision Report (NADR) Submitted for VDOT review
Summer 2017
Community Voting on Sound Wall Installation Fall 2017
Eastern HOV Shoulder Late 2017
Western HOV Shoulder Fall 2018
Pentagon Parking Improvements Completion
Spring 2019
Service Commencement Spring 2019
Final Completion Fall 2019
395 Express Lanes Project Update
![Page 4: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/4.jpg)
4
Sound Wall Voting Process
395 Express Lanes Project Update
Community voting process
– Voting began in fall 2017 after VDOT review of Final NADR – Residents by Barrier F1 voted 91% in favor of the wall – Residents by Barrier F2 voted 58.6% in favor of the wall
![Page 5: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/5.jpg)
5
Sound Wall Voting Outcome – Noise Barrier F-1
395 Express Lanes Project Update
Green/Black Dotted Line: Proposed Wall Location. Red/Black Dotted Line: Wall Not Recommended For Construction. Red Dots: Voted No. Green Dots: Voted Yes. Orange Dots: Ballot Unclaimed/Unknown/Returned. Purple Dots: Received, Survey Not Returned.
![Page 6: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/6.jpg)
6
Sound Wall Designs F-1
395 Express Lanes Project Update
Lightweight structure mounted barrier The wall with metal
panels will be mounted on the existing concrete barriers Wall height will average
21 feet.
![Page 7: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/7.jpg)
7
Sound Wall Voting Outcome – Noise Barrier F-2
395 Express Lanes Project Update
Green/Black Dotted Line: Proposed Wall Location. Red/Black Dotted Line: Wall Not Recommended For Construction. Red Dots: Voted No. Green Dots: Voted Yes. Orange Dots: Ballot Unclaimed/Unknown/Returned. Purple Dots: Received, Survey Not Returned.
![Page 8: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/8.jpg)
8
Sound Wall Build Update – Noise Barrier F-2
395 Express Lanes Project Update
Green/Black Dotted Line: Proposed Wall Location. Red/Black Dotted Line: Wall Not Recommended For Construction.
![Page 9: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/9.jpg)
9
Sound Wall Designs F-2
395 Express Lanes Project Update
![Page 10: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/10.jpg)
10
Sound Wall Designs F-2
395 Express Lanes Project Update
![Page 11: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/11.jpg)
11
Sound Wall F-1/F-2 Anticipated Schedule
395 Express Lanes Project Update
Spring 2019 – Earthwork and grading to begin – Utility relocation / fence removal
Summer 2019
– Drill foundation – Set wall posts – Pour concrete to set the foundation
Fall 2019
– Install wall panels – Drainage / backfill and grade – Close up walls – Construction completed
![Page 12: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/12.jpg)
12
Anticipated Construction Impacts
395 Express Lanes Project Update
Noise – The project team follows the Virginia Department of Transportation’s
policies to reduce the impact of construction noise on the surrounding community.
Vegetation Loss
– Vegetation is removed as required to build the wall. This is limited as much as possible.
Traffic Impacts – Temporary lane, ramp, and road closures may be needed to access certain
sound wall sections. During any necessary ramp/road closures a detour will be provided.
![Page 13: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/13.jpg)
13
Parkfairfax Gunston Road DMS
395 Express Lanes Project Update
![Page 14: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/14.jpg)
14 395 Express Lanes Project Update
Parkfairfax Gunston Road DMS
![Page 15: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/15.jpg)
15 395 Express Lanes Project Update
Parkfairfax Gunston Road DMS
![Page 16: 395 Express Lanes Project Update - Parkfairfax · – Addition of a fourth regular Southbound lane on ... Interchange and carpool access at the Pentagon – Installation and modification](https://reader034.fdocuments.net/reader034/viewer/2022042113/5e8fd93c4ea5e5477d3b1061/html5/thumbnails/16.jpg)
16
Thank you For more information
and to sign up for updates, please visit www.395expresslanes.com
or find us on Facebook at www.facebook.com/395expresslanes
395 Express Lanes Project Update
Questions or concerns should be directed to:
Michelle Holland, VDOT, [email protected], 703-586-0487
Brent McKenzie, 95 Express Lanes, [email protected], 571-326-5609
Andy Kropf, Lane/AECOM Design-Build Team, [email protected], 703-418-3170
Please contact us if you would like additional information or would like to be invited to briefings we host in your community.