2002 FDOT/FTBA Construction Conference
QC 2000 Concrete Specifications QC 2000 Concrete Specifications
Mike Bergin Mike Bergin
State Materials OfficeState Materials Office
Email: Email: [email protected]@dot.state.fl.us
April 3, 2002 2002 Construction Conference 2
The Presentation will include
Highlights of Changes to Section 346Highlights of Changes to Section 346 A draft Resolution Procedure to assist A draft Resolution Procedure to assist
project personnelproject personnel
April 3, 2002 2002 Construction Conference 3
QC 2000
Is not NEW any moreIs not NEW any more But the specs have changed and the But the specs have changed and the
major changes will be addressed today.major changes will be addressed today. Jobs have been let under QC 2000 for Jobs have been let under QC 2000 for
several years, as of July 1, 2002 all several years, as of July 1, 2002 all FDOT projects will be let with QC 2000 FDOT projects will be let with QC 2000 Specifications approved by FHWA.Specifications approved by FHWA.
April 3, 2002 2002 Construction Conference 4
What’s New in Section 346
New references to Section 6.8, 6.9 and 105 New references to Section 6.8, 6.9 and 105 and reference to Chapter 9.2 in the and reference to Chapter 9.2 in the Materials Manual Materials Manual Section 6.8 -Quality Control ProgramSection 6.8 -Quality Control Program Section 6.9 -Laboratory QualificationsSection 6.9 -Laboratory Qualifications Section 105 -Quality Control Program Section 105 -Quality Control Program
RequirementsRequirements
April 3, 2002 2002 Construction Conference 5
What’s New in Section 346 (cont.)
Chapter 9.2 of the Materials Manual (MM) Chapter 9.2 of the Materials Manual (MM) –Information pertaining to concrete plants.–Information pertaining to concrete plants.
April 3, 2002 2002 Construction Conference 6
What’s New in Section 346 (cont.) Changes in almost every subsection.Changes in almost every subsection. This presentation will focus on the major This presentation will focus on the major
changes and how these changes affect changes and how these changes affect Construction and Materials.Construction and Materials. Especially the relation between Especially the relation between
Construction and Materials, and the Construction and Materials, and the Resolution Process Resolution Process
April 3, 2002 2002 Construction Conference 7
Standard Operating Procedures for the Quality Control of Concrete (SOP) is gone
The Level I of the SOP identified how The Level I of the SOP identified how producers batched concrete to meet the producers batched concrete to meet the requirements of the Specification.requirements of the Specification.
This information is now moved to Chapter 9.2 This information is now moved to Chapter 9.2 of the Materials Manual (MM), “Concrete of the Materials Manual (MM), “Concrete Production Facilities Guidelines” (CPFG) and Production Facilities Guidelines” (CPFG) and is located on the DOT website.is located on the DOT website.
April 3, 2002 2002 Construction Conference 8
Standard Operating Procedures,… is gone (cont.) MM Includes the requirements for batch plants MM Includes the requirements for batch plants
such as:such as:Plant specific QC plan Plant specific QC plan
• QC plan no longer job specificQC plan no longer job specificDesign mix requirements (change)Design mix requirements (change)
• Hot weather,old 346, mix temp is 94 F at Hot weather,old 346, mix temp is 94 F at the the end end of the mixing cycleof the mixing cycle
• Hot weather, new 346, mixes are held at Hot weather, new 346, mixes are held at 94 F 94 F duringduring entire mixing cycle entire mixing cycle
April 3, 2002 2002 Construction Conference 9
Standard Operating Procedures,… is gone (cont.)
The Level II from the SOP has been moved The Level II from the SOP has been moved directly into Section 346.directly into Section 346.
The Contractor describes how he will maintain The Contractor describes how he will maintain the quality of the concrete once it arrives at the the quality of the concrete once it arrives at the job site.job site.
April 3, 2002 2002 Construction Conference 10
Mass Concrete (3.1)
Requires a Specialty Engineer to formulate, Requires a Specialty Engineer to formulate, implement, administer and monitor the implement, administer and monitor the temperature control plan.temperature control plan.
April 3, 2002 2002 Construction Conference 11
Mass Concrete (3.1)
Department no longer Department no longer approvesapproves the plan but the plan but acceptsaccepts the Contractor’s proposed plan. the Contractor’s proposed plan. The responsibility is the Contractor’s to ensure The responsibility is the Contractor’s to ensure
that the plan meets the specification.that the plan meets the specification. Contractor’s QC Manager is responsible to Contractor’s QC Manager is responsible to
ensure the plan is followed during and after ensure the plan is followed during and after placement.placement.
No concrete is placed unless there is an No concrete is placed unless there is an accepted Mass Concrete planaccepted Mass Concrete plan
April 3, 2002 2002 Construction Conference 12
Sampling and Testing (5.1)
ASTM is now the standard for all concrete ASTM is now the standard for all concrete tests except for following two FM’stests except for following two FM’s early sampling of fresh concrete FM 5-early sampling of fresh concrete FM 5-
501 501 testing of chlorides in hardened concrete testing of chlorides in hardened concrete
FM 5-516FM 5-516
April 3, 2002 2002 Construction Conference 13
Control of Quality (6.1)
The Contractor maintains one quality control plan The Contractor maintains one quality control plan for his entire project.for his entire project. The guidelines are identified in Section 6.8.The guidelines are identified in Section 6.8. Section 5.6 of MM identifies QC information Section 5.6 of MM identifies QC information
for material producersfor material producers He is responsible to identify how the quality of He is responsible to identify how the quality of
material will be maintained.material will be maintained. Failure to meet specifications or contract Failure to meet specifications or contract
documents voids that portion of the QC plan.documents voids that portion of the QC plan.
April 3, 2002 2002 Construction Conference 14
Delivery Certification of Concrete (6.3) Delivery ticket requirements have been Delivery ticket requirements have been
moved to the “Concrete Production Facility moved to the “Concrete Production Facility Guidelines”, Chapter 9.2 of the MM.Guidelines”, Chapter 9.2 of the MM. Batch Plant Operator (BPO) signs stating Batch Plant Operator (BPO) signs stating
that the batch was produced in that the batch was produced in accordance with the approved design mixaccordance with the approved design mix
April 3, 2002 2002 Construction Conference 15
Delivery Certification of Concrete (6.3) The Contractor or his agent signs stating the The Contractor or his agent signs stating the
W/C ratio was not exceeded at the project W/C ratio was not exceeded at the project site and that the concrete meets the site and that the concrete meets the requirements of the specs.requirements of the specs.
April 3, 2002 2002 Construction Conference 16
Adding Water at the Placement Site (7.7)
Contractor must perform a slump test Contractor must perform a slump test beforebefore any water is added to the load. any water is added to the load.
April 3, 2002 2002 Construction Conference 17
Plastic Concrete Sampling and Testing (8) The Contractor is responsible for ensuring The Contractor is responsible for ensuring
that plastic properties, determination of the that plastic properties, determination of the w/c ratio and compressive strength of w/c ratio and compressive strength of cylinders are in compliance with the cylinders are in compliance with the Specifications.Specifications.
April 3, 2002 2002 Construction Conference 18
Plastic Concrete Sampling and Testing (8) Testing will be performed:Testing will be performed:
by CTQP qualified technicians.by CTQP qualified technicians. on each lot of concrete from a random on each lot of concrete from a random
load within that lot.load within that lot.
April 3, 2002 2002 Construction Conference 19
Plastic Concrete Sampling and Testing (8) A Lot is 50 ydA Lot is 50 yd3 3 or one days production or one days production
which ever is less which ever is less except for: Pav’t – one lane mile or one days Pav’t – one lane mile or one days
productionproduction I Special –150 ydI Special –150 yd3 3 or one days productionor one days production III Seal – Each placementIII Seal – Each placement
April 3, 2002 2002 Construction Conference 20
Plastic Concrete Sampling and Testing (8) The Department will randomly select 1 of The Department will randomly select 1 of
every 4 lots to compare QC with every 4 lots to compare QC with Verification tests.Verification tests. Use a Random number generator Use a Random number generator
April 3, 2002 2002 Construction Conference 21
Plastic Concrete Sampling and Testing (8) 3 consecutive lots or 5 lots in two days out 3 consecutive lots or 5 lots in two days out
of tolerance (in the same mix) – the of tolerance (in the same mix) – the Contractor will suspend production from Contractor will suspend production from this plant.this plant.
Department may perform independent Department may perform independent verification test any time.verification test any time.
April 3, 2002 2002 Construction Conference 22
Acceptance Sampling and Testing (9.1) Contractor will cast a set of 3 cylinders from each Contractor will cast a set of 3 cylinders from each
lot, from a random load within the lot lot, from a random load within the lot For each lot that the Department verifies with the For each lot that the Department verifies with the
Contractor, cast an additional “hold” cylinder.Contractor, cast an additional “hold” cylinder. The “hold” cylinder will be used for resolution The “hold” cylinder will be used for resolution
if the QC tests do not compare with the if the QC tests do not compare with the Verification tests.Verification tests.
April 3, 2002 2002 Construction Conference 23
Acceptance Sampling and Testing (9.1) The laboratory performing the compressive The laboratory performing the compressive
strength tests shall meet the requirements of strength tests shall meet the requirements of Section 6-9Section 6-9
The concrete is verified when the Contractors The concrete is verified when the Contractors quality control (QC) cylinders compare within 750 quality control (QC) cylinders compare within 750 psi with the Verification cylinders.psi with the Verification cylinders.
If QC does not compare within the 750 psi of If QC does not compare within the 750 psi of Verification then the Engineer will initiate the Verification then the Engineer will initiate the Resolution Procedure. Resolution Procedure.
April 3, 2002 2002 Construction Conference 24
Reduced Frequency for Acceptance Tests (9.2.1) If the Contractor can show consistency in If the Contractor can show consistency in
his QC tests, the sample frequency can be his QC tests, the sample frequency can be reduced and lot size will be increased to reduced and lot size will be increased to 100 yds100 yds3.3.
April 3, 2002 2002 Construction Conference 25
Acceptance of Hardened Concrete (9.4) When 1 of the 3 QC cylinders are lost, damaged or When 1 of the 3 QC cylinders are lost, damaged or
destroyed, destroyed, Average the remaining 2 cylinders and payment Average the remaining 2 cylinders and payment
for the lot is reduced by 10%for the lot is reduced by 10% When more than 1 of the QC cylinders is lost, When more than 1 of the QC cylinders is lost,
damaged, or destroyed damaged, or destroyed The contractor, at the discretion of the engineer, The contractor, at the discretion of the engineer,
will core the structure to determine if the will core the structure to determine if the minimum strength is met and no payment is minimum strength is met and no payment is made for that lot.made for that lot.
April 3, 2002 2002 Construction Conference 26
Resolution Procedure (9.5)
Is initiated when QC and Verification do Is initiated when QC and Verification do not compare.not compare.
The Department may initiate an The Department may initiate an Independent Assurance (IA) review of:Independent Assurance (IA) review of: plastic propertiesplastic properties calculation of w/c ratiocalculation of w/c ratio handling of cylindershandling of cylinders
April 3, 2002 2002 Construction Conference 27
Resolution Procedure (9.5)
curing procedures curing procedures initialinitialfinalfinal
compressive strength testingcompressive strength testing cores may be requiredcores may be required
April 3, 2002 2002 Construction Conference 28
Resolution Procedure (9.5)
““Hold” cylinders are tested within 7 days of Hold” cylinders are tested within 7 days of the 28-day strength tests.the 28-day strength tests.
April 3, 2002 2002 Construction Conference 29
Resolution Procedure (9.5)
Concrete is accepted based on the strength test Concrete is accepted based on the strength test results deemed by the Department to be the most results deemed by the Department to be the most accurateaccurate If Verification is the most accurate, then If Verification is the most accurate, then
Verification represents the 4 lots, -Contractor Verification represents the 4 lots, -Contractor pays for the Resolution testingpays for the Resolution testing
If QC is the most accurate, QC represents the 4 If QC is the most accurate, QC represents the 4 lots, -Department pays for the Resolution lots, -Department pays for the Resolution testing.testing.
April 3, 2002 2002 Construction Conference 30
Resolution Procedure (9.5)
When the Department cannot determine that When the Department cannot determine that either QC or Verification data is in error, either QC or Verification data is in error, the concrete representing the four lots will the concrete representing the four lots will be evaluated based on the results of the be evaluated based on the results of the resolution investigation.resolution investigation.
April 3, 2002 2002 Construction Conference 31
Rest of Section 346 relatively unchanged
Same requirements for Same requirements for Investigation of low strength concrete for Investigation of low strength concrete for
structural adequacy (10)structural adequacy (10) Pay adjustments for low strength Pay adjustments for low strength
concrete (11)concrete (11)
April 3, 2002 2002 Construction Conference 32
State Materials Office Develops a Resolution Procedure:
The intent is to inform both Construction The intent is to inform both Construction and Materials personnel of a consistent and Materials personnel of a consistent process in the event that Resolution is process in the event that Resolution is needed on their projects.needed on their projects.
April 3, 2002 2002 Construction Conference 33
These are the hold cylinders from the same load of concrete
XXXXXXXXXXX XXXXXXXXXX
April 3, 2002 2002 Construction Conference 34
XXXXXXXXXXXXXXXXXXXXXX
April 3, 2002 2002 Construction Conference 35
The DRAFT Resolution Procedure will be available on the SMO website.
April 3, 2002 2002 Construction Conference 36
In General the DRAFT Resolution Procedure identifies what is needed: At start of project, the Project Engineer At start of project, the Project Engineer
should designate one person to; should designate one person to; make data entrees and track cylinder make data entrees and track cylinder
testing.testing. make the comparisons between QC and make the comparisons between QC and
Verification test results.Verification test results.
April 3, 2002 2002 Construction Conference 37
After the Concrete is Placed:
When placement is completed, the plastic When placement is completed, the plastic property data should be entered into the 6 property data should be entered into the 6 screen of the CQR system within screen of the CQR system within one one working dayworking day of the concrete placement by of the concrete placement by the Project Engineer’s designee.the Project Engineer’s designee.
April 3, 2002 2002 Construction Conference 38
After the 28 day Strength Tests are completed
QC and Verification Labs should notify the QC and Verification Labs should notify the Project Engineer, or his designee of test Project Engineer, or his designee of test results on the first working day after testing results on the first working day after testing and;and; within 3 working days of obtaining the within 3 working days of obtaining the
data it should be entered into the 7 screen data it should be entered into the 7 screen of the CQR systemof the CQR system
April 3, 2002 2002 Construction Conference 39
CQR Codes
Verification SamplesVerification Samples V =Verification compares with QCV =Verification compares with QC N =Verification did not compare with N =Verification did not compare with
QCQC Project Engineer reviews the data and Project Engineer reviews the data and
verifies the comparison or non-comparisonverifies the comparison or non-comparison
April 3, 2002 2002 Construction Conference 40
When QC and Verification do not Compare Notify your District Concrete Engineer Notify your District Concrete Engineer
immediatelyimmediately He may initiate an IA review of QC and He may initiate an IA review of QC and
Verification proceduresVerification procedures He will notify the State Materials OfficeHe will notify the State Materials Office
April 3, 2002 2002 Construction Conference 41
Transport the “hold” cylinders to the designated Resolution laboratory: Each sample is accompanied with a new C-Each sample is accompanied with a new C-
22 card, with all information included.22 card, with all information included. The QC and Verification Laboratories will The QC and Verification Laboratories will
enter a new 6 screen into CQRenter a new 6 screen into CQR
April 3, 2002 2002 Construction Conference 42
The Resolution Laboratory will enter the 7 screen data and indicate the status of the resolution samples under new codes.
April 3, 2002 2002 Construction Conference 43
NEW CQR Codes for Resolution Samples RQ =Resolution confirms QC results or RQ =Resolution confirms QC results or
both QC and Verification resultsboth QC and Verification results RV =Resolution results confirm RV =Resolution results confirm
Verification resultsVerification results RR =Resolution results do not confirm QC RR =Resolution results do not confirm QC
or Verification results.or Verification results.
April 3, 2002 2002 Construction Conference 44
If you have any questions concerning these new CQR codes please contact:
Glen Mans in Certifications at the SMO Glen Mans in Certifications at the SMO (352) 337-3146(352) 337-3146 SC 642-3146SC 642-3146 [email protected]@dot.state.fl.us
April 3, 2002 2002 Construction Conference 45
Thank You for your time and attention - Any Questions?