2 January 2011 - Northern Regional Grid of India Collapse
-
Upload
ppsingh123456789 -
Category
Documents
-
view
217 -
download
0
Transcript of 2 January 2011 - Northern Regional Grid of India Collapse
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
1/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 1 of15
MEL414PowerPlantTechnologies
Term Paper
2 Jan 2001 Northern Grid collapsePrashant Pratap Singh (P2008ME1119)
ABSTRACT:
For a modern economy, the electric power system is an axiomatic need. The woes of the power sector aregenerally seen as arising in generation or distribution. However, the collapse of the northern grid on 2 January
2001 is ominous. Over 1500 MW of generation was lost and the entire region plunged into darkness,
subjecting public at large to immense inconvenience and a loss to the tune of 7 billion rupees. It took 1620
hours for the system to limp back to near normalcy. The last major grid disturbance in the region was in
January 1997.
BACKGROUND:
Northern Regional Grid
The Northern Regional Grid covers Uttar Pradesh, Delhi, Punjab, Haryana, Rajasthan, Himachal Pradesh, and
Jammu and Kashmir. It is the second largest interconnected network in the country with an installed capacity
of over 27 000 MW and a plant mix of 31% hydro, 65% thermal, and 4% nuclear. The Region has major therma
power stations located at the pit-heads of coal mines at Singrauli, Rihand, Obra, and Anpara. Major
hydroelectric power stations are located in the Himalayas such as Bhakra, Dehar, Pong, Chamera, Baira-Siul,
Salal, Uri, and the hydro-power stations on Yamuna River in Uttar Pradesh (UP). The large coal-using pit-head
thermal power stations are located in the extreme south-eastern part of the Region. Therefore, there is a large
flow of power from the south-eastern part to the central and western parts of the grid throughout the year.
The following major links connect the large generation stations (total capacity > 6 GW) in the south-eastern
part of the grid to the load centres in Western UP and Delhi.I. Rihand Dadri (500 kV, 1500 MW) HVDC link. Power is transmitted on 2 wires which are 500 kV with
respect to the ground (this is commonly known as a bipole configuration).
II. 400 kV (AC) Singrauli- Kanpur-Ballabhgarh-DadriIII. 400 kV (AC) Singrauli-Lucknow-Moradabad-Muradnagar-DadriIV. 400 kV (AC) Singrauli-Vindhyachal-Kanpur-Agra-BallabhgarhV. 400 kV (AC) Obra-Panki-Muradnagar
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
2/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 2 of15
Northern Region Power Grid Map
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
3/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 3 of15
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
4/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 4 of15
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
5/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 5 of15
Why Does the Grid Collapse?
The distinguishing feature of electricity transport is that electricity cannot be stored: the supply of electricity
should be matched by its demand. If supply tends to exceed demand, the generating stations are asked to
back down. Conversely, when demand tends to exceed supply, load has to be shed. Three specific reasons can
cause a grid to trip:
I. Overdrawal of power by states above the day-to-day directive of the RLDCs. When several states turnerrant the frequency dips. If frequency falls below 47.5 Hz. (the desirable frequency is 50 Hz.), the grid
trips. Cascading effects are possible, if the grid operator does not quickly isolate portions of the grid.
II. Refusal of generating stations to back down. RLDCs determine demand and advise plants to generatepower accordingly. If generation is more than demand the grid frequency rises. If it rises above a
critical value the grid trips. High frequency is experienced mainly during the monsoon months when
the agricultural and air-conditioning and fans load crash due to widespread rains and fall in
temperature. Load collapse to the extent of 4000 MW due to rains, in the Northern Regional Grid, is
common during the monsoon season. During the winter rains, similar load collapse is observed.
III. Faulty equipment/poor maintenance leading to non-functional/under-performing transmission linescan also affect grid frequency. Grid frequency increases in generation-surplus regions and decreases in
generation-deficit regions.
IV. Other major causes of the blackout can be summarised as follows: Long duration of equipment (converter transformer) outage in the HVDC link Heavy pollution and fog causing insulation flashovers Inadequate preventive control Inadequate emergency control
Build up to collapse
In the early hours of 2 January 2001, the demand was much less than the availability, following idespread
rains, and a few thermal machines had been closed down to contain the frequency. However, there was aconstraint in the transmission capability in the eastwest corridor due to outage of one of the HVDC bi-poles
and a reduction of the power capability of the other pole to 500 MW. This reduced further when parts of the
two 400-kV links owned by the STU tripped in quick succession due to insulator flashovers. This in turn led to
heavy loading of the remaining links, with power flow touching 800 MW in one of the 400-kV lines, and
cascade tripping of the remaining lin ks. Eventually the grid split into two. In the western part, the frequency
dropped due to shortfall in generation and the subsystem collapsed, while in the eastern part the frequency
shot up to about 53 Hz, tripping all the running machines and leading to the eventual collapse of the
subsystem. Only a few gas turbine units in Delhi and one nuclear unit survived on local load. All other nuclear
units tripped and were poisoned out.
THE COLLAPSE
Following widespread rains on 1 January 2001, the demand in the Northern Region had reduced. A few
thermal units in Punjab and Haryana had been closed due to low demand. After 10 p.m. of 1 January 2001, the
frequency started rising and backing down had to be resorted to at a number of thermal power stations. The
salient events that led to the collapse of the Northern Region Grid (NRG) are brought out below:
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
6/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 6 of15
Time (Hrs.) Event
1st Jan, 2001 1st Jan, 2001
23:21, 23:33 and 23:41 Transient faults on the operating pole-1 of HVDC Rihand-Dadri
(POWERGRID) line. The line continued in operation with
successful auto-re-starts.
23:49 Singrauli and Rihand Stations were asked to back down from
1840 MW to 1620 MW and from 910 MW to 810 MW
respectively.2nd Jan,2001 2nd Jan,2001
00:02
Transient faults on the operating pole-1 of HVDC Rihand-Dadri
line. The line continued in operation with successful auto-re-
starts.
00:17 Pole-1 of HVDC bi-pole was put on reduced voltage mode of
operation thereby reducing power flow on this line from 750
MW to 500 MW.
01:05 400 kV Obra-Panki S/C (UPPCL) line tripped on fault and
remained under breakdown.
01:07 Frequency goes above 51.0 Hz, NRLDC asked Singrauli and
Rihand Stations to back down from 1620 MW to 1540 MW and
from 810 MW to 730 MW respectively.
02:45
02:47
03:26
03:41
04:31
400 kV Agra Ballabhgarh line tripped on Y-phase earth fault
and auto reclosed.
03:11 400 kV Panki Muradnagar developed fault. Circuit Breaker at
Panki end did not operate resulting in back-up protection
operation of Main bus A. 400 kV Panki Kanpur II and ICT -II
(inter-connecting transformer) at Panki connected to this busalso tripped.
03:12 400 kV Unnao Agra line also tripped on fault.
03:18 System frequency rose to 51.2 Hz.
03:31 220 kV Narora Atomic Power Plant Muradabad tripped on
fault.
03:35 220 kV Panki Fatehpur tripped on fault.
03:33
03:54
400 kV Agra Kanpur line also tripped on B-phase earth fault
and auto reclosed.
03:50 Load dispatcher asked Singrauli Generators to further
backdown from 1480 to 1320 MW. At 04:38 hrs, 220 kV Panki-Fatehpur line tripped on fault. With all these outages, the system could not be kept in synchronism and the following lines
tripped (as a consequence of relay response to an out of step situation) and the system
separated naturally into 2 subsystems.
04:38 400 kV Lucknow Moradabad, 400 kV Kanpur Agra, 400 kV Kanpur Ballabhgarh, East West separation of Northern Grid took place. The separation of the system into 2 islands need not have led to a complete blackout.
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
7/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 7 of15
Since one island had excess generation, quick tripping of a few generators or govenor actioncould have stabilised frequency. In the under-generated island, under-frequency load
shedding would have stabilised the frequency. However neither of these emergency
measures were in place. Therefore,
04:40 Frequency of western part dipped and sub-system collapsed.
04:40 04:44
Frequency of eastern part shot up to more than 52.5 Hz. All
running machines in eastern part tripped on over frequency
and sub-system collapsed
Practically, whole of North India was plunged into darkness. A few generators survived by separating
themselves from the rest of the grid and kept running supplying only their "house load". After the blackout, it
took almost 16 hours to fully recover and reconnect the grid.
RESTORATION:
If a blackout (a near total loss of generation and load) takes place, efforts have to be taken to bring back the
system to a normal state at the earliest. It may surprise you to know that this (black starting!) is not an easy
task. We shall see why in this lecture.
Once a generator is tripped, restarting it requires a significant amount of power. Power is required for 2 types
of activities:
Survival Power: For emergency lighting, battery chargers etc. Usually the requirement is 0.3% of thegenerator capacity.
Startup Power: For starting power plant auxiliaries (pumps etc.) Interestingly, nuclear and thermalunits require approximately 8 % of the unit capacity for auxiliaries alone! Therefore, a 500 MW
generator requires approximately 40 MW for running its auxiliaries.
Hydro and Gas units, on the other hand, require only about 0.5-2% of unit capacity for auxiliaries and can be
started usually from in-house DG sets.
MAJOR STEPS REQUIRED FOR RESTORATION:
Islands which have survived need to be stabilised for frequency and need to be used for starting otherunits
Hydro/Gas units which require less startup power need to be started using in-house DG sets. Larger thermal units need to be fed "startup power" from: 1) Islands which have survived 2)
Blackstarted generators 3) Other synchronous grids (temporarily)
Started units are synchronised with one another. Loads and Generation have to be matched as much as possible to avoid large frequency variations.
Governors have a major role in stabilizing frequency in an island.
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
8/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 8 of15
Problems in Restoration
a) Securing Islands
After a blackout a few islands may survive due to separation of the system in time. A few hydro or gas
generators could be blackstarted using in-house D-G sets. Therefore some small pockets will be there in the
otherwise blacked out grid wherein generators are supplying some loads. However, the situation in these
islands is usually precarious due to the small number of generators within the island (having very littlecumulative inertia).
Recall that the initial rate of change of frequency is determined by cumulative machine inertia and the initial
load-generation imbalance, while the final settling frequency is determined by the governor and load
frequency characteristics (see Module 3).
Therefore if the load in the island is fluctuating (for instance, traction loads), the rate of change of frequency
within the island due to fluctuating loads may be quite large -- large enough for the island to collapse due to
excessive frequency variations - causing generators to trip. Therefore control of generated power (by
governors) and frequency based tripping or energisation of load is important.
Black-starting of large generators is done by availing startup power from other started generators or islands.
Startup power may also be availed from neighboring synchronous grids if an AC transmission link exists
(normally disabled). Unfortunately, startup power cannot be availed via DC links (which use AC line voltagesfor commutating thyristors), because AC voltages are not available in the system which is blacked out.
Therefore a generator at Vindyachal (near the border of the western region and northern region grid of India,
which are not synchronized but exchange power through DC asynchronous links during normal conditions) can
avail startup power through an AC line from the northern grid.
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
9/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 9 of15
b) Extending Power to Loads from Generators which are black-started
The next step in power system restoration is to supply loads from black-started generators. Some of these
loads may be in the form of the startup (auxiliary) loads of other larger generating plants which need to be
black-started.
These loads are supplied via transmission lines. Enregising a transmission line initially without any load can
cause over-voltages. This is avoided by:
Energizing fewer high voltage lines Operating generators at minimum voltage levels (by keeping filed excitation low) Deactivating switchable capacitors
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
10/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 10 of15
Connecting shunt reactors and tertiary reactors Adjusting of transformer taps Pick up loads with lagging power factor Charging more transformers Charging shorter lines Operating synchronous condensers / SVCs where available Avoiding charging lines with series capacitors
c) Re-integrating the grid
As mentioned before, some islands which have been secured should be connected with each other so that the
system cumulative inertia increases, a better generation-load balance can be achieved by encompassing a
larger set of loads and generators, and better redundancy in transmission and generation is achieved.
Note that an important step in reconnecting islands to one another is "synchronisation". While each generator
has synchronising facilities, the interconnection of two islands may have to be done at some bus in the
network wherein such facilities are available. The basic requirements for successful synchronisation of two
systems are the same as those for an individual generator connected to a large grid (see Module 2). In
particular, the frequencies should be practically the same and phase angular difference at the instant of
connection should be small. If two systems are connected at an inappropriate instant, then the generators in
both islands will not synchronize, and the situation will be akin to an out-of-step scenario; the link will have to
be disconnected.
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
11/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 11 of15
ACTUAL RESTORATION OF THE NORTHERN GRID
The sequence of actual restorative actions which were taken after the Northern Grid Collapsed in January
2001 is given below
The system was restored in two parts.
The south-eastern part was restored by taking power from Western Region (a neighbouring grid)through an AC line which runs parallel to the HVDC back-to-back station at Vindhyachal.
The western part was restored after starting Bhakra (hydro) machines.
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
12/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 12 of15
Chronology of restoration process of Eastern and Western parts is given below:
a. RestorationofEasternPart(2ndJanuary2001)Time (Hrs.) Event
04:59 OnemachineofRihand(Hydrogeneration)wasstarted.
05:10
StartuppowerfromWesternRegion(WR)wasextendedto
SingrauligeneratorsthroughACbypassofHVDCback-to-
backstationatVindhyachal.
05:38
WRpowerwasfurtherextendedtoRihandGeneratorsby
charging400kVSingrauliRihandI.
06:32 Powerwas also extended to Kanpur by charging 400 kV
VindhyachalKanpurline.
07:01 400kVKanpurPankiwascharged.
07.42 Rihand(H)-Anpara132kVlinecharged
08.15 Anparaunitclearedforlightup.
12.38 ThepowerwasextendedtoMainpuri
Between09:11and11:20
Followingunitsweresynchronized:
Singrauliunit(500MW)at09:11hrs Rihandunit(500MW)at09:54hrs. Singrauliunit(210MW)at10:48hrs Singrauliunit(210MW)at11:20hrs
11:44 WRPowerwasextendedfromKanpurtoAgraat11:44hrs
bycharging400kVKanpurAgraline,and
11:57 furthertoBallabhgarhand
12:01 Dadri
12:17 400kVBallabhgarhDadritrippedonovervoltage
12:18 BallabhgarhInterconnectingTransformer(ICT)waschargedtoextendpowertoBallabhgarh
12:39 400kVAgraBallabgarhlinetripped
12.50 Anparaunit-synchronised
b. Restoration of Western PartAs specified in Black Start Procedures, immediately after the grid failure Bhakra hydro station
attempted two times to revive the system at 05:05 hrs. and 05:40 hrs. but the machines could not be
stabilized.
Time Event06:00 Unit 4 at Bhakra (L) started 07:07 Power was extended to Panipat by charging 220 kV Bhakra
Ganguwal Dhulkote Panipat sections.
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
13/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 13 of15
07:28 Panipat Dadri line was charged. This line however, tripped on overvoltage.
07:33 The line was again charged but tripped immediately on over voltage.
08:47 The line was again charged from Panipat end utilizing an opencircuited 220/400 kV transformer at Dadri as a reactor to limit overvoltage.
09:08 Dadri Ballabhgarh was charged but tripped immediately along withPanipat line on over voltage.
09:19 Panipat Dadri line was again charged. Dadri Gas Turbine generatorssynchronized and started generating 200 MW.
Between 09:29 to 09:54
The following 400 kV lines were charged from Dadri end
09:29 hrs Dadri Ballabhgarh,
09:39 hrs Dadri Murad Nagar (tripped at 10:10 hrs),
09:48 hrs Ballabgarh - Agra
09:54 hrs Dadri Mandola I
10:00 hrs Agra Auraiya
10:16 Bhakra island collapsed due to under frequency.
10:33
1st unit at Bhakra(R) station started but tripped at 10:42 dueto large fluctuations in loads.
It was again started at 10:46 hrs but again tripped at 10:52due to same reasons as above.
The unit was again started at 11:00 with manual regulation ofload by locking the load limiter in steps.
11:14 Power was extended to Panipat
12:04 220/400 kV Inter-Connecting Transformer 2 was charged.
13:08
Power to Badarpur was extended from Bhakra system through
Panipat - Charkhi Dadri - Ballabhgarh. Bhakra power was not
extended to Dadri as it received WR power from Ballabhgarh.
13:32 The eastern and western parts of the grid were synchronizedANALYSIS
The enquiry carried out by the CEA committee and the submission made during the public hearing held by the
CERC reveal the following.
i. There was a general lack of grid discipline. For example, (1) the generators had not been on free-governor mode operation although this was required by the IEGC (Indian Electricity Grid Code), (2)
instructions given from the RLDC (regional load dispatch centre) were not promptly acted upon, and (3)
under frequency relay schemes were not fully operational.
ii. The role played by the RLDC was not adequate or effective. Its orders for backing down, for example,did not reflect the urgency or the gravity of the situation. Also, it does not appear to have considered
other options for congestion management like increase in hydro generation in the western part,
coupled with load shedding. This might have helped avert the incident as it was not triggered by a
sudden event and the system depletion was gradual.
iii. The maintenance and performance of the transmission system was not adequate. The insulator flash -overs and the resultant tripping of the two important links in the eastwest corridor occurred due to
the poor maintenance of the 400-kV lines owned by the STU, which pass through the polluted areas
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
14/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 14 of15
near Panki. Similarly, the performance of the HVDC link, especially of the convertor transformers
manufactured by BHEL (Bharat Heavy Electricals Ltd), was not satisfactory and affected the
transmission capability in the corridor. Such lapses could jeopardize the security of the grid since the
system is planned to an n-1 contingency criterion. There were also inadequacies in the switchgear and
reactive power compensation devices at some locations, as the restoration process revealed.
iv. The load dispatch and communication facilities are not adequate. Lack of time synchronizationbetween recording instruments installed at different locations makes it difficult to correctly establish
the sequence of events.
v. The restoration procedure was slow. Extending supply and build up of load was difficult due toequipment problems, delays in providing start-up power, lack of coordination, etc. The black start
procedure and the grid protection scheme must be reviewed.
vi. There is need for better training and capacity building for grid operators.THE CERC ORDER
The CERC has looked into the incident primarily as part of its function to regulate interstate transmission. The
ambit of its enquiry was restricted to the role of various functionaries in ensuring compliance of the provisions
of IEGC.
In its order, the CERC noted that there was blatant violation in operating the grid as per the IEGC. While it has
not taken action against the erring bodies, it has warned the concerned functionaries of penalties in case of
future noncompliance. It has severely criticized the CTU/RLDC for not implementing the grid code with ful
commitment and for not managing the grid efficiently. It has directed the CTU to see if it is necessary for the
RLDC to control the state level generation as well if it has to have adequate control over the grid and maintain
its security.
ACTION PLAN OF MINISTRY
The Ministry of Power has decided to adopt a time-bound action plan for various organizations to take
remedial measures to prevent the recurrence of such events. This covers tuning of governors, provision of
self-start facilities at gas turbine stations, implementation of revised under frequency relay scheme, review of
schemes for protection, islanding, and black start, simulator training for dispatch engineers, etc. A close follow
up of the action plan is proposed.
REFORM AND REGULATORY ISSUES
The collapse of the Northern Grid and the similar incident in the Eastern Region recently have brought to fore
certain reform and regulatory issues. These include the delineation of the interstate transmission system and
the responsibility of the CTU for STU-owned lines; command hierarchy in grid operation; desirability of
CTU/STU looking after the load dispatch functions; overlaps in roles, if any, of CERC, CEA, regional electricityboard, and the state regulatory commissions in enforcing grid code; and urgency for putting in place suitable
commercial mechanisms to promote grid discipline.
The collapse of the grid highlighted once again that integrated operation of large grid systems is a complex
task requiring orchestrated functioning of all agencies connected to the grid (generators, transmission
companies, and generation companies), a well-equipped hierarchical load dispatch system manned by trained
professionals, and a comprehensive grid code.
-
8/3/2019 2 January 2011 - Northern Regional Grid of India Collapse
15/15
MEL 414 Power Plant Technologies SMMEE, IIT Ropar
Page 15 of15
REFERENCES:1. http://www.cdeep.iitb.ac.in/nptel/Electrical%20Engineering/Power%20System%20Operation%20and%20Contro
l/Course_home_L30.html
2. http://nrldc.org/nrldc/powermaps.asp3. http://www.nrldc.org/4. http://www.teriin.org/index.php?option=com_publication&task=details&sid=258