Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire Alarm System Replacements William Howard Taft HS Engineering Firm: Wallis Engineering Group, Inc. NISD Project Manager: Troy Spear Contract Amount: $1,210,738.00 Contractor: Convergint Technologies, LLC Construction Period: June 9, 2014 – August 8, 2014 (95% Construction) Fire Marshall doing final Inspections. Project Scope: Replace existing Fire Alarm System (2007 Bond Savings) Engineering Services 5900 Evers Road San Antonio, Texas 78238-1699 Tel: 210-397-1240 Fax: 210-257-1244 www.nisd.net Taft HS – Fire Alarm System Replacement 9-2014

Transcript of 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21...

Page 1: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 1 of 21

ENGINEERING PROJECTS

September 12, 2014

PROJECTS IN CONSTRUCTION (Qty. 21) Fire Alarm System Replacements William Howard Taft HS

Engineering Firm: Wallis Engineering Group, Inc. NISD Project Manager: Troy Spear Contract Amount: $1,210,738.00 Contractor: Convergint Technologies, LLC Construction Period: June 9, 2014 – August 8, 2014 (95% Construction) Fire Marshall doing final Inspections.

Project Scope: Replace existing Fire Alarm System (2007 Bond Savings)

Engineering

Services

5900 Evers Road San Antonio, Texas

78238-1699 Tel: 210-397-1240 Fax: 210-257-1244

www.nisd.net

Taft HS – Fire Alarm System Replacement 9-2014

Page 2: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 2 of 21

… CONSTRUCTION

Rhodes Station – Transportation Engineering Firm: Alderson & Associates, Inc. NISD Project Manager: Ramiro Guerrero Contract Amount: $57,300.00 Contractor: Quinney Electric, Inc. Construction Period: June 2014 – August 2014 (95% Construction)

Project Scope: Replace existing Fire Alarm System (2010 Bond Funds)

Rhodes Station Transportation – Fire Alarm System Replacement 9-2014

Page 3: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 3 of 21

… CONSTRUCTION

Child Nutrition and Human Resources Engineering Firm: CNG Engineering, PLLC NISD Project Manager: Ramiro Guerrero Contract Amount: $132,591.00 Contractor: Convergint Technologies, LLC Construction Period: June 2014 – August 2014 (65% Construction)

Project Scope: Replace existing Fire Alarm System (2010 Bond Funds)

Child Nutrition Dept. – Fire Alarm System Replacement 9-2014

Human Resources Dept. – Fire Alarm System Replacement 9-2014

Page 4: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 4 of 21

… CONSTRUCTION Valley Hi Elementary Engineering Firm: DBR Engineering Consultants, Inc. NISD Project Manager: Ramiro Guerrero Contract Amount: $131,000.00 Contractor: Consolidated Electric Services, Inc. Construction Period: June 2014 – August 2014 (95% Construction)

Project Scope: Replace existing Fire Alarm System (2010 Bond Funds)

Valley Hi ES – Fire Alarm System Replacement 9-2014

Page 5: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 5 of 21

… CONSTRUCTION HVAC Upgrades

Henry T. Brauchle ES Engineering Firm: Cleary Zimmermann Engineers NISD Project Manager: Rob Ibarra Contract Amount: $690,455.00 Contractor: Comfort Air Engineering, Inc. Construction Period: June 9, 2014 – August 8, 2014 (95% Construction) Project Scope: Chiller Replacement (2010 Bond Funds)

Brauchle ES - York Chillers 9-2014

Page 6: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 6 of 21

… CONSTRUCTION

Raul B. Fernandez ES Engineering Firm: Wallis Engineering Group, Inc. NISD Project Manager: Rob Ibarra Contract Amount: $1,051,000.00 Contractor: E Z Mechanical, Inc. Construction Period: June 11, 2014 – August 13, 2014 (95% Construction) Project Scope: Chiller Replacement and Partial Building HVAC Renovations (2010 Bond Funds)

Fernandez ES – York Chillers 9-2014

Page 7: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 7 of 21

… CONSTRUCTION Clarence Galm ES Engineering Firm: Wallis Engineering Group, Inc. NISD Project Manager: Rob Ibarra Contract Amount: $1,103,069.00 Contractor: Flo-Aire Service, Inc. Construction Period: June 11, 2014 – August 13, 2014 (95% Construction) Project Scope: Chiller Replacement and Partial Building HVAC Renovations (2010 Bond Funds)

Galm ES - Chiller Replacement 9-2014

Page 8: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 8 of 21

… CONSTRUCTION

Robert F. McDermott ES Engineering Firm: DBR Engineering Consultants, Inc. NISD Project Manager: Rob Ibarra Contract Amount: $464,000.00 Contractor: R.E.C. Industries, Inc. Construction Period: June 9, 2014 – August 8, 2014 (95% Construction) Project Scope: Chiller Replacement (2010 Bond Funds)

McDermott ES – York Chillers 9-2014

Page 9: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 9 of 21

… CONSTRUCTION

William Howard Taft HS Engineering Firm: Wallis Engineering Group, Inc. NISD Project Manager: Rob Ibarra Contract Amount: $2,100,000.00 Contractor: D. Wilson Construction Co. Construction Period: June 2014 – August 8, 2014 (95% Construction) Project Scope: Chiller and Cooling Tower Replacement (2007 Bond Funds)

Taft HS – York Centrifugal Chiller 9-2014

Taft HS – Cooling Tower 9-2014

Page 10: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 10 of 21

… CONSTRUCTION Lighting Upgrades

William J. Thornton ES, Central Office, and Grissom Annex Engineering Firm: DBR Engineering Consultants, Inc. NISD Project Manager: Ramiro Guerrero Contract Amount: $125,000.00 Contractor: Consolidated Electric Service, Inc. Construction Period: June 2014 – August 2014 (95% Construction) Project Scope: Lighting Retro-Fit (2010 Bond Funds)

Central Office – Board Room 9-2014

Thornton ES 9-2014

Grissom Road Annex – 9-2014

Page 11: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 11 of 21

… CONSTRUCTION Earl Rudder MS and Braun Station ES

Engineering Firm: Alderson & Associates, Inc. NISD Project Manager: Ramiro Guerrero Contract Amount: $151,122.54 Contractor: Excel Energy Group, Inc. Construction Period: June 2014 – August 2014 (95% Construction) Project Scope: Lighting Retro-Fit (2010 Bond Funds)

Rudder MS - Gymnasium 9-2014

Braun Station ES 9-2014

Page 12: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 12 of 21

… CONSTRUCTION

Robert F. McDermott ES and Meadow Village ES Engineering Firm: CNG Engineering, PLLC NISD Project Manager: Ramiro Guerrero

Contract Amount: $ 123,971.00 Contractor: Excel Energy Group, Inc. Construction Period: June 2014 - August 2014 (95% Construction) Project Scope: Lighting Retro-Fit (2010 Bond Funds)

McDermott ES – Gymnasium 9-2014

Meadow Village ES - 9-2014

Page 13: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 13 of 21

… CONSTRUCTION Tom C. Clark HS

Engineering Firm: Alderson & Associates, Inc. NISD Project Manager: Ramiro Guerrero

Contract Amount: $ 163,138.00 Contractor: CRI Electric Construction Period: June 2014 – August 2014 (95% Construction) Project Scope: Auditorium Lighting Upgrade (2010 Bond Funds)

Clark HS – Auditorium 9-2014

Page 14: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 14 of 21

… CONSTRUCTION

Leon Springs ES Engineering Firm: Alderson & Associates, Inc. NISD Project Manager: Ramiro Guerrero Contract Amount: $60,910.00 Contractor: Quinney Electric, Inc. Construction Period: June 2014 - August 2014 (95% Construction) Project Scope: Lighting Retro-Fit (2010 Bond Funds)

Leon Springs ES – Gymnasium 9-2014

Page 15: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 15 of 21

… CONSTRUCTION Playground Upgrades

District-Wide Upper-Level Playgrounds, Group 7: (Adams Hill ES, Gregorio Esparza ES, Dolores B. Linton ES, Virginia A. Myers ES & Dr. Carl and Bunny Jean Raba ES) Engineering Firm: Moy Tarin Ramirez Engineers, LLC NISD Project Manager: Troy Spear Contract Amount: $990,722.00 Contractor: Davila Construction, Inc. Construction Period: June 2014 – August 2014 (99% Construction) Project Scope: Upgrade Playground Equipment, install new wood fiber surfacing and ADA accessibility upgrades in upper level playgrounds (2010 Bond Funds)

Playground Improvements, Group 7 – Linton ES 9-2014

Playground Improvements, Group 7 – Esparza ES 9-2014

Page 16: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 16 of 21

… CONSTRUCTION

District-Wide Upper-Level Playgrounds, Group 8: (Henry T. Brauchle ES, W. Z. Burke ES, Timberwilde ES & Anna Mae Nichols ES) Engineering Firm: Moy Tarin Ramirez Engineers, LLC NISD Project Manager: Troy Spear Contract Amount: $672,500.00 Contractor: R. L. Rohde General Contracting, Inc. Construction Period: June 2014 – August 2014 (99% Construction) Project Scope: Upgrade Playground Equipment, install new wood fiber surfacing and ADA accessibility upgrades in upper level playgrounds (2010 Bond Funds)

Playground Improvements, Group 8 - Timberwilde ES 9-2014

Playground Improvements, Group 8 - Nichols ES 9-2014

Page 17: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 17 of 21

… CONSTRUCTION

District-Wide Upper-Level Playgrounds, Group 9: (Bob J. Beard ES, Jimmy L. Elrod ES, Shirley J. Howsman ES & Monroe S. May, Jr. ES) Engineering Firm: Moy Tarin Ramirez Engineers, LLC NISD Project Manager: Troy Spear Contract Amount: $707,000.00 Contractor: The GFP Group Construction Period: June 2014 – August 2014 (99% Construction) Project Scope: Upgrade Playground Equipment, install new wood fiber surfacing and ADA accessibility upgrades in upper level playgrounds (2010 Bond Funds)

Playground Improvements, Group 9 - Howsman ES 9-2014

Playground Improvements, Group 9 - Elrod ES 9-2014

Page 18: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 18 of 21

… CONSTRUCTION Athletics Upgrades

Jack C. Jordan MS – Bleachers Replacement Engineering Firm: Moy Tarin Ramirez Engineers, LLC NISD Project Manager: Darren M. VanFossen Contract Amount: $19,290.00 Contractor: Industrial Construction Co. Construction Period: May 2014 – June 2014 (95% Construction) Project Scope: Replace Bleacher sections (2010 Bond Funds)

Jordan MS – Bleachers 9-2014

Page 19: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 19 of 21

… CONSTRUCTION Clock System Upgrade

Clock System Upgrade @ 17 Various Schools (Adams Hill ES, Allen ES, Colonies North ES, Esparza ES, Colby Glass ES, Helotes ES, Holmes HS, Howsman ES, Mary Hull ES, John Jay HS, Anson Jones MS, Meadow Village ES, Passmore ES, Pease MS, Powell ES, Sul Ross MS, and Westwood Terrace ES) Engineering Firm: DBR Engineering Consultants, Inc. NISD Project Manager: Troy Spear Contract Amount: $562,654.21 Contractor: Convergint Technologies, LLC Construction Period: June 2014 – August 2014 (100% Construction)

Project Scope: Replace existing clock system with new GPS Clock System. (2010 Bond Funds)

Jay HS – Cafeteria Prep Area

Jay HS – Hallway

Page 20: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 20 of 21

… CONSTRUCTION Fuel Tank Replacement

South Transportation (Propane Tank Replacement) Engineering Firm: Richard N. Berry, P.E., Inc. NISD Project Manager: Darren M. VanFossen Contract Amount: $264,511.00 Contractor: Propane Specialty Services, LLC Construction Period: June 2014 – August 2014 (85% Construction) Project Scope: Fuel Tank Replacement – Propane (2007 Bond Funds)

South Transportation – Propane Tank 9-2014

Page 21: 140912 - Sep 2014 Eng Svcs BC · Engineering Projects Status Report September 12, 2014 Page 1 of 21 ENGINEERING PROJECTS September 12, 2014 PROJECTS IN CONSTRUCTION (Qty. 21) Fire

Engineering Projects Status Report September 12, 2014

Page 21 of 21

… CONSTRUCTION Fuel Tank Replacement

Mainland Fuel Center (Fuel Tank Replacement) Engineering Firm: Richard N. Berry, P.E., Inc. NISD Project Manager: Darren M. VanFossen Contract Amount: $386,993.00 Contractor: R.L. Rohde General Contracting, Inc. Construction Period: July 14, 2014 – October 10, 2014 (5% Construction) Project Scope: Fuel Tank Replacement – Diesel and Unleaded (2010 Bond Funds)

Mainland Fuel Center – Fuel Tank Replacement 9-2014