1407424167 Harding, D. Harding D Dissertation 2014

download 1407424167 Harding, D. Harding D Dissertation 2014

of 105

description

qss

Transcript of 1407424167 Harding, D. Harding D Dissertation 2014

  • 1

    The Future Role of the Quantity Surveyor and the impact of

    the New Rules of Measurement.

    Debs Harding

    MSc QUANTITY SURVEYING

    SCHOOL OF THE BUILT ENVIRONMENT

    APRIL 2014

    Matriculation No: 061137095

  • 2

    Declaration

    I .. confirm that this work submitted for

    assessment is my own and is expressed in my own words. Any use made

    within it of the works of other authors in any form (eg. Ideas, equations,

    figures, text, tables and programmes) are properly acknowledged at the

    point of their use. A full list if the references employed has been included.

    Signed:

    Date:

  • 3

    Table of Contents

    Declaration 2

    Contents 3

    Abstract 7

    Acknowledgments 8

    List of Tables and Illustrations 9

    Glossary of Abbreviations 11

    Chapter 1 Introduction 12

    1.1 Introduction 12

    1.2 Rationale 13

    1.3 Research Proposal 15

    1.4 Aims and objectives 15

    1.5 Research Methodology 16

    1.6 Research Structure 18

    Chapter 2 2.1 Introduction 18

    2.2 Parties involved in a Construction Project 18

    2.3 The Construction Supply Chain 19

    2.4 The Composition of the Construction

    Industry 20

    2.4.1 Contracting 20

    2.4.2 Services 21

    2.4.3 Products 22

    2.5 The Importance of the Construction

    Industry 23

  • 4

    2.6 The Significance of the various Industry

    Reports 24

    2.6.1 Latham Report (1994) 24

    2.6.2 Levene Report (1995) 25

    2.6.3 The Egan Report (1998) 25

    2.6.4 Modernising Construction (2001) 25

    2.6.5 The follow up to Egan 27

    2.6.6 The Wolstenholme Report (2009) 28

    2.7 RICS Reports carried out between 1967

    and 1981 30

    2.7.1 RICS (1967) 30

    2.7.2 RICS (1971) 31

    2.7.3 RICS (1983) 32

    2.7.4 RICS (1991) 32

    2.7.5 RICS (1998) 33

    2.8 The Initial Role of the Quantity Surveyor 34

    2.9 The Current Role of the Quantity Surveyor 35

    2.10 SMM7 and the need for change 38

    2.11 The New Rules of Measurement 41

    2.11.1 NRM 1 41

    2.11.2 NRM 2 45

  • 5

    2.11.3 NRM 3 47

    2.12 The Black Book 48

    2.13 Building Information Modelling (BIM) 49

    2.14 Summary 49

    Chapter 3 Data Analysis 50

    3.1 Introduction 50

    3.2 Research Aims 50

    3.3 Types of Data Collection 50

    3.3.1 Qualitative Data 51

    3.3.2 Quantitive Data 51

    3.4 Primary and Secondary Data 51

    3.5 Research Methods 51

    3.6 Questionnaire 1 52

    3.6.1 Parties in Question 1 52

    3.7 Questionnaire 2 52

    3.7.2 Parties in Question 2 53

    3.8 Interviews 53

    3.9 Telephone Interviews 54

    3.9.1 Telephone Interview

    Participants 54

  • 6

    Chapter 4 Analysis of Data 55

    4.1 Introduction 55

    4.2 The Questionnaire 55

    4.3 Interview Results 73

    4.4 Software 81

    4.5 Education 83

    Chapter 5 Evaluation of Data 84

    5.01 Introduction 84

    5.02 The Construction Industry the

    Various Industry and RICS Reports 84

    5.03 The Role of the QS 86

    5.04 Methods of Measurement SMM7 & NRM 87

    Chapter 6 Conclusion 89

    6.01 Introduction 89

    6.02 Objective 1 89

    6.03 Objective 2 90

    6.04 Objective 3 91

    6.05 Objective 4 92

    6.06 Objective 5 93

    6.07 Research Gap 93

  • 7

    Abstract

    The Role of the Quantity Surveyor is very complex and involves many disciplines and

    personal traits. As a result of changes, within the Economy and the Construction

    Industry, the role is constantly being adapted and changed. Following a period of

    review and discussion, The Royal Institution of Chartered Surveyors introduced the

    New Rules of Measurement to assist in the preparation of cost plans and measurements.

    Measurement is still an important part of the Quantity Surveyors role, however, the

    preparation of cost advice is equally as important. Over the past 10 years or so, a new

    breed of Quantity Surveyor has emerged who is commercially aware and plays an

    essential role in day-to-day running of construction project. The Contractors Quantity

    Surveyor is now a key member of the Project Team.

  • 8

    Acknowledgements

    I would firstly like to thank my late mum and dad for their love support and

    encouragement that has lead me along this path, may you both rest in peace. I would

    also like to thank God for giving me the inner strength to take the path that has finally

    enabled me to complete my studies. I would like to thank all my friends, and

    neighbours for their support and encouragement, friends are the family that we chose

    for ourselves and without good friends I would not have achieved my ultimate aim to

    complete this dissertation. Special thanks to Dr Fiona Grant for her help and

    encouragement in helping me to achieve something that I never thought I would.

    Special thanks to my beloved boy Becks who has encouraged me in his own special

    way.

  • 9

    List of Tables and Illustrations.

    Figure 1 Diagrammatical mind map of Dissertation.

    Figure 2 The Construction Supply Chain.

    Figure 3 The Composition of the UK Construction Sector.

    Figure 4 United Kingdom GDP Growth Rate.

    Figure 5 National Audit Office Analysis if Latham, Levene and Egan.

    Figure 6 Factors Required for Better Construction Performance.

    Figure 7 The Key Recommendations of Accelerating Change.

    Figure 8 Survey response on the benefits since Egan.

    Figure 9 The Role of the Quantity Surveyor.

    Figure 10 Contents of SMM& compared to NRM2.

    Figure 11 NRM Suite of Documents.

    Figure 12 Logic and arrangement of cost data structure used by NRM1 and the

    updated BCIS SFCA Level 1 and 2.

    Figure 13 The RICS formal cost estimating and cost planning stages in context

    with the RIBA Plan of Work and OGC Gateways.

    Figure 14 Pie chart showing responses to question 1

    Figure 15 Bar chart showing responses to question 2

    Figure 16 Bar chart showing responses to question 3

    Figure 17 Bar chart showing responses to question 4

    Figure 18 Bar chart showing responses to question 5

    Figure 19 Pie chart showing responses to question 6

    Figure 20 Pie chart showing responses to questions 7

    Figure 21 Bar chart showing responses to question 8 and 9

  • 10

    Figure 22 Pie chart showing responses to question 10

    Figure 23 Bar chart showing responses to question 11

    Figure 24 Pie chart showing responses to question 12

    Figure 25 Bar chart showing responses to question 13

    Figure 26 Pie chart showing responses to question 14

    Figure 27 Pie chart showing responses to question 15

    Figure 28 Pie chart showing responses to question 16a

    Figure 29 Bar chart showing responses to question 16b

    Figure 30 Pie chart showing responses to question 16c

    Figure 31 Pie chart showing responses software question 3

  • 11

    Glossary of Abbreviations

    QS Quantity Surveyor

    CI Construction Industry

    RICS Royal Institution of Builders

    CIOB Chartered Institute of Builders

    NRM New Rules of Measurement

    NRM 1 New Rules of Measurement 1

    NRM 2 New Rules of Measurement 2

    NRM 3 New Rules of Measurement 3

    SMM Standard Method of Measurement

    SMM7 Standard of Method of Measurement Seventh Edition

    SMM6 Standard of Method of Measurement Sixth Edition

    BIM Building Information Modelling

    CDM Construction Design and Management

    UK United Kingdom

    BCIS Building Cost Information

    SFCA Standard Form of Cost Analysis

    M & E Mechanical and Electrical

    OGC Office of Government Commerce

  • 12

    Chapter One Introduction

    1.1 Introduction

    The purpose of this chapter is to give an overview of the dissertation. The rationale is

    detailed, followed by the research proposal, the aims and objectives set out, research

    methodology given and finally a breakdown of the chapters detailed.

    Figure 1: Diagrammatical Mind Map of Dissertation

  • 13

    1.2 Rationale

    The role of the Quantity Surveyor (QS) and the Construction Industry (CI) have both

    been through significant change over the past 30 years. Long before the recent

    recession, and as far back as the recession of the early eighties, it was widely known

    that the CI had been labelled by Clients, The Government and the Public as having a

    poor image with many projects over running in both cost and time. In an attempt to

    resolve this, several industry reports were commissioned namely: The Latham Report

    Constructing the Team (1994), The Egan Report Rethinking Construction (1998),

    Modernising Construction (2001) National Audit Office, Egan Report Accelerating

    Change (2002) and The Wolstenholme Report (2009). In the late 1960s and early

    1970s, The Royal Institution of Chartered Surveyors (RICS) noticed that Quantity

    Surveying as a profession was suffering from a Crisis of Identity, so much so that it was

    predicted that Quantity Surveying would soon become redundant. The RICS, therefore,

    identified that there was a potential problem and commissioned several reports. The

    main ones being: RICS (1971) The Future Role of the Quantity Surveyor, RICS (1983)

    The Future Role of the Chartered Quantity Surveyor, RICS (1991) Quantity Surveying

    2000 The Future Role of the Quantity Surveyor, RICS (1998) and The Challenge of

    Change QS Think Tank: Questioning the Future of the Profession. QSs play a key

    role in ensuring that construction projects are delivered both on time and within budget.

    As a result of the Industry and the RICS reports, the role of the QS has been reinvented

    several times from its initial role as Measurer. The current role of the QS is to

    manage costs on building projects from early conception to completion and as a result

    enhancing value for money.

    Following the collapse of the World Banking system in 2008, the World Economy has

    been in a fragile state and in an attempt to survive top Construction corporations were

    forced to adapt. Unfortunately as a result of change there was also an element of

    collateral damage. Due to the recent recession the CI has been in a severe state of

    decline, with the number of large commercial, residential and infrastructure projects

    being vastly reduced. The Economic downturn during 2008 and 2013 has, had a severe

    detrimental effect on the CI, and apart from there being a vast number of redundancies,

  • 14

    tender margins have also been slashed and several Companies have been operating at

    break-even and also negative margins in an attempt to remain in business. On a more

    positive note, the recent financial indicators show that the economy is showing signs of

    improvement. It has been hinted that 2014 will be the biggest growth year since the

    recession. Mair (2014) recently reported that the CI is currently in a period of growth

    rising for the first time in five years with employment in the CI being required in all

    areas of the United Kingdom. It is however of paramount importance that lessons are

    learnt from the recent period of austerity and that tight financial controls are maintained.

    QSs are responsible for controlling costs on a project from the initial cost plan stage to

    the final completion stage. It was identified that the information completed at cost plan

    stage was of paramount significance to a project as this was used by Clients when

    establishing their construction budget. Benge (2009) highlighted that there was a need

    to change in the way that Cost Plans were prepared. Ashworth (2010) identified how

    during 2008 The RICS and the Construction Faculty set up a Steering Group, The

    Measurement Initiative Steering Group, identified issues associated with the

    measurement of building works at all stages of the design and construction process and

    as defined by Benge (2010) to develop a suite of measurement rules to support the cost

    management and procurement of construction projects from cradle to grave dealing

    with cost estimating and cost planning. The suite of measurement rules introduced

    was The New Rules of Measurement (NRM) a suite of documents developed by the

    (RICS) to set out a standard set of measurements rules that can be understood by all

    parties involved in a project. According to the RICS the documents are the most

    significant thing to happen in the industry in 25 years.

  • 15

    1.3 The Research Proposal

    The purpose of this dissertation is to analyse the journey of the QS from Standard

    Method of Measurement of Building Works Seventh Edition (SMM7) to New Rules of

    Measurement (NRM) the associated Black Book and the implications of Building

    Information Modelling (BIM) and to establish whether or not any of these changes will

    assist the QS in recreating their identity within the CI and whether or not their

    implementation will assist in projects becoming more efficient.

    1.4 Aims and Objectives

    To reach this objective it will be necessary to:

    Analyse the findings of the RICS and Industry reports and establish how the role

    of the QS has had to change due to current market trends and changes in

    legislation.

    Review current academic literature and establish why the role of the QS has been

    in crisis for a number of years and to identify the ways in which the role of the QS

    has been vastly diversified over the last few years and therefore identify the

    current role of the QS.

    Analyse the background to and the introduction of the New Rules of Measurement

    within the Industry and how it can be implemented to ensure that the role of the

    QS can be reinvented.

    Carry out a brief overview of SMM7 versus the New Rules of Measurement and

    to establish why the RICS felt that it was time for change.

    Identify how the NRM is being filtered into student syllabus and what training

    companies need to implement.

  • 16

    1.5 Research Methodology

    In order to reach the objectives the following research will be carried out:

    An overview of the CI since the Eighties will be given in order to establish

    whether or not changes within the Industry have led to an alteration in the role of

    the QS.

    In order to research the impact of NRM it will be necessary to carry out both a

    Questionnaire based study and a series of Interviews. The Research based

    questionnaire will be aimed at a variety of QS across all fields of the industry.

    The Interviews would provide more precise responses.

    Research will also need to be carried out on how Universities are filtering the

    New Rules of Measurement into their Syllabus. This will be done by collecting

    information from Course Descriptors of various Universities.

    There will also be a requirement to analyse the impact that the NRM has had in

    Estimating Software. Again a brief Questionnaire will be formulated and

    forwarded to several Software Companies in order to establish this.

  • 17

    1.6 Research Structure

    The Research will be broken down into the following Chapters:

    Chapter 1 Introduction

    Chapter 2 Literature Review

    An overview of the Construction Industry

    The Role of the Quantity Surveyor

    The New Rules of Measurement

    Chapter 3 Data Gathering

    Chapter 4 Analysis of all Data

    Chapter 5 Evaluation of Data

    Chapter 6 Conclusions

  • 18

    Chapter Two - Literature Review

    2.1 Introduction

    The aim of this chapter is to carry out a literature review relating to the role of the QS

    and their future position within the CI (CI). The chapter provides an insight into the CI

    followed by a review of the role of the QS, in particular in relation to the findings of the

    Reports carried out by the RICS between the periods of 1967 1998. There will be also

    be an overview of the NRM along with, the Black Book and a brief review on how

    Building Information Modelling (BIM) can support the New Rules of Measurement.

    2.2 The Parties involved in a Construction Project.

    This Dissertation is concerned in particular with the future role of the QS, it is should

    however be noted that the QS is part of a team of Professionals. Construction Projects

    involve several different professionals and parties such as Architects; Structural

    Engineers; Main Contractors; Services Engineers and Construction Design and

    Management (CDM) Co-ordinators who all play an active part in the Construction

    Project at differing stages. These professionals all work independently, either directly

    for the Client, or the Contractor, they all make decisions that ultimately affect each

    other and the construction project. All parties to a project are important as they are all

    links in the chain.

  • 19

    2.3 The Construction Supply Chain

    As highlighted in The Department for Business Innovation and Skills Report (July

    2013), the supply chain within the CI is large with most of the resources being sourced

    within the UK, and approximately 90% of the monies spent on construction projects

    staying within the UK. Kwakye (1997) identified that the CI is fragmented in the way

    it undertakes works, the range of companies carrying out the works and the complex

    nature of its structure. Morledge et.al (2006) developed this theory and noted that the

    fragmentation of the industry means that it tends to be a diverse supply markets from

    which Clients may source their specific needs. The Industry does have a number of

    large organisations, however, it is made up predominantly of a high number of small to

    medium sized enterprises and a vast amount of works are carried out by subcontractors.

    The CI has a high amount of people working on a Freelance basis whom work with

    several different Private Practices, Consultants and Contractors. Refer to diagram

    below:

    Figure 2: The Construction Supply Chain

    Source: Department for Business Innovation and Skills Report UK Construction: An economic analysis of the

    Sector (July 2013)

  • 20

    2.4 Composition of the Construction Industry

    The CI has been defined by Towey (2012) as being a generic term for the service

    industry that forms part of the nations economy, carrying out the planning, design,

    construction, alteration, refurbishment, maintenance, repair and demolition of

    structures. Whereas Cartlidge (2013) identified the CI as a unique, complex and often

    fragmented industry. According to Harvey et.al (1997) The CI has literally built

    Great Britain. The CI covers a variety of areas including, Housing Building, Private

    Finance Initiative (PFI), Infrastructure, Industrial Construction, and Commercial

    Construction. Works are undertaken for both Public and Private Clients and are

    therefore, a major part of the Economic make-up of the United Kingdoms Economy.

    Construction is an extremely valuable source of employment for a variety of individuals

    involved in many different and variable roles from the field of Main Contracting,

    Developing, All Trades Sub-contracting, and Self-Employment in both the Private and

    Public Sector and Consultancies. The CI currently employs a vast no of people who

    work in a Freelance basis for a variety of Client, Private Practice, Consultancies and

    Contractors. There are also the fringe workers such as those who operate the plant

    machinery on construction sites, haulage companies who deliver and take away

    materials and of course catering companies. This makes for employment and a healthy

    economy.

    The Industry has three main sectors:

    1. Contracting

    2. Services

    3. Products.

    2.4.1 Contracting

    Contracting is by far the largest of the three sectors as identified in The Department for

    Business Innovation and Skills Report (July 2013),it can be apportioned as covering

    70% of the sector. Contracting includes all aspects of Construction works from the

  • 21

    construction of buildings, infrastructure works and specialist activities. Construction

    works can be either commercial or residential and can be for either private or public

    clients. Construction works can therefore be either on an extremely vast or small scale.

    Infrastructure includes the construction of civil engineering works such as Roads,

    Bridges, Tunnels, and Utilities. Specialist activities include plumbing, electrical,

    decoration, roofing, roughcasting, plastering and demolition to name but a few.

    Specialist works are very often carried out on construction projects by subcontractors

    who have specialised in their particular trades. Due to the number of Design and Build

    and Contractor Design Works Contracting can also include some service works from

    Architects and Structural Engineers. Contractor will very often have their own

    Commercial Team which will be made up of QSs and Construction Estimators.

    2.4.2 Services

    The Services Sector is the second largest sector and as identified in The Department for

    Business Innovation and Skills Report (July 2013), can be apportioned as covering

    15.5% of the sector. The Services sector includes the Professional Services of

    Architects, Structural Engineers, Services Engineers, CDM Co-ordinators, QSs,

    Wholesale Suppliers and the Renting and Leasing of Construction Equipment.

    Professional Services are carried out on construction projects both at Pre Construction

    and Construction stages. Wholesale suppliers are responsible for the procurement and

    supply of the various construction materials involved in any form of construction

    project. The Contractor relies on a vast number of such suppliers to provide all elements

    of materials required for the construction of their projects. The Wholesale suppliers will

    work closely with the Contractors ensuring that all of the critical path elements of the

    project are covered. Renting and Leasing of Construction Equipment include items

    such as the various dumpers, diggers, mobile towers, skips and portaloos required on a

    construction project.

  • 22

    2.4.3 Products

    The Products Sector is smallest sector and, as identified in The Department for Business

    Innovation and Skills Report (July 2013), can be apportioned as covering 14.5% of the

    sector. The Products Sector includes the manufacture of construction products and

    materials. The manufacture of construction products and materials are an important part

    of the construction process. The Products Sector works closely with Wholesale

    Suppliers to ensure that they can supply the materials that the suppliers demand. The

    Products Sector will also be in close communication with Architects to ensure that they

    are aware of all of the latest materials.

    A diagram showing the composition of the UK construction sector is shown

    below:

    Source: Department for Business Innovation and Skills Report UK Construction: An economic analysis of the

    Sector (July 2013)

    Figure 3: The Composition of the UK Construction Sector

  • 23

    2.5 The importance of the Construction Industry to the UK Economy

    The CI is not just an important part of the UK Economy, the industry has worldwide

    importance. As a result of this worldwide importance, many of the UKs larger

    organisations and it must be said some of the smaller organisations are now involved in

    working internationally. Harvey et.al (1997) identified the importance of the CI as

    being a result of rapid growth in the late 1980s. Cartlidge (2013) noted that the CI is a

    major player in the Gross Domestic Product (GDP) and that the CI in 2011 had a

    turnover of almost 100 billion which equates to almost 8.5% of the GDP. Hillebrant

    (1984) noted the net contribution of the industry in 1981 as being 6.4 percent. Harvey

    et.al (1997) note the GDP as 6%. The Department for Business Innovation and Skills

    Report (July 2013) identified that Construction is one of the largest sectors in the UK

    economy and comprises almost 90 billion to the UK Economy. The CI is therefore an

    extremely important commodity made up of a range of products, services and

    technologies. As shown in the diagram below the UK GDP improved following a long

    period of decline.

    Source: Trading Economies -www.tradingeconomics.com/united-kingdom/gdp- 26th February 2014

    Figure 4 United Kingdom GDP Growth Rate

  • 24

    2.6 The Significance of the Various Construction Industry Reports

    During the nineteen eighties and early nineteen nineties, the CI had an extremely poor

    image. Due to this poor image and in an attempt to deliver value for money, several

    reports have been written namely:

    1. The Latham Report Constructing the Team (1994)

    2. The Levene Report - The Levene Efficiency Scrutiny into Construction

    Procurement by Government (1995)

    3. The Egan Report Rethinking Construction (1998)

    4. Modernising Construction (2001) National Audit Office

    5. The follow up to the Egan Report Accelerating Change (2002)

    6. The Wolstenholme Report (2009)

    Each of these reports highlighted ways of making improvements within the industry.

    2.6.1 The Latham Report Constructing the Team (1994)

    Following a period of lapse in the CI and several controversial issues, The Latham

    Report was commissioned jointly by the Government and the CI, with invaluable

    participation of Clients. The report was aimed at reviewed procurement and contractual

    arrangements. As noted in Wikipedia, Latham identified industry inefficiencies,

    condemning existing industry practices as 'adversarial', 'ineffective', 'fragmented',

    'incapable of delivering for its clients' and 'lacking respect for its employees'. Latham

    made a total of 53 recommendations, several of which were radical. The main ones

    relate to best practice clients, the establishment of a construction clients forum,

    adjudication, guidance on partnering, roles and responsibilities of construction parties

    and building services design being defined.

  • 25

    2.6.2 The Levene Report - The Levene Efficiency Scrutiny into Construction

    Procurement by Government (1995)

    Following on from Latham the Levene Report was commissioned by the Cabinet

    Office to review Procurement and Best Practice in relation to Government Contracts.

    2.6.3 The Egan Report Rethinking Construction (1998)

    The Egan Report Rethinking Construction (1998) was commissioned by John Prescott

    on scope for improving quality and efficiency in UK Construction. The Report

    identified five key drivers of change that should set the agenda for the CI at large. The

    Report proposed that if the UK CI was to improve there needed to be radical change in

    the way we build. The Report set objectives that within a 5 year period the CI delivers

    its products to its customers in the same way as the best consumer-lead manufacturing

    and service industries.

    2.6.4 Modernising Construction (2001) National Audit Office

    This Report was ordered by the House of Commons. The report was split into three

    sections -

    The challenge improving construction performance.

    Improving Client and Supplier Performance

    Procuring.

    Modernising Construction reviewed previous reports focusing in particular on the

    recommendations. Each of these recommendations was closely scrutinised to ascertain

    whether or not they have been implemented. The Report identified that these reports

    have identified a number of fundamental barriers that need to be overcome if

    construction performance was to improve and become more cost-effective. The report

    tabulated the key reviews Refer to Figure 5.

  • 26

    Source: Modernising Construction 2001

    Figure 5 National Audit Office analysis of Latham, Levene and Egan

    The Report also noted in order to achieve a better construction performance there would

    be a requirement to ensure that Better Construction is fit for purpose for a specific

    purpose and that it meets the requirements of its end user. This information was

    collated by analysing the findings of the Latham, Levene and Eugene.

    Refer to Figure 6 below:

  • 27

    Figure 6 Factors Required for Better Construction Performance.

    2.6.5 The follow up to the Egan Report Accelerating Change (2002)

    This Report was an extension of Rethinking Construction. The Report covered topics

    such as Strategic Direction and Targets, Client Leadership, Supply side Integration and

    Integrated Teams. The Report made 21 key recommendations.

  • 28

    A diagram of the key recommendations is detailed below:

    Source: The Egan Report - Accelerating Change (2002)

    Figure 7 The Key Recommendations of Accelerating Change.

    2.6.6 The Wolstenholme Report (2009)

    The Wolstenholme Report reviewed the findings of the reports since Egan and

    identified that the need for change was still as strong today as it was in 1998. A factor

    that needs to be considered is that, at the time of publication of the previous reports, the

    economy was buoyant whereas 2009 was during a long period of recession.

    The Report analysed the blockers to change as Business and Economic Models,

    Capability, Delivery Model, and Industry Structure. The Report carried out a

    review to establish the benefits to the Industry since Egan 1998. The main

    benefits are shown in the following figure 8.

  • 29

    Figure 8: Survey responses on the benefits since Egan.

    The Report identified key 8 requirements. The report highlighted the key elements for

    change in the Industry for Suppliers, The Government and Client as being a new vision

    for the Industry based on the concept of the built Environment. This means

    understanding how value is created over the whole life cycle of an asset, rather than

    simply looking at the building cost which is only part of the total equation.

  • 30

    2.7 RICS Reports carried out between 1967 and 1998

    During a thirty year period, spanning from the late nineteen sixties to the late nineteen

    nineties, the RICS wrote a number of reports each analysing the role of the QS and how

    it could adapted and further developed. Topics considered included changes in

    construction practices, design, construction process, tendering and procurement, and

    changes in the CI.

    These reports included:

    1. RICS (1967) Evolving the Quantity Surveyor

    2. RICS (1971) The Future Role of the Quantity Surveyor

    3. RICS (1983) The Future Role of the Chartered Quantity Surveyor

    4. RICS (1991) Quantity Surveying 2000 The Future Role of the Quantity

    Surveyor

    5. RICS (1998) and The Challenge of Change QS Think Tank: Questioning

    the Future of the Profession.

    2.7.1 RICS (1967) Evolving the Quantity Surveyor

    The Research for this Report was carried out by the Quantity Surveying Research and

    Information Group (QSRIG) as a result of their research the role of the QS was defined

    as working from initial measurement after it had been executed then measuring and

    valuing building works before work commenced.

  • 31

    2.7.2 RICS (1971) The Future Role of the Quantity Surveyor

    The research in RICS (1971) indicated that there was a need for change and that the

    profession was becoming concerned with the economic and financial aspects of

    construction projects and, as well as carrying out its duties relating to tendering and

    contracts along with measurement, it should ensure that necessary control measures are

    put in place to protect the client. The results highlighted a need to concentrate on

    factors such as population growth, economic measures, political activities, and

    increasing abilities of clients and design. Additionally, due consideration should be

    given also to technological changes such as the computer and the need for industrialised

    buildings. The QS needed to become more familiar with Mechanical and Electrical

    Services and Civil Engineering along with diversification into the field of contracting.

    There was also a requirement for the QS to become more acquainted with project co-

    ordination, environmental economics, cost engineering and production and resources

    control.

    2.7.3 RICS (1983) The Future Role of the Chartered Quantity Surveyor

    The research within RICS (1983) was carried out by four study groups set up by The

    Quantity Surveyors Divisional Council. Each group was responsible for reflecting on

    how the role of the QS should be developed. As a result research, it was identified that

    following the previous reports, the role of the QS had further developed into the fields

    of manpower planning, resource controls and analysing the effect of time on

    construction projects. The QSs expertise within the CI embraces many skills.

    However it also emerged that the role needs to be further developed in the areas of

    policy making, numerate skills, strategic planning and contracting. The changing role

    in relation to political and economic policies is another essential part of the QSs role.

    The building procurement function and how the QS should become more involved in

    Construction Management, multi-disciplinary working, diversity in procurement total

    costs which encompasses the area of life cycle costs were also considered. The Report

    indicated that the traditional Bills of Quantities prepared using SMM7 may be side

    stepped for a more abbreviated and streamlined document. This was therefore one of

  • 32

    the first indications that there was a need for change in the way that Bills of Quantities

    are prepared and that SMM7 was outdated.

    2.7.4 RICS (1991) Quantity Surveying 2000 The Future Role of the QS

    RICS (1991) comprises of four main areas: changing markets, a changing industry, the

    profession in transition and challenges in the 1990s. Research results revealed that the

    services the QS would need to be increasingly developed to meet efficient standards.

    With the advancement of technology it was widely expected that computer technology

    would soon stream line the role of the QS. The introduction of computer assisted

    billing and estimating packages signposted Information technology as the way ahead.

    During this period there was an increased requirement for Industrialised Building and

    the associated processes which would ultimately result in a greater use of performance

    specifications the QS would be required to consider and understand the costing of

    these buildings.

    Mechanical and Electrical Services, Civil Engineering and Contracting, was considered

    and it was noted that as this was a particular specialised area, Clients were not

    necessarily receiving the best cost advice. Therefore, there was a requirement for the

    development of knowledge and specialism in this area. It was suggested that QSs were

    given the appropriate additional training to ensure that they could be appointed into

    managerial roles with high levels of responsibility.

    It highlighted that during the 1980s there was a vast change in the pattern of

    construction investment with a change from public to private funded construction work

    and as a result QSs had to adapt to changes in both the procurement and organisation of

    construction work. In contrast to this, it was noted that Construction companies were

    using Specialist Sub-Contractors and that Main Contractors were becoming increasingly

    involved in the Design process.

  • 33

    2.7.5 RICS (1998) and The Challenge of Change QS Think Tank: Questioning

    the Future of the Profession.

    RICS (1998) investigated the future role of the QS in relation to changing markets, a

    changing industry, and the profession in transition and the challenges in the 1990s. It

    was forecasted that there would be key developments in private commercial

    development, retail developments, public building, private house building, industrial

    building, repair, maintenance and improvements and major infrastructure works. The

    report highlighted that the CI was on the brink of major change and therefore there

    would be the opportunity of new challenges for the Quantity Surveying profession as a

    whole. It was envisaged that the QS would have a much more involved role in housing,

    civil engineering and repair and maintenance.

    A need for QSs to become more involved in the new geographical markets was

    considered in RICS (1998). The expanded market meant that there was more

    requirement for the services of QSs who would evolve in the existing market or

    diversify into the new work areas. The advanced improvements in Computer

    Technology were also reviewed and it was identified that several Software programmes

    were currently being developed that would be able to replace some of the duties

    currently carried out by the QS.

    The report focused on the future role of the Contractors Quantity Surveyor (CQS) and

    highlighted skills that candidates would be required to have. The tasks that would be

    carried out by the CQS included, project strategy work, procurement advice, initial and

    detailed cost planning, Bills of Quantities, preparing tender and contract documents,

    cost management, final accounts, monitoring work, project auditing / analysis,

    employers agent, construction management, dispute resolution specialist, information

    manager and facilities management.

  • 34

    2.8 The Initial Role of the Quantity Surveyor

    The role of the QS is as noted by Towey (2012), unfamiliar to the public. This could

    be a result of the various activities carried out by a QS, thus making the role difficult to

    define. The role of the QS is however a role that is familiar within the CI. Towey

    (2012) defined the initial role of the QS in the 17th

    Century as that of measurer,

    whilst during the 19th

    Century the role had evolved whereby the QS was responsible for

    the production of schedules which quantified building materials along with plant and

    labour. These schedules were forwarded to builders for pricing: the theory behind this

    was that all builders when pricing the information based their prices on the same

    information thus enabling the tenders to be easily analysed. Morton (2008) confirmed

    that the construction of the Houses of Parliament in the 1830s was a great landmark in

    the history of the QS, as it was one of the first buildings to be approved of detailed

    drawings and a bill of quantities based on them. Traditionally the role of the QS was

    to work with the Client preparing tender documents and valuing building works carried

    out by the Main Contractor on a development. The QS who carried out this role was

    usually heavily involved in measurement known as a Private Quantity Surveyor (PQS).

    As a result of improvements in the CI and a need for the Client to achieve value for

    money, Main Contractors are more commercially aware than they used to be and, as a

    result, the role of the Contractors QS has evolved. The Contractors Quantity Surveyor

    (CQS) is responsible for all aspects associated with the running of a building project

    from Cost Planning, Estimating, Contract Administration and sometimes Project

    Management. Contractors QSs are often called Commercial Managers, and they are

    responsible for all aspects of procurement and cost control.

  • 35

    2.9 The Current Role of the Quantity Surveyor

    Towey (2012) and Walker and Wilkie (2002) identified that Commercial Managers

    within Main Contracting Organisations are responsible for budgets and forecasting;

    interim valuations for both the Client and the various Subcontractors; Cost Value

    Comparisons; Contracts, certificates and Notices and the preparation of contracts for

    subcontractors. The Commercial Manager will also be involved in working with supply

    chain procurement, running the project in conjunction with the Project Manager,

    Measurement and Quantities, Project Commencement and Project Completion. The

    current role of the QS in both the Private Practice and Main Contracting are now more

    complex and far removed from the initial role of measurer.

    QSs are becoming increasingly involved in the areas as noted in the table below:

    Procurement

    Routes

    Harvey et.al (2007) defines Procurement as the process that

    is used to deliver construction projects. The correct choice

    of procurement route is of major importance in a Construction

    Project. Morledge et al (2006) highlights that strategies for

    procurement of new construction projects have been

    significantly changed over the last 25 years.

    Construction

    Management

    Construction Management has been defined by Harvey et.al

    (2007) as the process whereby the client appoints a

    Construction Manager who will be responsible for the overall

    control of the Design Team and Trade Contractors throughout

    the Design and Construction stages of the project.

  • 36

    Cost Planning

    Harvey et.al (2007) defines cost planning as not simply a

    method of pre-tender estimating, but seeks also to offer a

    controlling mechanism during the design stage expenditure

    is controlled to offer the Client value for money. Cost

    planning is a critical part of a QSs role. Ferry et al (2007),

    Ferry et al (2005) and Harvey et.al (2007) all highlight the

    principles of cost planning requirements from inception to

    conception. It is widely known that Clients always remember

    the first figure that is presented to them with regards to a

    construction budget. The preparation of a cost plan is

    therefore an extremely important part of the role of a QS.

    The introduction of NRM1 has aided the preparation of

    Elemental Cost Plans.

    Preparation of

    tender and contract

    documents and

    appraisals

    Cartlidge (2013) reviews the tender process and contract

    documents. Towey (2012) reviews the appraisal process. The

    preparation of tender and contract documents along with

    appraisals are all key elements associated with the day to day

    activities of the QS it is therefore essential that these

    documents are all prepared correctly.

    Project

    Management

    Cartlidge (2011) highlighted how QSs are becoming involved

    in Project Management.

    Mechanical and

    Electrical

    Engineering

    Mechanical and Electrical Engineering is a highly specialised

    area and not all QSs can adapt to the requirements of this area.

    QSs working in this area require to be familiar with all aspects

    of Mechanical and Electrical Engineering.

  • 37

    Construction

    Design and

    Management

    (CDM)

    responsibilities

    The introduction of Construction Design and Management

    regulations has seen QSs being increasingly involved in all

    aspects of Health and Safety from the preparation of Health

    and Safety Policies to Method Statements and the Control of

    Substances Hazardous to Health (COSHH) Assessments and

    also Health and Safety Plans. Additionally QSs need to be

    aware Pre Tender Health and Safety requirements on a project

    when preparing costs.

    Value Engineering

    Value management and value engineering both maximise the

    functional value of the project, and are associated with clearly

    defined objectives and effective communications between the

    correct people with the correct skills.

    Estimating

    Cartlidge (2013) describes estimating as one of the core skills

    of QSs. Contractors QSs are usually heavily involved in both

    pre and post contract duties. The preparation of an estimate

    involves obtained quotations for all the materials and plant

    elements of the project. The QS when preparing an estimate

    will be responsible for submitting certain packages to various

    Subcontractors to price. There will also be a requirement to

    price up works that are to be carried out in house by using a

    series of labour outputs. The material and plant costs of these

    elements will be added and an adjudication process will then

    be carried out in which a decision will be made regarding the

    percentages to be added to the costs to cover both overheads

    and profit.

    Table 1: The roles of the Quantity Surveyor.

  • 38

    2.10 The Standard Method of Measurement and the need for change

    The Standard Method of Measurement (SMM) was first published by The Royal

    Institution of Chartered Surveyors in 1922 as a means of providing a uniform basis for

    measuring building works and embodying the essentials of good practice. Over the

    years this document has been updated and reissued several times. The Seventh Edition -

    Standard Method of Measurement 7 (SMM7) was published originally in 1988 and

    revised in 1998. Benge (2009) pointed out that documents, prepared using the Standard

    Method of Measurement documents, were aimed at preparing Bill of Quantities to

    obtain tender prices. There were no specific guidelines for the QS to use when

    preparing Cost Plans and Cost Estimates and therefore QSs tried to adapt the principles

    of the SMM which invariably lead to inconsistencies. For this reason, Clients were not

    entirely confident that the costs produced were accurate. Benge (2012), pointed out that

    SMM has served the industry since 1922 and over the years has been revised 7 times,

    the last major revision being in 1998. Since then construction methods have changed

    and coupled with the Clients increased requirements for best value have suggested that

    it is time for change.

    On 1st January 2013 SMM7 was superseded by NRM2 and all future documents should

    now be prepared using NRM2.

    SMM7 has 22 items noted for splitting up measurements whereas NRM2 has 41.

    NRM2 should allow a more detailed breakdown of the respective elements of the

    building.

    The following table compares the contents of SMM7 with NRM2. From this table it is

    apparent that SMM7 can no longer meet the requirements that QSs require when billing

    current buildings.

  • 39

    Table comparing contents Source: Designing Buildings WIKI

    Figure 10: Contents of SMM7 compared to NRM2

  • 40

    As noted by Earl (2006), during the initial development stage of NRM, the Steering

    Group identified that Quantities are, without doubt, the best control of cost on a

    project. The group also identified that Somebody has to quantify the building works

    and the best person to do this is the QS. During the early stages of the development of

    the NRM suite it was noted that members continue to use SMM7 and also nobody uses

    measurement anymore.

  • 41

    2.11 The New Rules of Measurement

    The NRM Suite of Documents showing the interaction between the RICS New Rules of

    Measurement and the BCIS Standard Form of Cost Analysis

    Figure 11: NRM Suite of Documents

    The New Rules of Measurement is a suite of documents set up by the RICS and a

    Construction Steering Group. These documents are made up of three volumes:

    Volume 1: Order of Cost Estimating and Elemental Cost Planning First Edition

    Published March 2009. Amended to Order of Cost Estimating and Cost Planning

    for Capital Building Works - Second Edition Published 2012.

    Volume 2: Construction Quantities and Works Procurement Published 2012.

    Volume 3: Maintenance and Operation Cost Planning and Procurement. -

    Expected to be published January 2015.

  • 42

    Group element Element 0 Facilitating works 0.1 Toxic/hazardous material removal

    0.2 Major demolition works 0.3 Temporary supports to adjacent structures 0.4 Specialist und ks 0.5 Temporary diversion works 0.6 Extraordinary site investigation works

    1 Substructure 1.1 Substructure 2 Superstructure 2.1 Frame

    2.2 Upper floors 2.3 Roof 2.4 Stairs and ramps 2.5 External walls 2.6 Windows and external doors 2.7 Internal walls and partitions 2.8 Internal doors

    3 Internal finishes 3.1 Wall finishes 3.2 Floor finishes 3.3 Ceiling finishes

    4 Fittings, furnishings and equipment 4.1 Fittings, furnishings and equipment 5 Services 5.1 Sanitary installations

    5.2 Services equipment 5.3 Disposal installations 5.4 Water installations 5.5 Heat source 5.6 Space heating and air conditioning 5.7 Ventilation systems 5.8 Electrical installations 5.9 Fuel installations/systems 5.10 Lift and conveyor installations 5.11 Fire and lightning protection 5.12 Communication, security and control systems 5.13 Specialist installations/systems 5.14 Builde s work in connection with services

    Figure 12: Logic and arrangement of the cost data structure used by NRM1

    and the updated BCIS SFCA Levels 1 and 2 Extracted from RM1 Source

    Construction Journal April-May 2012.

    2.11.1 New Rules of Measurement Volume 1 Order of Cost Estimating and Cost

    Planning for Capital Building Works NRM1

    This document provides rules of measurement for the preparation of order of cost

    estimates and elemental cost plans. The following diagram shows how the cost plan

    can be broken down into the respective Five elements of Substructure, Superstructure,

    Internal Finishes, Fittings, furnishings and equipment and Services. Each element can

    be further broken down into sub elements thus providing a fully detailed breakdown of

    costs.

  • 43

    As noted in Earl (2012) NRM1 has been recently been updated in line with comments

    from practitioners. Eight key changes were made Benge (2012) highlights these key

    changes. These changes were made to simplify and augment certain aspects of the rules.

    Changes were also made to strengthen the link between the method of measurement and

    how contractors procure works. Earl (2012) clarified that the Building Cost

    Information Services (BCIS) Standard Form of Cost Analysis (SFCA) was updated in

    line with the NRM Suite. Benge (2011) further clarifies how the use of NRM1

    demonstrates a responsible approach to the cost management of construction projects.

    Benge (2011) also noted that NRM1 represents the essentials of good practice and the

    cornerstone of good cost management of construction projects. Cost Plans should,

    under NRM1 be prepared in line with the requirements of the RIBA Work Stages; RICS

    Cost Estimating and Elemental Cost Planning Stages and the OGC Gateway.

    Refer to Figure 13.

  • 44

    Source: New Rule of Measurement 1

    Figure 13: The RICs formal cost estimating and cost planning stages in context

    with the RIBA Plan of Work and OGC Gateways (adapted for the RIBA Outline

    Plan of Work 2007.

  • 45

    2.11.2 New Rules of Measurement Volume 2: Construction Quantities and Works

    Procurement NRM2

    The main difference between SMM7 and NRM2 according to Benge (2012)

    that NRM2 rules for quantifying building works items now reflect current construction

    practices. NRM2 also addresses all aspects of bills of quantities (BOQ) production,

    including defining the information requirements and dealing with the quantification of

    non-measureable work items, contractor-designed works and risks. Benge (2012) also

    gives a review of how NRM2 deals with Preliminaries; non-measureable works such as

    provisional sums and Contractor-designed works; risks works to be carried out by

    statutory undertakers; overheads and profits; credits and other pricing considerations

    such as price fluctuations; directors adjustment; day works; VAT. Benge (2012) further

    reviews how NRM2 has been devised to consider the implications of BIM. NRM2 can

    be utilised and developed when preparing a bill of quantities which includes bespoke

    items.

    An overview of NRM2 was detailed by Davidson (2012) and it was highlighted how it

    should satisfy the needs of different parties within the CI. Davidson (2012) also points

    out that a firm understanding of construction technology and an ability to measure

    construction works are two core skills that QSs need if they are to properly provide

    construction cost advice to clients. Davidson (2012) confirms the previously noted

    comments that SMM was vastly out of date and did not suit the requirements needed

    today by QSs if they are to offer a best value service to their Clients. It was also

    highlighted how the QS and Construction Professional Group that were set up in 2003

    to review Construction Measurement. Additionally, SMM7 had several items

    throughout the document for extra over items which meant that a QS had to trawl

    through the drawings and tediously all of the items, whereas in NRM2 these items are

    all deemed to be included. Davidson (2012) describes the main benefit of NRMs that

    should allow any QS to measure any type of construction work. There is also an

    example of how the NRM2 sets out bill items under five main columns.

  • 46

    Davidson (2012) details several main comparisons between NRM2 and SMM7. The

    main changes detailed include: - NRM2 has a list of items within the rules section

    which are detailed as being Mandatory in preparing a Bill of Quantities the QS must

    fully describe the work element so that the tenderer can fully price the work item.

    NRM2 allows for composite descriptions to be included. Prime cost work and

    provisional work is more clearly defined. A Works Section for off-site manufacturing is

    included. Working space is now deemed to be included when measuring excavations.

    Earthwork support is no longer measurable unless the use is not left to the discretion of

    the contractor. In-situ concrete is now categorised into vertical and sloping. Common

    rules apply to types of masonry. In essence, the works items have all been up dated to

    reflect current working methods on site. The Estimator when pricing a BOQ prepared

    using NRM2 should, in theory, be able to prepare a more cost effective tender as the

    descriptions of works within the BOQ should include much more detailed breakdowns

    and descriptions of works.

    Davidson (2012) notes that M&E services are still described by their differing systems

    but the measurement is simplified, concentrating in principal elements. This change

    makes it much easier for M&E Services works to be both billed and priced. Using

    SMM7, if a QS was billing a heating installation, they would be required to measure

    and quantify every metre of copper pipe, bends, tees, insulation etc. along with each

    individual radiator and valve to be measured and the Estimator would be required to rate

    these accordingly.

  • 47

    2.11.3 New Rules of Measurement Volume 3: Maintenance and Operation

    Cost Planning and Procurement NRM3

    NRM3 is currently being developed and is due for publication early in January 2015.

    The prime function of the NRM suite of documents is defined by Green (2013) as to

    provide consistent rules and guidelines for the quantification and measurement of

    capital, maintenance and renewal works.

    Klein (2007) highlighted how the construction sector has the reputation of making

    lowest initial costs the basis of investment decisions, but future procurers of buildings

    cannot afford to ignore sustainability requirements. Whole life cycle costing is a

    phenomenon that needs to be considered when costing a building. Ashworth et. al

    (2007) defines whole life cycle cost plans as a combination of initial, maintenance,

    replacement, energy, cleaning and management costs.

    Green (2013) pointed out how links from costs plans produced using NRM1, can be

    made to the maintainable elements of a building in NRM3. Blackburn (2013) Reviews

    the potential political impact of NRM3 on the built asset cost maintenance. The paper

    notes how, due to the current economic climate, the Government has reduced budgets

    for both Public Construction and Repair and Maintenance. There are strong indications

    that the Economy is finally in a state of recovery and therefore the Government should

    hopefully be in a position to review budgets and for construction works to commence.

    The whole life cycle cost of these buildings could be reviewed and implemented thus

    ensuring that the projects are cost effective.

  • 48

    2.12 The Black Book

    The RICS define the The RICS Quantity Surveyor and Construction Standards as a

    comprehensive suite of documents that defines good technical standards for QS and

    Construction Professionals. The documents are written as RICS guidance notes and are

    aimed at providing advice to RICS members on aspects of their work. Where

    procedures are recommended, they are intended to represent best practice. These

    documents are an invaluable source of reference for QSs, particularly for Students

    preparing for their Assessment of Professional Competence when read in conjunction

    with RICS Pathway to qualifying in Quantity Surveying and Construction (2008) would

    be an invaluable source of material.

    2.13 Building Information Modelling

    When considering the future role of the QS, it is necessary to briefly mention Building

    Information Modelling. According to the RICS (2014) greater automation of quantity

    surveying functions would actually increase the relevance of the profession. Withers

    (2014) stated that BIM will enhance rather than damage. RICS (2014) is a report

    prepared by the RICS to establish How Building Information Modelling (BIM) can

    support the New Rules of Measurement (NRM1). The report analysed two main areas:

    BIM and its application in cost estimating and cost planning and NRM1 for cost

    estimating and element cost planning. The report also includes a Technical review for

    BIM based estimating tool to support NRM. The report highlighted that BIM based

    measurement and cost estimating is still at its early stages and that supporting the

    NRM1 format through BIM based estimating is the way forward. QSs need to consider

    how the quantity of information in the BIM model can be used in cost estimating and

    planning.

  • 49

    2.14 Summary

    This chapter has reviewed current literature in the form of Journals, Industry Reports

    and Textbooks relating to the future role of the QS and their future position within the

    CI. It is apparent from the reports that, since the publication of the first RICS report in

    1967 the role of the QS has been vastly developed from that of Measurer. The QS is

    involved in a wide variety of roles and specialisms thus making the role one that is

    extremely interesting and highly adaptable.

    Cartlidge (2013) noted that the principle message behind the Industry reports is that the

    CI, as a whole, needs to concentrate on modernisation, innovation and mass

    production. For a construction project to be a complete success, there needs to be

    greater co-operation between all parties, As previously noted, they are all links in the

    chain and therefore need to work together to ensure the ultimate aim of Client

    satisfaction and Value for Money are achieved. The nature of the Client has also

    changed as they now expect value for money. Whilst Contractors are more

    commercially aware.

    Although it is still in its early stages, it would appear that if utilised correctly, The New

    Rules of Measurement should have a positive effect on not just the role of the QS, but

    on the industry as a whole. The documents should assist in greater cost control in all

    areas of the building as more accurate cost plans can be prepared following guidelines

    set out within the rules something that was not available in SMM7. There is also

    greater scope for measurement and the whole life of the building from inception to

    demolition can now be considered. However it should be noted that the majority of the

    literature reviews have been carried out by parties either associated with its

    implementation or those closely associated to it and therefore the findings from

    Industrial research could put a completely different perspective on this.

  • 50

    Chapter 3 Data Gathering

    3.1 Introduction

    The aim of this chapter is to identify the data gathering methods carried out in order to

    research the objectives of this dissertation as set out in chapter 1. This chapter will

    describe all methods of research carried out, and the reasons for using each method.

    3.2 Research Aims

    In order to analyse the objectives effectively it was necessary to carry out research

    within both the Construction Industry and Education. The research within the

    Construction Industry entailed carrying out a questionnaire with several Quantity

    Surveyors from various fields of the Industry, there was also a requirement to carry out

    a follow up questionnaire with several software companies in order to establish what

    changes they have made in relation to NRM. To expand on the data gained from the

    questionnaires carried out with the QSs a few interviews took place. In order to review

    the educational implications of the topic area short telephone interviews were carried

    out with University Quantity Surveying Faculty Course Leaders.

    3.3 Type of Data Collection

    There are two main types of data collection these being qualitative and quantitative.

    The type of data selected depends on the information that the researcher is trying to

    obtain as a result of their research. Although these data collections types are different

    they can be linked as a result of research and then the data collection can sometimes fall

    into both categories.

  • 51

    3.3.1 Qualitative Data

    Qualitative Data is data that does not present itself in numerical format and is obtained

    from real life experiences. Naoum (2009) defines Qualitative research as being

    subjective in nature. Farrell (2011) notes that the qualitative goal is to define

    categories during the process of the study. Qualitative data is in theory harder to obtain

    as it involves carrying out a series of studies.

    3.3.2 Quantitative Data

    Quantitative Data is data that is calculated in the form of statistical analysis. Naoum

    (2009) describes quantitative data as being objective in nature, defined as an inquiry

    into a social or human problem, based on testing a hypothesis or a theory composed of

    variable, measured with numbers, and analysed with statistical procedures, in order to

    determine whether the hypothesis or the theory hold true.

    3.4 Primary Data and Secondary Data

    Primary Data is raw data that has been sourced by the researcher whereas Secondary

    Data that has been sourced by others.

    3.5 Research Methods

    Research was carried out in the form of a series of Questionnaires, and Interviews. Two

    separate questionnaires were carried out, to test the findings within the Industry in

    relation to the main objectives of this dissertation. The first questionnaire was aimed at

    the Quantity Surveying Profession and the second at Software Companies.

  • 52

    3.6 Questionnaire 1

    The questions contained within the first questionnaire were aimed at obtaining and

    finding the views of the Quantity Surveying Profession relating to the main objectives

    of this dissertation. The questions were all closed questions and the responses required

    were chosen from a list of several options. The questions were structured in this way

    so that specific areas could be analysed. The questionnaire comprised of 16 questions,

    with 1 question having 3 parts and 1 question having 2 parts, there was 20 participants.

    The first 3 questions in the questionnaire were aimed mainly at obtaining further

    information on the participants. These questions cover topics such as which sector of

    the industry they belong, what professional bodies that they belong to and how long

    they have been a QS. The next 8 questions are all associated with SMM7 and NRM.

    These questions were all included in order to establish the Professionals opinions

    relative to measurements, SMM7 and NRM2.

    3.6.1 The Parties in Questionnaire 1

    The Parties involved in the Quantity Surveying questionnaire were carefully chosen in

    order for there to be a wide spectrum of responses. The parties who carried out the

    questionnaires comprised of eight candidates who are currently employed by Main

    Contractors, four candidates who are currently employed as Consultants and finally

    eight candidates who are currently employed in Private Practice. The number of years

    experience of the parties was also an important factor as the dissertation is looking at

    the roles of the QS over a 40 year period it was prudent that a number of the participants

    had as much experience as possible, 45% of the participants have over 25 years

    experience with 30% having 40 years. The least experienced candidate had 1 years

    experience.

  • 53

    3.7 Questionnaire 2

    The questions contained within the second questionnaire were aimed at clarifying

    whether or not the respective software companies have implemented changes, to ensure

    that the professionals can achieve the required objectives, there were 4 participants.

    3.7.1 The Parties in Questionnaire 2

    The Parties involved in the software questionnaire were chosen from what is currently

    thought to be the most popular Quantity Surveying and Estimating Packages. The

    questions again were open ended. There was initially 6 questions, however if parties

    could answer questions 1 4 then there was no requirement to complete questions 5 and

    6. All parties fell into this category.

    3.8 Interviews

    After analysing the results of the questionnaires it was apparent that further research

    was required in certain areas. Two interviews were carried out with the view of further

    exploration of some of the questions asked within the Questionnaire. The interviews

    would enable the participants to give their viewpoints on the topics. The interviewees

    did not take part in the Questionnaire.

    3.8.1 Interview Participants

    The Participants both had 20 years experience and they were specifically chosen so that

    they could offer their particular viewpoint on the research aims and objectives. The

    Participants were from different sectors of the Industry. Both interviews lasted

    approximately 30 minutes and both parties were given a copy of the questions that they

    would be asked a week before the interviews took place. Both parties wished to remain

    anonymous. The analysis of the results notes only the main points taken from the

  • 54

    interview the items noted in the results are therefore not purely a transcript of the

    interviews.

    3.9 Telephone Interviews

    In order to establish what the Educational Establishments are doing in relation to the

    implementation of NRM it was necessary to carry out short telephone conversations

    with the Quantity Surveying Faculty Course Leaders to establish what changes to the

    structure of the BSc Quantity Surveying Degree Course.

    3.9.1 Telephone Interview Participants

    In choosing the participants to take part in the telephone interviews, it was decided that

    the best person to speak to would be the Quantity Surveying Faculty Course Leader as

    they would have the best insight into the content of the BSc QS Course. There were 2

    participants in these interviews. 1 participant was based in Edinburgh the other was

    based in Reading.

  • 55

    Chapter 4 Analysis of Data

    4.1 Introduction

    The aim of this chapter is to analyse the data collected and to relate it to the key aims

    and objectives of this dissertation. Chapter 2 analysed the findings in literature on the

    topic, this chapter will analyse the industry finding.

    4.2 The Questionnaire

    The findings of each of the following questions are detailed below. There were a total

    of 20 participants all parties answered all questions.

  • 56

    4.2.1 Question 1

    Question 1 was aimed at establishing the mix of participants in relation to their

    respective work sectors the Sectors being broken down into Private Practice,

    Consultant and Main Contractor the results show that 40% (8 people) were from the

    Private Practice Sector, 20% (4 people) were from the Consultancy. From this it can be

    seen that the proportion of people taking part in the Questionnaire is evenly distributed

    in regards to the respective sectors.

    Refer to Figure 14 below.

    Figure 14 Pie Chart showing response to question 1

    40%

    20%

    40%

    Question 1: Which sector of the Industry do you belong?

    Private Practice Consultant Main Contractor

  • 57

    4.2.2 Question 2

    Question 2 was set up in 2 parts and aimed at establishing the mix of participants in

    relation to their memberships of Professional Bodies, the participants were given a list

    of the main bodies and a section to complete any others not noted. The first part of the

    question highlighted that The Professional Bodies that participants belongs to were The

    Royal Institution of Chartered Surveyors (RICS), The Chartered Institute of Builders

    (CIOB) and the Association of Project Safety RMaPS), the results show that 60% (12

    people) were members of the RICS, 15% (3 people) were from the CIOB, 5% (1

    person) was from the RMaPS and the remaining 20% (4 people) do not belong to any

    Professional Bodies. The second part of this question asked the participants to confirm

    what level of membership that they currently had the results showed that from the

    60% (12 people) of RICS members 15% (3 people) were student members, 30% (6

    people) were Full members and 15% (3 people) were Fellow members of the RICS.

    From the 15% (3 people) who were members of the CIOB, 5% (1 person) was an

    incorporated member and 10% (2 people) were Full members. From this it can be seen

    that the participants taking part in the Questionnaire are all highly qualified in their

    chosen area.

    Refer to Figure 15 below

  • 58

    60

    %

    15

    %

    5%

    20

    %

    15

    %3

    0%

    15

    %

    5%

    10

    %

    5%

    T h e R o y a l I n s t i t u t i o n o f

    C h a r t e r e d S u r v e y o r s ( R IC S )

    T h e C h a r t e r e d I n s t i t u t e o f

    B u i l d e r s ( C I O B )

    T h e A s s o c i a t io n o f P r o j e c t S a f e t y -

    R M a P S

    N o n e

    Professional Bodies and membership levels.

    Que stion 2 : Are you a me mbe r of any Profe ssional bodie s? I f so which one s

    and at which le ve l?Membership of Professional Bodies StudentMRICS FRICSICIOB MCIOB

    Figure 15: Bar Chart showing responses to question 2

  • 59

    4.2.3 Question 3

    Question 3 was aimed at establishing the experience of the participants in relation to the

    number of years that they have worked as a QS. The results show that 5% (1 person)

    had under 5 years experience, 15% (3 people) had between 6 and 10 years experience,

    15% (3 people) had between 11 and 15 years experience, 20% (4 people) had between

    16 and 20 years experience, 5% (1 person) had between 26 and 30 years experience,

    10% (2 people) had between 30 and 35 years experience and 30% (6 people) had 36-40

    years experience. From this it can be seen that the parties taking part all have a vast

    amount of experience.

    Refer to figure 16 below.

    Figure 16 Bar chart showing responses to question 3.

  • 60

    4.2.4 Question 4

    Question 4 was aimed at establishing whether or not the participants were familiar with

    SMM7. The results of this question show that 100% (20 People) all confirmed that they

    are familiar with SMM7.

    Refer to figure 17 below.

    Figure 17 Bar chart showing responses to question 4.

  • 61

    4.2.5 Question 5

    This question was included to establish how often the participants use SMM7. The

    result of this question is that 5% (1 person) uses SMM7 on a daily basis, 20% (4 people)

    use SMM7 on a weekly basis, 15% (3 people) use SMM7 on a monthly basis, 55% (11

    people) use SMM7 occasionally and 5% (1 person) never uses it.

    Refer to figure 18 below.

    Figure 18 Bar chart showing responses to question 5.

  • 62

    4.2.6 Question 6

    This question was included to establish whether or not participants were familiar with

    NRM. The results of this question was that 55% (11 people) were familiar with NRM

    and 45% (9 people) were not familiar with NRM.

    Refer to figure 19 below

    Figure 19 Pie chart showing responses to question 6.

  • 63

    4.2.7 Question 7

    This question was asked to find out the participants opinion on the promotion of NRM.

    25% (5 people) said yes, 75% (15 people) said no.

    Refer to Figure 20 below.

    Figure 20 Pie Chart showing responses to Question 7

  • 64

    4.2.8 Question 8

    This question was asked to establish how often the parties use NRM1. 5% (1 person)

    responded weekly, 15% (3 people) responded occasionally, and 80% (16 people)

    responded never.

    4.2.9 Question 9

    This question was asked to establish how often the parties use NRM2. 5% (1 person)

    responded monthly, and 95% (19 people) responded never.

    The results to question 8 and 9 have been entered into the same bar chart to show the

    comparison between use of NRM1 and NRM2.

    Refer to Figure 21 below.

    Figure 21 Bar chart showing responses to question 8 and 9

  • 65

    4.2.10 Question 10

    This question was asked to ascertain what method of measurement that participants

    prefer. 5% (1 person) chose NRM, 70% (14 people) chose SMM7, 5% (1 person)

    chose The Civil Engineering Method of Measurement (CESMM), and 20% (4 People)

    chose Standard Method of Measurement 6 (SMM6).

    Refer to figure 22 below.

    Figure 22 Pie Chart showing results of question 10

  • 66

    4.2.11 Question 11

    This question was asked to establish the Professions viewpoint as to whether or not they

    though that NRM would re-invent the role of the QS. Interestingly this question was

    the only question for which there was not a 100% decisive response. 5% (1 person)

    responded no, 60% (12 people) responded no, 25% (5 people) didnt know and 10% (2

    people) said that they didnt know.

    Refer to figure 23 below.

    Figure 23 Bar chart showing responses to question 11.

  • 67

    4.2.12 Question 12

    This question was asked to obtain participants opinions on BIM and whether it would

    detract from the importance of NRM. 30% (6 people) said yes and 70% (14 people)

    said no.

    Refer to Figure 24 below.

    Figure 24 Pie Chart showing responses to question 12.

  • 68

    4.2.13 Question 13

    This question set up in 3 parts and was aimed at establishing the activities of the

    participants in relation to cost planning, measurement and whole life cycle costing and

    how often they carry them out.

    Part 1 Costing Planning 75% (15 people) answered yes and 25% (5 people)

    answered no. In relation to how often cost planning is carried out 15% (3 People)

    responded daily, 35% (7 people) responded weekly, 20% (4 people) responded monthly.

    Part 2 Measurement 100% (20 people) answered yes. In relation to how often cost

    planning is carried out 40% (8 people) responded daily, 30% (6 people) answered

    weekly, 15% (3 people) answered monthly, and 10% (2 people) answered rarely.

    Part 3 Whole Life Cycle Costing - 40% (8 people) answered yes, 60% (12 people)

    answered yes. In relation to how often whole life cycle costing is carried out 5% (1

    person) answered daily, 5% (1 person) answered weekly.

    Refer to figure 25 below.

    75%

    25%

    15%

    35%

    20%

    0% 0%

    25%

    100%

    0

    40%

    30%

    15%10% 10%

    0

    40%

    60%

    5% 5% 5%

    15%10%

    60%

    0%

    20%

    40%

    60%

    80%

    100%

    120%

    Yes No Daily Weekly Monthly Occasional Rarely Never

    Question 13: Does your brief include for carrying out the following activities?

    Cost Planning Measurement Whole Life Cycle Costing

    Figure 25 Bar chart showing responses to question 13.

  • 69

    4.2.14 Question 14

    This question was asked to establish participants viewpoint on whether they thought

    that there was still a requirement for a traditional bill of quantities in construction

    projects. 5% (1 person) answered no and 95% (19 people) answered no.

    Refer to diagram 26 below.

    Figure 26 Pie chart showing responses to question 14.

  • 70

    4.2.15 Question 15

    This question was asked to establish participants viewpoint on whether they thought

    that the role of the QS had changed in recent years. 20% (1 people) answered no and

    80% (16 people) answered yes.

    Refer to diagram 27 below.

    Figure 27 Pie chart showing responses to question 15.

  • 71

    4.2.16 Question 16

    The first part of this question was asked to ascertain the use of computer technology.

    Participants were asked whether or not the used any computer software in their daily

    activities. 25% (5 People) answered no and 75% (15 people) answered yes.

    Refer to Figure 28 below.

    Figure 28 Pie Chart showing responses to question 16a

    The second part of this question was asked to relating to which software programmes

    are currently being used. A total of 15 programmes were identified. Several

    participants use several programmes. 5% (1 person) uses Conquest, 15% (3 people) use

    Word, 10% (2 people) use Masterbill, 5% (1 person) uses QS Elite, 5% (1 person) uses

    Candy, 75% (15 people) use excel, 5% (1 person) uses Sage, 15% (3 people) use

    Vector, 5% (1 person) use Auto Cad, 5% (1 person) use Ripac, 10% (2 people) use True

    View, 5% (1 person) uses Blue beam, 5% (1 person) uses Cato and 10% (2 people) use

    QS Script.

  • 72

    Refer to Figure 29 below.

    5%

    15%10%

    5% 5%

    75%

    5%

    15%

    5% 5%10%

    5%10%

    5%10%

    0%

    20%

    40%

    60%

    80%

    Question 16b: Computer software which programmes people use.

    Programmes

    Figure 29 bar chart showing responses to question 16b

    The third part of this question was aimed at identifying which of the programmes

    noted in 16b include software specifically for the use of NRM. The result of this

    questions can be summarised thus out of 15 programmes 79% (12 Programmes)

    did not include NRM, 21% (3 programmes) included NRM. Out of these 3

    programmes and equating back to the 21% figure Conquest, Masterbill and Vector

    all account for 7% each.

    Refer to Figure 30.

  • 73

    Figure 30 Pie chart showing responses to question 16c

  • 74

    4.3 Interview Results

    4.3.1 Question 1 How long have you been a Quantity Surveyor and what

    factors influence your decision to follow a career as a Quantity Surveyor?

    Interviewee 1

    Responded that they had been a QS for 20 years and that they had decided to become a

    QS more by accident than anything else. They had been employed within a Company in

    the late 80s, working as a Civil Engineering Technician, and as result of the Recession,

    their work had dried up so they started to help the QSs out by to start with filling out

    day works sheets and as they were familiar with construction and drawings carrying out

    a few measures. From this they obtained a job with a Contractor and started a distance

    learning course in order to obtain their BSc.

    Interviewee 2

    Responded that they had been a QS for 20 years and that they had become a QS as their

    father was a Partner in a large QS Practice and they always thought that his work

    sounded very interesting so they followed in his footsteps and after leaving school

    enrolled in a University and obtained their degree.

  • 75

    4.3.2 Question 2 What Sector of the Industry do you currently work in and

    have you always worked in this Sector?

    Interviewee 1

    Responded that they working for a Main Contractor and that they had always worked in

    this Sector. They also added that it was the nature of the Beast as to what sector a QS

    worked in. If you enjoyed working on the coalface and getting your feet dirty then

    Contracting was for you. However if you prepared to sit in an office suited and

    booted then Private Practice was for you. They added that they found Contracting, a

    very challenging and rewarding role and that they have found that the role of the CQS

    has been vastly developed over the last 10 or so years. A CQS needs to extremely

    commercially minded, a good negotiator.

    Interviewee 2

    Responded that they worked in Private Practice for a total of 19 years out of the 20 that

    they had been working. They had a short spell of 1 year working for a Ground works

    subcontractor. They had 5 years experience working for a Private Practice when a

    Groundworks Contractor approached them and asked them to work with their

    Company. They gave it due consideration and decided to give it a bash, however, they

    soon realised that they were a bit out their depth and opted to go back to Private

    Practice.

  • 76

    4.3.3 Question 3 What Method of Measurement do you currently prefer and

    why do you prefer this method?

    Interviewee 1

    Responded that they preferred SMM7, however, the Method of Measurement used

    depended on the type of Contract that they were working on and the way that it was

    billed. The majority of their works were carried out using SMM7, however if they

    were working on a Contract that was Civil Engineering orientated then they use

    CESMM. They further added that their organisation had recently priced and secured a

    contract that was measured and priced using NRM 2.

    Interviewee 2

    Responded that they preferred SMM7 but this was solely because it was the document

    that they were most familiar with. They used CESMM on a very rare occasion. The

    Trainees in their office were starting to ask if they could use NRM as the Universities

    were implementing this in their measurement studies. They added that the Partners all

    felt that it was possibly time for change but stated that as humans we are all slightly

    scared on change but sometimes change is for the better.

  • 77

    4.3.4 Question 4 Have you had any experience of NRM? If so which

    Volume? Can you give a brief overview?

    Interviewee 1

    Responded by confirming that interestingly enough they have recently prepared a tender

    and had the Contract awarded for a project based entirely on NRM. When the

    document arrived in the office it was treated with a great deal of scepticism, however on

    further scrutiny it was noticed that the layout of the document made it much easier to

    submit separate trade sections to both Suppliers and Subcontractors. We found that all

    parties that we asked to price returned their tenders. Also when it got to the pre-tender

    award meeting with the Client and the Design Team is was easier to find respective

    sections that the Client was asking for clarity on as all the elements were grouped

    together so we were not jumping from one section of the bill to another. When it came

    to procurement it was relatively easy to again split up all the items into the various

    packages. The package that we found the best improvement in was the Mechanical and

    Electrical Installations we usually hav