128 April 2008 Spectrometer Solenoid Fabrication Update MICO Meeting 19 May 2008 S. Virostek, M....
-
date post
19-Dec-2015 -
Category
Documents
-
view
216 -
download
0
Transcript of 128 April 2008 Spectrometer Solenoid Fabrication Update MICO Meeting 19 May 2008 S. Virostek, M....
128 April 2008
Spectrometer SolenoidFabrication Update
MICO Meeting19 May 2008
S. Virostek, M. ZismanLBNL
228 April 2008
Magnet #1 Completion Schedule
• End plate errors corrected and end-plate welding completed
• Magnet “tower” components installed and insulated with MLI
• Tower will be vacuum sealed today and made ready for pumpdown
• Pumping will take a few days, followed by detailed leak check
• Barring vacuum problems, magnet cool down will commence Starting May 24 using LN2 and LHe
• Week of June 2: magnet filling w/LHe, energizing and magnetic testing
• Lost about 1 week due to end-plate glitch
• Instrumentation and power cables being prepared by next week; Wang will provide connectors for instrumentation used at Fermilab and RAL
328 April 2008
Cryocooler Testing, FNAL Testing Prep
• Still under way
• Currently working on shipping arrangements to FNAL
• Still have to decide if the magnet will be shipped cold
- If shipped warm, need to decide if under vacuum or not
- Shipping cold is the current preference