Spectrometer Solenoid Fabrication & Testing Update S. Virostek and Mike Zisman Lawrence Berkeley...

36
Spectrometer Solenoid Fabrication & Testing Update S. Virostek and Mike Zisman Lawrence Berkeley National Lab NFMCC 2010 Collaboration Meeting University of Mississippi, Oxford

Transcript of Spectrometer Solenoid Fabrication & Testing Update S. Virostek and Mike Zisman Lawrence Berkeley...

Spectrometer Solenoid Fabrication & Testing

Update

S. Virostek and Mike ZismanLawrence Berkeley National Lab

NFMCC 2010 Collaboration Meeting University of Mississippi, Oxford

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page2

MICE Cooling Channel Layout

Spectrometer Solenoid #1 (reassembly under way)

Spectrometer Solenoid #2 (modified & ready to cool down)

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page3

Topics

•Recent magnet cool down and training

•HTS lead burn out•Technical review•Current status of Magnet 2•Thermal modeling and measurements

•Magnet 1 progress•Upcoming task schedule

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page4

Magnet Status Summary

•Magnet 1 was completed in 2008, and training had begun

•Ice blockages in LHe recondensing system piping prevented proper operation

•Magnet 2 assembly proceeded with design improvements (improved recondensing system, added cold mass venting, better shield connection, precise mechanical alignment)

•Magnet 2 became the first unit & Magnet 1 was disassembled

•Training of completed Magnet 2 was carried out during 2009

•An HTS lead burned out at 90% of design current due to inadequate cooling

•With repairs complete, cool down of Magnet 2 to start soon

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page5

Magnet Cooldown

Transfer line for LHe cooldown(FNAL contribution)

500 literLHe dewar

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page6

LHe Cooldown of Magnet 2

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page7

Magnet Quench during Training

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page8

•A leak was found in one of the cold mass vent lines during initial cooldown and was repaired in June ’09

•The subsequent cooldown was successfully completed in only ~3 days w/o incident

•However, the shield temperature fell slowly to only about ~115 K at the ends of the cylinder, resulting in added heat flow into the cold mass via the cold mass supports

•After filling, the coolers are expected to hold the LHe level, but ~1% of the LHe was boiling off overnight (unpowered)

•Training began and was going well with five training quenches at currents ranging from 182 to 238 A

Magnet 2 Testing Results

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page9

•At 238 A (w/all coils in series), one of the HTS leads burned out due to a higher than allowable temp. at its upper end

•The upper lead temperature without current was ~80 K, increasing to >90 K with current, eventually resulting in failure of the lead farthest from the coolers

•The lead problem was a surprise, as it was not noticed in the earlier Magnet 1 tests; the feedthroughs and all the leads are the same ones used before in Magnet 1

•The Magnet 2 turret was disassembled to access leads

•We are currently thermally testing the feedthroughs and leads in an off line test to see what can be learned

Magnet 2 Testing Results (cont’d)

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page10

Upper and HTS Leads Configuration

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page11

Magnet 2 Burned Out HTS Lead

Burned out500 A lead

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page12

MICE Internal Technical Review

•Spectrometer Solenoid technical review was held on November 18-19, 2009 at LBNL

•Review committee: Pasquale Fabbricatore (chair), Amalia Ballarino, Elwyn Baynham, Tom Bradshaw, Mike Courthold, and Chris White; Alain Blondel and Andy Nichols (ex officio)

•The committee came up with several recommendations including the following:- Approved the adding of a single stage cooler to Magnet 2- Recommended additional thermal modeling of the system- Advised installing additional magnet instrumentation- Suggested Magnet 2 test results be used to determine the final modifications to Magnet 1

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page13

Magnet 2 Repair and Modification

•A modification to Magnet 2 was proposed that adds a single-stage cryocooler to provide additional cooling to the HTS leads and does not require full magnet disassembly

•The plan to add a single-stage Cryomech AL330 cooler (arrived 11/13/09) provides 170 W at 55 K and requires modifications only in the “turret” area

•The added cooling power should lower the HTS lead temperature sufficiently to train to full current

•The new cooler could remove enough heat to permit the other 3 two-stage coolers to maintain the cold mass LHe level (i.e. closed system)

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page14

1st Stage Area after Lead Removal

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page15

Original Magnet 2 Configuration

HTS leads

Cold head 1st stage

Radiation shield

Fill & vent lines

Cold mass

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page16

Magnet 2 with Added Cryocooler

Single-stage cooler

Thermal link

HTS leads

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page17

Modification Details

Added turret space

Access port

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page18

Current Status of Magnet 2

•The Magnet 2 turret area has been disassembled and modified to allow installation of the single stage cooler

•New HTS leads are being installed that have been tested in an off-line apparatus

•Additional temperature sensors on the cold heads and voltage taps on the lower HTS leads have been added

•Initial pumpdown and leak check of the magnet insulating vacuum is expected during the week of January 18

•Cooldown for testing and training will follow

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page19

Magnet 2 Single Stage Cooler

Single stage cooler and flexible copper thermal link during fit check in Magnet 2

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page20

Future HTS Lead Protection

The HTS leads can be actively protected from burnout due to quench as follows:

i) Interlock the power supply with the temperature of the top of the HTS leads/heat sink to disable power supply when the temperature is too high

ii)Active quench protection based on the voltage across the HTS leads in case of resistive transition (~3 mV limit); voltage taps have been added to the lower end of the leads

Both of these systems could be implemented in the RAL control system after magnet delivery

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page21

• Our modeling indicates the new cooler won’t substantially affect the shield temperature

• It is uncertain whether the addition of the single-stage cooler will solve the LHe boil off issue

• Cannot address known deficiencies in Magnet 2 (shield connection, copper plate thickness, leads arrangement) without fully disassembling magnet

• Additional cooler(s) will increase utility costs for running the magnets (water and power)

Other Issues

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page22

•If the addition of a single-stage cooler to Magnet 2 does not result in a closed system, there are two options:

i) Accept the thermal properties as is and top up the magnet with external cryogens as needed

ii) Disassemble and modify the magnet to improve the shield connections and to accommodate a fourth two-stage cooler (in addition to the single-stage cooler)

•The 2nd option would add ~6 months to the delivery of the 2nd magnet to RAL and create additional risks of damage or assembly errors in the repair process

•For these reasons, the first option is preferred

Magnet 2 Fallback Scenario

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page23

•A thermal model of the magnet was developed and is being used to understand the cooling mechanisms and heat loads

•Initial calculations indicate the upper HTS leads temp. will be <70K during operation w/the added cooler

•The temperature drop across the thermal link between the single stage cooler and the 1st stage copper plate is expected to be ~10 K

•An off-line magnet lead test is being carried out by Wang NMR to measure all relevant temperatures and voltages during operation

•Additional sensors will directly measure cold head temps.

Thermal Calculations and Measurements

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page24

Thermal Shield Model•FEA model of thermal shield, 1st stage plate and HTS leads

•Proposed magnet modifications are also being modeled

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page25

Magnet Lead Test

HTS lead

1st stageplate

Thermalconnection

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page26

Initial Test Results (1)

• Tests began on January 14, 2010– at initial equilibrium (no current), leads gave

~10 W heat load into cooler stage 1• temperature at top of leads was below freezing• cooler temperatures: 33.8 K (stage 1); 3.5 K (stage

2)

– next, powered leads to 275 A• voltage drops on leads were 99 and 95 mV,

respectively– means about 27 W per lead…unexpectedly high

leads too long for their cross-sectional area

• temperature at top of leads was 350 K (hot!)• cooler temperatures: 42.4 K (stage 1); 3.5 K (stage

2)

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page27

Initial Test Results (2)• Added 20 W to shield (stage 1 load) with 275 A in leads

– results:• cooler temperatures: 56 K (stage 1); 3.9 K (stage 2)• lead voltage drops increased to 104 and 101 mV,

respectively– because leads now running hotter than before

• T between stage 1 and copper plate (across plug-in joint): 1.1 K at 33.8 K, 2.4 K at 42.4 K, and 1.4 K at 56 K– grease probably more conductive at higher

temperature• means that “plug-in” aspect working as expected

• Next, will increase cross section and decrease L of leads– then retest next week

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page28

Magnet 1 Plans

– implement ideas to improve thermal connection between coolers and shield and lower cold mass support intercept temperature•use copper sheets rather than Al cylinder•use Al-1100 strips on outside of shield to improve heat conductivity

– make preparations for using additional 2-stage cooler•augmenting the single-stage cooler to solve both thermal problems

•decision to add 5th cooler depends on outcome of Magnet 2 tests

– modify cold mass fill pipe to facilitate clearing a blockage should one occur

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page29

Magnet 1 Cold Mass

Added port for possible 4th 2-stage cooler

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page30

Magnet 1 Shield• Corresponding hole for 4th 2-stage cooler added to shield

• shield is also being “beefed up” locally to improve heat transfer to edges– this is where cold-mass

support intermediate temperature point is connected

•extra heat load from higher temperature at this point is burden for stage 2 of coolers

– probably more of an issue than bulk radiation load

Attachment point for LN2 reservoir

New connection for cooler added

Area where cold-mass support intercept attached

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page31

Heat Shield Thermal Connections• Previous attempt to improve thermal connection

between stage 1 of coolers and shield was a failure– aluminum bands were even worse than

original copper strips– next iteration will make connections

between stage 1 copper plates and shieldwith thick copper sheets

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page32

2-Stage Cooler Modification

Top view:

• A fourth 2-stage cooler could be added as shown below– still leaves room for the single-stage cooler

Side view:

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page33

Magnet 1 Issues• Need to determine whether we need fourth 2-stage cooler to maintain cryogen level– the single-stage cooler for Magnet 1 is on order

• Possible that improvements to the shield connection, along with the single-stage cooler, will suffice– if it works on magnet 2, the answer is clear– if it “almost” works, the answer is not so clear

• We can answer the questions “sequentially”, but each trial costs time and money

• Present approach requires one additional cooler per magnet, and maybe two

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page34

* These step are only required if the initial modifications to Magnet 2 are unsuccessful

Schedule Overview

Complete design of magnet modifications

Procure single stage cryocooler

Test recently delivered 2 stage coolers

Set up and perform magnet lead test

MICE review of Spectrometer Solenoid

Complete Magnet 2 fixes (w/added cooler)

Complete power supply modifications

Cooldown and train Magnet 2

Ship Magnet 2 to FNAL (if successful)

Magnetic measurement of Magnet 2

Ship Magnet 2 to RAL

Complete assembly of Magnet 1 w/all fixes

Cooldown and train Magnet 1

Ship Magnet 1 to FNAL

Magnetic measurement of Magnet 1

Ship Magnet 1 to RAL

Disassemble Magnet 2 for modification*

Re-assemble Magnet 2 w/all fixes*

Cooldown and train Magnet 2*

Ship Magnet 2 to FNAL*

Magnetic measurement of Magnet 2*

Ship Magnet 2 to RAL*

AUGAPR MAY OCT

Calendar Year 2009 Calendar Year 2010

JUN JULFEB MARDEC JAN SEPNOV Task/Component Description

SEP OCT

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page35

Coupling Coil Status

• Coupling coil design essentially finished– still working to get complete and consistent set of drawings

•LBNL (DeMello) will assist in this

• Coil fabrication job out for bid– expect responses in February, aim to sign contract in March

•for all three coils•HIT may not have enough funds for entire job

– may need additional U.S. contribution

•New management structure in place at HIT– Li Wang, Chief Engineer; FengYu Xu, Project Manager

•contract in place with IHEP consultants (technical experts)

• D. Li, S. Virostek, A. DeMello, M. Green are key players

Virostek/Zisman -- Lawrence Berkeley National Laboratory -- January 16, 2010

MICE Spectrometer Solenoid Fabrication and Testing Update Page36

• A fix to Magnet 2 has been implemented which did not require full magnet disassembly

• Addition of a single-stage cooler to the first stage copper plate is expected to solve the HTS leads temperature problem

• Temperature of the thermal shield may still be an issue (cooler will have minimal impact)

• Operation without the need for cryogen top off is not guaranteed

• Magnet 2 test results will be used to assess the degree of modification required for Magnet 1

Summary