Platts oilgram news julio 29 2014 articulo pag 7 Colombia oil Orlando Hernandez
11LucianoVillani_NICHI_BusinessSummit
-
Upload
nichiusa -
Category
Environment
-
view
96 -
download
0
description
Transcript of 11LucianoVillani_NICHI_BusinessSummit
Storm Hardening Initiatives at Con Edison
May 7th, 2014
Luciano VillaniDepartment Manager, Project Engineering,
Con Edison
2
Network Systems Non-Network Systems
Generating Station(electricity generated at 13.8 to 22.0 kV)
Transmission Substation
Area Substation(voltage stepped down to primary distribution voltage)
Transformers(voltage stepped down to 480, 208, or 120 V)
Feeders
Con Edison Overview
Super Storm Sandy Statistics
• Largest Atlantic storm on record spanning 1,000 miles
• Impacted over 8.5 million customers across 21 states
• Sustained winds reached 64 mph at LaGuardia Airport with peak gust of 90 mph on Staten Island
• 14.06 foot storm tide recorded at Battery Park
Super Storm Sandy Impact to Con Edison
• 1.1 million customer outages
• Lost 4,000 MW of generation
• 60% of 345 kV feeders lost
• 5 transmission substations– 11 Manhattan networks
– 3 Staten Island area stations
• 2 steam stations and 561 steam customers impacted
• 398 gas services interrupted
4
Con Edison Response
• Service Restoration – restore service as quickly as possible
• System Normalization – repair equipment damage
• Site Assessments
– Multidiscipline engineering teams visited all impacted stations
– Identification of critical impacted equipment and water infiltration
– Conceptual storm hardening scopes and estimates
• Immediate Storm Hardening (June 1, 2013)
• Long-Term Storm Resiliency
5
6
Sandy Aftermath TimelineOct 2012 Jan 2013 Apr 2013 July 2013 Oct 2013 Jan 2014
Sandy Hits
Normalization
Immediate/Phase 1 Storm Hardening
Phase 2 (thru 2017)
June 1, 2013 – Construction Complete
71
East River Substation
E13th Street Substation
East 14th Street
FDR
Aven
ue C
East River Generating
Station
Substations & Generating Stations
Typical SubstationPre-hardening
Power Transformer
Breaker
Dis
conn
ect
Poth
ead
Stan
d
BreakerControl Room Pumping
Plant
Power line Control/protection line(s) Oil line
Terminal boxInsulator To Distribution
From Transmission
Rel
ay
Hou
se
Dis
conn
ect
Poth
ead
Stan
d
Sewer Drain
Immediate Hardening ScopeJune 1st, 2013
New walls/barriers around critical equipment
New sump pumps
Sealed conduit penetration points with RTV
Shrink wrap important control boxes
Install backup nitrogen pumps
Raised equipment where feasible and
economic
Valve-off sewer drains
Governing flood control elevation, higher of:
1. SLOSH 2010
2. 2007 FEMA 100-yr flood +2 feet
3. Witnessed Sandy level
Breaker
Dis
conn
ect
Poth
ead
Stan
d
Breaker
Rel
ay
Hou
se Control Room Pumping
Plant
Power line Control/protection line(s) Oil line
Terminal boxInsulator To Distribution
From Transmission
Power Transformer
Flood Control Elevation
Dis
conn
ect
Poth
ead
Stan
d
Sandy Flood Elevation
Sewer Drain
June 1, 2013 Accomplishments
• Work completed at 9 Substations and 3 Generating Stations
– 54 new concrete moats (6100 LF)
– 210 flood doors and barriers
– 81 submersible pumps
– 21 high capacity diesel pumps
– Approx. 3000 conduit and trough seals
10
11
Con Edison Rate Case & Collaborative
• Filed January 2013
• All 3 commodities (Electric, Steam & Gas)
• Storm Hardening Program
– $1 billion Company-wide
– Projects span 2014 – 2017
• Storm Hardening Collaborative
– Cooperation among all interested rate case parties
– Risk prioritization and project justification
12
Collaborative Activities
• Collaborative Parties
– PSC, NYC, Attorney General, Utility Intervention Unit, EDF, Columbia Center for Climate Change, Local 1-2
• Benchmarking
– United Illuminating
– PSE&G
– Brooklyn Navy Yard
– NYC MTA
– Swedish Delegation
• With Collaborative
– 8 meetings and 2 field visits
– 3 detailed presentations
– 32 technical and economic questions/information requests
– 11 order of magnitude estimates
– Established flood control criteria (FEMA 100yr + 3’)
– Ongoing meetings
13
Next Steps – Phase 2 Storm Hardening
• More robust walls, doors and barriers
• Additional pumps with redundant feeds
• Backup generators
• Raise or relocate critical equipment
• New control room and automation system
2013 Flood
Protection Level0-8
Feet
New Flood
Protection Level 3-4Feet
Design Standard: FEMA 100 year flood level + 3 feet
(design level re-examined every five years)
14
Goethals – Proposed Perimeter WallBefore & After
• Interlocking metal sheet pile wall.
• 25 feet below grade
• 10 feet above grade
15
New Control Room & Lifting Electrical Panels
Digital HMI and Automation System
16
Questions?