1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

18
1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

Transcript of 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

1

Warm Magnets Work Package Status

J. Bauche, TE-MSC Technical Meeting,

9th January 2014.

2

Outline

Magnet work packages

Warm magnets in LINAC and HEBT

Budget

Production status- Dipoles

- Quadrupoles

- H/V correctors

Magnetic measurements

Conclusions

3

Magnet Work Packages

TE/MSC/MNC

Design of magnets

Procurement in industry

Tests and electro-mechanical measurements

Installation and commissioning

TE/MSC/MM

Magnetic characterization of pre-series magnets and check of series magnets

Fiducialization of quadrupole magnets

Hall probes for on-line B field measurement on dipoles

4

4 + 3* dipoles(TESLA, UK)

24 + 8* quads(ELYTT, ES)

13 + 10*H/V steerers

(ANTEC, ES)

* Options additional to baseline order

Warm Magnets in LINAC and HEBT

HEBT magnet installation schedule: starts in September 2014

5

Budget

Overall envelope ~ 2 MCHF

(incl. 200 kCHF for magnetic measurements, and 300 kCHF for supporting system)

6

Dipoles

Curved C-shape magnet with PFR = ½ bending angle Glued laminated yoke with welded reinforcement plates Water-cooled racetrack coils (glass fiber - epoxy insulation)

7

Supply Contractual delivery dates

Manufacturing file, schedules and samples 13th December 2013

Pre-series dipole 30th May 2014

One series dipole 1st August 2014

Two series dipoles + coils 10th October 2014

Two optional series dipoles 5th December 2014

One optional series dipole 5th January 2015

1st b

eam

line

Contract placed at Tesla (lamination stamping at Righton & Sons, UK) Manufacturing file received (final iteration before approval) Raw materials ordered, tooling manufacture in progress

Dipole Production Status

- On schedule so far; magnet and tooling design convincing

- Stamping at sub-contractor to be carefully followed-up

8

Quadrupoles

Glued laminated yoke reinforced with solid end-plates and tie rods

Bolted assembly of quadrants Water-cooled racetrack coils (glass fiber -

epoxy insulation)

9

Supply Contractual delivery dates

Manufacturing file, schedules and samples 14th October 2013

Two pre-series quadrupoles 14th April 2014

Four series quadrupoles (batch #1) 30th May 2014

Four series quadrupoles (batch #2) 27th June 2014

Four series quadrupoles (batch #3) 25th July 2014

Four series quadrupoles (batch #4) 15th September 2014

Four series quadrupoles (batch #5) 13th October 2014

Two series quadrupoles + coils (batch #6) 27th October 2014

Four series quadrupoles (optional batch #1) 24th November 2014

Four series quadrupoles (optional batch #2) 22nd December 2014

1st b

eam

line

Quadrupole Production Status Contract placed at Elytt (lamination stamping at Omedec, FR) Manufacturing file received (final iteration before approval) Raw materials ordered, tooling manufacture in progress

- On schedule so far; transparent attitude form manufacturer- Not experienced with laminated yokes, but reactive to proposals

10

H/V correctors

Compact window frame solid iron yoke

Bolted assembly Water-cooled racetrack coils (glass

fiber - polyimide - epoxy insulation)

90 mm

11

Supply Contractual delivery dates

Manufacturing file, schedules and samples 7th February 2014

One pre-series H/V steerer 20th June 2014

Four series H/V steerers (batch #1) 8th August 2014

Four series H/V steerers (batch #2) 29th August 2014

Four series H/V steerers (batch #3) 19th September 2014

Four series H/V steerers (optional batch #1) 10th October 2014

Four series H/V steerers (optional batch #2) 31st October 2014

Two series H/V steerers (optional batch #3) 14th November 2014

1st b

eam

line

H/V corrector Production Status

Contract placed Kick-off meeting held Insulated copper ordered (CERN supply via Luvata (FI) and Sofilec (FR))

- Quality issues experienced on products delivered in the past

- New chance given with this contract, to be carefully followed-up

12

Magnetic Measurements (1/2)

Bent flux-meter development

Magnetic measurement specification discussed with beam optics physicists need longitudinal distribution of the field

Dipole:

– Pre-series: full characterization requires Hall probe 3D mapper (LEP tool to be refurbished)

– Series: integrated field mapping with bent flux-meter

13

Magnetic Measurements (2/2)

Quadrupole:

– Pre-series: need measurement of field gradient in center + longitudinal profile (3D mapping, but few points and small size)

– Series: integrated field harmonics with rotating coil (existing equipment) + fiducialization with stretched wire

H/V correctors:

– Pre-series: measurement of field longitudinal profile (3D mapping, small size) + stray field at several locations (magnetic interference)

– Series: integrated field harmonics with rotating coil (existing equipment), possibly with sampling (one magnet per batch)

Important workload from this project, can be quite challenging in terms of resources

14

Magnet production– All contracts placed; budget within estimates

– Dipoles and quadrupoles: manufacturing design completed; raw materials ordered; tooling manufacture in progress

– H/V correctors: manufacturing design in progress

Technical (and schedule) risks– Dipoles: lamination stamping sub-contractor not experienced with accelerator magnets

– Quadrupoles: manufacturer unexperienced with laminated yokes

– Steerers: quality issues from manufacturer in the past

Magnetic measurements– Scope defined; standard measurements for quadrupoles and steerers

– Refurbishment / development of tooling required for dipoles

– Important workload of this project will add to the present situation

Conclusions

15

Spare slides

16

Dipoles

Parameters

17

Quadrupoles

Parameters

18

H/V correctors

Parameters