1 Software Project Management Final Stages

description

3 Migration Plan Includes –Description of environment (computers, DBs, interfaces) –Description of existing data needed –Description of operational constraints (ex: when can we move to the new system? Weekends only? Last week of month only?) –List of affected organizations and contacts –Plan of steps to be taken

Transcript of 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your...

Page 1: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

1

Software Project Management

Final Stages

Page 2: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

2

Migration

• Moving users from existing system to your new one

Page 3: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

3

Migration Plan

• Includes– Description of environment (computers, DBs,

interfaces)– Description of existing data needed– Description of operational constraints (ex:

when can we move to the new system? Weekends only? Last week of month only?)

– List of affected organizations and contacts– Plan of steps to be taken

Page 4: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

4

Migration Plan

• Does it require a service interruption?• If so, when does this happen? A weekend?

• Training?• Is there a helpdesk?

• If do, do they have “scripts” or new material?

Page 5: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

5

Migration Strategies

• Communication with customers is crucial• What is happening, when, and why • “Why” should remind them of the benefits• Not too much detail or too little• Where do customers go for more information?

• Minimize intrusiveness• Find-out about customer’s key dates

• When does the system absolutely need to be stable?• Know about their important deadline dates• They must buy-into the approach!

Page 6: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

6

Migration Strategies

• 1. Flash-Cut– Straight-move from old system to new– A) Immediate Replacement

– Fastest approach– Still want a back-out plan– Requires strong planning and testing

– B) Parallel Operation– Mitigates risk– Parallel to either existing manual or system process– Cut occurs once new system “burned-in”

• 2. Staged• Replace one part of existing system at a time

Page 7: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

7

Migration Strategies

• Considerations:– Level of business disruption– Degree of latitude in “production” date– How much internal opposition to system is

there?• If higher, perhaps a longer ‘adjustment’ period

– Your comfort level of system quality• If questionable, may want to mitigate risk

Page 8: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

8

Cutover

• Criteria: What conditions must be met prior?

• Responsibility: Who decides?• Operations: Who ‘owns’ it once it’s live?• Rehearsals: Sometimes used.

Page 9: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

9

Flash-Cut

• Immediate Replacement– Ex: new corporate-wide calendaring system

• Requires very careful planning & testing• Still try to get some users to “try” it first if

possible• Develop a back-out plan

Page 10: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

10

Back-Out Plan

• Especially important for “conversions”• Customers already have expectations and needs as defined by

their existing system• Must be able to restore customer’s service ASAP

• May mean running both simultaneously “just in case”

• Leave it in place for awhile (more than a day!)• When to fall-back?

• Mgmt: sooner, Tech: one-more-fix• Set a time limit (ex: 3 hours of start)

Page 11: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

11

Data Conversion

• Quote:– If you add a cup of champagne to a barrel of sewage,

you’ll have a barrel of sewage– If you add a cup of sewage to a barrel of champagne,

you’ll have a barrel of sewage• Most systems need this step• Most PMs forget this• Impacts both completely new and replacement

systems• The “data” often more valuable than the “system”

Page 12: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

12

Data Conversion Areas

• Data Sources: • Where does it come from? • Do you need to modify data on the way in?• Is it accurate?

• Process Controls:• Does it happen all at once?• How do you guarantee it’s been done correctly?

• Completion:• How do you handle any ‘exceptions’?• Do you make backups? Can you restart?

Page 13: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

13

Parallel Operation

• Multiple variations of this method• An “adoption” period

– See telephone industry w/new area codes– Both work for a period of time

• Strategies– Avoid flash-cuts if possible

• Start with test subjects

Page 14: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

14

Rollout

• Create a “Release Checklist”– Avoid activities falling through the cracks– Example– Activities by Group:

• Engineering, QA, Documentation, Operations– Possibly sign-off signatures

• Roll-out: Must have a plan for the process– Often on a given day (ex: a Sat.)– Must be a very detailed plan

Page 15: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

15

Training

• Often more than just end-users– Users– Sales & Marketing staff– System operators– Maintenance engineers (possibly)– Sales engineers (possibly)

Page 16: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

16

Documentation

• Must be ready by ship-date• Final user documentation• Updates to other

– Operations documentation– Development documentation– Sales and marketing material– Wed site– Test reports

Page 17: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

17

Shipping Details

• Packaging (if commercial product)• Marketing collateral• Security mechanisms (if commercial

product)• Licensing

• Plan• Mechanism

Page 18: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

18

Installation

• Scripts• Uninstall (if not Web-based)• If you need to install your software (as on

PCs):– Don’t underestimate:

• Time this takes to develop• Importance of a “first impression”

• Or, if “custom” software you’re reselling– Installation at site is often a “mini-project”

Page 19: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

19

Project Recovery

• How to save a “drowning project”• 3 Approaches

– 1. Cut the size of the software– 2. Increase process productivity– 3. Slip the schedule, proceed with damage control

• Opportunity for decisive leadership action• Not a time to ‘just cut corners’

– Be realistic (not foolish)• Timing: politically important

– Not too early, not “too” late

Page 20: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

20

Project Recovery

• Steps• Assess situation

– Is there a hard deadline, what’s negotiable, etc.• Don’t do what’s been done already• Ask team what needs to be done

– People Steps• Restore morale

– Cleanup personnel problems• Focus people’s time

– Remove non-essential work

Page 21: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

21

Project Recovery

• Process Steps– Fix classic mistakes

• Inadequate design, shortchanged activities, etc?– Create “Miniature Milestones”

• Small (in day(s)), binary, exhaustive• Boosts morale: getting things done!

– Track progress meticulously– Recalibrate after a short time– Manage risk painstakingly

Page 22: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

22

Project Recovery

• Product Steps– Stabilize the requirements– Raise the bar on change requests– Trim the feature set

• Determine priorities, cut the low ones– “Take out the garbage”

• Find error-prone modules; re-design– Get to a known, stable state & build from there

Page 23: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

23

Post Project Reviews (PPR)

• a.k.a. – Lessons Learned Review– Postmortem– Post Project Analysis (PPA)– Post Performance Analysis

• Focused on: Process not People!– Potentially a finger-pointing, blame-game

exercise

Page 24: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

24

PPR Steps

• Email team to schedule meeting• Use a Survey Form to gather initial feedback• Ask them to collect all potentially relevant data

– Dimensional project data work products: size, qty, etc– Change requests– Time and effort data

• Conduct meeting• Collect data and feedback, discuss

• Summarize in a PPR report

Page 25: 1 Software Project Management Final Stages. 2 Migration Moving users from existing system to your new one.

25