1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH-...

56
1 REGIONAL GRIDS QUICK FACTS

Transcript of 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH-...

Page 1: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

1

REGIONAL GRIDS

QUICK FACTS

Page 2: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

2

SOUTHERN REGION

WESTERNREGION

EASTERN REGION

NORTHERN REGION

NORTH-EASTERN REGION

INSTALLED CAPACITY

NORTHERN :- 34,207 MW

EASTERN :- 16,478 MW

SOUTHERN :- 36,921 MW

WESTERN :- 37,100 MW

NORTH-EASTERN :- 2,404 MW

TOTAL 127,110 MW

REGIONAL GRIDS

Page 3: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

3

EASTERN REGION

SOUTHERN REGION

WESTERNREGION

NORTHERN REGION

NORTH-EASTERN REGION

THE NATIONAL GRID : PHASE 1

ER

500 MW VINDHYACHAL

WR-NR HVDC B2B LINK

Commissioned in Nov. 1989

BIRPARA(ER) – SALAKATI(NER) 220 KV AC LINK in April 87

(400 KV Malda-Boangigaon in April 2000)

500 MW SASARAM

WR-NR HVDC B2B LINK

Commissioned in June 2001

500 MW GAZUWAKA

ER-SR HVDC B2B LINK

Commissioned in Sep. 1999

(2nd pole in March, 2005)500 MW BHADRAWATI

WR-SR HVDC B2B LINK

Commissioned in Sept. 1997

(2nd pole in March, 1998)

NATIONAL GRID PHASE-1 COMPLETE

Page 4: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

4

EASTERN REGION

SOUTHERN REGION

WESTERNREGION

NORTHERN REGION

NORTH-EASTERN REGION

THE NATIONAL GRID : PHASE II

ER

500 MW VINDHYACHAL

WR-NR HVDC B2B LINK

Commissioned in Nov. 1989

BIRPARA(ER) – SALAKATI(NER) 220 KV AC LINK in April 87

(400 KV Malda-Boangigaon in April2000)

RAIPUR(WR) – ROURKELA(ER) 400 KV AC D/C Commissioned Mar. 2003

GORAKHPUR(NR) - MUZZAFARPUR(ER) 400 KV AC D/C Commissioned in Aug. 2006

500 MW SASARAM

WR-NR HVDC B2B LINK

Commissioned in June 2001

500 MW GAZUWAKA

ER-SR HVDC B2B LINK

Commissioned in Sep. 1999

(2nd pole in March, 2005)500 MW BHADRAWATI

WR-SR HVDC B2B LINK

Commissioned in Sept. 1997

(2nd pole in March, 1998)

2000 MW TALCHER(ER)-KOLAR(SR)

HVDC LINK comissioned in SEP 2002

Page 5: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

5

Inter Regional Links – Current Capacity

2700 MW2700 MW

1200MW1200MW

2000MW2000MW

1200 MW1200 MW

900 MW900 MW33,782 MW

16,680

34,867 MW

36,031 MW

2433

1850 MW1850 MW

1650 MW1650 MW

Present IR Present IR Capacity = Capacity = 11,500 MW11,500 MW

Page 6: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

6

By 2007

Inter-regional capacity - 18,400MW

Name of the link Capacity(MW)

East-North

Patna – Balia 400kV D/c (Quad)

2000

Biharshariff – Balia 400kV D/c (Quad)

2000

Sub-total 4000

East-West

Ranchi- Sipat 400kV D/c with series compensation

1200

Sub-total 1200

East-South

Upgradation of Talcher-Kolar HVDC bipole

500

Sub-total 500

West-North

Gwalior – Agra 765kV S/c (initially ch. at 400kV)

1200

Sub-total 1200

Inter-regional capacity – By

2006

11500

GRAND TOTAL 18400

Page 7: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

7

Salakati

Bongaigaon

Birpara

Malda

Dehri

Sasaram

Sahupuri

Allahabad North-eastern

Eastern

Northern

Belgaum

Kolhapur

Budhipadar

Rourkela

Korba

Raipur

Auraiya

Malanpur

Western

Southern

Balimela

Upper Sileru

Chandrapur

Ramagundam

Jeypore

Gazuwaka

Singrauli

Vindhyachal

Talcher

Kolar

Kota

Ujjain

Inter-regional Links – By 2007

Gorakhpur Muzaffarpur

Balia Patna

BiharshariffBalia

SipatRanchi

Agra

Gwalior

Nagjhari

Ponda

2100 MW

6650 MW 1200 MW

3650MW1400 MW

2850 MW

Page 8: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

8

11850 MW

1200 MW6050 MW

5500 MW

1400 MW6150 MW

36,700 MW OF INTER-REGIONAL POWER BY 2012

EASTERN REGION

SOUTHERN REGION

WESTERNREGION

NORTHERN REGION

NORTH-EASTERN REGION

INTER-REGIONAL TRANSFER BY END OF 11th PLAN (2012)

4000 MW

Eastern

Region

Page 9: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

9

TRANSMISSION VOLTAGE

OWNERSHIP TOTAL

CENTRAL STATE

Circuit Kilometer

+ 500 kV HVDC

4,372 1,504 5,876

765 kV charged at 400 kV

917 409 1,326

400 kV 40,854 22,607 63,461

220 kV 9,220 98,521 107,741

132 kV* 2,152 93,126 95,278

Total 57,515 216,167 273,682

EHV Infrastructure

Page 10: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

10

68 0 72 0 76 0 88 0 92 0 96 080 0 84 0

S S

W W

NN

EE

NE

82.5 0

L

GEO POLITICAL

POWER REGIONS

B’DESH-

SRI

NEPALBHUTAN

INDIAINDIA

J&K

HPPUNJAB

HARIANA

RAJASTHANUP

MP

BIHAR

ORISSA

WBGUJARAT

MAHARASHTRA

KARNATAKA

TAMIL

NADU

AP

ASSAM

MNP

MIZTRP

NG

ME

LAKSHADWEEP

A&N

MYANMAR

SKM

PONDICHERY

DELHI

GOA

DIU

DAMAN

NER NER

LANKA

JKND

CTGR

UTTARANCHAL

Page 11: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

11

State Govt.

SERC

IPPs SGC CPPs

STU

SLDC

Distn Cos.

Consumers

INDIAN POWER SECTOR - HIERARCHICAL SET UP

CEA

CENTRAL ELECTRICITY AUTHORITY UNDER CENTRAL GOVT.POWER

MINISTRY – PLANNING AND ASSISITING GOVT

CERC

CENTRAL GENERATING STATION

JOINTLY OWNED UNITS CONSTRUCTED BY PUBLIC SECTOR UNDERTAKINGS

CENTRAL GOVT.

RPC

REGIONAL POWER COMMITTEE (FORMERLY REB) – ONE AT EACH REGION

SECRETARIAT TO THE ELECTRICITY BOARDS OF THE REGION

CTU

CENTRAL TRANSMISSION UTILITY

POWERGRID

RLDC

REGIONAL LOAD DESPATCH CENTRE – APEX BODY – RUN BY POWERGRID

CGS

REGIONAL LOAD DESPATCH CENTRE – APEX BODY – RUN BY POWERGRID

Page 12: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

12

Ministry of Power, Govt of India

MOP, State Govt.

Central Sector Companies

• Generating Utilities- NTPC, NHPC, NEEPCO, NPCIL

• Transmission Utility-POWERGRID

• Grid Operator -RLDC

• Finance- PFC

• Rural Electrification -REC

Authorities

CEA

R&D

CPRI, NPTI, PSTI

Mega IPPs

State Sector

• Generation

• Transmission

• DistributionState IPPs

CERC

SERC

Appellate

Tribunal

Trading Co.

Pvt. DISCOM

Institutional Framework

Page 13: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

13

ALL INDIA MARKET COMPOSITION

5%9%

3%

46%

37%

State Sector long termPPACentral Sector longterm PPAIPP generation

Short Term Trading

Balancing market

(1,27,110 in 2006) AS on 31-07-06

Page 14: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

14

3310, 3%6158, 5% 32135, 26%

82227, 66%

HydroThermalNuclearWind & Others

Source wise composition of installed capacity in India (1,27,110 in 2006) AS on 31-07-06

Page 15: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

15

Coal

Hydro

Energy Resource Map

Page 16: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

16

ALL INDIA GENERATION COMPOSITION

16.8, (3%)

486.1, (83%)

84.5, (14%)

ThermalHydroNuclear

Total Market Size = 587.4 BU

Total Installed Capacity 1,27,110 MW

Page 17: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

17

Sector wise consumption of electricity in India

22%

29%

5%

35%

6%

3%

IndustryDomesticRailwaysAgricultureCommercialOthers

Total Installed Capacity 1,27,110 MW

Page 18: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

18

SOUTHERN REGIONAL GRID

OVERVIEW

Page 19: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

19

SOUTHERN REGION – GEOGRAPHY

ANDHRA PRADESH

TAMIL NADU

KARNATAKA

KE

RA

LA

POPULATION :- 22.5 CRORES ( 22% OF INDIA)

AREA :- 651 (‘000 SQ KM)(19% OF INDIA)

INSTALLED CAPACITY:- 36,921 MW(29.0%)

WEATHER :- South-west monsoon

North-east monsoon

SEA COAST :- AROUND 4000 KM

Page 20: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

20

SR STATES – POWER SYSTEM STATISTICSANDHRA PRADESH

INSTALLED CAPACITY – 8944 MW

MAX DEMAND MET – 8241 MW

DAILY CONSUMPTION MAX – 171 MU

DAILY CONSUMPTION AVG – 142 MU

CONSUMER PROFILE –

INDS -27%, DOM-22%, COMM-5%, IRRI-39% & OTHERS-7%

KARNATAKA

INSTALLED CAPACITY – 6180 MW

MAX DEMAND MET – 5612 MW

DAILY CONSUMPTION MAX – 125 MU

DAILY CONSUMPTION AVG – 95 MU

CONSUMER PROFILE –

INDS -26%, DOM-19%, COMM-7%, IRRI-39% & OTHERS-9%

KERALA

INSTALLED CAPACITY – 2284 MW

MAX DEMAND MET – 2602 MW

DAILY CONSUMPTION MAX – 41 MU

DAILY CONSUMPTION AVG – 34 MU

CONSUMER PROFILE –

INDS -34%, DOM-44%, COMM-13%, IRRI-2%& OTHERS-7%

TAMIL NADU

INSTALLED CAPACITY – 10015 MW

MAX DEMAND MET – 8371 MW

DAILY CONSUMPTION MAX – 166 MU

DAILY CONSUMPTION AVG – 135 MU

CONSUMER PROFILE –

INDS -39%, DOM-25%, COMM-7%, IRRI-24% & OTHERS-5%

Page 21: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

21

ANDHRA PRADESH

POPULATION :- 7.6 CRORES

AREA :- 275 (‘000 SQ KM)

NO OF CONSUMERS :- 162 LAKHS

PER CAPITA CONS. :- 719 UNITS

MAIN AGRICULTURE CROP :- RICE

CLIMATIC CONDITION :- HOT AND HOT & HUMID

SR STATES – GEOGRAPHYKARNATAKA

POPULATION :- 5.3 CRORES

AREA :- 192 (‘000 SQ KM)

NO OF CONSUMERS :- 105 LAKHS

PER CAPITA CONS. :- 642 UNITS

MAIN AGRICULTURE CROP :- COFFEE & RAGI

CLIMATIC CONDITION :- HOT AND HOT & HUMID

KERALA

POPULATION :- 3.2 CRORES

AREA :- 39 (‘000 SQ KM)

NO OF CONSUMERS :- 61 LAKHS

PER CAPITA CONS. :- 386 UNITS

MAIN AGRICULTURE CROP :- COCONUT & SPICES

CLIMATIC CONDITION :- HUMID

TAMIL NADU

POPULATION :- 6.2 CRORES

AREA :- 130 (‘000 SQ KM)

NO OF CONSUMERS :- 152 LAKHS

PER CAPITA CONS. :- 866 UNITS

MAIN AGRICULTURE CROP :- SUGAR CANE & OIL SEEDS

CLIMATIC CONDITION :- HOT AND HOT & HUMID

Page 22: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

22

INSTALLED CAPACITY IN SRSUMMARY OF INSTALLED CAPACITY(MW)

         AS ON 31.07.2006

AGENCY HYDRO THERMAL GAS/DIESEL WIND/OTHERS NUCLEAR TOTAL

ANDHRA PRADESH 3587 2963 272 2 --- 6824

KARNATAKA 3389 1470 128 4 --- 4991

KERALA 1835 --- 235 2 --- 2072

TAMILNADU 2137 2970 423 19 --- 5549

PONDICHERRY --- --- 32 --- --- 32

CENTRAL SECTOR --- 8090 360 --- 880 9330

IPP 278 387 3149 4309 --- 8123

TOTAL

11226 (30%)

15880 (43%)

4599 (13%)

4336 (12%)

880 (2%)

36921 (100%)

Page 23: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

23

11226(30%)

15880(43%)

4337(12%)

880(2%)

4599(13%)

SOURCE-WISE INSTALLED CAPACITY OF SR

All Figures In MW

TOTAL 36,921 MW

HYDRO

THERMAL

WIND/OTHERS NUCLEAR

NAPTHA/GAS/DIESEL

Page 24: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

GENERATING UNITS IN SOUTHERN REGION

A.PKAR

TNKERGENERATORS ABOVE 1000 MW

GENERATORS 500 – 1000 MW

GENERATORS BELOW 500 MW

TYPICAL

GENERATOR

SPREAD

IN SR

UNIT CAPACITY AP KAR KER TN CGS TOTAL

THERMAL (500 MW) 2 8 10

THERMAL

(200-250 MW)10 7 13 15 45

GAS/THERMAL

(100-150 MW)9 2 3 10 24

HYDRO

(>50 MW)27 29 16 15 87

TOTAL 48 38 19 38 165

- HYDRO

- THERMAL

- GAS / NAPTHA

- NUCLEAR

Page 25: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

CPP/IPP PLANTS IN SOUTHERN REGION

A.P

KAR

TNKER

Station Name I/C in MW

Variable Cost (Ps)

TATA ELECTRIC 79.1 390

JINDAL 260 280

THANNEERBAVI 220 500

Station Name I/C in MW

Variable Cost (Ps)

KASARGOD PCL 22 470

BSES 157 560

KUTHUNGAL 21 ---

MANIYAR 12 ---

KAYAMKULAM 360 580

Station Name I/C in MW

Variable Cost (Ps)

HITEC 15

TCPL 63.5

GMR VASAVI 196 444

SAMALPATTY 105 474

ST-CMS 250 161

P P NALLUR 330.5 550

ABAN 113 88

MADURAI POWER 106 456

ARKAY 38

Station Name I/C MW

Variable Cost (Ps)

SIMHADRI 1000 104

BSES 220 168

VEMAGIRI PGL 233

SPECTRUM 208 104

JEGURUPADU EXT.

220

JEGURUPADU 216 102

LANCO 355 125

Page 26: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

26

LOAD 500-1500 MW

LOAD 200-500 MW

TYPICAL

LOAD

SPREAD

IN SR

Page 27: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

KHAMMAM

VIJAYAWADANAGARJUNASAGAR

GAZUWAKA

HYDERABAD

RAICHUR

GOOTY

HOODY

SALEM

UDUMALPET

TRICHUR

MADURAI

TRICHY

MADRAS

NEYVELI

CUDDAPAH

DAVANAGERE

RAMAGUNDAM

BANGALORE

MUNIRABAD

PP

P

P

P

P

P

P

P

P

P

PP

P

KOLAR

63

HOSUR

1

60

P

NELLORE

NELAMANGALA

KURNOOL

KALPAKKA

SIMHADRI

HIRIYUR

TALAGUPPA

MAMIDIPALLY

SRI SAILAM

-- OF NTPC

-- OF ANDHRA PRADESH

-- OF TAMIL NADU

-- OF NLC

-- OF POWERGRID

400KV SUB-STATIONS IN SR

NEYVELI TPS I (EXP)

  POWERGRID STATE OTHERS TOTAL

AP 8 9 2 19

KAR 6 5 1 12

KER 2     2

TN 6  1 2 9

TOTAL 22 15 5 42

TRIVENDRUM

NARENDRA

VEMAGIRIGMR

JEGRUPADU EXTN

MEHA BOOB NAGAR

CHITTOOR

-- OF NPC

KAIGA

MYSORE

-- OF KARNATAKA

ALMATHI

Page 28: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

28

TRANSMISSION IN SOUTHERN INDIA

ABOUT 3000 CKM OF 400 KV LINES ADDED IN THE PAST 2 YEARS

VOLTAGE LEVEL AP KAR KER TN CGS TOTAL

400 KV 2680 1616     10905 15201

220/230 KV 10274 7839 2692 6538 366 27709

132/110 KV 12360 6060 3720 10220   32360

TOTAL 25314 15515 6412 16758 11271 75270

Page 29: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

29

11000

13000

15000

17000

19000

21000

23000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

HOUR ---->

DE

MA

ND

IN

MW

--->

TYPICAL LOAD CURVE OF SR

WINTER

MONSOON

SUMMER

EVENING PEAK

WEATHERCONSUMPTION

Page 30: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

30

GRID CONTROL

ISSUES & CARDINAL EVENTS

Page 31: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

31

GRID OPERATION – TYPICAL ISSUES IN PAST

• LOW / HIGH FREQUENCY PROBLEMS

– FREQUENCY EXCURSES TO LOW/HIGH VALUES

• LOW / HIGH VOLTAGE OPERATION

– CRITICALLY LOW VOLTAGES AT LOAD CENTRES

– SUBSTANTIALLY HIGH VOLTAGES AT FAR ENDS

• SYSTEM BROWNOUTS / BLACK OUTS

– SEPERATION OF SYSTEMS / LOSS OF LOAD

• ECONOMIC IN-STABILITY / INCREASED ELECTRICAL LOSSES– UNRELIABLE / INEFFICIENT OPERATION OF EQUIPMENT

Page 32: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

32

GRID OPERATION: A TIGHT ROPE WALK

BLACK-OUTVOLTAGE

COLLAPSE IN-ECONOMIC

OPERATION

INSTABILITYPOWER

SWINGSINCREASED

LOSSES

Page 33: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

Aug, 2005

By 2007

Inter-regional capacity - 18,400MW

Page 34: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

Salakati

Bongaigaon

Birpara

Malda

Dehri

Sasaram

Sahupuri

Allahabad North-eastern

Eastern

Northern

Belgaum

Kolhapur

Budhipadar

Rourkela

Korba

Raipur

Auraiya

Malanpur

Western

Southern

Balimela

Upper Sileru

Chandrapur

Ramagundam

Jeypore

Gazuwaka

Singrauli

Vindhyachal

Talcher

Kolar

Kota

Ujjain

Inter-regional Links – By 2007

Gorakhpur Muzaffarpur

Balia Patna

BiharshariffBalia

SipatRanchi

Agra

Gwalior

Nagjhari

Ponda

2100 MW

6650 MW 1200 MW

3650MW1400 MW

2850 MW

Page 35: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

35

SOUTHERN REGION

WESTERNREGION

EASTERN REGION

NORTHERN REGION

NORTH-EASTERN REGION

1

2

3

Three ELECTRICAL REGIONS w.e.f. March 2003

Page 36: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

36

SOUTHERN REGION

WESTERNREGION

EASTERN REGION

NORTHERN REGION

NORTH-EASTERN REGION

1

2

TWO ELECTRICAL REGIONS w.e.f Aug. 2006

Page 37: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

37

Components of inter-utility tariff(Pre – ABT Mechanism)

Fixed charges Interest on loans Depreciation O & M charges Return on equity Interest on Working Capital

Energy charges (fuel cost) Incentives Surcharge & other levies No charge for reactive energy

Page 38: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

38

Components under Availability Based Tariff (ABT)

Capacity chargesEnergy chargesUnscheduled Interchange (UI)

Page 39: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

39

0

50

100

150

200

250

300

350

400

450

500

550

600

650

48.9 49 49.1 49.2 49.3 49.4 49.5 49.6 49.7 49.8 49.9 50 50.1 50.2 50.3 50.4 50.5 50.6 50.7 50.8 50.9 51

Frequency ----------->

UI ra

te

-----

------

------

>

Below 49.0 Hz UI rate =570 p/u

At 50.0 Hz UI rate =150 p/u

At 49.8 Hz UI rate =210 p/u

Above 50.5 Hz UI rate =0 p/u

UI RATE

Rate of Unscheduled Drawal/InjectionFrequency (Hz) Rate (p/u)

Above 50.5 0

50.0 150

49.8 210

49.0 and below 570

Page 40: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

40

UI - A RATIONAL AND SCIENTIFIC VECTOR

BALANCING MARKET

MERIT ORDER OPERATION

TRANSPARENCY

NEUTRALITY

SIMPLICITY

PRICE SIGNAL EASILY AVAILABLE

NO NEED TO NEGOTIATE ANY PRICE

EASY SETTLEMENT

EASY TO UNDERSTAND AND IMPLEMENT

EASE OF REGULATION

Page 41: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

41RTU RTU RTU

SUB LDC SUB LDC SUB LDC

SLDC SLDC SLDC

ERLDC

WRLDC NRLDC SRLDC

NERLDC

NLDC

32 Nos.

51 Nos.

1160Nos.

Unified Grid OperationUnified Grid Operation

5 Nos.

NationalLevel

RegionalLevel

State HQLevel

Group / Distt Level

Plant / Sub-Station Level

Page 42: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

42

RLDC,Bangalore

KalamasseryHyderabad BangaloreChennai

Cuddapah

Warangal

Vijayawada

Kalam’erry

Kannur

Trivandrum

Chennai

Erode

Madurai

Bangalore

Lingusugur

Hubli

CPCC SCC, Pondy

Hyderabad

Hierarchy of The ULDC Scheme in Southern Region

Andhra Kerala Tamilnadu Karnataka

Page 43: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

43

Southern Region Grid Complexities in Monitoring & Control

Annual Inter-Regional Energy Transfer

≈10,000MU

Transformers (220kV and

above)480 nos.

Installed Capacity

≈36031 MW

Integrated Opn

of Ten Power Utilities

Dynamic Grid

Conditions

Generators –Hydro,

Thermal,Gas/IPP

422 nos.

Transmission

Network 400/220kV

≈ 40700 Ckm

30,000 POINTSActive Power, Reactive

Power,Voltage, Frequency,

TransformerTap Position, Circuit

Breaker Position, Isolator Position etc

Transformation

Capacity ≈45000 MVA

Page 44: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

44

GROWTH OF INSTALLED CAPACITY OF SR

1947

5

1983

0

2030

4

2129

8

2213

3

2298

3

2417

3

2616

3 2850

1

2952

6 3273

3 3603

1

10000

15000

20000

25000

30000

35000

40000

1994-95 1995-96 1996-97 1997-98 1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06

YEARS - - ->

IN MW

Page 45: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

45

Kolar

Chintamani

Cudappah

HoodyHosur

Salem

Udumalpet

Madras B’lore

+/- 500 KV DC line 1370 KM

ElectrodeStation

ElectrodeStation

TALCHER

400kv System

220kv system

KOLAR

TALCHER KOLAR TALCHER KOLAR SCHEMATICSCHEMATIC

Page 46: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

46

NR-ER

SR-ERWR-SR

ER-NEREASTERN

REGION

SOUTHERN

REGION

WESTERN

REGION

NORTHERN

REGION

NORTH-EASTERN REGION

SHORT TERM OPEN ACCESS(STOA) RATES

(2006-07)

WR-ER

757.04

(3.2)

407.87

(1.7)

521.37

(2.2)

345.10

(1.4)

1893.14 (7

.9)

1114.72

(4.6)

560.

09 (2.

3)

1335.50 (5.6)

557.96 (2.3)441.24 (1.8)

WR-N

R

Notes: i) The indicated STOA Rates are in Rs./MW/Day.

ii) The figures shown in bracket correspond to the

indicative STOA Rates in Paise/Unit. (approx.)

Page 47: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

47

UI vs STOA market (All regions)

5% UI market

3% STOA market

100% power market

92% long term market

Page 48: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

48

DETAILS OF REGION WISE STOA TRANSACTIONS IN 2005-06

2263

1241

35 109 290

1012610561

772 623 444

0

2000

4000

6000

8000

10000

12000

NR WR SR ER NER

No.Of Transactions Energy Approved in MU

Page 49: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

49

Constituent-wise STOA Import/Export Energy2004 – 05

519503

0

358

00

185

00

200

400

600

800

1000

1200

1400

1600

1800

2000

AP KPTCL KSEB TNEB

Import Export

All figures in MUs2005 – 06

434

1717

356

808 842

3 0 00

200

400

600

800

1000

1200

1400

1600

1800

2000

AP KPTCL KSEB TNEB

Import Export

Page 50: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

50

MONTHWISE EXPORT STOA BY CPPs/ IPPs

0

20

40

60

80

100

120

140

160A

pr-

05

May

-05

Jun

-05

Jul-

05

Au

g-0

5

Sep

-05

Oct

-05

No

v-05

Dec

-05

Jan

-06

Feb

-06

Mar

-06

Ap

r-06

May

-06

Jun

-06

EN

ER

GY

IN M

Us

---

>

JINDAL NAVBHARAT

Page 51: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

51

KADAMPARAI PUMP OPERATION

-300

-200

-100

0

100

200

300

400

5000:

001:

002:

003:

004:

005:

006:

007:

008:

009:

0010

:00

11:0

012

:00

13:0

014

:00

15:0

016

:00

17:0

018

:00

19:0

020

:00

21:0

022

:00

23:0

00:

00

TIME ---->

IN M

W --

-->

48.50

49.00

49.50

50.00

50.50

51.00

FREQ

UENC

Y IN

HZ

---->

GENERATOR MODE

PUMP PUMP

Page 52: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

52

KADAMPARAI ENERGY GENERATED/PUMPED DURING LAST 5 YEARS (MU)

MONTHS2001-02 2002-03 2003-04 2004-05 * 2005-06

GENERATOR MODE

GENERATOR MODE

GENERATOR MODE

PUMP MODE

GENERATOR MODE

PUMP MODE

GENERATOR MODE

PUMP MODE

APRIL 0.1 3.9 35.0 40.0 26.0 35.0 0.0 2.6

MAY 0.0 1.4 37.0 43.0 41.0 48.0 29.6 45.7

JUNE 1.0 6.4 29.0 45.0 55.0 35.0 45.3 51.2

JULY 27.5 6.9 47.0 49.0 50.0 49.0 79.0 62.3

AUGUST 21.4 8.8 54.0 55.0 55.0 41.0 49.5 25.0

SEPTEMBER 11.0 8.6 36.0 48.0 30.0 25.0 40.8 15.2

OCTOBER 19.5 18.5 26.0 15.0 0.0 0.0 46.9 45.1

NOVEMBER 17.9 16.7 23.0 24.0 0.0 0.0 64.1 59.2

DECEMBER 20.3 20.5 49.0 53.0 0.0 0.0 70.0 62.5

JANUARY 18.4 39.0 44.0 58.0 0.0 0.0 72.0 92.9

FEBRUARY 14.0 39.0 21.0 21.0 0.0 0.0 53.3 55.6

MARCH 5.7 32.0 6.0 18.0 0.0 0.0 30.9 37.9

TOTAL 156.7 201.8 407.0 469.0 257.0 233.0 581.4 555.3

Note: The plant was under shutdown from 16th Sep 2004 to 28th April 05 for dam maintenance works.

Page 53: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

53

KADAMPARAI ENERGY GENERATED/PUMPED DURING LAST 5 YEARS (MU)

157

202

407

257

581

469

233

555

0

100

200

300

400

500

600

700

2001-02 2002-03 2003-04 2004-05 2005-06

Generation Pumped

Page 54: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

54

UI IMPORT BY SR FROM ER ON 12-JUL-06

0

100

200

300

400

500

600

700

800

900

0:00

1:00

2:00

3:00

4:00

5:00

6:00

7:00

8:00

9:00

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

TIME---->

IN M

W --

-->

48.4

48.6

48.8

49.0

49.2

49.4

49.6

49.8

50.0

50.2

50.4

FREQ

IN H

Z--->

ER UI SR FREQ ER FREQ

ER FREQ

SR FREQ

UI IMPORT

FROM ER

AMOUNT SAVED FOR SR CONSTITUENTS = 71 LAKHS

Page 55: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

55

GENERATION vs FREQUENCY FOR

10

30

50

70

90

08

:21

09

:21

10

:21

11

:21

TIME IN HH:MM ----->

MW

---

-->

49.00

49.20

49.40

49.60

49.80

50.00

50.20

50.40

FR

EQ

IN

HZ

---

-->

GENERATING UNITS PARTICIPATION IN PRIMARY RESPONCE

SHARAVATHI -1

FREQ DROP FROM 49.72 HZ TO 49.27 HZ

i.e. ~ 0.45HZ

Page 56: 1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.

56

LOW DEMAND(VALLEYS)

SHARP PEAKS

0000 HRS OF 01 SEP 06

29 AUG 06 30 AUG 06 31 AUG 06