Transcript of 1 Portfolio Management Initiative Briefing Sessions May 23, 2005 I. Strategic Business and IT...
1
Portfolio Management InitiativeBriefing Sessions
May 23, 2005
I. Strategic Business I. Strategic Business and IT Planning and and IT Planning and Investment Selection Investment Selection
and Budgetingand Budgeting((Investment Portfolio Investment Portfolio
ManagementManagement))
III. Investment III. Investment Operation and Operation and
Maintenance, and Maintenance, and Renewal, Retirement, Renewal, Retirement,
or Replacementor Replacement ((Applications and Assets Applications and Assets Portfolio ManagementPortfolio Management))
II. Project Implementation II. Project Implementation ((Project Portfolio ManagementProject Portfolio Management))
Life Cycle of IT Investments
Framework for Managing IT Investments
2
Session Agenda
• Welcome and Introduction of Presenters• Background of IT Related Legislation, Project
History, and Overview of Portfolio Management• Key Concepts of Portfolio Management and
Proposed Use in State Government– Investment Portfolio Management– Project Portfolio Management– Applications Portfolio Management
• Implementation Phases in State Government• Project Training and Implementation Schedule• Workflow for Project Approval and Status Reporting• Wrap-up – Questions and Suggestions
3
Four Intentions of Legislation for Better Management of IT
1. Improve the planning for and budgeting of IT investments.
2. Prepare better researched and more thoroughly developed project plans.
3. Provide stronger project management and more appropriate oversight.
4. Improve the inventorying and analysis of major IT assets.
4
History of Portfolio Management Initiative
• Summer 2004 – Ratification of legislation transferring many duties of the IRMC to the State CIO regarding investment review and project approval and oversight, with involvement of OSBM, OSC, and Sec. of Adm.
• Late 2004 – Purchase of UMT software tool from competitive bidding process.
• January 2005 – Begin software tool implementation project.• February 2005 – Submission of State CIO IT Plan to the
General Assembly – portfolio management is key component of three of the seven initiatives.
• April 2005 – Completion of extensive design phase involving agency staff participation in configuration of tool to meet state government use.
5
Overview of Portfolio Management• Assists in the life-cycle management of investments - to
determine where to invest and what to invest in; perform satisfactorily the acquisition and implementation of them; and decide when and how to renovate, retire, or replace them. Do the right things, in the right ways, at the right times, and for the right reasons.
• Analyzes and evaluates investments from individual and group perspectives - the group perspective compares and contrasts each investment relative to the others, considers interdependencies among the members of the group, and rates each individually and as a group. An analogy from the financial sector is the management and reporting of a 401(k) account with multiple investments.
• Guide and direct multi-level review and approval processes - to provide discipline, consistency, and rationality to collaborative decision making. The CIO’s project approval process is an example.
6
Overview of Portfolio Management
Involves the following to enhance business/IT decision making activities:
• Techniques, methodologies, and practices.• Governance process for rational and consistent
decisions:– Leadership.– Organizational structures.– Direction and processes.
• Automated support tool– Guide process, perform calculations, prepare analyses,
and produce reports.– Decision support – not decision making - capability.
7
Use of Portfolio Management Concepts and Tool in State Government
• Identifying, analyzing, and prioritizing potential IT investments (investment portfolio management) – assist departments in evaluating alternative IT investment needs and opportunities and preparing funding requests.
• Approving and monitoring IT implementation projects (project portfolio management) – Streamline and improve the effectiveness of department and statewide approval and periodic (monthly) status reporting.
• Analyzing legacy business software (applications portfolio management) – Maintain a statewide database of current business systems and provide analytical capabilities for managing these, including the identification of those at-risk and the forecasting of long-term cost liabilities for replacements and renovations.
8
Framework for Managing IT Investments
I. Strategic I. Strategic Business and IT Business and IT
Planning and Planning and Investment Investment
Selection and Selection and BudgetingBudgeting
(Linking IT Investments (Linking IT Investments to Agency Missions and to Agency Missions and Business/Program Goals Business/Program Goals
and Objectives, and and Objectives, and Investment Portfolio Investment Portfolio
ManagementManagement))
III. Investment III. Investment Operation and Operation and
Maintenance, and Maintenance, and Renewal, Renewal,
Retirement, or Retirement, or Replacement Replacement (IT (IT Service Management; Service Management;
Enhancement, Renovation, Enhancement, Renovation, or Termination; IT Asset or Termination; IT Asset
Management; and Management; and Applications and Assets Applications and Assets Portfolio ManagementPortfolio Management))
II. Project Implementation II. Project Implementation (Acquisition (Acquisition of Products and Services, System Development of Products and Services, System Development
Life Cycle Methodology, Project Management Life Cycle Methodology, Project Management Methodology, Agency and Statewide Governance, Methodology, Agency and Statewide Governance,
and and Project Portfolio ManagementProject Portfolio Management))
Life Cycle of IT
Investments
9
Investment Portfolio Management
• Theory dates to 1950s with the evaluation of financial investments on both returns and risks – led to the practice of diversification of capital assets.
• Since late 1990s, becoming popular in public and private sectors to help align IT investments with organizational missions and business priorities.
• Recognizes that the management of IT is a joint business and IT responsibility.
• Helps evaluate and rank potential investments using a variety of criteria – agreement with business strategies and goals (governmental priorities), costs, financial and societal benefits/value, project and business risks, architectural fit, accomplishable within fiscal limitations and staffing constraints, etc.
10
Applications Portfolio Management
• Business/Program Goals and Objectives• Processing and Information Flows• Organization Charts• Business Reengineering Opportunities
Department Business Strategy &
Department Business Architecture
(Business Service Models)
• Department Mission• Statuary Mandates• Governmental Initiatives
Asset InfrastructureManagement
New Initiatives
IT Investment Portfolio Management • Identify potential investments and
evaluate candidates against defined criteria
• Prioritize projects based on analysis results (relative weighted scores)
• Balance staffing and fiscal resources• Determine disposition – invest, adjust,
or sunset
• Retirements • Replacements• Modernizations• Maintenance
Other Plans and Strategies
• State CIO IT Plan• Statewide IT Initiatives• Department & Statewide
Tech. Architectures• Department IT Plan
Current IT Project Portfolio
Funding Requests and Project Approvals
• Refreshment Cycles• Security/Reliability
Upgrades
• New Applications• Infrastructure
Additions/Upgrades
Overview of IT Investment Portfolio Management in State Government
• Status of all projects (schedule, budget, business objectives, etc.)
• Projects no longer relevant or with lower priorities
• Projects with higher priorities or increased urgency
11
Objectives of Project Portfolio Management
• Clarify roles and responsibilities.• Provide for well understood and comparable
oversight.• Ensure projects are:
– Planned well and researched thoroughly prior to starting – business case.
– Managed and monitored proficiently to achieve budget, schedule, scope, and quality expectations - dashboard.
– Completed successfully so that business goals and objectives are realized - post-implementation assessment/closeout review.
Advance the management of IT implementation projects:
12
Project Portfolio Management
• Covers roles and responsibilities for project approval and monitoring.
• Applies to review and approval processes at both department and statewide levels – integrated workflow.
• Defines phases of project development, with review points (called gates) at predetermined intervals for approvals to proceed.
13
Project Portfolio Management
• Approval points (gates) are positioned to:– Ensure projects are positioned for success before proceeding
to succeeding phase.
– Verify business cases are still viable based on governmental events and realities and project progress since funding.
• Monthly status reports monitor costs, schedule, staffing, and results against plans and budgets.
• Governance process that builds upon – but does not replace – the disciplines and techniques of system development life cycle methodologies (e.g., IEEE model) and project management methodologies (e.g., PMI model).
14
Objectives of Applications Portfolio Management
Develop and maintain a comprehensive database of major state software applications to assist in managing them, including:
• Identifying present technical and business status.
• Determining best approaches and ascertaining the priorities and timeframes for remediation/renovation, retirement, or replacement.
• Estimating associated costs – future liabilities.
15
Management of Legacy Applications – Example of Risk Management
• December 24, 2004 – Comair’s 18-year-old flight crew management systems failed:– All 1,100 flights cancelled Christmas day, and Comair did
not return to full schedule until December 29 – total 3,900 flights cancelled or delayed.
– 200,000 passengers stranded at cost of $20 million, and image and reputation tarnished – key executives replaced.
• No backup system – plans for replacement in works for 7 years, but no implementation.
• System had a critical flaw that was not known – could handle only 32,000 crew changes/month – tipping point reached Christmas Eve due to snow storm.
16
Management of Legacy Applications – Business Value
Expenditure TypePercent of Total IT
SpendingBusiness Value of
Investment1. Infrastructure to run
the business and maintenance of legacy applications
47% Low
2. New Applications:
Utility
Enhancement
Frontier
Total
53%
21%
21%
11%
100%
Low
Medium
High
Two-thirds of spending (infrastructure and utility applications) gives one-third of business value – need to reverse this ratio (reduce percents on these and increase percents on enhancement and frontier applications) as much as possible.
17
Issues Surrounding Systems Obsolescence and Risk
Seems to run forever, but ultimately has a finite business, economic,
and/or technical life
Sources of Risks
• Over time, sustainability of applications becomes questionable due to age and technology advances, combined with changed business needs. They no longer: Support business goals and objectives, are cost-effective to operate or maintain, and/or are risk-acceptable by presenting too great a likelihood of failure with cataclysmic consequences.
Business Issues Impediment to the implementation of new and more cost-effective
service delivery models Becomes a constraint in meeting regulatory requirements
Staffing issues - Unavailability of Skills Unavailability of staff skills to maintain or integrate with application Unavailability of third-party vendors Dependency on individual contractors
Technology issues Expired warranties, with no vendor support Cannot handle increased usage or volumes of data Does not run anymore on available platforms Used beyond original intent, and cannot be enhanced Cannot meet security, privacy, or confidentiality requirements System can fail, with untraceable error
18
Legacy Applications Study - Statewide Findings
In the portfolio of approximately 900 applications: 40% are considered critical for department mission/strategy and 17% are enterprise (statewide) applications.
The statewide portfolio is relatively young, with an average age of 7.5 years.
Health status is: 23% presenting functional, technical, or both problems; 50% with some problems, but manageable; and 27% healthy.
Remediation timeframes are: 11% require action immediately (within next two years), 35% require action in the near term (2 to 4 years), and 54% require action in the long term (4 to 6 years).
Although the immediate needs of the portfolio appear to be manageable, projections of its future status if no remediation actions are taken indicate an increasingly deteriorating condition as the applications age – pay some now or pay a lot later.
19
Gartner Perspective on Portfolio Management
Portfolio management approaches are maturing across the industry, and significant savings or budget reallocations are not uncommon
Source: Gartner Research
Enterprise Architecture
Strategic Planning
ApplicationPortfolio
Management
Investment and Project Portfolio
Management
Drives
Supported by Impacts
Influences
IT Mgt and Governance
Key IT Management Processes
20
Key Points1. Portfolio management is a business
responsibility:• Review current projects and their status for continued
viability, priority, and staffing and fiscal resource commitments.
• Review staffing and fiscal commitments to applications and infrastructure maintenance and renovations/upgrades for benefits and priority.
• Present new investment recommendations.• Reprioritize portfolios based on needs and resources.• Examine completed projects for effectiveness and
performance against business goals and objectives.
2. IT investment management is a joint business and IT responsibility – ensure IT sustains and extends the enterprise’s mission and objectives in a planned manner.
21
Portfolio Management Tool – Implementation Priorities
• First priority (Summer 2005) is project approval and monitoring – streamlining and simplifying of present processes:– Important ongoing activity.– No change in underlying concepts and principles, but better way of
managing and communicating.– Immediate benefit to projects, departments, and oversight
organizations.
• Second priority (Fall 2005) is legacy applications – transfer of study data to tool and department update of information:– Validate study findings, especially for immediate action applications.– Begin cost estimating efforts for submitting long-term liabilities to
General Assembly.
22
Portfolio Management Tool – Implementation Priorities
• Third priority (Winter 2005-06) is planning and budgeting – investment analysis and funding requests:– Involves more sophisticated techniques and analysis
activities (portfolio optimization and staffing resource scheduling).
– Less pressing timetable, as follows budget cycle.
– Some departments have volunteered to test these capabilities further before statewide rollout.
23
Training ApproachTheory and Concepts of Portfolio Management
(the “Why”)Hands-On with Tool (the
“What” and “How”)Overview Briefing
Conceptual Portfolio Management Course
Hands-On Tool Course
Abbreviated Hands-On Tool Course
• Two sessions lasting 11/2 hours each• May 23• CIOs, CFOs, CBOs, etc.• Understanding of key principles and practices
• Three sessions lasting 3 hours each• June 6, 10, and 13• PMs, QAs, Architects, etc.• Understanding of key principles and practices• Major concepts and uses of business cases
• 4 sessions lasting 3 hours each
• June 23 and July 13.• CIOs, CFOs, CBOs, etc.• How to use tool to perform reviewer and approver jobs – its capabilities and features
• 11 sessions lasting 6 hours each
• June 13-16, 20-22, 27-28, and July 7 and 14.• PMs• How to use tool to perform project manager jobs – its capabilities and features
Prerequisites and no Attendance Limitations
People with Assigned Licenses and Attendance Slot Limitations
24
Implementation Schedule
1. Convert current 34 projects in portfolio (does not include registrations) with required information fields
2. Convert latest monthly status report for the 34 projects in portfolio (risk will only be High, Issues will only be Open, MS Project file conversion if provided)
3. Exceptions – projects ending by August, 2005 will not be converted to the tool
4. For those trained by June 24 –monthly status will begin with report due in mid-July
5. For all others – monthly status will begin with report due in mid-August
6. All SB 991 Approvals must be entered using the tool once trained (after 7/15/2005, all SB 991 approval requests must be through the tool)
7. After 8/31/2005, all monthly and quarterly status reports must be entered using the tool