1
JAG/CCMCOPC Status Updates and
Recommendations
NOV 4-5, 2015
LCDR Tristan BorneJAG-CCM Chairperson
![Page 2: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/2.jpg)
2
JAG/CCM
• Purpose Coordinate communication issues between the Operational Processing Centers (OPC), monitor the effectiveness of those communications, and to do capacity planning and forward projection of capability needs.
![Page 3: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/3.jpg)
3
Outline• CCM Team Membership• Network Outages• Process Towards the End Goal
– End goal diagram– Process Flow Chart– Decision Points
• Primary Connection Status• 2nd Connection Status• Bandwidth Sizing• DREN and DSRC
![Page 4: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/4.jpg)
4
CCM TeamMember Organization
Jason RanceBilly Cowgill*Marvin CunninghamTSgt Michael Dent
Air Force/557 WW
Cameron Shelton Doug Fenderson
NOAA/NWS/NCEP/NCO
Craig Wade OSGSRussell Dyson OSPO
NOAA/NESDIS
Tracy LePire Navy/NAVO
*LCDR Tristan Borne (CCM Chair)Trent HancockDerek Eddington
Navy/FNMOC
Kevin Greenlee Navy/NAVIDFOR/N462
Ken Barnett OFCM
Technical Advisor/SME/Alternate Organization
*MAJ Rubin Neypes*Bruce Kenison (alternate)
DISA Field Office USSTRATCOM
Quincy AllenJagdish Rai
DISA
* New to the role or group
![Page 5: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/5.jpg)
Network Outages
Date OPC (circuit) Outage1 2/10/15 NAVO – 73WU 9hrs (fiber cut)
2 3/10/15 NAVO – 73WU 1hr
3 4/15/15 NAVO – 73WU 5hrs
4 7/1/15 FNMOC – 7CU2 12hrs (fiber cut)
5 9/16/15 FNMOC – 7CU2 18hrs (fiber cut)
6
7
8
9
10
115
• NCEP (@NSOF) circuit tracking.– Does not include DoD to DoD outages, nor data issues.
• 2nd connection could help in some cases.• 2nd connection and multiple NFGs with dynamic routing should
prevent many outages but not for the last mile outages.
![Page 6: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/6.jpg)
What JAG CCM is working towards
6
DoDNOAA
![Page 7: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/7.jpg)
Process Flow Chart
7
Navy Bandwidth upgrade
NMIC SN9K Install
SuitlandSFP OC48 NOAA Boulder MSPP
Enable 3 DOD circuits
Test end to end connectivity
Perform a failover test
Boulder
Submit the NFG connection request
Test the latency through NFG
Switch secondary path to NFG
Final Goal: dual NFG connections
Decision Point 1
Decision Point 2
COPCCCM/DISA
![Page 8: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/8.jpg)
COPC Network Decision PointsCCM / DISA Decision Point 1:• COPC Action 2015-1.4: Make a recommendation about the utilization of the 2nd COPC
network path (Boulder). [Concurrent usage or regular scheduled failover tests].– CCM recommends keeping this action item open.– Once the dual paths are in place, CCM can provide COPC recommendations for usage (concurrent
or failover-only).• Pursue the first NFG connection through Suitland to Columbus or through Boulder to San
Antonio.
COPC Decision Point 2:• COPC Action Item 2013-1.5: Implement an end-to-end latency test exchange using
representative proxy data from NOAA (NESDIS, TOC, and NCEP) through NFG to each DOD OPC]. – CCM recommends keeping this action item open.
• Utilize NFG as primary COPC data exchange paths.
Final Goal:• Establish dual paths from the two NOAA access points (Suitland & Boulder).
– Per 557th WW, direction was to hold off migrating to NFG until further notice and focus on 2nd P2P connection from Boulder AFB.
– Determine the supportability of Navy going through NFG and 557 th WW staying on P2P link. 8
![Page 9: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/9.jpg)
Primary COPC Network ConnectionUpgrades to the bandwidth for both Navy sites are pending a switch upgrade at NMIC.• Currently 557th is 1gb, FNMOC is 155mb, and NAVO is 28mb. • Both FNMOC and NAVO have TSOs for upgrading to 400mb.• F2F meeting with the NMIC:
– Understand why the SN9K installation has been delayed at NMIC.– COPC/Navy working with NMIC in coordinating this install with DISA.
9
![Page 10: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/10.jpg)
2nd COPC Network Connection Status• Boulder: The commercial segment for circuit (6QU2) has been delivered by
CenturyLink.– Waiting on a part (SFP for the OC48).
• NCEP NCO has reached out to the CISCO rep and CISCO understands the criticality of the order and is working to resolve it.
– All 3 Operation Centers (557th @ 1GB, FNMOC @ 400MB, & NAVO @ 400MB) TSOs have been issued but on hold.
– The NOAA build-out (Phase 2) of the Boulder IDP was completed and expect FOC in 2016. However DoD exchange will be available when the circuit is fully functioning.
• DoD circuit cost sharing for the OC48 Boulder/Buckley:– Planning to use a DD Form 1144 Support Agreement as the official document for
sharing costs to replace the MOA method.
10
![Page 11: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/11.jpg)
Bandwidth Requirements
COPC Action Item 2014-1.2 To update the estimated bandwidth requirements (including ports and protocols).
• Both CNMOC and 557WW have validated their requirements for bandwidth, ports, and protocols.
• Sizing of a 4GB path for the DoD/NOAA exchange through NFG should be appropriate.
Recommend closing this action item.
11
![Page 12: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/12.jpg)
12
Questions
![Page 13: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/13.jpg)
13
Backup Slides
![Page 14: 1 JAG/CCM COPC Status Updates and Recommendations NOV 4-5, 2015 LCDR Tristan Borne JAG-CCM Chairperson.](https://reader031.fdocuments.net/reader031/viewer/2022013005/5a4d1ae97f8b9ab059979f29/html5/thumbnails/14.jpg)
14
- R 071652Z OCT 11FM: USCYBERCOM FT. GEORGE G. MEADE MDSUBJECT: (U//FOUO) USCYBERCOM TASKORD J3-11-0508, ESTABLISHMENT OF THENIPRNET FEDERAL DEMILITARIZED ZONE (DMZ). //OPER/GLADIATOR SHIELD//MSGID/ORDER/USCYBERCOM/ J3-11-0508/ PRIORITIZE ACTIONS IN SUPPORT OF MOVINGALL CONNECTIONS BETWEEN THE NIPRNET AND NETWORKS BELONGING TO EXECUTIVEBRANCH DEPARTMENTS, AGENCIES, CLEARED DEFENSE CONTRACTORS AND EDUCATIONALINSTITUTIONS INTO THE NIPRNET FEDERAL DMZ. /TASKORD/(U//FOUO)//REF/A/DOC/(U) OPORD 11-002 OPERATION GLADIATOR SHIELD (OGS)/COMMANDER, U.S.CYBER COMMAND (CDRUSCYBERCOM)/231800MAY11 (S//REL TO USA, FVEY)//REF/B/DOC/ (U) WARNORD 11-0377, ESTABLISHMENT OF THE NIPRNET FEDERALDEMILITARIZED ZONE/USCYBERCOM/ 021834Z SEP 11 (S//REL TO USA, FVEY)//
- R 211154Z OCT 11 ZYBFM COMFLTCYBERCOM FT GEORGE G MEADE MDMSGID/GENADMIN/FLTCYBERCOM/-/OCT//SUBJ/ESTABLISHMENT OF NIPRNET FEDERAL DEMILITARIZED ZONE (DMZ)//REF/A/MSGID:TASKORD/USCC/071652ZOCT2011/-/NOTAL//AMPN/REF A IS USCYBERCOM (USCC) TASKORD J3-11-0508, ESTABLISHMENT OFTHE NIPRNET FEDERAL DMZ.//
USCYBERCOM TASKORD J3-11-0508, ESTABLISHMENT OF THE
NIPRNET FEDERAL DEMILITARIZED ZONE (DMZ).