Landfill Gas Collection System
Design and Construction
Jim Park
1
![Page 2: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/2.jpg)
Landfill Gas Collection System Design Steps (1)
Consider objectivesControl migration of gasControl emissionControl odorsMaximize gas collection fir energy
recoveryComply with regulations
Define limits of landfillHorizontal and vertical limits
2
![Page 3: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/3.jpg)
Landfill Gas Collection System Design Steps (2)
Gas extraction wells or trenchesWell diameter and spacingWell materials(HDPE/PVC) and depthNon-well (leachate collection risers and
trench systems) extraction points
Layout gas wellsShallow wells - small ROIDeep wells - large ROITypically 150’ ROI (per NR 500)Liquid levels in landfillAffected by landfill design,
permeability, waste type, and operating pressure/vacuum
3
![Page 4: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/4.jpg)
Landfill Gas Collection System Design Steps (3)
Locate gas header pipe Monitoring capability Liquid level accessibility Resistance to environmental effects Versatility after installation
Establish condensate management
Adjust gas wells, if needed
Prepare a well schedule (example) 0.5 to 1.5 cfm/slotted foot of pipe
Determine gas generation and flow
4
![Page 5: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/5.jpg)
Landfill Gas Collection System Design Steps (4)
Header and blower sizing calculationsCalculate by handSpreadsheetComputer model KY GAS (Hardy cross
method)
Condensate Headers need to be sloped so condensate
does not pool in them Need to size headers to carry condensate
along with LFGNeed to size the pipe Calculate by hand
5
![Page 6: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/6.jpg)
Landfill Gas Collection System Design Steps (5)
Condensate Management StructuresKnock-outsLift stationsBarometric drip legsTransfer stationsDrip legs - Potential for air intrusionPneumatic vs. ElectricConsequences of inadequate condensate
management Flooded headers Low vacuum at well heads Effectively reduces pipe diameter Increased operating cost
6
![Page 7: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/7.jpg)
Landfill Gas Collection System Design Steps (6)
Select blower/flare systemCalculate by handSpreadsheetComputer model KY GAS (Hardy cross
method)Enclosed vs. open (destruction efficiency,
cost, and simplicity of operation)Sizing – gas rate, operating temperature,
ignition source, etc. Capacity ranges (turndown capability)May be importance for some of the closed
sites with very little gas
7
![Page 8: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/8.jpg)
Condensate Knockout Pump
8
![Page 9: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/9.jpg)
Rules of Thumb for Header Design (1)
A velocity of 50 ft/sec is the maximum allowed during concurrent flow conditions
A velocity of 30 ft/sec is the maximum allowed during countercurrent flow conditions
A velocity of 30 ft/sec is the maximum allowed within condensate management structures
A pressure drop of 1 inch water column per 100 feet of header is the maximum allowed under any flow conditions
9
![Page 10: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/10.jpg)
Flow conditions within a header must not exceed either pressure loss nor velocity limitations
10 inches of vacuum required at furthest extraction well
10 to 20 inch loss of vacuum at blower flare station
10
Rules of Thumb for Header Design (1)
![Page 11: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/11.jpg)
Well Pipe Materials PVC Rigid Higher temperature Structurally functional when slotted Easy to extend Higher cost Variety of manufactured fittings
HDPE Los cost Very flexible Temperature effects
11
![Page 12: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/12.jpg)
Landfill Gas Movement Patterns
12
![Page 13: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/13.jpg)
13
Landfill Gas Movement Patterns
Looping systemBenefits vs. costDesigned to be
redundantAccepts
expansions Control valves at
strategic locations in header system
Isolation portions of the system for maintenance, etc.
TypesButterfly, gate or
other values
![Page 14: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/14.jpg)
Landfill Gas Collection System
Design and Construction
14
![Page 15: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/15.jpg)
Typical Landfill Gas Well(Active System)
15
![Page 16: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/16.jpg)
16
![Page 17: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/17.jpg)
17
Vertical Gas Well Construction (1)
![Page 18: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/18.jpg)
18
Vertical Gas Well Construction (2)
![Page 19: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/19.jpg)
19
Vertical Gas Well Construction (3)
![Page 20: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/20.jpg)
20
Vertical Gas Well Construction (4)
![Page 21: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/21.jpg)
21
Vertical Gas Well Construction (5)
![Page 22: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/22.jpg)
22
Vertical Gas Well Construction (6)
![Page 23: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/23.jpg)
23
![Page 24: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/24.jpg)
At some landfills, gas collection wells are installed after the facility reaches grade. At others, the gas collection network is continuously built and expanded.
24
![Page 25: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/25.jpg)
Gas Collection Well
25
![Page 26: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/26.jpg)
LFG Collection Pipe Systems
26
![Page 27: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/27.jpg)
27
![Page 28: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/28.jpg)
28
![Page 29: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/29.jpg)
Header Pipe Trench
29
![Page 30: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/30.jpg)
Vertical Extraction Wells
30
![Page 31: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/31.jpg)
Landfill
Perimeter Vertical LFG
Collection WellPerimeter Vertical LFG
Collection Well31
![Page 32: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/32.jpg)
Example of Radius of Influence Calculation
32
Q
Extraction Well Grade
D-S
D
SH
Zone ofInfluence
LandfillBottom
IsobarsRI Rw
![Page 33: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/33.jpg)
Horizontal Wells
33
![Page 34: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/34.jpg)
Shredded Tires for Drainage Media
34
![Page 35: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/35.jpg)
Horizontal Extraction Wells
35
![Page 36: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/36.jpg)
Gas Collection from Leachate Collection System
Leachate collection system retrofitted for gas collection 36
![Page 37: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/37.jpg)
Change in Vacuum before and after Leachate Recirculation
37
![Page 38: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/38.jpg)
38
![Page 39: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/39.jpg)
LFG Collection and Beneficial Use
39
![Page 40: 1. Consider objectives Control migration of gas Control emission Control odors Maximize gas collection fir energy recovery Comply with regulations](https://reader037.fdocuments.net/reader037/viewer/2022103122/56649c9b5503460f9495920d/html5/thumbnails/40.jpg)
Typical LFG Production Curves for Bioreactor and Traditional Landfill
40
Bioreactor
Traditional
Time, yrs
Meth
an
e P
rodu
ctio
nC
fm o
f LF
G
Landfill closure