1 Andrew Howard UNFCCC secretariat [email protected] Progress in implementing the international...

14
1 Andrew Howard UNFCCC secretariat www.unfccc.int [email protected] Progress in implementing the international transaction log Consultations on registry systems prior to SBSTA 22 Bonn 13-14 May 2005

Transcript of 1 Andrew Howard UNFCCC secretariat [email protected] Progress in implementing the international...

Page 1: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

1

Andrew HowardUNFCCC secretariat

[email protected]

Progress in implementing the international transaction log

Consultations on registry systemsprior to SBSTA 22

Bonn13-14 May 2005

Page 2: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

2

Technical design work

Applicability of the CITL for ITL development

Development schedule

Initialization of registries

Overview

Page 3: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

3

Basis for the ITL established in the standards

• Transaction types

• Checks to ensure conformity with rules

• Reconciliation to eliminate inconsistencies

• Electronic communications with registries

• Data records to be kept

• Administrative processes

Version 1.0 of the technical specifications for the standards

Data exchange standards

Page 4: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

4

Version 1.0 (draft #7) of the ITL technical design specifications

• Database design and structure

• Logical flows for transaction and reconciliation processes

• Detailed specifications of coding components

• Detailed methods for ITL checks

• Links to other databases for reference information

- Compilation and accounting database

- CDM information system

- JI information system (track 2)

• Detailed specifications for ITL notifications

ITL technical design

Page 5: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

5

• Review ITL technical design

• Create database

• Develop programme code and an administrator interface

• Establish hardware environment

• Testing (individual components and overall functionality)

• ITL deployment in a production environment

• Initialization of secure communications with registries

• Documentation (plans, guides, training)

• Public website

ITL development tasks

Page 6: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

6

EU ‘Community Independent Transaction Log’

• Performs checks on transactions under the EU trading scheme

• Modelled on Kyoto’s ITL

• Development based on ITL technical design

CITL programme code provides a robust basis for the ITL

• Strong architecture for transactions, data integrity and checks

• Around half of required ITL functionality contained in CITL code

• Challenge is to safely and seamlessly adapt, remove and add code

A head start through the CITL

Page 7: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

7

EU transaction log (CITL)

EU communications hub

Nationalregistry

Nationalregistry

Nationalregistry

EU Member State registries

EU checks

Current EU communications

Page 8: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

8

Future Kyoto Protocol communications

Kyoto international transaction log

Kyoto communications hub

EU transaction log (CITL)

UNchecks

Other supplementarytransaction logs Other

checks

Nationalregistry

EU Member State registries

Nationalregistry

Nationalregistry

CDMregistry

Nationalregistry

Nationalregistry

Other Kyoto registries

EUchecks

Page 9: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

9

• Create new database or modify CITL database

• Add web service communications (tCERs and lCERs, notifications, STL communications)

• Add functions to interact with STLs (routing and processing communications, reconciliation, data sharing)

• Add transaction types (replacement, expiry date change)

• Add ITL notification functions and running totals

• Modify existing checks and add ITL-specific checks (tCER and lCER checks, transaction-specific checks, reconciliation checks)

• Remove unneeded CITL code (account management, EU-specific checks, EU supplementary unit and transaction types)

Adaptation of CITL code

Page 10: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

10

• Unit testing on individual code and database components

• Integration testing of compiled ITL code (with registries and STLs)

- Cover all transaction, reconciliation and notification cases

- Cover all ITL check cases

• Regression testing (after fixes made through earlier testing)

• Performance testing (for efficiency improvements)

- In actual hardware/software environment

- Under realistic load scenarios

Testing the ITL

Page 11: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

11

Indicative ITL development schedule

Estimatedcompletion

Review of ITL technical design

Establish development environment

Creation/modification of database Dec 2005

Programme code development and unit testing Mar 2006

Administrator interface development and unit testing Apr 2006

Establish hardware environment

Integration and regression testing (non-STL case) May 2006

Integration and regression testing (STL case) Jun 2006

Performance testing Jul 2006

ITL deployment (including prototype) Jul/Aug 2006

ITL administrator training

Page 12: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

12

• Administrator training

• Receipt and review of initialization documentation

• Establishment of VPN connection

• Transaction and reconciliation tests (web services tests)

• Tests for other data submission to ITL

• Full registry tests

• Activation of production environment connection

Concentrate initially on registries not associated with an STL

Initializing registries

Page 13: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

13

CITL initialization

• Similar process as for registries

• Establishment of secure ITL-CITL connection

• Data migration schedule (coordinated with EU registry migration), including standardized data migration procedures and scripts

Migration of registry connections from the CITL to the ITL

• One migration round or several?

• Coordination through the administrators cooperative forum

The special EU case

Page 14: 1 Andrew Howard UNFCCC secretariat  ahoward@unfccc.int Progress in implementing the international transaction log Consultations on registry.

14

Communications and planning through the cooperative forum

• ITL requirements

• Planning and schedules for development, testing, deployment, initialization (including data and registry migration in the EU case)

Support for initialization

• Provision of ITL prototype

• VPN purchase/configuration support for registries

• Further guidance on documentation

• Initialization support being incorporated in contractor selection

Communications with administrators