People Equipment Materials OHP TOTAL
Variation buildup 1,170.96 1,232.04 2,600.00 0.00 1,000.60 6,003.60
Total Variation 1,170.96 1,232.04 2,600.00 0.00 1,000.60
6,003.60
Sub-Contractors
Labour
Personnel No. Duration Unit Rate TotalChargehand 1 12 Hrs 30.30 363.60Helper 4 12 Hrs 16.82 807.36
1170.96
Plant
Item No. Duration Unit Rate TotalPlate Compactor 1 12 Hrs 10.00 120.00 Pickup truck 1 12 Hrs 92.67 1,112.04
1,232.04
Materials
Material Quantity Unit Rate TotalLockable Bollards 4 No. 650 2,600.00
2,600.00