Variation Cost Cost Analysis

Post on 15-Apr-2016

216 views 1 download

description

example

Transcript of Variation Cost Cost Analysis

People Equipment Materials OHP TOTAL

Variation buildup 1,170.96 1,232.04 2,600.00 0.00 1,000.60 6,003.60

Total Variation 1,170.96 1,232.04 2,600.00 0.00 1,000.60

6,003.60

Sub-Contractors

Labour

Personnel No. Duration Unit Rate TotalChargehand 1 12 Hrs 30.30 363.60Helper 4 12 Hrs 16.82 807.36

1170.96

Plant

Item No. Duration Unit Rate TotalPlate Compactor 1 12 Hrs 10.00 120.00 Pickup truck 1 12 Hrs 92.67 1,112.04

1,232.04

Materials

Material Quantity Unit Rate TotalLockable Bollards 4 No. 650 2,600.00

2,600.00