Variation Cost Cost Analysis

6
People Equipment Materials OHP TOTAL Variation buildup 1,170.96 1,232.04 2,600.00 0.00 1,000.60 6,003.60 Total Variation 1,170.96 1,232.04 2,600.00 0.00 1,000.60 6,003.60 Sub- Contractors

description

example

Transcript of Variation Cost Cost Analysis

Page 1: Variation Cost Cost Analysis

People Equipment Materials OHP TOTAL

Variation buildup 1,170.96 1,232.04 2,600.00 0.00 1,000.60 6,003.60

Total Variation 1,170.96 1,232.04 2,600.00 0.00 1,000.60

6,003.60

Sub-Contractors

Page 2: Variation Cost Cost Analysis

Labour

Personnel No. Duration Unit Rate TotalChargehand 1 12 Hrs 30.30 363.60Helper 4 12 Hrs 16.82 807.36

1170.96

Page 3: Variation Cost Cost Analysis

Plant

Item No. Duration Unit Rate TotalPlate Compactor 1 12 Hrs 10.00 120.00 Pickup truck 1 12 Hrs 92.67 1,112.04

1,232.04

Page 4: Variation Cost Cost Analysis

Materials

Material Quantity Unit Rate TotalLockable Bollards 4 No. 650 2,600.00

2,600.00

Page 5: Variation Cost Cost Analysis
Page 6: Variation Cost Cost Analysis