Thermal Remediation of TCE at a Former Asphalt Lab · 2018. 7. 6. · Thermal Remediation of TCE at...

Post on 29-Aug-2020

5 views 0 download

Transcript of Thermal Remediation of TCE at a Former Asphalt Lab · 2018. 7. 6. · Thermal Remediation of TCE at...

TRB Summer Workshop – Presented by Jeff Gernand and Shawn Schmelzer July 20, 2017

Thermal Remediation of TCE at a Former Asphalt Lab

Presentation Purpose

Describe site conditions.

Describe thermal treatment technology and why it was used.

Present results and lessons learned.

Site Location

Maryland DOT SHA’s former Eastern Regional Lab, 7857 Ocean Gateway, Easton, MD

US 50

SITE

Site History

1963 – 1988 – SHA operates the lab; TCE was used to extract aggregate from asphalt core samples

Mid 1980’s – SHA and MDE begin site assessment

1994-2003 – SHA operates groundwater pump and treat

2008 – SHA and MDE sign a Consent Order

2008-2011 – SHA completes the RI/FS process and develops the Thermal Remediation Work Plan

Project History

2011, SHA awarded a performance based contract : Contractor to design, install, and operate Reduce TCE in soil by an average of 95% Meet MDE Non-Residential Cleanup Standard for TCE in Soil

Remediation to be completed within 210 calendar days

SHA awards to the lowest bidder; must meet Contractor Equipment and Experience Statement

Contract successfully completed in September 2012, post-remediation groundwater monitoring underway

RI - Geologic Cross-Section

MIP

MIP – Conceptual Site Model

RI – MIP Results in Section

RI – MIP Results in Plan

Remedial Investigation Findings

TCE Contamination • Soil – Ranges up to 360,000 ppb • Groundwater – Ranges up to 230,000 ppb • Evidence of DNAPL • Source in Clay to 43 ft bgs; 2,324 Ft2

Remediation Requirements: • Cleanup Standard for Soil = 7,200 ppb • MDE required TCE mass removal

RI – TCE Source Area

Thermal Treatment – Application at ERL

Install 16 electrodes (41-51 feet deep) Apply electrical current to heat the soil to an

average of 87 degrees C Apply vacuum to collect the generated steam

and vapor for treatment Sample vapor to determine that flux peaked Use soil samples to document 95% TCE

reduction in the source area

Thermal Treatment Concept

Electrode Construction

Electrode Field

Thermal Treatment – Treatment Train

Thermal Treatment – Offgas Monitoring

Thermal Treatment – Field Monitoring Criteria

Thermal Treatment – Confirmatory Soil Sampling

Thermal Treatment – Results Energy applied: 923,070 kWh Subsurface temperatures: 87⁰ – 100+⁰ C VOC removal up to 3.3 lbs./ hour 38 soil samples; Days 66, 125, and 140 Operated for 141 days (vs. 50-70 estimated) 1,500 lbs. of TCE recovered

Post-Remediation Monitoring Network

Monitoring Results - Source

0

50,000

100,000

150,000

200,000

250,000

7/1/2007 7/1/2008 7/1/2009 7/1/2010 7/1/2011 7/1/2012 7/1/2013 7/1/2014 7/1/2015 7/1/2016

ppb

Treatment Zone Results (composite maxima) Trichloroethene (TCE) cis-1,2-Dichloroethene Vinyl Chloride

Thermal Treatment

0

50,000

100,000

150,000

200,000

250,000

7/1/2007 7/1/2008 7/1/2009 7/1/2010 7/1/2011 7/1/2012 7/1/2013 7/1/2014 7/1/2015 7/1/2016

ppb

Treatment Zone Results (composite maxima)

Trichloroethene (TCE) cis-1,2-Dichloroethene Vinyl Chloride

Thermal Treatment

Monitoring Results – MW-10

Thermal Treatment

0

50000

100000

150000

200000

250000

300000

3/19/2009 3/19/2010 3/19/2011 3/19/2012 3/19/2013 3/19/2014 3/19/2015 3/19/2016 3/19/2017

MW-10 Results - at Source Area Scale

Trichloroethene (TCE) cis-1,2-Dichloroethene Vinyl Chloride

Thermal Treatment

Monitoring Results - MW-10

Thermal Treatment Thermal Treatment

Monitoring Results - MW-12s

Thermal Treatment Thermal Treatment

0

20

40

60

80

100

120

3/1/

2009

6/1/

2009

9/1/

2009

12/1

/200

9

3/1/

2010

6/1/

2010

9/1/

2010

12/1

/201

0

3/1/

2011

6/1/

2011

9/1/

2011

12/1

/201

1

3/1/

2012

6/1/

2012

9/1/

2012

12/1

/201

2

3/1/

2013

6/1/

2013

9/1/

2013

12/1

/201

3

3/1/

2014

6/1/

2014

9/1/

2014

12/1

/201

4

3/1/

2015

6/1/

2015

9/1/

2015

12/1

/201

5

3/1/

2016

6/1/

2016

9/1/

2016

12/1

/201

6

3/1/

2017

ppb

MW-13 Results (260 feet downgradient)

Trichloroethene (TCE) cis-1,2-Dichloroethene Vinyl Chloride

Thermal Treatment

Monitoring Results - MW-13

Thermal Treatment – Lessons Learned Work with your regulator, define and document

measureable goals Mixtures of TCE and asphalt influence the remedy Be cautious using old data to specify the remedy Be cautious drawing the source area boundary at

the property line Performance-based contracts address risk and

reduce design effort If performance is based only on parent material

concentrations (e.g. TCE), consider that daughter product concentrations may increase

Comments/Questions?

KCI Contact: Mr. Jeff Gernand

410-891-1810 jeffrey.gernand@kci.com

SHA Contacts:

Mr. Greg Keenan 410-582-5585

gkeenan@sha.state.md.us

Mr. Shawn Schmelzer (410) 582-5589

sschmelzer@sha.state.md.us