Operational Research & Management Operations Scheduling
Project Scheduling
1. Project Planning (revisited)
2. Resource Constrained Project Scheduling
3. Parallel Machine Scheduling
Operational Research & Management Operations Scheduling
Topic 1
Project Planning (revisited)
Operational Research & Management Operations Scheduling 3
node: fase in project
(end of 1 or more tasks)
every task := arc
(dummies for precedence)
Project Planning: Jobs on Arcs
A
B
D
C
H
JG
FEd
umm
y
j prec duration pj
A: -3
B: -2
C: A4
D: A, B3
E: A2
F: E5
G: E6
H: C, F2
J: D, G4
Finish: A to J
Operational Research & Management Operations Scheduling 4
Critical Path Method (CPM)
ES1 = 0
ESj = maxi { pi + ESi | i P(j)}
1
2
3
4
6
5
7
A 3
B 2
C 4
H 2
J 4
G 6
F 5E 2d
umm
y
D 3
0
3
3
10
5
11
15 15
11
13
5
3
0
8
j prec
A: -
B: -
C: A
D: A, B
E: A
F: E
G: E
H: C, F
J: D, G
LFn = ESn
LFi = minj { LFj - pj | j Si }
Operational Research & Management Operations Scheduling 5
Alternative Network: Jobs on Nodes
A 3
B 2
C 4
E 2 F 5
J 4D 3
H 2
G 6
A 3
B 2
C 4
E 2 F 5
J 4D 3
H 2
G 6
3
3
3
5
5
?
11
0
0 = max{0+2,0+3}
j =n+1j = 0
150
Advantages- no dummy-jobs needed to enforce precedence- length of node may represent duration or arc-length
j prec
A: -
B: -
C: A
D: A, B
E: A
F: E
G: E
H: C, F
J: D, G
Operational Research & Management Operations Scheduling 6
Jobs on a time axis
A 3
B 2
C 4
E 2
F 5
J 4
D 3
H 2
G 6
0 3 5 11 15 t
jobs
j prec
A: -
B: -
C: A
D: A, B
E: A
F: E
G: E
H: C, F
J: D, G
Operational Research & Management Operations Scheduling 7
Project Planning with crashing
Heuristic
0
1 5
6
8
n+1
Graph of all Critical Path(s)
cut set
minimal cut set
4
6
4 5
6
Operational Research & Management Operations Scheduling
Topic 2
Resource Constrained Project Scheduling
Problem (RCPSP)
Operational Research & Management Operations Scheduling 9
Project Planning as Scheduling
Activities within project are jobs
Criterium: makespan onder volgorde- (en resource-restricties?)
P | prec (, rjk, Rk ) | Cmax
CPM-solution assumes: always enough resources
RCSP notation/assumptions:
Job j uses rj k units of resource k, during pj periods
Renewable resources: At any time one has Rk of resource k available
Determine all finish times Fj (=genoeg om hele schedule weer te geven)
Operational Research & Management Operations Scheduling 10
With resource requirements rj on jobs j
9A3
8B2
7C4
3E2
2F5
3J4
7D3
8H2
3G6
0 3 5 11 15 t
j prec
A: -
B: -
C: A
D: A, B
E: A
F: E
G: E
H: C, F
J: D, G
rj j pj Example: job A requires 9 workers for 3 days, etc.
With R=16 workers availableIs Cmax=15 days still possible?
Operational Research & Management Operations Scheduling 11
With resource requirements rj on jobs j
9A3
3E2
2F5
3J4
7D3
8H2
3G6
0 3 5 11 15 t
j P(j)
A: { }
B: { }
C: {A}
D: {A, B}
E: {A}
F: {E}
G: {E}
H: {C, F}
J: {D, G}
8B2
7C4
rj j pj
Feasible, even with 12 workers
Operational Research & Management Operations Scheduling 12
CPM on (resource-relaxed) RSCP
Generates “earliest” start- ESj and “latest” LFj finish times
The CPM-time is lower bound on RSCP-time: LFn+1 Cmax
Critical path jobs must start at ESj to accomplish Cmax = LFn+1
Other jobs have “slack”
– Their start time is NOT fixed by CPM
– Shift non-critical j in [ESj , LFj] smoothing the use of resources: after resource loading, balancing resource requirements
– If capacity Rk is still exceeded, then lengthen makespan
(let Fj exceed LFj for some j ).
Later, we discuss heuristic methods for RCPSP
Operational Research & Management Operations Scheduling 13
Resource loading and leveling
B
7A
10
D
13
19
C
C
DE
F
ED
loading: jobs start at ESj
leveling: shift jobs in time
Operational Research & Management Operations Scheduling 14
Conceptual Model Notation
– Decision variable: Fj (finish time) for j J
– P(j) = set of predecessors of job j
– A(t) set of active jobs j in period t
Model
Min Fn+1
s.t. Fh Fj - pj j J, hP(j)
Fj 0 j J
jA(t) rjk Rk resources k , t
A(t) = { j | Fj – pj < t Fj } t
Operational Research & Management Operations Scheduling 15
To achieve an ILP formulation:
How can we linearize A(t)={ j | j active at t } and Fj?
Change to discrete time-horizon [0,H], periods t = 1,2, ..H
For j J: Fj {1, …, H} ( Choosing H large enough)
Use extra binary variables
– Xjt = 1 if task j ends in period t;
– Ajt = 1 if task j is active in period t;
Making an ILP Model for RCPSP
j jttF t X1jtt
X
1jt p
jt jts tA X
E.g.
Fj = 4 en pj = 2
Xj4= 1
Aj3= 1 Aj4= 1
43210
Operational Research & Management Operations Scheduling 16
Resulting ILP model for RCPSP
Min
s.t. (1) j J, hP(j)
Precedence restrictions
(2) j J
(3) j J
Determine one last period
(4) j J, t = 1, …, H
Determining active periods of tasks
(5) t = 1, …, H, k K
Consumption of scarce resources
1jt p
jt jts tA X
1
j jtt
jtt
F t X
X
h j jF F p
jt jk kjA r R
1nF
Operational Research & Management Operations Scheduling 17
Remarks
Aiding variables Fj en Ajt can be eliminated: see book
Exact ILP methods useful only for benchmarking other methods on small problem sizes
RCPSP is generalization of job shop problem
Operational Research & Management Operations Scheduling 18
Heuristic methods for RCPSP
Two Schedule Generation Schemes can construct a schedule
– Serial Method (task oriëntated): fixes in each of n iterations one task
at earliest feasible starting time
– Parallel Method (time oriëntated): at next finish time of active task
start one or more tasks Example
00
2A3 4B2 3C1
3D4 4E2 2F4
00
0/13 3/15 5/16
4/120/10 6/16
rj j pj 00
2A3 4B2 3C1
3D4 4E2 2F4
00
0/13 3/15 5/16
4/120/10 6/16
ESj / LSj 8/16
Operational Research & Management Operations Scheduling 19
Parallel SGS (informal)
At most n stages
Each stage g <= n represents:
1. Schedule time tg (=next finish time of scheduled job)
2. A partial schedule, consisting of four disjoint sets of jobs:
– Completed, scheduled jobs at time tg
– Active jobs: scheduled jobs, not yet completed at time tg
– Decidable jobs: unscheduled, schedulable jobs (that can be chosen to start at time tn)
– remaining set: unscheduled jobs that cannot start at time tn
Operational Research & Management Operations Scheduling 20
Parallel SGS (on example)
tg finished R(tg) schedulable Dg j select R(tg) Fj
0 4 {A, D} 3D4 1 4 (3D)
{} - (* not A,E ; both require > 1 *)
4 3D 4 {2A3, 4E2} 4E2 0 6 (4E)
6 4E 4 {2A3, 2F4} 2A3 2 9 (2A)
{F} 2F4 0 10 (2F)
9 2A 2 { }({B}) - (* 2 short for B *)
10 2F 4 {B} 4B2 0 12 (4B)
12 4B 4 {C} 3C1 1 13
Operational Research & Management Operations Scheduling 21
Parallel SGS (formal) Notation (sets in bold)
– Cg = activities: scheduled and finished; C0 = {0}; – Ag = activities: scheduled and still active; A0 = {};
– Dg = activities: schedulable according to prec.- AND cap. restrictions
– Rk(t) = remaining capacity of resource k at time t Rk(0) = Rk
Algorithm
While some jobs Cg Ag do (* i.e., unscheduled jobs *) – g = g+1;
– tg = minjA(g) {Fj} , jg=arg (* next finish time active task *)
– Update Cg, Ag, Rk(tg), Dg (* for jg scheduled and finished *)
– While Dg do (* also Rk(tg) sufficient *)
Take jDg, set Fj = tg + pj en update Ag, Rk(tg), Dg
Operational Research & Management Operations Scheduling 22
Serial SGS (informal)
Each stage selects a job n stages
set of jobs already selected and planned: scheduled jobs (S )
decision set (D ): jobs with all predecessors in S
remaining set of jobs: these will first enter D and then S
Procedure
1. Start with scheduled set S=empty; j=0
2. Add j to S; Update schedulable set D ( := {j | P(j) S} );
3. Select job j from decision set D (with highest priority), and
(using {t/R(t) : finish times t } ) set j’s start/finish time as early as possible;
4. If |S|<n then go to step 2 (otherwise be happy with an 'active schedule')
Operational Research & Management Operations Scheduling 23
Serial SGS (on example)
step { t / R(t) | t in Fg } Dg rj j pj Sj Fj updates t / R(t)
0. {0/4} {A, D} 3 D 4 0 4 R(0)=1, R(4)=4
(e.g. as priority rule: D has lower slack 8=10-(0+2))
1. {0/1,4/4} {A, E} 4 E 2 4 6 R(4)=2, R(6)=4
(idem, E has lower slack)
2. {0/1,4/2,6/4} {A, F} 2 A 3 6 9 R(6)=2, R(9)=4
(idem)
4. {0/1,4/2,6/2,9/4} {B, F} 4 F 2 6 10 R(6)=0, R(9)=2, R(10)=4
(idem)
5. {0/1,4/2,6/0,9/2,10/4} {B}4 B 2 10 12 R(10)=0, R(12)=4
6. {.. 10/0, 12/4} {C} 3 C 1 12 13 R(12)=1
Sj =min {t Fg | t ESj and k, t’ [t, t+pj) Fg : Rk(t’) rj }
Operational Research & Management Operations Scheduling 24
Serial SGS (formal)
Notations (sets in bold)
– Sg = activities already scheduled (in steps <=g-1) S0 = { 0 (dummy)};
– Dg = activities (precedence-)schedulable (i.e, predecessors in Sg)
– Fg = { finishtimes of jobs j Sg } F0 = {0}; F0 = 0;
– Rk(t) = remaining capacity of resource k at time t
Repeat n times (i.e., “for g := 0 to n do”)
– Determine : Fg, Rk(t) voor tFg (*Initially F0 = {0}, Rk(0)=full resource k *)
– Determine Dg and take j Dg (* Dg set of decidable jobs *)
// schedule job j :
– Determine ESj = max { Fh | hP(j) } (* respecting precedence *)
– Determine Fj = pj + min { t [ESj, LSj] Fg | Rk(t) is feasible for j }
– Update Rk(t)
Operational Research & Management Operations Scheduling 25
Comments on Serial SGS
Constructs a feasible schedule
When resources are ample: schedule is optimal
Leads to schedule in class of ‘active schedules’,
– I.e., no operation can be earlier without others finishing later
– Class of ‘active schedules’ contains an optimal schedule
One can specify selection in “Take j in Dg” by giving:
– priority rule(s)
– an a priori list // and this explais the name ‘list scheduling’
Operational Research & Management Operations Scheduling 26
Comments on Parallel Method
Algorithm (informal)
1. Start with finish time of active job 0 (scheduled with finish time 0)
2. In step g: tg = earliest time (that unscheduled jobs may start.)
and Dg = collection of jobs that may start at time tg
Normally, when Dg empty: tg = first finish time of active job j
3. Select the job from D with the highest priority, let it start at time tg
4. If jobs are still unscheduled then goto step 2
else stop
Operational Research & Management Operations Scheduling 27
Comments on Parallel SGS
If ample resources then schedule is optimal
Schedule will be a non-delay schedule:
– Exercise: why is that so?
– Class of ‘Non-Delay schedules’ contains not always an optimal schedule
For serial en parallel:
– Single pass: 1 SGS combined with one Priority Rule
– Multi pass
1 SGS with all PR’s
Forward-backward scheduling
Sampling method: “random”, “biased” or “regret based biased”
Metaheuristics
Operational Research & Management Operations Scheduling
Topic 3
Parallel Machine Scheduling Problems
Operational Research & Management Operations Scheduling 29
Parallel Machine Models
Lets say we have
– Multiple machines (m), where
– the makespan should be minimized (Cmax)
We denote this problem as
Problem already NP-hard for m = 2 (partitioning problem)
LPT-rule good heuristic
max||Pm C
Operational Research & Management Operations Scheduling 30
Worst case behaviour LPT
Maximal deviation from optimal value
Example: four parallel machines, nine jobs
Cmax(opt)=12 but Cmax(LPT)=15
max
max
( ) 4 1
( ) 3 3
C LPT
C OPT m
jobs 1 2 3 4 5 6 7 8 9p ( j ) 7 7 6 6 5 5 4 4 4
Operational Research & Management Operations Scheduling 31
More makespan problems
easy
NP-hard
easy
Least Flexible Job first is optimal
if Mj is nested
max1| |prec C
max| |Pm prec C
max| |P prec C
max| 1, |j jPm p M C
Operational Research & Management Operations Scheduling 32
Allowing preemptions Lets say we have
– Multiple machines (m)
– preemption is allowed at any point in time
– and makespan is to be minimized (Cmax)
We denote this problem as
LP model gives Cmax but not a schedule
– only total time spent on machine
max| |Pm prmp C
Operational Research & Management Operations Scheduling 33
Heuristic solution
Longest Remaining Processing Time First (LRPT-rule)
– Academic solution
– Not practical
LRPT-rule optimal for in discrete time
Example: two parallel machines, three jobs with p = (8, 7, 6)
max| |Pm prmp C
Operational Research & Management Operations Scheduling 34
One final model
Lets say we have
– Multiple machines (m), where
– the total completion time should be minimized (Cj)
We denote this problem as
SPT-rule gives optimal schedule
For the weighted case: WSPT does not give optimal schedule
|| jPm C