ISPA Measure 2002 BG 16 P PE 015 WWTP Popovo and main collectors

Post on 05-Jan-2016

37 views 0 download

Tags:

description

ISPA Measure 2002 BG 16 P PE 015 WWTP Popovo and main collectors. Works Contract. Commencement Date:13 th June 2007 Completion Date:31 st Dec. 2009 Physical Execution:100 % Financial Execution:100 % WWTP became operational on 29 th March 2010 - PowerPoint PPT Presentation

Transcript of ISPA Measure 2002 BG 16 P PE 015 WWTP Popovo and main collectors

ISPA Measure 2002 BG 16 P PE 015

WWTP Popovo and main collectors

Works Contract

• Commencement Date: 13th June 2007

• Completion Date: 31st Dec. 2009

• Physical Execution: 100 %

• Financial Execution: 100 %

• WWTP became operational on 29th March 2010

• 1 year DNP will expire on 29th March 2011

WWTP Popovo - Completed

WWTP Popovo (during DNP and operation)

WWTP Popovo (during DNP and operation)

WWTP Popovo (during DNP and operation)

WWTP Popovo (during DNP and operation)

WWTP PopovoPublicity

Supervision Contract

• Commencement Date: 24th April 2007

• Completion Date: 30th April 2011

• Time elapsed: 100 %

• Financial Execution: 100 %

Compliance with Article 8of the Financing Memorandum

Art. 8.3.a)

According to EC’s letter Ref. REGIO I2/UN/ sd (2011) 910308 dated 01.08.2011 the conditions under point 8.3.a are considered as fulfilled.

Art. 8.3.b)According to EC’s letter Ref. Reg12/SP/vg D/(2010)920241), 007401 dated 16.08.2010 the conditions under point 8.3.b are considered as fulfilled.

Art. 8.3.c)

According to EC’s letter Ref. Reg12/VN/vg D/(2011)668482), 610178 dated 07.06.2011, the EC considers the conditions under Article 8.3.c as fulfilled.