Introduction to Introduction to Last Last Planner Planner ...

Post on 12-Jan-2022

24 views 0 download

Transcript of Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Insert Presenter name, company affiliation

Introduction to Last Planner System

© LEAN CONSTRUCTION INSTITUTE

Tuesday, Oct. 16

Rich Seiler, Unified-Works

Introduction to Last Planner® System

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Lean Construction Institute Provider Number H561

Introduction to Last Planner® SystemLCITB.IntrLPS

Rich SeilerOct. 16

2

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

4 LU Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.

This course is registered with AIA CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner ofhandling, using, distributing, or dealing in any material or product._______________________________________Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

4

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

This introductory training will include an overview to Last Planner®

System (LPS) implementation. LPS integrates Lean principles and is based on conversation leading to reliable commitments by team members. Participants will learn the fundamentals of LPS. The training will include a hand on simulation to revel the importance of removing variation in work flow.

5

Course Description

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

01. 02. 03. 04.At the end of this presentation, participants will have an overview understanding of each of the 5 levels of Last Planner® System (LPS) and how they inter-relate.

At the end of this presentation, participants will understand the need for reliability on projects and how LPS produces it.

At the end of this presentation, participants will understand the need to reduce variation in work flow and how LPS supports this.

At the end of this presentation, participants will know the basic mechanics of the 5 levels of LPS.

6

Learning Objectives

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

8

Lean Journey to Mastery

Unaware

Awareness

Understanding

Mastery

Competency

Continuous Learning Cycle(s)

8

How will you reach the next level on your journey?

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

9

Learning Overview

Why Last Planner® System

LPS Overview

Milestone Planning

Phase Pull Planning

Look Ahead Planning

Weekly Work Planning

Learning/Improving

9

1.

2.

3.

4.

5.

6.

7.

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

12

Discussion Question

What are your dissatisfactions with the way projects are currently planned?

Large Group Discussion 5 min

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

13

Six Tenets of Lean

2

13

1

2

3

4

5

6

Respect for people

Optimize the Whole

Generate Value

Eliminate Waste

Focus on Flow

Continuous Improvement

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

54%of commitments

made on construction projects were

completed on time

Brief History

14

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

15

2004 study by the Construction Industry Institute

The Opportunity…

Productive Time

Waste 12%

Productive Time Waste 57%

Productive Waste

MANUFACTURINGDESIGN/

CONSTRUCTION

15

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Time —70% were delivered late

70%Delivered Late

20%Delivered On

Time

10%Delivered Early

73%Over Tender

Price

14%On Tender

Price

13%Under Tender

Price

Cost —73% were over budget

Why Use Last Planner® System?

16

Source: Benchmarking the Government Client Stage Two Study December 1999

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Correlation of lean intensity to outcomes (% likelihood on best projects)

Completed Ahead ofSchedule

Completed UnderBudget

Low Lean Intensity

3X

2X

Why Use LPS?

17

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Workflow and Risk

1. Workflow losses are real, lead to adversarial relations, and are difficult to quantify, so…

2. Everyone protects themselves by adding contingency and/or holding back labor to keep utilization high.

3. This further reduces workflow predictability and increases project risk

4. By their/our actions, we increase that risk and shift it along.

18

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

19

1. Traditional planning systems are unable to producepredictable workflow.

2. Workflow reliability directly affects system speed and cost.

3. All plans are forecasts, all forecasts are wrong, further in advance –more wrong, more detail – more wrong.

Key Concepts

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

20

1. Improves communication & reliability.

2. Fosters an enjoyable environment, trust, and collaboration.

3. Promotes early stakeholder engagement.

4. Improves visibility of the project plan (transparency).

5. Creates team buy in.

6. Rapid learning through metrics, revealing areas for improvement.

7. Improves planning in both design & construction phases.

Last Planner® System Benefits

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

21

Project is a Promise

A project is a very big promise delivered by

people in an ever changing network of

promises.

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

22

Performance

PERFORMERCUSTOMER

Credit: Dr. Fernando Flores

Preparation

Acceptance

Negotiation

Conditions of

Satisfaction,Time

Request or Offer

Acceptance(2 mutual promises)

Declaration ofSatisfaction

Report of Completion

Basic Action Flow

22

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

23

Last Planner® System OverviewMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

24

Lookahead

Phase Pull

Milestone

Weekly

Learning

Milestoneinforms

Phase Pull

Phase Pullinforms

Lookahead

Lookaheadinforms Weekly

Weeklyinforms

Learning

Learninginforms

Milestone

System for Planning

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

25

Continuous Improvement

25

Last Planner® System follows the Continuous Improvement Cycle of:

Plan, Do, Check, Act/Adjust

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Focus on Hand-offs

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

DAILY HUDDLE

PHASE PULL PLANNING LOOKAHEAD PLANNING

WEEKLY WORK PLANNING

Last Planner® System

27

Courtesy of : PCL

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Levels of Granularity

Milestone Planning

Phase Pull Planning

Lookahead Planning

Weekly Work Planning

Boulder

Rock

Pebble

Sand

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

A Last Planner can make the reliable commitment to

complete the work

Person closest to work, with authority to make

decisions creates schedule

Who is the Last Planner?

29

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

30

Milestone PlanningMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

Boulder

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

31

Define the overall road map and gain alignment

Identify milestones important to client and stakeholders – especially immovable dates

Informs the Phase Pull Planning

MILESTONE PLANNING

31

Phase “Pull” Planning Phase “Pull” Planning

Milestone Planning

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

32

Milestone Planning Example Tag

Complete Structure11/8/16

CompleteExterior2/10/17

CompleteFinishes2/13/18

Color CodeOrient as Diamond

or other distinguishing

manner

Add dates or durations

Add intermediate milestones to

create small batch phases of 8-12 weeks duration

Add intermediate milestones for date to pull each phase

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

33

Milestone Planning Example

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Courtesy of : The ReAlignment Group of California

Milestone Planning Example

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Courtesy of : JE Dunn

Milestone Planning Example

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

36

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

37

through Floor 35

etc . . .

Floor 14

Floor 13

Floor 12

Floor 11

Floor 10

Floor 9

Floor 8

Floor 7

Floor 6

Floor 5

Floor 4

Floor 3

Floor2

Floor 1

Parade of Trades

01.

02.

03.

04.

05.

The building has 35 floors.

There are seven trades.

Each trade has work on every floor.

The work must be done in sequence, with each trade only able to work on those floors that have been given to them by the previous trade.

The trades mobilize to the site one week apart.

37

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

38

Parade of TradesHow will you develop the

project schedule?

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

39

39

Build-out 35 Floors

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

40

Work Sequence

Week 1 Week 2 Week 3 Week 4 Week 5

Build-out 35 Floors

40

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

41

Distribute score sheets as directed

Chips START in the queue of Layout

Establish queue spaces

Give die to Casework

Move 35 pieces of work through 7 tasks. Work is completed at the end of the week and passed to next trade. Place materials on table as shown.

Layout

35

FramingRough

Plumbing

RoughElectrical

DrywallPaint

Casework

41

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

42

Pass the Die to the LEFT, Pass Chips to the RIGHT !

WEEKCOLUMN 1CAPACITY

NUMBER ON DICE

COLUMN 2CAPACITY

PIECES PASSED

COLUMN 3REMAINING INCOMING

INVENTORY (BACKLOG)AVAILABLE - PASSED

1 3 3 32

2

3

Week 1

42

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

43

Layout

32

RoughElectrical

3

43

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

44

WEEKCOLUMN 1CAPACITY

NUMBER ON DICE

COLUMN 2CAPACITY

PIECES PASSED

COLUMN 3REMAINING INCOMING

INVENTORY (BACKLOG)AVAILABLE - PASSED

2

3

NO INVENTORY THIS WEEK. DO NOT ROLL – JUST PASS DICE.

Framing

Pass the Die to the LEFT.

44

Week 2

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

45

WEEKCOLUMN 1CAPACITY

NUMBER ON DICE

COLUMN 2CAPACITY

PIECES PASSED

COLUMN 3REMAINING INCOMING

INVENTORY (BACKLOG)AVAILABLE - PASSED

1 3 3 32

2 1 1 31

3

Layout

45

Week 3

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

46

Layout

30

FramingRoughPlumbing

RoughElectrical

Drywall

Paint

Casework

1

31+0

46

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Casework

It’s your job to keep everyone at the table on the same week

. Announce the week as you get the dice (and to start the game)

Layout

35

FramingRough

Plumbing

RoughElectrical

DrywallPaint

Casework

1

3

Layout

You will finish first.

Please tally the results on the Tally Sheet and send it to your right.

47

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

48

Trade Week Complete

Sum of Available Capacity

Total Column 1

Sum of Remaining Inventory

Total Column 3

Maximum Inventory in any

weekColumn 3

Layout

FramingRough

PlumbingRough

ElectricalDrywall

Paint

CaseworkSum

We’ll ask you to report when everyone’s done

Note the highest amount of Inventory in any week for each trade.

Sum and record the total Remaining Inventory for all Trades except Layout.

Record the week each Trade finishes. Sum and record the Available Capacity for all Trades.

When Work is Complete

48

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

TABLEWEEK

LAYOUT COMPLETE

WEEK PROJECT

COMPLETE

TOTAL USED

CAPACITY

TOTAL REMAINING INVENTORY

MAX INVENTORY

IN ANY WEEK

Blue

Black

Green

Red

Summary

49

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

1.2.2.5.5.6 1.2.3.4.5.6 2.2.3.4.5.5 2.3.3.4.4.5 3.3.3.4.4.41.1.1.6.6.6

AverageWorst

Best

40

35

30

25

20

10

10

5

0

Results

50

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

51

What would be the specific advantages of improved work flow

reliability on your projects?

Group discussion 10 min

Discussion Question

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

52

Phase Pull PlanningMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

Rock

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

53

Phase of the work (~8-12 weeks)

After – add dates and transfer to the Look Ahead Plan

Work out the structure and durations

Informed by the Milestone Plan

Phase Pull Planning

Courtesy of : PCL

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

54

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Work

Information

Pull Creating Flow

54

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

55

Phase Pull Planning Example Tag

55

Name

MY PROMISE / ACTIVITY

• What I will Deliver

• Be specific

• Small batchWork Zone / Area

MY REQUEST / TRIGGER

• What Releases my Work

• Be specific

# Days1 week max

# People

Constraint

Name of person making the commitment

Description of the activity

Work zone or area

Description of the predecessor activity or work that releases the start of your activity

Known constraint such as RFI

# of People for the work

Duration of the work in daysSmall batch work into 5 days maximum

• Format tag to best fit your team needs

• Add more information as valued

• Color code by trade or discipline

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

56

Phase Pull Example

Mike G 5 days4 Crew

Underground Piping Zone 1

Vaults Backfilled

Dave S 3 days3 Crew

Backfill Vaults Zone 1

Vaults Set

Mike G 3 days4 Crew

Vaults Set Zone 1

Vaults on Site

Dave S 3 days3 Crew

Backfill UG PipingZone 1

UG Piping

Promise Promise Promise

Request Request56

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

57

Start at End

57 Start at EndCourtesy of : Turner Construction

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

58

Pull the Work

58Pull the Work Courtesy of : Turner Construction

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

59

Arrive at the Start

59 Arrive at the StartCourtesy of : Turner Construction

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

60

Innovative Pull Planning

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

61

Lookahead PlanningMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

Pebble

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

62

• Transferred from the Phase Pull Plan to a plan with dates/weeks

• Boards, P6 or other software documentation• Rolling (6-10 weeks) Lookahead to

“make work ready”• Supports Team Meeting Discussion/Action for:• Identify Risk – Risk Log

– High/Medium/Low– Plan to Mitigate

• Identify Constraints – Constraint Log– Plan to Mitigate

• Informs the Weekly Work Plan62

Lookahead Planning

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

63

Lookahead Planning Example

Track PPC & Variance

2 WeeklyWork Plan

Boards

Constraint Log

Lookahead

5-6 LookaheadPlan Boards

63

Courtesy of: Turner Construction

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

64

• P6• Microsoft

Project• TouchPlan

• LeanKit• vPlanner• Others

Electronic

Lookahead Planning Options

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

65

Date Promised

DateResolved

Constraint Log Example

ConstraintDescription

ResponsiblePerson & CO

DateIdentified

DateNeeded

Date Promised

Date Resolved

65

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

66

Discussion Question

How will looking ahead to remove constraints help your projects?

Discuss amongst selves in small groups

Table discussion 10 min with 5 min report out

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

67

Weekly Work PlanningMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

Sand

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

68

• Informed by the Look Ahead Plan

• Detail work by trade at the Daily Level

• Detail of the current week

• Detail of the next week

• Informs the Daily Huddle

• Take to the field68

Weekly Work Planning

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

69

Weekly Work Plan Informs the Daily Huddle

Weekly Work Planning

69

Courtesy of : PCL Courtesy of : Turner/DPR JV

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

70

“What, Who & When”

Commitment Description

What & Where?

Who?

When will it be done?

Crew Size?

Weekly Work Planning Example

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

71

Learning & ImprovingMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

72

1. What did I complete?

2. What will I complete?

3. What needs to bere-planned?

4. How can we prevent this from happening again?

Daily HuddleCourtesy of KHS&S

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

73

Percent Plan Complete

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

74

Reasons for Variance

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

75

Standard Work Available @ LeanConstruction.org

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

LPS Construction:

• Pull Plans identify work structure and duration

• Milestones must be clearly defined by expected outcome which will be observable

• Is linear and the flow is “tangible materials”

LPS For DesignLPS Design:

• Pull Plans identify work needed and date needed

• Milestones are often “decision points”

• Milestones must be clearly defined by expected outcome which will describe what we need to know

• Is emerging based on new information and the flow is “information”

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

77

Last Planner® System in DesignMILESTONE

Planning

PHASE PULL Planning

DESIGN CYCLEPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Advance the Plan

Make Promises

PPC/Variance

5 Connected Conversations

Key Difference

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

LPS In DesignPhase Pull

Plan/DesignCycle Planning

Continuously Advance 2-3 Week

Cycles(Should)

Weekly Work Planning

Work Register& Constraint Log

(Can)

Check – in Sessions

Percent PlanComplete PPC

(Did)

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

79

Pull-Creating Flow

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Work

Information

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

80

Massport Logan Airport Team Turner Alamodome Renovations Team

Phase Pull PlanningPhase Pull Planning “schematic phase”

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

81

What new actions or ideas that you learned today can you take

back to your project?

Write down on Take Away Sheet (5 minutes)Share with your neighbor (5 minutes)

Discussion Question

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

82

Lean Journey to Mastery

Unaware

Awareness

Understanding

Mastery

Competency

Continuous Learning Cycle(s)

82

How will you reach the next level on your journey?

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

83

References & Learning OpportunitiesEvents:• Local Community of Practice• Congress• Design Forum

LCI Education Courses:• Introduction to Lean Project Delivery • Introduction to Last Planner® System• Mindset of Effective Big Room• Target Value Delivery

LCI E-Learning Courses:• Introduction to LP® S

www.LeanConstruction.org

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

85

Plus/Delta

85

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

This concludes The American Institute of Architects Continuing Education Systems Course

Lean Construction Institute info@leanconstruction.org

86