Introduction to Introduction to Last Last Planner Planner ...

82
INTRODUCTION TO LAST PLANNER ® SYSTEM Insert Presenter name, company affiliation Introduction to Last Planner System © LEAN CONSTRUCTION INSTITUTE Tuesday, Oct. 16 Rich Seiler, Unified-Works Introduction to Last Planner® System

Transcript of Introduction to Introduction to Last Last Planner Planner ...

Page 1: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Insert Presenter name, company affiliation

Introduction to Last Planner System

© LEAN CONSTRUCTION INSTITUTE

Tuesday, Oct. 16

Rich Seiler, Unified-Works

Introduction to Last Planner® System

Page 2: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Lean Construction Institute Provider Number H561

Introduction to Last Planner® SystemLCITB.IntrLPS

Rich SeilerOct. 16

2

Page 3: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

4 LU Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.

This course is registered with AIA CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner ofhandling, using, distributing, or dealing in any material or product._______________________________________Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

4

Page 4: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

This introductory training will include an overview to Last Planner®

System (LPS) implementation. LPS integrates Lean principles and is based on conversation leading to reliable commitments by team members. Participants will learn the fundamentals of LPS. The training will include a hand on simulation to revel the importance of removing variation in work flow.

5

Course Description

Page 5: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

01. 02. 03. 04.At the end of this presentation, participants will have an overview understanding of each of the 5 levels of Last Planner® System (LPS) and how they inter-relate.

At the end of this presentation, participants will understand the need for reliability on projects and how LPS produces it.

At the end of this presentation, participants will understand the need to reduce variation in work flow and how LPS supports this.

At the end of this presentation, participants will know the basic mechanics of the 5 levels of LPS.

6

Learning Objectives

Page 6: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

8

Lean Journey to Mastery

Unaware

Awareness

Understanding

Mastery

Competency

Continuous Learning Cycle(s)

8

How will you reach the next level on your journey?

Page 7: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

9

Learning Overview

Why Last Planner® System

LPS Overview

Milestone Planning

Phase Pull Planning

Look Ahead Planning

Weekly Work Planning

Learning/Improving

9

1.

2.

3.

4.

5.

6.

7.

Page 8: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

12

Discussion Question

What are your dissatisfactions with the way projects are currently planned?

Large Group Discussion 5 min

Page 9: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

13

Six Tenets of Lean

2

13

1

2

3

4

5

6

Respect for people

Optimize the Whole

Generate Value

Eliminate Waste

Focus on Flow

Continuous Improvement

Page 10: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

54%of commitments

made on construction projects were

completed on time

Brief History

14

Page 11: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

15

2004 study by the Construction Industry Institute

The Opportunity…

Productive Time

Waste 12%

Productive Time Waste 57%

Productive Waste

MANUFACTURINGDESIGN/

CONSTRUCTION

15

Page 12: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Time —70% were delivered late

70%Delivered Late

20%Delivered On

Time

10%Delivered Early

73%Over Tender

Price

14%On Tender

Price

13%Under Tender

Price

Cost —73% were over budget

Why Use Last Planner® System?

16

Source: Benchmarking the Government Client Stage Two Study December 1999

Page 13: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Correlation of lean intensity to outcomes (% likelihood on best projects)

Completed Ahead ofSchedule

Completed UnderBudget

Low Lean Intensity

3X

2X

Why Use LPS?

17

Page 14: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Workflow and Risk

1. Workflow losses are real, lead to adversarial relations, and are difficult to quantify, so…

2. Everyone protects themselves by adding contingency and/or holding back labor to keep utilization high.

3. This further reduces workflow predictability and increases project risk

4. By their/our actions, we increase that risk and shift it along.

18

Page 15: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

19

1. Traditional planning systems are unable to producepredictable workflow.

2. Workflow reliability directly affects system speed and cost.

3. All plans are forecasts, all forecasts are wrong, further in advance –more wrong, more detail – more wrong.

Key Concepts

Page 16: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

20

1. Improves communication & reliability.

2. Fosters an enjoyable environment, trust, and collaboration.

3. Promotes early stakeholder engagement.

4. Improves visibility of the project plan (transparency).

5. Creates team buy in.

6. Rapid learning through metrics, revealing areas for improvement.

7. Improves planning in both design & construction phases.

Last Planner® System Benefits

Page 17: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

21

Project is a Promise

A project is a very big promise delivered by

people in an ever changing network of

promises.

Page 18: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

22

Performance

PERFORMERCUSTOMER

Credit: Dr. Fernando Flores

Preparation

Acceptance

Negotiation

Conditions of

Satisfaction,Time

Request or Offer

Acceptance(2 mutual promises)

Declaration ofSatisfaction

Report of Completion

Basic Action Flow

22

Page 19: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

23

Last Planner® System OverviewMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

Page 20: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

24

Lookahead

Phase Pull

Milestone

Weekly

Learning

Milestoneinforms

Phase Pull

Phase Pullinforms

Lookahead

Lookaheadinforms Weekly

Weeklyinforms

Learning

Learninginforms

Milestone

System for Planning

Page 21: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

25

Continuous Improvement

25

Last Planner® System follows the Continuous Improvement Cycle of:

Plan, Do, Check, Act/Adjust

Page 22: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Focus on Hand-offs

Page 23: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

DAILY HUDDLE

PHASE PULL PLANNING LOOKAHEAD PLANNING

WEEKLY WORK PLANNING

Last Planner® System

27

Courtesy of : PCL

Page 24: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Levels of Granularity

Milestone Planning

Phase Pull Planning

Lookahead Planning

Weekly Work Planning

Boulder

Rock

Pebble

Sand

Page 25: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

A Last Planner can make the reliable commitment to

complete the work

Person closest to work, with authority to make

decisions creates schedule

Who is the Last Planner?

29

Page 26: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

30

Milestone PlanningMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

Boulder

Page 27: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

31

Define the overall road map and gain alignment

Identify milestones important to client and stakeholders – especially immovable dates

Informs the Phase Pull Planning

MILESTONE PLANNING

31

Phase “Pull” Planning Phase “Pull” Planning

Milestone Planning

Page 28: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

32

Milestone Planning Example Tag

Complete Structure11/8/16

CompleteExterior2/10/17

CompleteFinishes2/13/18

Color CodeOrient as Diamond

or other distinguishing

manner

Add dates or durations

Add intermediate milestones to

create small batch phases of 8-12 weeks duration

Add intermediate milestones for date to pull each phase

Page 29: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

33

Milestone Planning Example

Page 30: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Courtesy of : The ReAlignment Group of California

Milestone Planning Example

Page 31: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Courtesy of : JE Dunn

Milestone Planning Example

Page 32: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

36

Page 33: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

37

through Floor 35

etc . . .

Floor 14

Floor 13

Floor 12

Floor 11

Floor 10

Floor 9

Floor 8

Floor 7

Floor 6

Floor 5

Floor 4

Floor 3

Floor2

Floor 1

Parade of Trades

01.

02.

03.

04.

05.

The building has 35 floors.

There are seven trades.

Each trade has work on every floor.

The work must be done in sequence, with each trade only able to work on those floors that have been given to them by the previous trade.

The trades mobilize to the site one week apart.

37

Page 34: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

38

Parade of TradesHow will you develop the

project schedule?

Page 35: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

39

39

Build-out 35 Floors

Page 36: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

40

Work Sequence

Week 1 Week 2 Week 3 Week 4 Week 5

Build-out 35 Floors

40

Page 37: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

41

Distribute score sheets as directed

Chips START in the queue of Layout

Establish queue spaces

Give die to Casework

Move 35 pieces of work through 7 tasks. Work is completed at the end of the week and passed to next trade. Place materials on table as shown.

Layout

35

FramingRough

Plumbing

RoughElectrical

DrywallPaint

Casework

41

Page 38: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

42

Pass the Die to the LEFT, Pass Chips to the RIGHT !

WEEKCOLUMN 1CAPACITY

NUMBER ON DICE

COLUMN 2CAPACITY

PIECES PASSED

COLUMN 3REMAINING INCOMING

INVENTORY (BACKLOG)AVAILABLE - PASSED

1 3 3 32

2

3

Week 1

42

Page 39: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

43

Layout

32

RoughElectrical

3

43

Page 40: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

44

WEEKCOLUMN 1CAPACITY

NUMBER ON DICE

COLUMN 2CAPACITY

PIECES PASSED

COLUMN 3REMAINING INCOMING

INVENTORY (BACKLOG)AVAILABLE - PASSED

2

3

NO INVENTORY THIS WEEK. DO NOT ROLL – JUST PASS DICE.

Framing

Pass the Die to the LEFT.

44

Week 2

Page 41: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

45

WEEKCOLUMN 1CAPACITY

NUMBER ON DICE

COLUMN 2CAPACITY

PIECES PASSED

COLUMN 3REMAINING INCOMING

INVENTORY (BACKLOG)AVAILABLE - PASSED

1 3 3 32

2 1 1 31

3

Layout

45

Week 3

Page 42: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

46

Layout

30

FramingRoughPlumbing

RoughElectrical

Drywall

Paint

Casework

1

31+0

46

Page 43: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Casework

It’s your job to keep everyone at the table on the same week

. Announce the week as you get the dice (and to start the game)

Layout

35

FramingRough

Plumbing

RoughElectrical

DrywallPaint

Casework

1

3

Layout

You will finish first.

Please tally the results on the Tally Sheet and send it to your right.

47

Page 44: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

48

Trade Week Complete

Sum of Available Capacity

Total Column 1

Sum of Remaining Inventory

Total Column 3

Maximum Inventory in any

weekColumn 3

Layout

FramingRough

PlumbingRough

ElectricalDrywall

Paint

CaseworkSum

We’ll ask you to report when everyone’s done

Note the highest amount of Inventory in any week for each trade.

Sum and record the total Remaining Inventory for all Trades except Layout.

Record the week each Trade finishes. Sum and record the Available Capacity for all Trades.

When Work is Complete

48

Page 45: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

TABLEWEEK

LAYOUT COMPLETE

WEEK PROJECT

COMPLETE

TOTAL USED

CAPACITY

TOTAL REMAINING INVENTORY

MAX INVENTORY

IN ANY WEEK

Blue

Black

Green

Red

Summary

49

Page 46: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

1.2.2.5.5.6 1.2.3.4.5.6 2.2.3.4.5.5 2.3.3.4.4.5 3.3.3.4.4.41.1.1.6.6.6

AverageWorst

Best

40

35

30

25

20

10

10

5

0

Results

50

Page 47: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

51

What would be the specific advantages of improved work flow

reliability on your projects?

Group discussion 10 min

Discussion Question

Page 48: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

52

Phase Pull PlanningMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

Rock

Page 49: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

53

Phase of the work (~8-12 weeks)

After – add dates and transfer to the Look Ahead Plan

Work out the structure and durations

Informed by the Milestone Plan

Phase Pull Planning

Courtesy of : PCL

Page 50: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

54

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Work

Information

Pull Creating Flow

54

Page 51: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

55

Phase Pull Planning Example Tag

55

Name

MY PROMISE / ACTIVITY

• What I will Deliver

• Be specific

• Small batchWork Zone / Area

MY REQUEST / TRIGGER

• What Releases my Work

• Be specific

# Days1 week max

# People

Constraint

Name of person making the commitment

Description of the activity

Work zone or area

Description of the predecessor activity or work that releases the start of your activity

Known constraint such as RFI

# of People for the work

Duration of the work in daysSmall batch work into 5 days maximum

• Format tag to best fit your team needs

• Add more information as valued

• Color code by trade or discipline

Page 52: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

56

Phase Pull Example

Mike G 5 days4 Crew

Underground Piping Zone 1

Vaults Backfilled

Dave S 3 days3 Crew

Backfill Vaults Zone 1

Vaults Set

Mike G 3 days4 Crew

Vaults Set Zone 1

Vaults on Site

Dave S 3 days3 Crew

Backfill UG PipingZone 1

UG Piping

Promise Promise Promise

Request Request56

Page 53: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

57

Start at End

57 Start at EndCourtesy of : Turner Construction

Page 54: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

58

Pull the Work

58Pull the Work Courtesy of : Turner Construction

Page 55: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

59

Arrive at the Start

59 Arrive at the StartCourtesy of : Turner Construction

Page 56: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

60

Innovative Pull Planning

Page 57: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

61

Lookahead PlanningMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

Pebble

Page 58: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

62

• Transferred from the Phase Pull Plan to a plan with dates/weeks

• Boards, P6 or other software documentation• Rolling (6-10 weeks) Lookahead to

“make work ready”• Supports Team Meeting Discussion/Action for:• Identify Risk – Risk Log

– High/Medium/Low– Plan to Mitigate

• Identify Constraints – Constraint Log– Plan to Mitigate

• Informs the Weekly Work Plan62

Lookahead Planning

Page 59: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

63

Lookahead Planning Example

Track PPC & Variance

2 WeeklyWork Plan

Boards

Constraint Log

Lookahead

5-6 LookaheadPlan Boards

63

Courtesy of: Turner Construction

Page 60: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

64

• P6• Microsoft

Project• TouchPlan

• LeanKit• vPlanner• Others

Electronic

Lookahead Planning Options

Page 61: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

65

Date Promised

DateResolved

Constraint Log Example

ConstraintDescription

ResponsiblePerson & CO

DateIdentified

DateNeeded

Date Promised

Date Resolved

65

Page 62: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

66

Discussion Question

How will looking ahead to remove constraints help your projects?

Discuss amongst selves in small groups

Table discussion 10 min with 5 min report out

Page 63: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

67

Weekly Work PlanningMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

Sand

Page 64: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

68

• Informed by the Look Ahead Plan

• Detail work by trade at the Daily Level

• Detail of the current week

• Detail of the next week

• Informs the Daily Huddle

• Take to the field68

Weekly Work Planning

Page 65: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

69

Weekly Work Plan Informs the Daily Huddle

Weekly Work Planning

69

Courtesy of : PCL Courtesy of : Turner/DPR JV

Page 66: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

70

“What, Who & When”

Commitment Description

What & Where?

Who?

When will it be done?

Crew Size?

Weekly Work Planning Example

Page 67: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

71

Learning & ImprovingMILESTONE

Planning

PHASE PULL Planning

LOOKAHEADPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Make Work Ready

Make Promises

PPC/Variance

5 Connected Conversations

Page 68: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

72

1. What did I complete?

2. What will I complete?

3. What needs to bere-planned?

4. How can we prevent this from happening again?

Daily HuddleCourtesy of KHS&S

Page 69: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

73

Percent Plan Complete

Page 70: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

74

Reasons for Variance

Page 71: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

75

Standard Work Available @ LeanConstruction.org

Page 72: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

LPS Construction:

• Pull Plans identify work structure and duration

• Milestones must be clearly defined by expected outcome which will be observable

• Is linear and the flow is “tangible materials”

LPS For DesignLPS Design:

• Pull Plans identify work needed and date needed

• Milestones are often “decision points”

• Milestones must be clearly defined by expected outcome which will describe what we need to know

• Is emerging based on new information and the flow is “information”

Page 73: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

77

Last Planner® System in DesignMILESTONE

Planning

PHASE PULL Planning

DESIGN CYCLEPlanning

WEEKLY WORKPlanning

LEARNING/IMPROVING

Set Milestones

Specify Handoffs

Advance the Plan

Make Promises

PPC/Variance

5 Connected Conversations

Key Difference

Page 74: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

LPS In DesignPhase Pull

Plan/DesignCycle Planning

Continuously Advance 2-3 Week

Cycles(Should)

Weekly Work Planning

Work Register& Constraint Log

(Can)

Check – in Sessions

Percent PlanComplete PPC

(Did)

Page 75: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

79

Pull-Creating Flow

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Promise/Request

Work

Information

Page 76: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

80

Massport Logan Airport Team Turner Alamodome Renovations Team

Phase Pull PlanningPhase Pull Planning “schematic phase”

Page 77: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

81

What new actions or ideas that you learned today can you take

back to your project?

Write down on Take Away Sheet (5 minutes)Share with your neighbor (5 minutes)

Discussion Question

Page 78: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

82

Lean Journey to Mastery

Unaware

Awareness

Understanding

Mastery

Competency

Continuous Learning Cycle(s)

82

How will you reach the next level on your journey?

Page 79: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

83

References & Learning OpportunitiesEvents:• Local Community of Practice• Congress• Design Forum

LCI Education Courses:• Introduction to Lean Project Delivery • Introduction to Last Planner® System• Mindset of Effective Big Room• Target Value Delivery

LCI E-Learning Courses:• Introduction to LP® S

www.LeanConstruction.org

Page 80: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

Page 81: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

85

Plus/Delta

85

Page 82: Introduction to Introduction to Last Last Planner Planner ...

© LEAN CONSTRUCTION INSTITUTE

I N T R O D U C T I O N T O L A S T P L A N N E R ® S Y S T E M

This concludes The American Institute of Architects Continuing Education Systems Course

Lean Construction Institute [email protected]

86