Heavy Lift Barinas 06.20.2012

Post on 12-Jun-2015

681 views 0 download

Tags:

description

Turbines & Generators Heavy Lift

Transcript of Heavy Lift Barinas 06.20.2012

MAJOR MECHANICAL EQUIPMENT INSTALLATION - TURBINE GENERATORS

Date 06/20/2012

Activities:

1. Leveling Plate & Steel Plates Placement in Foundations 100/200 Generators and Turbines. (18 to 20 June 2012)

2. Turbines Transportation fromStorage Yard to CTG-200 (2)Foundations.

3. Turbine placement inFoundation CTG-200 (1)

MAJOR MECHANICAL EQUIPMENT INSTALLATION - TURBINE GENERATORS

Leveling Plate & Steel PlatesPlacement in Foundations 100/200 Generators and Turbines.

MAJOR MECHANICAL EQUIPMENT INSTALLATION - TURBINE GENERATORS

Turbines Transportation from Storage Yard to CTG-200 (2) Foundations

MAJOR MECHANICAL EQUIPMENT INSTALLATION - TURBINE GENERATORS

Turbine placement in Foundation CTG-200 (1)

MAJOR MECHANICAL EQUIPMENT INSTALLATION - TURBINE GENERATORS

Date 06/21/2012

Activities:

1. Turbines Transportation fromStorage Yard to CTG-100 (2)Foundations

2. Turbine placement inFoundation CTG-100 (1)

3. Verification of Lifting PointsGenerator CTG-100/200

MAJOR MECHANICAL EQUIPMENT INSTALLATION - TURBINE GENERATORS

Turbines Transportation from StorageYard to CTG-100 (2) Foundations

Turbine placement in Foundation CTG-100 (1)

MAJOR MECHANICAL EQUIPMENT INSTALLATION - TURBINE GENERATORS

Date 06/22/2012

Activities:

1. Rigging and Transportation Generator CTG-100